Billy Smith Enterprises, Inc. v. Hutchison Construction, Inc.
Full Opinion (html_with_citations)
OPINION
This appeal arises from a dispute between a general contractor on a public works project, Hutchison Construction, Inc. (HCI), and a subcontractor, Billy Smith Enterprises, Inc., (BSE). BSE and HCI sued each other for breach of their subcontract, and BSE alleged violations of the Prompt Pay Act. See Tex. Govât Code Ann. §§ 2251.001-.055 (West 2000 & Supp. 2007). A jury found that both BSE and HCI had breached the subcontract, and that BSE had committed the first material breach, but awarded HCI no damages. The jury also found that HCI had violated the Prompt Pay Act, and rendered a verdict for damages and attorneyâs fees. The district court disregarded the juryâs findings with respect to the Prompt Pay Act claim and rendered a final judgment that BSE take nothing on its claims.
The controlling question in this appeal, as framed by the record and our standard of review, is whether the Prompt Pay Act independently creates a right to payment under a contract that a party otherwise has no duty to perform. Concluding that the Act does not create such a right, we will affirm the district courtâs judgment.
BACKGROUND
The following summary is taken from the clerkâs record; no reporterâs record was requested by any party or filed. BSE sued HCI and HCIâs surety on its payment bond, Mid-Continent Company, for sums allegedly owed under a âSubcontract Agreementâ in which BSE agreed to provide construction services to HCI in connection with a Travis County public works project. BSE alleged that HCI was Travis Countyâs general contractor on the project. BSE pled that the Subcontract Agreement was a âlabor onlyâ contract in which HCI agreed to pay it $43,970.00 for construction services, plus any additional amounts for change orders made after commencement of the project. BSE alleged that it performed all work contemplated by the original agreement and all work change orders, and submitted timely payment applications and documents as required by the agreement. BSE alleged that HCI failed and refused to pay it for invoices submitted in September and November 2003 for its labor on the project. BSE claimed it was owed a balance of $46,797.73 net of lawful offsets and credits. BSE asserted causes of action that included breach of the Subcontract Agreement and quantum meruit. It also alleged violations of the Prompt Pay Act, and sought interest and attorneyâs fees. See id. §§ 2251.025(a), .028, .043. 1 HCI and Mid-Continent answered, filed a counterclaim for breach of the subcontract, and sought attorneyâs fees.
The final judgment reflects that the claims were tried before a jury, and attaches and incorporates the juryâs verdict. The district court submitted, and the jury found, that both HCI and BSE had breached the Subcontract Agreement, that neither partyâs breach was excused, but that BSE had been the first to materially breach the Subcontract Agreement. 2 *373 Predicated on these findings, the jury considered what contract damages to award HCI; it awarded zero damages. 3 Regarding BSEâs quantum meruit claim, the jury found that BSE had performed compensa-ble work for HCI but that it had come into court with unclean hands. However, the jury was more favorable to BSE regarding the Prompt Pay Act, finding for BSE on the following issue:
Did [HCI] fail to properly and timely pay BSE the appropriate share of the payment, if any, that [HCI] received from Travis County relating to the construction project and attributable to the work done by BSE as part of the Subcontract Agreement, not later than the 10th day after the date [HCI] received its payment from Travis County?
See Tex. Govât Code Ann. § 2251.022(a) (âA vendor who receives a payment from a governmental entity shall pay a subcontractor the appropriate share of the payment not later than the 10th day after the date the vendor receives the payment.â). The jury was instructed that, âIf a bona fide dispute exists between BSE and [HCI] about the services performed, then [HCI] has not failed to properly and timely pay BSE for the period during which the bona fide dispute continues.â Id. § 2251.002(a)(2).
Having found HCI liable under the Prompt Pay Act, the jury proceeded to find that the âsum of money ... [HCI] failfed] to promptly and timely pay to BSE regarding BSEâs appropriate share of the payment from Travis Countyâ was $25,381.00. Predicated on these findings, the jury further found that BSE had incurred reasonable and necessary attorneyâs fees of $60,000.
Based on the juryâs favorable Prompt Pay Act findings, BSE moved for judgment awarding it $25,381.00 in actual damages and $60,000 in attorneyâs fees. Appellees responded that BSE was not entitled to recover under the Prompt Pay Act âgiven the juryâs finding that [HCI] had no obligation to pay [BSE], either in law or in equityâ and because the Act âdoes not create an additional and independent entitlement to receive paymentâ that HCI did not otherwise owe. For these reasons, appellees moved the district court to disregard the juryâs findings of Prompt Pay Act liability and damages as immaterial. Appellees also urged the court to disregard the finding of Prompt Pay Act liability because it lacked eviden-tiary support, specifically arguing that the jury could not have concluded that a bona fide dispute regarding BSEâs âservicesâ did not exist, as necessary to find a violation, where âthere was ample evidence that BSE breached the contract by failing to man the job properly and stay on schedule ... the thrust of [HCIâs] argument regarding BSEâs prior breach.â
The district court subsequently rendered its final judgment. The court expressly incorporated the juryâs verdict without modification âfor all purposesâ and made it the basis for the judgment. 4 The *374 judgment ordered that the parties take nothing by their claims. The district court did not make an express ruling on the motion to disregard the juryâs Prompt Pay Act findings.
BSE appealed. 5
ANALYSIS
In two issues, BSE contends that the district court erred in rendering a take-nothing judgment disregarding the juryâs Prompt Pay Act findings. As a threshold matter, the parties dispute the grounds on which the district court could have impliedly disregarded the Prompt Payment Act findings. Analogizing to motions for j.n.o.v., appellees maintain that we must presume the court sustained every ground that appellees raised below for disregarding the findings and that, consequently, BSE has the appellate burden of demonstrating error as to each ground. 6 Appel-lees moved to disregard the Prompt Pay Act findings, as noted, on grounds that included lack of evidentiary support for the liability finding. Because BSE has not brought forward a reporterâs record, ap-pellees reason, we must presume that the record would have supported an implied conclusion by the district court that the finding lacked evidentiary support. See Enterprise Leasing Co. of Houston v. Barrios, 156 S.W.3d 547, 549-50 (Tex.2004). BSE responds that the record belies the inference that the district court disregarded the juryâs Prompt Pay Act liability finding for lack of evidentiary support. It emphasizes that the court explicitly incorporated the juryâs verdict without modification into its judgment, and did not explicitly disregard the Prompt Payment Act findings. Instead, BSE suggests, the court erred in âproperly interpret[ing] the juryâs verdict.â
The district court could have disregarded the juryâs Prompt Payment Act findings only if the findings had no support in the evidence or were immaterial. Southeastern Pipe Line Co. v. Tichacek, 997 S.W.2d 166, 172 (Tex.1999); Spencer v. Eagle Star, 876 S.W.2d 154, 157 (Tex.1994). The district courtâs judgment is consistent with its having impliedly disregarded the Prompt Pay Act findings as immaterial and rendered judgment based on the remaining findings. A jury question is immaterial âwhen it should not have been submitted, it calls for a finding beyond the province of the jury, such as a question of law, or when it was properly submitted but has been rendered immaterial by other findings.â Tichacek, 997 S.W.2d at 172.
We accordingly turn to whether the district court would have erred in determining that the Prompt Pay Act findings were immaterial. The parties join issue regarding the relationship between the *375 juryâs Prompt Pay Act findings and its findings that BSE committed the first material breach of the Subcontract Agreement and was not entitled to recover in quantum meruit. BSE urges that the adverse jury findings have no effect on its right to recover under the Act because the Act âcreates a separate statutory right to recover payment for monies received from the government by a vendor for services performed by a subcontractor,â and is thus an independent, alternative theory of recovery. See Alamo Cmty. College Dist. v. Browning Constr. Co., 131 S.W.3d 146, 165-67 (Tex.App.-San Antonio 2004, pet. dismâd by agr.). It also suggests that, due to timing or otherwise, the evidence supported the juryâs finding both that HCI violated the Prompt Pay Act and that BSE had committed the first material breach, observing that âthere are many ways to breach a contract that would in no way violate the Prompt Pay provisions and vice-versa.â 7
Appellees respond that the Prompt Pay Act does not create âan independent obligation to pay monies not owed under contract or in equity,â but merely provides contractors and subcontractors remedies for enforcing preexisting underlying payment obligations. They contend that the juryâs findings regarding material breach and quantum meruit negated the existence of any underlying payment obligation in this case. See Mustang Pipeline Co. v. Driver Co., 134 S.W.3d 195, 196 (Tex.2004) (âIt is a fundamental principal of contract law that when one party commits a material breach of that contract, the other party is discharged or excused from further performance.â). Consequently, they urge, the Prompt Pay Act findings were rendered immaterial by the contract and quantum meruit findings. See Tichacek, 997 S.W.2d at 172 (immaterial jury questions include questions that were âproperly submitted but ha[ve] been rendered immaterial by other findingsâ).
We consider first whether the Prompt Pay Act creates an independent entitlement to payment. Our resolution of this question turns on statutory construction. Statutory construction presents a question of law that we review de novo. E.g., State v. Shumake, 199 S.W.3d 279, 284 (Tex.2006). Our primary objective in statutory construction is to give effect to the legislatureâs intent. Id. We seek that intent âfirst and foremostâ in the statutory text. Lexington Ins. Co. v. Strayhorn, 209 S.W.3d 83, 85 (Tex.2006). We rely on the plain meaning of the text, unless a different meaning is supplied by legislative definition or is apparent from context, or unless such a construction leads to absurd results. City of Rockwall v. Hughes, 246 S.W.3d 621, 625-26 (Tex.2008) (citing Texas Depât of Transp. v. City of Sunset Valley, 146 S.W.3d 637, 642 (Tex.2004); Taylor v. Firemenâs and Policemenâs Civil Serv. Commân of City of Lubbock, 616 *376 S.W.2d 187, 189 (Tex.1981); University of Tex. Sw. Med. Ctr. v. Loutzenhiser, 140 S.W.3d 351, 356 (Tex.2004)); see Jones v. Fowler, 969 S.W.2d 429, 432 (Tex.1998) (we consider statutory language in context, not isolation). We also presume that the legislature acted with knowledge of the background law. Acker v. Texas Water Commân, 790 S.W.2d 299, 301 (Tex.1990).
The Prompt Pay Act, in relevant part, requires that â[a] vendor who receives a payment from a governmental entity shall pay a subcontractor the appropriate share of the payment not later than the 10th day after the date the vendor receives the payment.â Tex. Govât Code Ann. § 2251.022(a) (emphasis added). 8 The district courtâs Prompt Pay Act liability submission tracked this statutory language: âDid [HCI] fail to properly and timely pay BSE the appropriate share of the payment, if any, that [HCI] received from Travis County relating to the construction project and attributable to the work done by BSE as part of the Subcontract Agreement, not later than the 10th day after the date [HCI] received its payment from Travis County?â The Act further provides that the âappropriate shareâ owed by the vendor to the subcontractor âis overdue on the 11th day after the date the vendor receives the payment.â Id. § 2251.022(b). Failure to timely pay âthe appropriate share,â in turn, is the basis for the Actâs interest penalties, see id. §§ 2251.025(a), .028, and prevailing-party attorneyâs fee provision. See id. § 2251.043.
The Prompt Pay Act does not define âthe appropriate share of the paymentâ that a subcontractor is entitled to receive from a vendor. Nor does it purport to create a right to such a payment beyond merely requiring that the âappropriate shareâ (whatever that may be) be paid within ten days after the date the vendor receives the payment from the governmental entity. See id. § 2251.022(a). Reading the Act as a whole, it appears to contemplate that a subcontractorâs right to an âappropriate shareâ of payment would generally be governed by the subcontractorâs contract with the vendor. See id. §§ 2251.001(9) (â âsubcontractorâ means a person who contracts with a vendor â) (emphasis added), .052 (entitling âa subcontractor of a vendor under a contract with a governmental entity [to] suspend performance required under the contract with the vendor â under certain conditions) (emphasis added). Whatever the source of that right, we cannot conclude that it is one created by the Prompt Pay Act itself. Although the Act provides remedies for ensuring payment of âthe appropriate share,â it is not the source of that payment entitlement itself. See Chilton Ins. Co. v. Pate & Pate Enters., 930 S.W.2d 877, 886 & n. 6 (Tex.App.-San Antonio, pet. denied) (reaching the same conclusion regarding the similar statutory structure of the McGregor Act); Tex. Govât Code Ann. §§ 2253.001-.079 (West 2000 & Supp.2007).
Accordingly, we agree with appellees that the Prompt Pay Act does not âcreate[ ] an independent obligation to pay monies not otherwise owed under contract or in equityâ and that they âcannot be liable to [BSE] for failure to timely pay BSE an amount that it did not owe in the first place.â And, without the predicate of an underlying obligation to pay an âappropriate share,â it is irrelevant that, as BSE contends, the Act does not contain an ex *377 plicit âbreach-of-contractâ exception to the Actâs requirements. See Tex. Govât Code Ann. § 2251.002(2). The remedies and requirements of the Act are simply not implicated.
In contending otherwise, BSE relies extensively on Alamo Community College District v. Browning Construction Co., 131 S.W.3d at 165-67. In that case, a jury found that a community college district had breached its contract with a general contractor by withholding payments owed to the contractor, but failed to find the district violated the Prompt Pay Act by âallowing] any payment owed to [the contractor] under the Contract to become overdue.â See id. at 165-66 & n. 6. The contractor argued that the findings were in irreconcilable conflict because it was undisputed that the withheld payments constituting breach of the contract were held beyond the deadline that would constitute a Prompt Pay Act violation. See id. at 166-67. In light of the asserted conflict, the contractor argued that the court should reverse and render judgment notwithstanding the juryâs failure to find for prompt-payment damages and attorneyâs fees. See id. The court of appeals held that the two findings were not in conflict, reasoning that âthe two questions go to different causes of actionâ such that the âthe conflict is not such that one answer would establish a cause of action or defense while the other would destroy it.â Id. at 167.
Emphasizing the caseâs âdifferent causes of actionâ reference, BSE extracts from Alamo Community College District a general principle that contractual defenses have no bearing on the viability of Prompt Pay Act claims. BSE reads the case too broadly. In Alamo Community College District, a claimant was attempting to utilize a favorable finding on its breach-of-contract claim to recover damages under Prompt Pay Act, notwithstanding a juryâs adverse finding on that claim. In that context, the court of appeals held that the jury findings did not irreconcilably conflict because âthe two questions go to different causes of action.â The present case presents a converse situation-a claimant is attempting to recover under the Prompt Pay Act despite adverse contract findings. The contract findings, furthermore, have the legal effect of negating the underlying right to payment that is the predicate for Prompt Pay Act liability, thereby rendering immaterial the juryâs finding of a Prompt Pay Act violation. We agree with appellees that the rationale of Alamo Community College District is inapplicable here.
BSE suggests that the evidence was such that HCI incurred at least some Prompt Pay Act liability without violating the Subcontract Agreement and before BSE committed the first material breach of the agreement. Appellees maintain that BSEâs material breach occurred so as to excuse HCI from any payment obligation under the Subcontract Agreement that could possibly have been the predicate for Prompt Pay Act liability. Absent a reporterâs record, we simply do not know what the evidence actually showed. We are bound to presume that the evidence supported the district courtâs judgment. See Enterprise Leasing Co. of Houston, 156 S.W.3d at 549-50. Consequently, we must presume that the evidence showed BSEâs material breach of the Subcontract Agreement, which excused HCIâs payment obligations under the agreement, occurred so as to excuse it from any payment obligations that could have given rise to Prompt Pay Act liability.
On this record, the district court did not err in impliedly concluding that the juryâs Prompt Pay Act findings were immaterial. Accordingly, it did not err in disregarding *378 the findings and in rendering judgment, based on the remaining findings, that BSE take nothing. We overrule BSEâs issues and affirm the judgment of the district court.
. BSE also asserted certain claims against Keith Hutchison, alleged to be HCIâs president and owner. These claims were severed prior to trial.
. The jury was instructed that in determining whether a breach is "material,â it should consider (1) âthe extent to which the injured party will be deprived of the benefit which it reasonably expectedâ; (2) "the extent to which the injured party can be adequately *373 compensated for the part of that benefit of which it will be deprivedâ; (3) "the extent to which the party failing to perform or to offer to perform will suffer forfeitureâ; (4) âthe likelihood that the party failing to perform or to offer to perform will cure its failure, taking account of the circumstances including any reasonable assurancesâ; and (5) "the extent to which the behavior of the party failing to perform or to offer to perform comports with standards of good faith and fair dealing.â
. Because it had found against BSE on its contract claim, the jury did not reach a counterpart issue inquiring as to BSEâs contract damages.
. The judgment stated, in relevant part:
*374 At the conclusion of the evidence, the Court submitted the cause to the jury on written questions. The Charge of the Court, including jury questions and the verdict of the jury is incorporated by reference in this Final Judgment for all purposes.
IT IS THEREFORE ORDERED, ADJUDGED and DECREED that the parties take nothing by way of those causes of action asserted by them against any other party herein, and all such claims and causes of action shall be dismissed with prejudice.
. HCI also filed what it styled a "cross-notice of appealâ giving notice of âits intent to raise cross-points to Plaintiff's appeal.â For this reason, HCI appears in the caption as a cross-appellant, although it has not brought issues seeking to alter the district courtâs judgment.
. See Gallas v. Car Biz, Inc., 914 S.W.2d 592, 593 (Tex.App.-Dallas 1995, writ denied); American Produce & Vegetable Co. v. J.D. Campisiâs Italian Restaurant, 533 S.W.2d 380, 385 (Tex.Civ.App.-Tyler 1975, writ refâd n.r.e.).
. Throughout its briefing, BSE frames its arguments in terms of whether a conflict existed between the juryâs Prompt Pay Act findings and its contract and quantum meruit findings. BSE argues that the district court was obligated to reconcile the âconflictingâ findings so as to give effect to all. However, these assertions ultimately turn on whether the Prompt Pay Act findings were rendered immaterial by the jury's other findings. See Bender v. Southern Pac. Transp. Co., 600 S.W.2d 257, 260 (Tex.1980).
BSE also contends that the district court should have given effect to all of the jury findings because appellees waived any âconflictâ complaint by failing to raise it before the jury was discharged. See Tex.R. Civ. P. 295; Spring Window Fashions Div. v. Blind Maker, Inc., 184 S.W.3d 840, 867 (Tex.App.-Austin 2006, pet. granted, remand by agr.). BSE has failed to bring forward a record demonstrating error on this ground.
. There is no dispute that HCI was a "vendorâ and BSE a "subcontractorâ for purposes of the Act. See Tex. Govât Code Ann. § 2251.001(9) (West Supp.2007) (" âSubcontractorâ means a person who contracts with a vendor.â), (10) (" âVendorâ means a person who supplies goods or a service to a governmental entity or another person directed by the entity.â).