In Re Luminant Generation Company LLC. NRG Texas Power LLC, Calpine Corp., ExGen Handley Power, LLC N/K/A Constellation Handley Power LLC v. the State of Texas
Date Filed2023-12-14
Docket01-23-00097-CV
Cited0 times
StatusPublished
Full Opinion (html_with_citations)
Opinion issued December 14, 2023
In The
Court of Appeals
For The
First District of Texas
ââââââââââââ
NO. 01-23-00097-CV
NO. 01-23-00102-CV
NO. 01-23-00103-CV
NO. 01-23-00392-CV
NO. 01-23-00393-CV
âââââââââââ
IN RE LUMINANT GENERATION COMPANY LLC, NRG TEXAS
POWER LLC, CALPINE CORP., EXGEN HANDLEY POWER, LLC N/K/A
CONSTELLATION HANDLEY POWER LLC, ET AL., Relators
Original Proceeding on Petition for Writ of Mandamus
OPINION
The underlying multidistrict litigation (âMDLâ) arises from Winter Storm
Uri that hit Texas in February 2021 and the resulting outages of electricity that
crippled much of the state. Hundreds of retail electricity customers sued hundreds
of entities involved in the electricity market in Texasâincluding natural gas
providers, power generators and co-generators (collectively âwholesale power
generatorsâ),1 transmission utilities, public power companies, retail electric
providers, and the Electric Reliability Council of Texas (âERCOTâ)âfor damages
sustained due to the loss of electrical power.2
This mandamus proceeding concerns the retail customersâ claims against the
wholesale power generators for negligence, gross negligence, and negligent
undertaking, and their assertions of nuisance. The wholesale power generators, the
relators, argue that the claims brought by the retail customers, the real parties in
interest, have no basis in law or fact and that the pretrial MDL court, the
respondent, abused its discretion by denying their Rule 91a motions to dismiss
these claims.
We agree and conditionally grant mandamus relief.
Background
In February 2021, Winter Storm Uri hit Texas. It swept bone chilling Arctic
air and frigid precipitation across the state. For nearly a week, temperatures
1
Power generators, including co-generators, generate electricity that is intended to
be sold at wholesale. See TEX. UTIL. CODE § 31.002(10). A separate âretail
electric providerâ then sells the electricity to retail customers in this state. Id.
§ 31.002(17).
2
The Supreme Court of Texas recently held that ERCOT is protected from suit by
sovereign immunity. See CPS Energy v. Elec. Reliability Council of Tex., 671
S.W.3d 605, 621, 629 (Tex. 2023).
2
plunged to record lowsâwith many areas experiencing prolonged temperatures in
the teens, and even below zero. For many Texans, the extreme cold was
accompanied by heavy accumulations of snow and ice. It has been noted that
Winter Storm Uri was âcatastrophicâ and âmay have been the most severe winter
weather event in the recorded history of Texas.â See CPS Energy v. Elec.
Reliability Council of Tex., 671 SW.3d 605, 612 (Tex. 2023); see also Luminant Energy Co. v. Pub. Util. Commân of Tex.,665 S.W.3d 166
, 174 (Tex. App.â
Austin 2023, pet. granted).
The prolonged and extreme cold temperatures along with the heavy snow
and ice led to an unprecedented demand for electricity and resulting power
blackouts across the state. CPS Energy, 671 SW.3d at 612; Luminant, 665 S.W.3d
at 173â76. It has been estimated that approximately 4.5 million households and
businesses lost electrical power for days at a time during some of the coldest days
ever recorded in the stateâs history. See Luminant, 665 S.W.3d at 175. This
litigation followed.
As noted above, hundreds of retail customers across Texas sued hundreds of
entities involved in the Texas electricity market for damages sustained due to the
resulting electrical outages. The MDL Panel established a pretrial MDL court to
3
streamline the various lawsuits.3 The pretrial MDL court ordered the parties to
select five bellwether suits to proceed first with dispositive motions and discovery.
The five bellwether suits that were chosen have dozens of retail customers as
plaintiffs and hundreds of defendants, including over 200 wholesale power
generators.4 With respect to the wholesale power generators, the retail customers
alleged negligence, gross negligence, negligent undertaking, nuisance, tortious
interference with contract, civil conspiracy, concert of action, and indivisible injury
against them.5
The wholesale power generators filed motions to dismiss under Rule 91a.6
See TEX. R. CIV. P. 91a. After conducting a two-day hearing, the pretrial MDL
3
TEX. R. JUD. ADMIN 13. The MDL panel selected the Honorable Sylvia A.
Matthews to serve as the pretrial judge.
4
The five bellwether suits, which were transferred into the MDL court for pretrial
proceedings, Master Cause Number 2021-41903, include: Randy Turner,
Individually and as Personal Representative of the Estate of Terrill Turner a/k/a
Terrell Turner, Deceased, et al v. NRG Texas Power, et ux, cause no. 2021-24797,
pending in the 164th District Court of Harris County; Bernadine Edwards,
Individually, as Next of Kin of Lauralene Butler Jackson, Deceased, and as
Wrongful Death Beneficiary v. ERCOT, Inc. et al, cause no. 2021-84438, pending
in the 281st District Court of Harris County; Ernest Peterman, Individually and on
Behalf of the Estate of Ella Peterman v. ERCOT et al, cause no. 2021-18532,
pending in the 164th District Court of Harris County; Valerie Daniels v.
Centerpoint Energy, Inc. et al, cause no. 2021-18513, pending in the 215th
District Court of Harris County; and All America Ins. Co. et al v. ERCOT et al,
cause no. 2022-13706, pending in the 281st District Court of Harris County.
5
All of the bellwether suits asserted nuisance except All America Insurance.
6
After the retail customers amended their pleadings, the wholesale power
generators filed amended Rule 91a motions. See TEX. R. CIV. P. 91a. These are
the live pleadings governing this mandamus proceeding.
4
court signed orders granting in part and denying in part the Rule 91a motions.
Without elaboration, the pretrial MDL court dismissed the causes of action against
the wholesale power generators for tortious interference with contract, civil
conspiracy, concert of action, and indivisible injuryâand allowed the claims and
assertions for negligence, gross negligence, negligent undertaking, and nuisance to
proceed.
The wholesale power generators in the five bellwether suits now seek
mandamus relief from the denial in part of their Rule 91a motions.7 See TEX. R.
JUD. ADMIN. 13.9(b) (authorizing review by court of appeals of order or judgment
from MDL pretrial court).
Standard of Review
Mandamus relief is appropriate when a trial court abuses its discretion in
denying a Rule 91a motion to dismiss. In re Farmers Tex. Cnty. Mut. Ins. Co., 621
S.W.3d 261, 266 (Tex. 2021) (orig. proceeding). A trial court abuses its discretion when it fails to correctly analyze or apply the law. In re Cerberus Cap. Mgmt. L.P.,164 S.W.3d 379, 382
(Tex. 2005) (orig. proceeding). âA trial court has no
7
Three of the five mandamus petitions were filed in this Court (Nos. 01-23-00097-
CV, 01-23-00102-CV, and 01-23-00103-CV). The other two were filed with our
sister court and then transferred to our Court, to promote judicial efficiency, under
our Local Rule 2 (Nos. 01-23-00392-CV, 01-23-00393-CV). See 1st TEX. APP.
(Houston) LOC. R. 2 (permitting transfer of cases between First and Fourteenth
Court of Appeals in MDL). Because all five mandamus petitions are nearly
identical, we address them together in this opinion. Id.
5
discretion in determining what the law is or applying the law to the facts, even
when the law is unsettled.â In re Prudential Ins. Co., 148 S.W.3d 124, 135(Tex. 2004) (orig. proceeding). Mandamus relief will issue only when the moving party has no adequate remedy by appeal. See In re Essex Ins. Co.,450 S.W.3d 524, 528
(Tex. 2014) (orig. proceeding).
Rule 91a allows a party to move for early dismissal of a cause of action on
the ground that it has âno basis in law or fact.â See Bethel v. Quilling, Selander,
Lownds, Winslett & Moser, P.C., 595 S.W.3d 651, 654 (Tex. 2020) (quoting TEX. R. CIV. P. 91a.1). A cause of action has no basis in law if the allegations, taken as true, together with any inferences reasonably drawn from them, do not entitle the claimant to the relief sought.Id.
A cause of action has no basis in fact if no reasonable person could believe the facts as pleaded.Id.
We review a trial courtâs decision on a Rule 91a motion de novo. See id.This is so because the availability of a remedy under the facts alleged is a question of law and the ruleâs factual-plausibility standard is akin to a legal sufficiency review. City of Dallas v. Sanchez,494 S.W.3d 722, 724
(Tex. 2016).
In conducting our review, we cannot consider any evidence. See In re First
Reserve Mgmt., L.P., 671 S.W.3d 653, 659 (Tex. 2023) (orig. proceeding). Rather,
we must make our determination based solely on the substance of the Rule 91a
6
motion, the plaintiffâs live pleadings, and any pleading exhibits permitted by Rule
59. See id. at 660.
Negligence
The retail electricity customers alleged that the wholesale power generators
had continuing duties to: (1) weatherize and maintain their facilities and equipment
to prevent the loss of electrical power; (2) assure that they had adequately trained
staff to prevent the loss of electrical power; (3) provide reserve electricity to the
ERCOT power grid; (4) provide electricity to the ERCOT power grid; and
(5) supply electricity to the ERCOT power grid to assure its reliability.
Taken together and construed liberally, as we must, the retail customers
principally allege that the wholesale power generators had an overarching duty to
continuously supply electricity to the power grid, and thus to all retail customers.
They further assert that preceding and during Winter Storm Uri, the wholesale
power generators breached that duty in various ways that can be summarized as
follows: (1) failing to winterize and maintain its equipment; (2) failing to supply
electricity to the ERCOT power grid by not securing adequate fuel supply and
reserve energy; (3) failing to properly supervise and train workers to ensure against
generator outages that occurred during Winter Storm Uri; (4) failing to ensure that
their facilities and equipment would be exempted from ordered blackouts by filing
appropriate forms and/or taking other necessary or reasonable actions; and
7
(5) failing to avoid more widespread power blackouts by enrolling in ERCOTâs
emergency load-shedding program, which caused the retail customers to lose
electricity when ERCOT activated the program.
This asserted duty forms the basis of the retail customersâ cause of action for
negligence against the wholesale power generators, including their assertion of
negligent nuisance.8 It is therefore the beginning point, and crux, of our analysis.
A. Legal Duty
âThe threshold inquiry in a negligence case is duty.â Elephant Ins. Co. v.
Kenyon, 644 S.W.3d 137, 145 (Tex. 2022) (quoting Greater Hous. Transp. Co. v. Phillips,801 S.W.2d 523, 525
(Tex. 1990)). This is a âquestion of law for the court to decide from the facts surrounding the occurrence in question.âId.
at 144â 45 (quoting Phillips,801 S.W.2d at 525
). This inquiry encompasses several questions of law; namely, the existence, scope, and elements of such a duty.Id.
Here, the initial controlling question before us is whether the wholesale power generators owed a duty to the retail customers to continuously supply them with electricity under the factual allegations presented. Seeid.
8
â[T]he term ânuisanceâ refers not to a cause of action . . . but to the legal injury . . .
that gives rise to the cause of action.â Crosstex N. Tex. Pipeline, L.P. v. Gardiner,
505 S.W.3d 580, 604 (Tex. 2016). â[A] claim [for negligent nuisance] is governed
by ordinary negligence principles. The elements the plaintiff must prove are âthe
existence of a legal duty, a breach of that duty, and damages proximately causes
by the breach.ââ Id. at 607.
8
âA duty is âa legally enforceable obligation to conform to a particular
standard of conductââ and can be assumed by contract or imposed by law. Helbing
v. Hunt, 402 S.W.3d 699, 702(Tex. App.âHouston [1st Dist.] 2012, pet. denied); see, e.g., ElliottâWilliams Co. v. Diaz,9 S.W.3d 801
, 803â04 (Tex. 1999). Here,
the retail customers do not allege any duty imposed by contract.9 Consequently,
we must determine whether the retail customers pleaded a recognized legal duty
owed to them by the wholesale power generators to continuously supply
electricity.
To determine whether a defendant owes a particular legal duty to a claimant,
a court must first ascertain whether the law has recognized such a duty under the
same or similar circumstances. Elephant Ins., 644 S.W.3d at 144â45 (explaining
that duty inquiry involves evaluating factual situation presented âin the broader
context of similarly situated actorsâ (quoting Pagayon v. Exxon Mobil Corp., 536
S.W.3d 499, 504 (Tex. 2017)). For example, if a special relationship exists between the parties under a statute or legal precedent that gives rise to a legal duty, that duty exists in the case presented as a matter of law and âthe duty analysis ends there.â Golden Spread Council, Inc. v. Akins,926 S.W.2d 287, 292
(Tex. 1996); see Tex. Home Mgmt., Inc. v. Peavy,89 S.W.3d 30
, 33â34 (Tex. 2002)
9
The wholesale power generators had bilateral contracts with purchasers of
wholesale energy, including the retail electric providers, but not with any retail
customers.
9
(recognizing that relationship between parties is factor to consider in determining
whether duty exists). That, however, is not the case here. The retail customers
also did not plead any facts to support the existence of any special relationship
with the wholesale power generators. See, e.g., Wakefield v. Bank of Am., N.A., No.
14-16-00580-CV, 2018 WL 456721, at *5 (Tex. App.âHouston [14th Dist.] Jan.
18, 2018, no pet.) (mem. op.).
1. Existing Legal Duty
For much of the Twentieth Century, electric utilities in Texas were
authorized by law to operate as tightly regulated, vertically integrated monopolies.
See Luminant, 665 S.W.3d at 170. In any given geographic area of Texas, just a
single, vertically integrated electric utility was authorized to provide electricity to
every retail customer in the area. Id.
Under that regime, being vertically integrated meant that an electric utility
controlled every principal component of how electricity actually reached each
retail customer in its areaâ(1) the generation of electrical power; (2) the
transmission of that electrical power on high-voltage lines over long distances; and
(3) the distribution of electricity over shorter distances to the ultimate retail
customer. Id. at 171; Oncor Elec. Delivery Co. v. Pub. Util. Commân of Tex., 507
S.W.3d 706, 708â09 (Tex. 2017).
10
All of that changed on January 1, 2002. That is when Texas implemented a
new, fully-competitive retail market for electricity.10 Under this new regime, every
retail customer chooses its own provider of electricity and the rates are set by
competition rather than by regulation. TEX. UTIL. CODE § 31.002(4); see Luminant,
665 S.W.3d at 171; Oncor Elec. Delivery, 507 S.W.3d at 711â12. This meant that
every vertically integrated electric utility had to âunbundleâ into three separate
units: (1) a power generation company that generates electricity to be sold at
wholesale; (2) a retail electric provider; and (3) a transmission and distribution
utility that actually provides electricity to the retail customers. See TEX. UTIL.
CODE § 39.051(b); see also id. § 31.002(10), (17), (19).
The end-result is that wholesale power generators are no longer public
electric utilities. See id. §§ 11.004(1), 31.002(2), (5). Wholesale power generators
do not, and cannot, own or operate the transmission and distribution facilities that
carry electricity to the retail customers. See id. § 31.002(10). They also do not, and
cannot, enter into agreements with retail customers to sell them electricity. See id.
§ 31.002(6)(C), (16)â(17).
Instead, wholesale power generators solely produce âelectricity that is
intended to be sold at wholesaleâ to retail electric providers, who in turn sell the
10
See TEX. UTIL. CODE § 39.001(b)(1) (âThe legislature finds that it is in the public
interest to: implement on January 1, 2002, a competitive retail electric market that
allows each retail customer to choose the customerâs provider of electricity and
that encourages full and fair competition among all providers of electricity.â).
11
electricity directly to retail customers. See id. § 31.002(10)(A), (17). The
electricity enters a sprawling electrical grid managed and operated by ERCOT,11
and then transmission utilities distribute the electricity to retail customers. See id.
§ 31.002(19).
Importantly for our analysis here, wholesale power generators are now
statutorily precluded by the Legislature from having any direct relationship with
retail customers of electricity. See, e.g., id. §§ 31.002(10), (16), (17), 39.051.
Under this statutory framework, wholesale power generators can have no legal
relationship with retail customers as a matter of law. See id.; see also Hous. Area
Safety Council, Inc. v. Mendez, 671 S.W.3d 580, 588 (Tex. 2023) (noting that petitioners had no direct relationship with employee in finding no duty); Guerra v. Regions Bank,188 S.W.3d 744, 747
(Tex. App.âTyler 2006, no pet.) (holding no
duty as matter of law owed to plaintiff because plaintiff was not customer and had
no relationship to bank).
Indeed, we are not aware of any controlling Texas authority under this
current statutory scheme, and the retail customers have cited none, that holds a
wholesale power generator owes a legal duty to continuously supply electricity to
11
This self-contained grid covers approximately 70 percent of the State of Texas
geographically and serves nearly 90 percent of the stateâs electricity customers.
See Luminant Energy Co. v. Pub. Util. Commân of Tex., 665 S.W.3d 166, 171â72
(Tex. App.âAustin 2023, pet. granted).
12
the grid and thus ultimately to retail customersâwho must contract with retail
electric providers to purchase their electricity.
Instead, the retail customers rely upon In re Centerpoint Energy Houston
Electric, LLC, 629 S.W.3d 149, 161â63 (Tex. 2021), Cura-Cruz v. Centerpoint Energy Houston Electric LLC,522 S.W.3d 565, 572
(Tex. App.âHouston [14th Dist.] 2017, pet. denied), and Bearden v. Lyntegar Electric Co-op., Inc.,454 S.W.2d 885, 887
(Tex. App.âAmarillo 1970, no writ), for the proposition that
wholesale power generators have a common law duty to provide reliable
electricity. But these cases are distinguishable for several reasons.
First, Bearden was decided pre-deregulation. Since 2001, ERCOT is the
entity that has the statutory responsibility âto ensure the reliability and adequacyâ
of the Texas power grid. See CPS Energy, 671 S.W.3d at 611; see also TEX. UTIL.
CODE § 39.151. Second, none of these cases hold that a wholesale power generator
under the current statutory regime has a duty to continuously supply electricity to
the grid and thus to retail customers.
The retail customers also contend that our Legislature has codified common
law duties owed to them by the wholesale power generators. Relying on sections
186.001 and 186.002 of the Utilities Code, the retail customers maintain that a
wholesale power generator is a âpublic utilityâ and, as such, owe them a duty âto
maintain continuous and adequate service at all times.â See TEX. UTIL. CODE
13
§§ 186.001â.002. Significantly, these statutory provisions were enacted pre-
deregulation. See Act of May 8, 1997, 75th Leg., R.S., ch. 166, § 1, sec. 186.001â
.002, 1999 Tex. Gen. Laws 998, 999 (codified at TEX. UTIL CODE §§ 186.001â
.002). Section 186.001 defines a âpublic utilityâ as a âprivate corporation that does
business in this state and has the right of eminent domain . . . engaged in the
business of generating, transmitting, or distributing electric energy to the public.â
TEX. UTIL. CODE § 186.001 (emphasis added).
Section 186.002(b) then provides that â[a] public utility is dedicated to
public service [and] [t]he primary duty of a public utility . . . is to maintain
continuous and adequate service at all times to protect the safety and health of the
public against the danger inherent in the interruption of service.â Id. § 186.002(b);
see also id. §§ 11.004 (defining âpublic utilityâ or âutilityâ to mean an âelectric
utilityâ as defined in section 31.002 (emphasis added)).
But the more recently enacted provisions in section 31.002 of the Utilities
Code, that are part of the current statutory framework, state that the term âelectric
utilityâ âdoes not include . . . a power generation company.â TEX. UTIL. CODE
§ 31.002(6) (emphasis added) (Act of May 27, 1999, 76th Leg., R.S., ch. 405, § 11,
sec. 31.002, 1999 Tex. Gen. Laws 2547, 2548). To the extent that these statutes
conflict, the most recently enacted statute prevails. See TEX. GOVâT CODE
§ 311.025 (â[I]f statutes enacted at the same or different sessions of the legislature
14
are irreconcilable, the statute latest in date of enactment prevails.â). Here, the most
recently enacted and prevailing statute is section 31.002 of the Utilities Code.
Even if sections 186.001 and 186.002 of the Utilities Code could be
applicable here, they still would not support the retail customersâ argument. This
is because we are not aware of any Texas authority, and the retail customers have
cited none, that currently gives the wholesale power generators the power of
eminent domainâwhich is necessary to trigger these statutes. See TEX. UTIL. CODE
§§ 186.001â.002.
In rewriting the electricity market in Texas, the Legislature could have
codified the retail customersâ asserted duty of continuous electricity on the part of
wholesale power generators into law. But it chose not to do so. And we may not
impose our own judicial meaning on these statutes by adding words and creating
relationships and duties that are not contained in the plain language of the statutes.
See Silguero v. CSL Plasma, Inc., 579 S.W.3d 53, 59(Tex. 2019). Indeed, âjudicial policy preferences should play no role in statutory interpretation.â See McLane Champions, LLV v. Hous. Baseball Partners LLC,671 S.W.3d 907
, 918
(Tex. 2023).
Accordingly, based on the current state of our jurisprudence in Texas and the
plain language of the controlling deregulatory statutes, we conclude that Texas
does not currently recognize a legal duty owed by wholesale power generators to
15
retail customers to provide continuous electricity to the electric grid, and ultimately
to the retail customers, under the allegations pleaded here by the retail customers.
We must therefore determine whether, under the MDL pretrial courtâs orders,
Texas caselaw should recognize this duty.
2. Creation of a New Legal Duty
The retail customers maintain that even if the Legislature and Texas courts
have not recognized a duty owed by wholesale power generators to provide
continuous electricity to the electric grid, and thus ultimately to them, that their
pleadings are sufficient to establish such a duty. âWhen a duty has not [already]
been recognized in particular circumstances, the question [for the Court] is whether
one should be.â Elephant Ins., 644 S.W.3d at 145 (quoting Pagayon, 536 S.W.3d
at 506).
Our supreme court has instructed that courts must weigh what are often
referred to as the âPhillips factorsâ in determining whether a duty exists and what
it is. See id. at 149. Specifically, we must weigh âthe risk, foreseeability, and
likelihood of injury against the social utility of the actorâs conduct, the magnitude
of the burden of guarding against the injury, and the consequences of placing the
burden on the defendant.ââ Id. (citing Humble Sand & Gravel, Inc. v. Gomez, 146
S.W.3d 170, 182 (Tex. 2004)). We may also consider whether one party had
16
superior knowledge of the risk or right to control the actor who caused the harm.
Id.
In determining whether to impose a duty in a defined class of cases, we do
not determine whether the facts show a breach of an applicable standard of care.
Id. at 145. Instead, the duty inquiry involves evaluating the factual situation
presented âin the broader context of similarly situated actors.â Id. In this context,
â[c]ourts may not hold people to very general duties of exercising ordinary care in
all circumstances.â Id. Rather, Texas law requires courts to be specific in
determining the existence, scope, and elements of any new legal duties. Id.
(quoting Pagayon, 536 S.W.3d at 506).
Here, under the facts alleged, the relevant risk of injury is that multiple
wholesale power generators cannot provide electricity to the ERCOT power grid,
potentially leaving retail customers without electricity. We note that wholesale
power generators have some control over whether they can generate electricity by
how they maintain their equipment. See Luminant, 665 S.W.3d at 170 (noting that
âgeneration and consumption must at all times be maintained in near-perfect
balanceâ or âelse a total grid collapseâ). And the Legislature has given ERCOT
oversight and enforcement authority to ensure a reliable and safe electrical grid and
that electricity production is accurately accounted for among the generators. See
TEX. UTIL. CODE § 39.151(a)â(j).
17
But, even if the wholesale power generators had perfect maintenance and
complete control over their production of electricity, the retail customersâ
pleadings acknowledge that it is âERCOT [who also] manages the delivery of that
electricityâ and that âERCOTâs function is âpower dispatch,â or the scheduling and
managing of how electricity will flow through the network.â Thus, as the retail
customers have pleaded, and the current statutory framework makes clear,
wholesale power generators have no actual control over the electricity they
produce once it leaves their generation facility. See Luminant, 665 S.W.3d at 170
(noting that âconstraints on transmission can result in grid congestion, and power
generated in one geographic region may not be available to consumers in
anotherâ).
The retail customers have also pleaded that the wholesale power generators
send electricity to the ERCOT power grid and then transmission utilities transport
the electricity, which ultimately results in delivery to the retail customers. And, in
the event of load-shed orders, âtransmission owners then decide where to cut
power and how to rotate outages.â12 Thus, the retail customers have also
acknowledged that the wholesale power generators neither have control over how
12
A load-shed event occurs when ERCOT âdirects operators of the transmission
system to reduce electricity consumption by involuntarily disconnecting customers
from the grid.â RWE Renewables Americas, LLC v. Pub. Util. Commân of Tex.,
669 S.W.3d 566, 570â71 (Tex. App.âAustin 2023, pet. granted); see also TEX.
UTIL. CODE § 38.076.
18
transmission utilities distribute electricity, nor control over ERCOTâwhich
âmonitors the flow of energy from more than 680 generation units to more than 26
million customers over more than 46,500 miles of transmission lines, all while
balancing generation with load to maintain a system frequency of 60 Hertz.â
Luminant, 665 S.W.3d at 172; City of San Antonio v. Pub. Util. Commân of Tex.,
506 S.W.3d 630, 635 (Tex. App.âEl Paso 2016, no pet.).
Moreover, the retail customers could not plead that they have any direct
relationship with the wholesale power generators in purchasing electricityâ
because the Legislature has precluded any such relationship as a matter of law. See
TEX. UTIL. CODE §§ 31.002(10), (16), (17), 39.051; see also Mendez, 671 S.W.3d
at 588 (noting that petitioners had no direct relationship with employee in finding
no duty); Peavy, 89 S.W.3d at 33â34 (recognizing that relationship between parties
is factor to consider in determining whether duty exists).
In conducting this duty analysis, foreseeability is a dominant consideration.
See Phillips, 801 S.W.2d at 525. But foreseeability alone is not enough to create a duty. City of Waco v. Kirwan,298 S.W.3d 618, 624
(Tex. 2009). âForeseeability does not necessarily equate to predictability.â Univ. of Tex. M.D. Anderson Cancer Ctr. v. McKenzie,578 S.W.3d 506, 519
(Tex. 2019). âRather, âforeseeabilityâ means that the actor should have reasonably anticipated the dangers that his negligent conduct created for others.âId.
19
Although foreseeability of the âgeneral dangerâ is a key part of the inquiry,
we must also evaluate the foreseeability of the specific danger at handânamely,
âwhether the injury to the particular plaintiff or one similarly situated could be
anticipated.â Elephant Ins., 644 S.W.3d at 149 (quoting Bos v. Smith, 556 S.W.3d
293, 303(Tex. 2018)). But âforeseeability requires more than someone, viewing the facts in retrospect, theorizing an extraordinary sequence of events whereby defendantâs conduct brings about the injury.âId.
at 150 (quoting Doe v. Boys Clubs of Greater Dall., Inc.,907 S.W.3d 472
, 478 (Tex. 1995)).
Here, the wholesale power generators did not dispute below that not
providing continuous electricity could foreseeably cause harm, and we
acknowledge that multiple wholesale power generators being unable to produce
electricity during a winter storm or otherwise would foreseeably result in a general
danger to retail customers. But, just as the wholesale power generators could
foresee extreme weather impacting their ability to generate electricity, retail
customers were also in as good a position to contemporaneously assess their
physical safety and economic interests and to act. See Elephant Ins., 644 S.W.3d at
150.
In that regard, the retail customersâ pleadings mention previous weather
events that resulted in the loss of electricity, such as a 1989 cold weather event, a
2011 winter storm, and the 2014 polar vortex. Accordingly, just as the wholesale
20
power generators could foresee that extreme weather could limit their production
of electricity, the retail customers could also foresee from these previous extreme-
weather events that they could experience outages. See Elephant Ins., 644 S.W.3d
144â45. This is not uncommon in Texas during an extreme-weather event. Thus,
the risks associated with extreme weather in our state and losing electricity was,
and is, equally foreseeable to the retail customers.
We may also consider the existing statutory regulatory framework in the
Phillips-factor analysis. See, e.g., Mission Petroleum Carriers, Inc. v. Solomon,
106 S.W.3d 705, 714â15 (Tex. 2003) (declining to impose duty after â[a]pplying
the Phillips risk/utility factorsâ because, in part, âcomprehensive statutory and
regulatory schemeâ reduces risk of harm). The retail customers acknowledge that
the Legislature created a comprehensive statutory framework to oversee and
manage the Texas electrical market, which went into effect in 2002. See TEX. UTIL.
CODE § 39.001.
As described above, this framework delegates oversight to creating a reliable
and safe electrical grid to ERCOT. See id. § 39.151(a). ERCOT has authority from
the Public Utility Commission (âPUCâ)13 to âadopt and enforce rules relating to
the reliability of the regional electrical network.â See id. § 39.151(d). Market
participants, including the wholesale power generators in these proceedings, âare
13
See TEX. UTIL. CODE §§ 12.001 et seq.
21
statutorily required to abide by all rules and procedures established by [ERCOT],
and their failure to do so could result in a penalty.â CPS Energy, 671 S.W.3d at
616â17. It is the Legislatureâs prerogative to create this statutory framework,
which may not completely eliminate the risk from electrical-grid outages, but it
meaningfully reduces the risk of harm. See, e.g., Mission Petroleum, 106 S.W.3d at
714â15 (declining to impose duty after â[a]pplying the Phillips risk/utility factorsâ
because, in part, âcomprehensive statutory and regulatory schemeâ reduces risk of
harm).
We next weigh the aforementioned factors against the social utility of the
wholesale power generatorsâ conduct, the magnitude of the burden of guarding
against the injury, and the consequences of placing the burden on the defendant.
See Elephant Ins., 644 S.W.3d at 145.
The social utility of the wholesale power generators in the state is
indisputably of great benefit. Retail customers and commercial and industrial
businesses depend upon having reliable electricity, especially during extreme
weather. The burden of guarding against the injury that retail customers
experience by not having electricity during extreme weather is not entirely clear.
But the retail customers list several burdens that they believe the wholesale
power generators would need to undertake, such as weatherizing equipment,
adequately staffing generation facilities during extreme weather, and verifying
22
adequate fuel to power generators, among others. After Winter Storm Uri, the
Texas Legislature sought to address these same concerns by passing legislation that
requires weatherization of wholesale power generatorsâ assets and giving ERCOT
authority to inspect for compliance. See CPS Energy, 671 S.W.3d at 628; see, e.g.,
TEX. UTIL. CODE § 35.0021 (providing that PUC will require each power
generation company to prepare generation assets to provide adequate electric
generation service during weather emergency). And, in doing so, the Legislature
did not create any new or corresponding duties on wholesale power generators
owed to retail customers. See TEX. UTIL. CODE § 35.0021.
We also must consider the consequences and burden of placing the new duty
urged by the retail customers on the wholesale power generators. If we created a
new duty for wholesale power generators to supply continuous electricity to the
grid, and ultimately to the retail customers, we would upend the carefully-crafted
framework that the Legislature has implemented. And legislative silence on this
new asserted duty does not give us the power to legislate from the bench. See Tex.
Med. Res., LLP v. Molina Healthcare of Tex., Inc., 659 S.W.3d 424, 432 (Tex.
2023); see also TEX. CONST. art. II, § 1 (dividing powers of state government
among âthree distinct departmentsâ and providing that their respective powers are
mutually exclusive).
23
In any event, the wholesale power generators cannot produce electricity in a
continuous manner but only when electricity is needed. See Luminant, 665 S.W.3d
at 170 (noting that âmost electricity generation must occur concurrently with
consumptionâ). Moreover, the supply of electricity must be âmaintained in near-
perfect balance at an equilibrium point of 60 Hertzâ or the electric grid may fail or
cause damage to grid equipment. Id. Accordingly, the new duty that the retail
customers assert for wholesale power generators, providing continuous electricity,
is essentially unworkable from a practical and statutory standpoint.14
Finally, if we created a new duty for wholesale power generators to supply
continuous electricity to retail customers, the potential burden of liability of
wholesale power generators to every retail customer would be statewide.
Considering that extreme weather is a normal occurrence in Texas, such a duty
would likely have significant consequences by increasing the price of electricity as
well as discouraging long-term investment in wholesale power generators in Texas.
In sum, and as referenced above, we believe that imposing any such new
duty on wholesale power generators is more appropriate for the Legislature,
âwhich is accountable to the people through the political process,â15 and who can
14
Indeed, different generators rely on different sources of power to produce
electricity that they do not control. In addition to natural gas, wind generation
requires wind which is not always available. And solar powered generation
requires sunlight which is limited by cloud cover.
15
See CPS Energy, 671 S.W.3d at 627.
24
âbalance [the] competing factors apart from the common law.â16 Our conclusion is
mandated by the separation of powers provision in our state constitution. See TEX.
CONST. art. II, § 1. We must respect the Legislatureâs policy choices in enacting
the current statutory framework for the electricity marketplace in Texas. Indeed,
the core responsibility of our judicial branch of government is to interpret and
apply the law consistently and predictably based on precedent, not to create it by
judicial fiat. Id.; see also Mouton v. Hous. Indep. Sch. Dist., No. 01-22-00205-CV,
2023 WL 4065602, at *4 (Tex. App.âHouston [1st Dist.] June 20, 2023, pet. denied) (mem. op.). As an intermediate appellate court, we are particularly cognizant of these principles. See Emscor Mfg. Inc. v. Alliance Ins. Grp.,879 S.W.2d 894, 910
(Tex. App.âHouston [14th Dist.] 1994, writ denied) (âIt is not
for an intermediate appellate court to create new causes of action.â)
We therefore decline to create a new negligence-based duty on the wholesale
power generators to continuously generate electricity for the retail customers in
these proceedings. To the extent that the MDL pretrial court recognized and
16
See Hous. Area Safety Council, Inc. v. Mendez, 671 S.W.3d 580, 590 (Tex. 2023);
see, e.g., Mission Petroleum Carriers, Inc. v. Solomon, 106 S.W.3d 705, 714â15
(Tex. 2003) (declining to impose duty after â[a]pplying the Phillips risk/utility
factorsâ because, in part, âcomprehensive statutory and regulatory schemeâ
reduces risk of harm); see J.P. Morgan Chase Bank v. Tex. Cont. Carpet, Inc., 302
S.W.3d 515, 535 (Tex. App.âAustin 2009, no pet.) (noting reluctance as
intermediate court in recognizing new common-law duty with no existence in
established law); Nichols v. McKinney, 553 S.W.3d 523, 528â29 (Tex. App.â
Waco 2018, pet. denied) (declining invitation to impose new duty).
25
imposed such a new duty on the wholesale power generators, it clearly abused its
discretion. Accordingly, we hold, for all of these reasons, that the MDL pretrial
court clearly abused its discretion in denying this aspect of the wholesale power
generatorsâ Rule 91a motions and in not dismissing the retail customersâ claims for
negligence and assertions for negligent nuisance because they have no basis in law
or fact as alleged.17
Negligent Undertaking
In their second issue, the wholesale power generators argue that the retail
customersâ claims for negligent undertaking, which are pled in the alternative to
negligence, also have no basis in law or fact because they âall involve purported
failures to take various reliability measures.â
The retail customers pleaded that the âPower Generator Defendants are
liable to Plaintiffs, as consumers of the ERCOT grid, for their negligent
performance of multiple voluntary undertakings.â The retail customers then
generally alleged that â[e]ach Power Generator Defendant undertook, either
17
Because the retail customersâ negligence-based claims fail on the threshold
element of legal duty, it is unnecessary for us to address the other elements of
negligence or their assertion of negligent nuisance. See TEX. R. APP. P. 47.1;
Nichols, 553 S.W.3d at 532 (negligent nuisance fails in absence of legal duty).
For the same reason, it is also unnecessary for us to address the retail customersâ
claim for gross negligence because, without a legal duty, the claim of gross
negligence also has no basis in law or fact as alleged. See RT Realty, L.P. v. Tex.
Util. Elec. Co., 181 S.W.3d 905, 915 (Tex. App.âDallas 2006, no pet.) (âWithout
a duty, there can be no negligence and no gross negligence.â); see also TEX. R.
CIV. P. 91a; TEX. R. APP. P. 47.1.
26
gratuitously or for consideration, to render services to Plaintiffs, which each Power
Generator Defendant recognized or should have recognized as necessary for the
protection of the Plaintiffs and their property.â
After that, the retail customers pleaded a series of alleged undertakings by
the wholesale power generators that can be summarized as follows: (1) undertaking
to winterize and maintain its equipment; (2) providing generating resources to the
grid for its registered rated load; (3) securing adequate fuel supply and choosing to
source critical natural gas supplies; (4) generating into the grid when instructed to
come online by ERCOT; (5) hiring and/or staffing an adequate amount of workers
before and during Winter Storm Uri to ensure against generator outages and
derates, as well as to ensure the power generating facility and equipment was
operating at maximum generation capacity; (6) ensuring that its natural gas
suppliersâ were exempted from ordered blackouts by filing appropriate forms
and/or taking other necessary or reasonable actions; and (7) warning plaintiffs
and/or ERCOT prior to Winter Storm Uri about the likelihood of outages and
derates in its equipment and facilities.
Our supreme court has recently explained that, â[u]nder Texas law, a
defendant who undertakes to render services that it knows or should know are
necessary for the protection of the otherâs person or things must generally exercise
reasonable care in performing the undertaking.â First Reserve, 671 S.W.3d at 660
27
(internal quotations omitted). âThe critical inquiry concerning the duty element of
a negligent-undertaking theory is whether a defendant acted in a way that requires
the imposition of a duty where one otherwise would not exist.â Id. (quoting Nall v.
Plunkett, 404 S.W.3d 552, 555 (Tex. 2013)).
The supreme court in First Reserve also importantly emphasized that â[this]
duty is only implicated when the complained-of undertaking is an affirmative
course of action; liability for negligent undertaking cannot be predicated on an
omission.â Id. (quoting Elephant Ins., 644 S.W.3d at 152 & n. 80 (â[N]ot giving a
safety warning is an omission, not an undertaking.â)).
Here, essentially every omission pleaded by the retail customers to support
their negligence cause of action is also alleged granularly as an affirmative
undertaking to support their negligent-undertaking claim. It is settled that a party
may plead multiple allegations in the alternative against a defendant, and they may
even conflict. See Low v. Henry, 221 S.W.3d 609, 615(Tex. 2007); see also TEX. R. CIV. P. 48. But Rule 48 does not permit a party to plead âin the alternativeâ a claim that has no basis in law or fact. See Low,221 S.W.3d at 615
. âThat is simply not permitted by Texas law.âId.
And artful pleading does not change the true nature and gravamen of such claims. See In re Breviloba, LLC,650 S.W.3d 508
, 512 (Tex. 2022) (orig. proceeding); Yamada v. Friend,335 S.W.3d 192, 196
(Tex.
2010).
28
By initially pleading their negligent undertaking allegations as negligent
omissions, the retail customers have acknowledged that their complained-of
undertakings are not affirmative courses of actionâand their artful pleading
cannot recast those alleged omissions to be otherwise. See Breviloba, 650 S.W.3d
at 512; Yamada, 335 S.W.3d at 196. Because the retail customers rely on purported omissions and failures to act to support their negligent-undertaking claims, they have not made factual allegations constituting a cause of action for negligent undertaking against the wholesale power generators with a basis in law. See First Reserve, 671 S.W.3d at 660, 663; see also Garcia v. Kellogg Brown & Root Servs., Inc., No. 01-19-00319-CV,2020 WL 3820426
, at *10 (Tex. App.â
Houston [1st Dist.] July 7, 2020, no pet.) (mem. op.) (â[F]ailures to act do not
create a negligent-undertaking duty.â).
The retail customers also argue that the wholesale power generatorsâ action
in generating electricity for the grid can be an affirmative course of action to
support their negligent-undertaking claim.
As detailed above, the retail customers pleaded that the wholesale power
generators failed to continuously provide electricity to them during Winter Storm
Uri due to various purported omissions and failures to act (i.e., failures to
winterize, failures to source adequate fuel, and failures to adequately staff). They
also pleaded that the wholesale power generators âundertook, either gratuitously or
29
for consideration, to render services to Plaintiffs.â But the retail customers did not
plead that the complained-of undertaking by the wholesale power generators was
the production of electricity during Winter Storm Uri. Indeed, such an allegation
would be nonsensical. See First Reserve, 671 S.W.3d at 660 (â[L]iability for
negligent undertaking cannot be predicated on an omission.â); Garcia, 2020 WL
3820426, at *10 (â[F]ailures to act do not create a negligent-undertaking duty.â).
Nevertheless, the retail customers argue that their general assertion that
â[e]ach Power Generator failed to exercise reasonable care while rendering such
servicesâ is enough to bridge the substantive gap for their negligent-undertaking
claims. Under the current statutory framework, the only service that wholesale
power generators can provide is the generation of electricity that is sold to retail
electric providers. See TEX. UTIL. CODE § 31.002(10)(A). And the wholesale
power generators can have no direct relationship with any retail customer. Id. The
retail customers must purchase their electricity through separate contracts with a
retail electric provider. Id. § 31.002(17).
As a result, this argument by the retail customers is plainly based on the
wholesale power generators agreements with retail electric providers to generate
and sell electricity. See id. § 31.002(10)(A). According to the retail customers, the
contractual obligations owed by wholesale power generators to the retail electric
30
providers can spring into a broad negligent undertaking duty owed by wholesale
power generators to all retail customers to continuously produce electricity.
But the retail customers have not directed us to any Texas authority, and we
are aware of none, that transforms the contractual duties owed by wholesale power
generators to the retail electric providers under the current statutory framework
into tort duties owed by the wholesale power generators to the third-party retail
customers.18 And the retail customers have not pleaded the existence of any
special relationship or any third party beneficiary status conferred to them from the
agreements between the wholesale power generators and the retail electric
providers.
Accordingly, this argument by the retail customers is simply a bridge too far.
We therefore conclude that the retail customersâ negligent undertaking against the
wholesale power generators also has no basis in law or fact as alleged and that the
trial court clearly abused its discretion in denying the Rule 91a motions on this
claim.19
18
See, e.g., Sw. Bell Tel. Co. v. DeLanney, 809 S.W.2d 493, 494â95 (Tex. 1991)
(claim for negligence could not be based on allegation that party failed to
adequately perform contractâsuch claim sounded in contract, not tort); Kuentz v.
Cole Sys. Grp., Inc., 541 S.W.3d 208, 219 (Tex. App.âHouston [14th Dist.] 2017,
no pet.) (contractual obligations owed by pre-employment background screening
company to car dealership client for background screening services did not impose
generalized tort duty owed to third-party victim of criminal act).
19
In light of concluding that the negligence and negligent-undertaking claims have
no basis in law or fact, it is unnecessary to address substantively whether the
31
Adequate Remedy by Appeal
Having concluded that the pretrial court abused its discretion in failing to
dismiss the retail customersâ claims for negligence, gross negligence, negligent
undertaking, and for nuisance, under Rule 91a because they have no basis in law
under the facts alleged, we now turn to the second requirement for mandamus
reliefâwhether the wholesale power generators have an adequate remedy by
appeal. See Essex, 450 S.W.3d at 528.
âThe adequacy of an appellate remedy must be determined by balancing the
benefits of mandamus review against the detriments.â Id.(citing Prudential,148 S.W.3d at 136
). In balancing these interests, the Texas Supreme Court has explained that âmandamus relief is appropriate to âspare private parties and the public the time and money utterly wasted enduring eventual reversal of improperly conducted proceedings.ââ In re John G. & Marie Stella Kenedy Memâl Found.,315 S.W.3d 519, 523
(Tex. 2010) (orig. proceeding) (quoting Prudential, 148 S.W.3d
pretrial court properly denied the Rule 91a motions on the retail customersâ
remaining assertions of nuisance. See TEX. R. APP. P. 47.1. As our supreme court
has instructed, nuisance is not a claim or cause of actionâbut a type of legal
injury. See Crosstex, 505 S.W.3d at 588, 594â95. Because the four bellwether
petitions asserting nuisance lack any surviving claim or cause of action against the
wholesale power generators, all of the assertions of nuisance against them
(including for negligent nuisance discussed above), likewise fails, as a matter of
law. See Bolton v. Fisher, 528 S.W.3d 770, 778 (Tex. App.âTexarkana 2017, pet.
denied) (concluding that trial court properly granted summary judgment on
nuisance when plaintiffâs petition did not include cause of action); Amini v.
Spicewood Springs Animal Hosp., LLC, No. 03-18-00272-CV, 2019 WL 5793115,
at *10 (Tex. App.âAustin Nov. 7, 2019, no pet.) (mem. op.).
32
at 136). When a trial court abuses its discretion in denying a Rule 91a motion, this
test is satisfied and mandamus relief is appropriate. See Farmers, 621 S.W.3d at
266; In re Hous. Specialty Ins. Co., 569 S.W.3d 138, 142 (Tex. 2019) (orig.
proceeding).
Accordingly, in light of our holdings above that the retail customersâ
pleadings allege causes of actions that have no basis in law or fact and should have
been dismissed under Rule 91a, we further conclude that mandamus relief is
appropriate here to spare the parties and the public the time and money spent on
fatally flawed proceedings. See Essex, 450 S.W.3d at 528.
Conclusion
We conditionally grant mandamus relief. We direct the respondent to grant
the wholesale power generatorsâ Rule 91a motions to dismiss the retail customersâ
claims for negligence, gross negligence, negligent undertaking, and the assertions
of nuisance in these five bellwether petitions. Our writ will issue only if the
respondent fails to comply in accordance with this opinion.
Terry Adams
Chief Justice
Panel consists of Chief Justice Adams and Justices Landau and Hightower.
33