Aerie Point v. Vorsteveld Farm
CourtVermont Superior Court
Date FiledNovember 17, 2026
Docket72-4-20 ancv
StatusUnknown
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
7ermont Superior Court
Filed 07/0 26
Addison
STATE OF VERMONT
SUPERIOR COURT CIVIL DIVISION
ADDISON UNIT Docket No. 72-4-20 Ancv
AERIE POINT HOLDINGS, LLC,
Plaintiff,
VORSTEVELD FARM, LLP,
Defendant
Decision: Part #2 of Motion to Demonstrate Compliance (Motion #42)
The Merits Decision of March 28, 2022 in this case resulted in an Injunction in which the
court found that Vorsteveld Farm LLC ("Farm'') had committed trespass and nuisance against its
downslope neighbor Aerie Point Holdings LLC ("Aerie Point") by increasing the volume and
velocity of water discharged into two streams that crossed Aerie Point land. This occurred as a
result of the installation of an extensive tile drainage system on the Farm's upslope land resulting
in the discharge of concentrated water from 17 discharge points from drain tiles in a manner that
caused damage in a number of ways, including erosion of land and deposits of sediment and
phosphorous.
The resulting Judgment was an Injunction that issued as follows:
"Defendant is enjoined from allowing water, and any particles it carries, from flowing
from the discharge points of Defendant's drain tile system into the public ditches and
culverts westerly of Defendant's land on Arnold Bay Road between Adams Ferry Road
and Pease Road."
In Decisions dated January 8, 2024, and September 13, 2024, the Farm was held in
contempt for failure to comply with the Injunction. The court imposed sanctions in the form of
daily fines but suspended them until November 16, 2024, to give the Farm time to come into
compliance.
On November 14, 2024 the Farm filed this motion claiming compliance. An initial
evidentiary hearing was held on April 24 and 25, 2025. Present at that hearing was Gerard
Vorsteveld for the Farm with attorneys Claudine C. Safar and Miles M. Stafford. Vicki and
Dennis Hopper were present for Aerie Point with attorney Merrill E. Bent.
The court issued a partial decision dated May 1, 2025 (Part #1 of rulings on the Motion).
It found in Part #1 that the Farm had taken steps to comply and had halted the ongoing flow of
water and particles that were damaging Aerie Point property at least on a temporary basis by
plugging the drain tiles at their discharge points, and thus the court suspended daily fines as of
November 14, 2024. Nevertheless, based on prior undisputed testimony in the case, both expert
and non-expert, the court found that the method of compliance might only be a temporary fix,
1
such that the required standard of compliance, clear and convincing evidence, was not met for an
injunction designed for permanence. 1 The court determined that the Motion would remain
pending to give the Farm the opportunity to meet the clear and convincing standard with
additional evidence.
A follow-up evidentiary hearing was held on June 17, 2026, one and a half years after the
plugging of the discharge outlets. Present in person was Gerard Vorsteveld on behalf of the Farm
with attorneys Claudine C. Safar and Miles M. Stafford. Dennis Hopper was present remotely on
behalf of Aerie Point, represented by attorney Merrill E. Bent in person.
Prior to the hearing, on May 29, 2026, the parties and attorneys engaged in a joint
inspection of the respective properties to observe conditions on the ground, and they filed a joint
statement of stipulated facts. The findings of fact below are based on both the stipulated facts and
the court’s evaluation of the testimony and exhibits introduced at the hearing.
Findings of Fact
The court hereby incorporates all of the Findings of Fact set forth in Part #1 of the
Decision on the Motion (#42) filed May 1, 2025 as well as all of the Findings of Fact in the
Decisions on the Motion for Contempt filed January 8, 2024 and September 12, 2024, as if fully
set forth herein.
In the Decision of May 1, 2025, based on the evidence at the April 2025 hearing (Part #1
of the present motion), the court found that the Farm had complied with the Judgment “on at
least a temporary basis but has not proved meaningful compliance with a permanent Injunction
by clear and convincing evidence.” (May 1, 2025 Decision, page 9.) “This is because, prior to
capping the tile drains, both parties in this case testified that plugging the tile drains was not
recommended because it would result in blowouts, and if it was done, it should be done at
multiple locations along the pipes, not just at the end.” Id. at 7.
Gerard Vorsteveld testified, and the court finds, that since the April 2025 hearing, he has
checked the capped ends every two weeks. He also checked the fields approximately every six
months. Otherwise, there is no evidence of any changes made to the system between the hearing
in April 2025 and the Part #2 hearing in June of 2026.
The parties and their attorneys were accompanied on the May 29, 2026 site visit by Aerie
Point’s expert, Dr. Harold Van Es, a professor of soil science, and the Farm’s expert, Richard
Hamlin, an engineer. The site visit included a visual inspection of fifteen tile drain outlets, and
in-field locations near the outlets.
Based on the site visit, Dr. Van Es, Plaintiff’s expert, made the following conclusions
which both Aerie Point and the Farm accept as findings of fact:
1
See legal standards for contempt proceedings in the Decision of January 8, 2024, pages 6-7 and Decision
of September 13, 2024, pages 9-10.
2
a. All tile drains have been effectively plugged. No drain water discharge was observed
in any of the plugged tile drains. Modest ground seepage is observed around some
(but not all) of the plugged tile drains. Seepage is presently not sufficient in amount to
result in significant off-site impacts.
b. Holes were identified in the field in the vicinity of Tile Drain 5A and12/13.
c. The holes are currently modest in number and size (observed approximately 7 holes,
each 5-10” in diameter) and have no known off-site impact at this time.
d. Other conservation practices (including grassed waterways, sediment retention basins,
and cover crops) are effectively implemented on site, at present.
e. The grassed waterways the Farm has planted and maintained in convergence areas are
having their beneficial effect.
f. Surface water retention structures have been effectively implemented in the lower
parts of the Arnold Bay and Exline fields.
g. Cereal rye cover crop was also effectively established in the Arnold Bay and Exline
Fields in fall 2025, with ameliorative effect.
h. Water flowing from the Vorsteveld Farm property onto the Aerie Point property
appears to be reduced in quantity and intensity.
i. Observations on April 22, 2026 (one week after a heavy rainfall) showed only modest
flow upslope of the Arnold Bay Road culverts.
j. No signs of high velocity flow such as erosion or vegetation flattening or damage
were observed at any of the three culverts leading onto Aerie Point along Arnold Bay
Road.
k. Low flow was observed at the culvert under Adams Ferry Road.
The remaining disagreement between the parties is what caused the holes, and the
implication of those holes for the future of how well the capping of the tile drains will prevent
damaging impact on Aerie Point land.
Gerard Vorsteveld thinks that the holes were made when the crop planting machine
crossed the field and kicked up stones, leaving holes. He also opined that they were made by
animals. The court does not find either of these explanations consistent with all the evidence
about them. The holes are all located toward the bottom of the sloped fields, within 30 feet of the
base of the slope along Arnold Bay Road and near the toeline pipe that runs perpendicular to the
drain lines and receives water from them. There is no evidence that there are such holes further
upslope.
Some of the holes are 3-5” deep and some are as much as 15” deep. They are all perfectly
round openings with the grass around the edges matted down, neatly enclosing the round
opening. Some have water in them. There is no indication of a machine having dragged stones
along the dirt near them, and no indication that animals have dug them out, leaving nearby loose
dirt displaced from digging. Moreover, it would be unusual for animals to dig holes as close
together as some of the holes are.
The Farm’s expert, Richard Hamlin is an engineer who works with water movement in
connection with his engineering work. His experience with tile drains was as an engineer on one
3
project. His opinion is that due to the expected behavior of the water table underground in the
fields as a whole, water would not be moving downhill and causing pressure that would
contribute to the development of such holes. He acknowledges the possibility that if a coupling
between two sections of tile drains fails, water and soil surrounding the failed coupling could go
down and enter the drain pipe, presumably creating a depression in the soil above. However his
primary opinion is that the water table in the entire fields is stable and above the level of the
drain pipes and exerting no downward pressure. He accepts Gerard Vorsteveld’s idea that the
holes are attributable to stones or animals. He particularly disagrees with a description of the
cause of the holes as “blowouts,” as there is no evidence of soil having erupted out of the holes
and scattering soil on the surrounding ground.
Aerie Point’s expert, Dr. Harold Van Es, has advanced degrees in soil physics and has
authored journal articles about soil hydrology and drainage. He also has experience with
installing drain tiles at the Cornell farm which is located across Lake Champlain from the subject
property and has similar soils to those on the Farm. His opinion is that what he calls “blowouts”
do not necessarily involve eruptions of water and soil and scattering of soil, especially in the type
of soil at the Farm, and that blowouts, as he labels them, are the cause of the holes. His
description of blowouts is similar to what Mr. Hamlin described: they occur when soil sinks
down into the drain pipe, such as when a coupling fails, and water that is under pressure moves
upward into the holes. To him it is telling that this is occurring at the base of the slope, where
water is most likely to be under pressure at the bottom of the sloping fields, and he does not
agree with Mr. Hamlin’s opinion that water is not under pressure in the hillside fields. His
opinion is that water upslope continues to flow downhill underground, exerting pressure as it
descends, and that this pressure contributes to blowouts.
The holes are all in some proximity to the toeline, and the experts differed about whether
the toeline was perforated or not and whether perforations would or would not affect
development of blowouts. The toeline is underground and the reality is unknown, but the court
finds the opinion of Dr. Van Es credible that blowouts as he describes them could occur with or
without perforation in the toeline. They can also occur along the pipelines and in the intervals
between lines of drain tiles, which is where some of the holes appear to be. The court finds the
explanation of Dr. Van Es of the cause of the holes to be credible.
It is clear that over a year and a half after the tile drains were capped at the discharge
outlets, as well as after the successful establishment of grassy waterways and sediment retention
basins in the fields and effective cover crops –all having beneficial mitigation effects on
concentration of downslope water flow--damaging water and sediment is not currently flowing
through the discharge outlets in the tile drain system into the ditch along Arnold Bay Road and
through the three culverts to Aerie Point land. There is currently no erosion effect or other
damage to Aerie Point property. The evidence shows that the steps taken have been effective
through two winters and spring melts and some heavy rains.
Whether there is a risk that deterioration of the drain tile system in the future could cause
water and sediment flow to increase and again flow onto Aerie Point land is a reasonable concern
expressed by Aerie Point, given prior testimony in the case and the development of the holes. Yet
4
the evidence does not currently support a conclusion that the system will inevitably fail causing
damage to Aerie Point land.
Dr. Van Es believes that additional blowouts could occur on an expanded basis in the
future. The evidence previously given in this case was that if plugging the system at the
discharge points were to be done, plugging should be done at multiple locations throughout the
fields in addition to those at the discharge points to minimize blowouts that could affect Aerie
Point land. This has not been done to date. Dr. Van Es also recommends additional land
management measures, such as planting particular crops that are beneficial, to protect against
damage to Aerie Point land.
The evidence is that the plugging of the discharge outlets that was done, while it has been
effective to date, is most likely not a one-time final solution to the problem, but that ongoing
vigilance will be required with a reasonable possibility that other measures will need to be taken
over time. As this court has previously made clear and the Farm’s counsel acknowledged in oral
argument, what the Farm has done to date does not absolve it from the obligation of on-going
compliance with the permanent Injunction in the future. However, the passage of time and the
current condition of both properties does not support a conclusion that the prior contempt is
ongoing.
Conclusions
The Farm has made a sufficient showing by clear and convincing evidence that
compliance actions were undertaken that have been effective over the last year and a half.
Consequently, the court concludes that the Farm has shown current compliance by the required
standard, and the fines previously established are now terminated. Attorney fees incurred by
Aerie Point to date are the consequence of not only the contempt but the failure to establish
compliance by clear and convincing evidence until now. They are the obligation of the Farm.
Order
Based on the foregoing:
1. The Farm is not currently in contempt of its obligation under the Injunction.
2. Fines previously imposed and suspended temporarily are now terminated.
3. Plaintiff Aerie Point is entitled to attorney fees in connection with the above Motion.
Any request for fees incurred to date, not previously addressed, must be filed by July
21, 2026 and must be supported by time and billing records If such a request is filed,
Defendant Farm may file any objection within 14 days.
Electronically signed July 7, 2026 pursuant to V.R.E.F. 9 (d).
Mary Miles Teachout
Superior Judge (Ret.), Specially Assigned
5