Raitz Enterprises Inc., D/B/A U.S. Sand and Gravel v. Javier Sanchez, Jr.
CourtTexas Court of Appeals, 11th District (Eastland)
Date FiledAugust 20, 2026
Docket11-25-00033-CV
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
Opinion filed July 30, 2026
In The
Eleventh Court of Appeals
__________
No. 11-25-00033-CV
__________
RAITZ ENTERPRISES, INC., D/B/A U.S. SAND AND GRAVEL,
Appellant
V.
JAVIER SANCHEZ, JR., Appellee
On Appeal from the County Court at Law
Erath County, Texas
Trial Court Cause No. CV09507
MEMORANDUM OPINION
This appeal concerns a contractual dispute between a general contractor and
its subcontractor. Appellant, Raitz Enterprises, Inc., d/b/a U.S. Sand and Gravel (the
general contractor), engaged Appellee, Javier Sanchez, Jr. (the subcontractor), to
perform concrete work on three separate construction projects. When problems
ensued with one of the projects, Raitz refused to pay Sanchez for work he performed
on all three projects; Sanchez then sued Raitz for breach of contract, quantum meruit,
and unjust enrichment. After a jury trial, the jury found that Raitz failed to comply
with the parties’ agreements, awarded Sanchez $26,640 in damages, and found
reasonable and necessary attorney’s fees for each of the contracts. The trial court
rendered judgment on the jury’s verdicts and awarded Sanchez $87,417.50 in
attorney’s fees.
On appeal, Raitz raises five issues: (1) the evidence is legally and factually
insufficient to support the jury’s liability and damages findings; (2) the trial court
abused its discretion when it excluded certain testimony proffered by Casey Raitz;
(3) the trial court abused its discretion when it refused to submit Raitz’s requested
jury instruction; (4) the trial court’s denial of Raitz’s request to amend its pleadings
was an abuse of discretion; and (5) the evidence is legally and factually insufficient
to support the award of attorney’s fees.
We affirm the trial court’s judgment and hold that: (1) the evidence is
sufficient to support the jury’s liability and damages findings, because the jury found
that Raitz failed to comply with the agreements and Sanchez did not; (2) the evidence
is sufficient to support the jury’s award of attorney’s fees; and (3) the trial court did
not err or abuse its discretion when it (a) excluded Casey Raitz’s proffered testimony
and (b) denied Raitz’s requested jury instruction and pleading amendment.
I. Factual Background
This dispute centers on three concrete jobs that Raitz hired Sanchez to
complete: the Woodlands project, the Slab project, and the Iredell project. The
concrete for each job was supplied by Big State Concrete, which Casey Raitz, the
owner of Raitz Enterprises and U.S. Sand & Gravel, also partially owned. Sanchez
had completed another concrete job for Raitz in the past in which Raitz supplied the
concrete and paid Sanchez.
2
Big State Concrete used volumetric trucks, which mix the ingredients that are
required to make concrete—sand, gravel, water, and cement—inside an auger that
is mounted on a truck. Volumetric trucks differ from “barrel-type” cement trucks
that are more typically seen on the road, which carry concrete that is pre-mixed at a
concrete plant and loaded into a truck for delivery to a job site.
A. The Woodlands Project
Raitz hired Sanchez to complete the Woodlands project—a large job for
which Raitz agreed to pay Sanchez $38,540. Sanchez was not paid any amount until
this project was about three-quarters completed, at which point he informed Raitz
that he would cease working on the project until he was paid; Raitz then paid him
one-half of the agreed price: $19,270. Sanchez testified that Raitz also agreed to
reimburse him for one-half of the rental cost—$1,745—of a pump truck. Although
a text message from Raitz’s representative stated “Casey probably isn’t going to
approve half on the pump,” Sanchez testified that the reimbursement was approved
in a subsequent phone call. After the completion of the Woodlands project, even
though Sanchez requested payment multiple times and did not receive any
complaints about the quality of the work that he performed, Raitz never paid him the
second half of the price for this project, nor did he reimburse him for one-half of the
pump truck rental.
B. The Slab Project
While Sanchez was working on the Woodlands project, Raitz hired him to
complete another job, the Slab project, at a facility for U.S. Sand & Gravel. The
parties did not formally discuss or agree on a price for this job. Sanchez testified
that he performed preparatory work for the Slab project, such as digging and forming
the soil, installing footing, and removing large rocks. After the preparatory work
was completed, the remaining tasks were to set rebar and pour concrete. Sanchez
testified that he estimated the value of the work that he completed on the Slab project
3
to be $4,950, based on a rate of $110 per hour for over eleven hours of work
performed by him and three hired workers. However, Sanchez alleged in his petition
that he only performed five hours of work on the Slab project, at a rate of $110 per
hour.
Casey testified that he discussed the Slab project with Sanchez, but ultimately
Sanchez did not perform any work on this project and Casey paid someone else to
do it. Casey agreed that multiple texts between he, Raitz’s project manager Kylee
Fields, and Sanchez indicated that Sanchez worked on the Slab project, but he
asserted that because Sanchez never provided him with a formal estimate, it was
never confirmed that Sanchez would work on the Slab project. But he also agreed
that, after the Iredell pour and amidst the ensuing dispute, he texted Sanchez, “Go
ahead and stop eastland yard [w]e are going another route,” which referred to the
Slab project. Consequently, Sanchez never set rebar or poured the concrete for the
Slab project, nor was he paid for the preparatory work that he had completed there.
C. The Iredell Project
Before Sanchez could complete the Slab project, Raitz asked him to pause
work on it and focus on another job—the Iredell project. Sanchez quoted a price of
$10,250 to Raitz for the Iredell project. Sanchez and five workers excavated the site
and completed preparatory work. However, problems ensued when they began to
pour the slab.
To pour the concrete that was mixed in these volumetric trucks, the Iredell
project required a rented pump truck that could pump the concrete out of the
volumetric truck through a hose. When they began to pour the Iredell slab, the
concrete mix began clogging the pump. Sanchez testified that the supply of gravel
and cement—ingredients required to mix concrete—provided by Raitz kept running
out. He testified that he informed Raitz over the phone that something was wrong,
but he was instructed to continue pouring the concrete.
4
Sanchez testified that these problems required the volumetric truck to leave
the jobsite multiple times to refill the missing ingredients. These delays affected the
quality of the concrete that had already been poured; Sanchez testified that the
optimal way in which to pour a concrete slab is to do it all at one time because if one
pours new, wet concrete next to concrete that has begun to set, a seam—sometimes
called a “cold joint”—is created that can lead to cracks in the slab. Multiple “cold
joints” occurred at the Iredell job because of the delays caused by the concrete mix
problems.
Rick Rodriguez, Jr., the operations manager for PumpCrete, the concrete
pump company, told Sanchez over the phone that the concrete mix was defective.
Later in the day, Rodriguez sent Sanchez a video of a clog in the pump; Rodriguez
could be heard in the video explaining that there was no sand in the mix, which was
clogging the pump. Rodriguez advised Sanchez to check the concrete mix because
of these problems.
Rodriguez testified that volumetric trucks tend to jam and have issues.
According to Rodriguez, he had worked in the concrete business for eleven years
and had completed over a thousand jobs that involved concrete pours. At the Iredell
project, the pump truck struggled to pump because the volumetric trucks were
jamming and the auger could not mix the concrete ingredients correctly. Rodriguez
testified that the mixture was either too rocky or too sandy; this required the
supervisor for the concrete supply company to adjust and readjust the mixture ratios
multiple times. The volumetric trucks also ran out of ingredients—sand and
gravel—which required the trucks to leave the jobsite to be refilled, as well as to be
cleared of the jamming problems. Because of these issues with the mix, the pump
truck had to stop operating and cleared multiple times. These were consistent
problems throughout the pour.
5
Eventually, the pump truck became entirely jammed and disabled; PumpCrete
left the jobsite to clean out the pipes of their pump truck before the concrete set
inside the pipes. This process delayed the pour for approximately four hours. While
cleaning out the pump truck, Rodriguez video recorded the concrete mix that came
out of the pipes and sent the video to Sanchez. Rodriguez testified that because the
mix was defective, it did not set in the pump truck pipes in the way they had expected
and instead appeared to be a large unhardened “clump” that never bound. This was
a further indication, according to Rodriguez, that the concrete mixture was defective;
it should have set hours before the pump truck was cleaned.
Rodriguez testified that the crumbling curbs were the result of the defective
concrete mix. He further testified that the defects in the Iredell job were not the kind
of flaws that could be attributed to the pourer, like Sanchez. Rodriguez stated it was
“more than likely that’s [a result of] bad mix . . . unless somebody purposely and
neglectfully decided just to shape it with their hand and leave it . . . I’ve never seen
concrete do that that’s properly mixed.” He agreed that a bad finish or removing the
forms too soon could also cause defects in the slab. He also agreed that problems
could arise from not having enough workers on a job. But Rodriguez testified that
he did not believe these issues arose from removing the forms too early because such
defects would likely run the length of the form, and the defects in the Iredell slab
appeared to be more scattered.
Casey denied that the issues on the Iredell project were because of a bad mix
of concrete. He testified that, although he was not present during the pour, it is not
possible for a mix to be deficient because his volumetric trucks are computer-
operated and preprogrammed, and a bad mix would have triggered an automatic
shutdown of a truck. He testified that the trucks’ computers also printed a report of
the precise mix components, but he was not in possession of those reports because
he had sold his interest in Big State Concrete. When Sanchez texted Casey the video
6
from Rodriguez that showed the “clump” that came out of the pump truck from the
Iredell project, Casey responded: “That’s not what went in concrete truck the entire
time. Cannot blame this on concrete from one little part they pulled out. I have
every ticket with [exact] pounds of everything that got poured.” Casey agreed that
any machine can operate incorrectly and testified that although he saw the video that
Rodriguez sent of the large “clump” that came out of the pump truck, it was
impossible for the volumetric trucks to produce a “clump” of sand that large.
D. The Dispute
Sanchez stated in a text message to Raitz that the Iredell slab was defective
because the concrete mix was bad and the waiting time on the concrete trucks was
problematic during the pour. Sanchez attempted to repair the Iredell slab by grinding
down parts of it with a rented grinder. He suggested the use of a two-inch overlay
of pea gravel as another repair option. He also offered to demolish the slab so Raitz
could restart the project from scratch, stating, “[N]o charge the least I can do s[]ince
I left a bad finish on that slab.” Throughout the contentious aftermath of the Iredell
project, Sanchez also continued to request payment for the Woodlands project.
Raitz refused to pay Sanchez the balance for the Woodlands project or for any
other project. Casey texted Sanchez that Raitz had hired another company to repair
the Iredell slab, that Sanchez was “on the hook” for the slab, and that Raitz would
not pay Sanchez anything until the Iredell slab was repaired and the cost of repairs
would be deducted from the balances due Sanchez.
After another refusal by Raitz to pay the Woodlands balance, Sanchez replied:
“I’m not charging you iradell [sic] i know you your not paying me for that job I get it
I lost money there it is what it is that’s why I didn’t mention it in the first place . . .
my concern is on my money that is owed to me on the [Woodlands] job.” Sanchez
testified that he made those statements because he needed to be paid for the
Woodlands project, he did not believe that any argument with Casey about fault
7
would be productive, and he wanted to preserve a business relationship with Raitz.
Sanchez testified that, despite those statements, he did not leave a bad finish on the
Iredell slab, and he did the best he could with the bad concrete mix that Raitz
provided. He believed that he did not have much leverage to negotiate with Raitz
since Raitz insisted that Sanchez, not the concrete mix, was to blame for the defects
in the Iredell slab.
A few days after the Iredell pour, Raitz paid Sanchez $5,125—one-half of the
quoted price for the Iredell project. At that point, according to Sanchez, Raitz still
owed, but refused to pay him:
• $19,270, the remaining balance for the Woodlands project;
• $5,125, the remaining balance for the Iredell project;
• reimbursement for one-half the rental payment to PumpCrete during the
Woodlands project; and
• the value of the preparatory work Sanchez performed on the Slab project.
Sanchez sued Raitz for breach of contract, quantum meruit, and unjust
enrichment. Raitz counterclaimed for breach of contract and breach of implied
warranty of good and workmanlike services. At trial, the trial court excluded Raitz’s
proffered evidence—Casey’s testimony—about the cost of remedial repairs for the
Iredell slab, because the issue required expert testimony and Raitz did not designate
Casey as an expert witness on the subject. Raitz made an offer of proof outside the
presence of the jury in which Casey testified that, based on his firsthand knowledge
and experience, the Iredell slab was deficient, and it was necessary to grind down
the slab and apply an epoxy finish to correct and complete the job. Casey further
testified that the cost charged by the other contractors he hired to complete these
repairs was reasonable and necessary.
The jury found that Raitz failed to comply with the Woodlands agreement and
awarded Sanchez damages of $19,225, the balance of the agreed price, as well as
8
$1,745 as reimbursement for one-half of the rental payment due to PumpCrete. The
jury also found that Sanchez performed compensable work for Raitz on the Slab
project and awarded him $550 as the reasonable value of the compensable work.
Finally, the jury found that Raitz, not Sanchez, failed to comply with the Iredell
agreement and awarded Sanchez $5,120 for the balance of the agreed price for the
Iredell agreement. The jury also awarded attorney’s fees to Sanchez for the three
projects. The trial court signed a final judgment awarding Sanchez $26,640 in total
damages and $87,417.50 in attorney’s fees.
II. Analysis
A. The Evidence is Sufficient to Support the Jury’s Verdicts
In its first issue, Raitz claims that the evidence is legally and factually
insufficient to support the jury’s liability and damages findings because, under the
doctrine of substantial performance, the burden was on Sanchez to establish the cost
of remedial repairs, and Sanchez offered no such evidence. Raitz also asserts that
the jury’s finding that Sanchez did not breach the Iredell agreement is against the
great weight and preponderance of the evidence because Sanchez admitted that he
was responsible for the defects in the Iredell slab.
We hold that the doctrine of substantial performance is inapplicable to this
case because the jury found that Sanchez did not breach the Iredell agreement, and
therefore Sanchez bore no burden to establish the cost of remedial repairs. Tacon
Mech. Contractors, Inc. v. Grant Sheet Metal, Inc., 889 S.W.2d 666, 670 (Tex.
App.—Houston [14th Dist.] 1994, writ denied) (“The jury found that Tacon, and not
Grant, breached the contract. Therefore, the doctrine of substantial performance is
inapplicable.”). Moreover, the jury’s finding that Raitz, and not Sanchez, failed to
comply with the Iredell agreement is not against the great weight and preponderance
of the evidence. The jury was free to credit the evidence that the flaws in the slab
were caused by defective concrete supplied by Raitz, as well as Sanchez’s testimony
9
that his text admitting fault was a desperate concession by him in an attempt to obtain
payment for the Woodlands project, which Raitz was withholding, rather than a true
admission of fault. See City of Keller v. Wilson, 168 S.W.3d 802, 819 (Tex. 2005).
1. Standards of Review: Legal and Factual Sufficiency
When parties challenge the legal sufficiency of the evidence to support an
adverse finding on which they did not have the burden of proof at trial, they must
demonstrate that there is no evidence to support the adverse finding. Mullins v.
McWhirter, 724 S.W.3d 571, 578 (Tex. App.—Eastland 2025, pet. denied) (citing
City of Keller, 168 S.W.3d at 827); see Croucher v. Croucher, 660 S.W.2d 55, 58
(Tex. 1983). Under a legal sufficiency review, we consider all the evidence in the
light most favorable to the prevailing party, make every reasonable inference in that
party’s favor, disregard contrary evidence unless a reasonable factfinder could not,
and indulge every reasonable inference that would support it. City of Keller, 168
S.W.3d at 807, 822, 827.
The evidence is legally insufficient to support a finding only if: (1) the record
discloses a complete lack of evidence of a vital fact; (2) the court is barred by rules
of law or evidence from giving weight to the only evidence offered to prove a vital
fact; (3) there is no more than a scintilla of evidence to prove a vital fact; or (4) the
evidence conclusively established the opposite of a vital fact. United Rentals N.
Am., Inc. v. Evans, 668 S.W.3d 627, 640 (Tex. 2023) (citing Gunn v. McCoy, 554
S.W.3d 645, 658 (Tex. 2018)); City of Keller, 168 S.W.3d at 810. “Anything more
than a scintilla of evidence is legally sufficient to support the finding.” Mullins, 724
S.W.3d at 578 (quoting Formosa Plastics Corp. USA v. Presidio Eng’rs &
Contractors, Inc., 960 S.W.2d 41, 48 (Tex. 1998)). “More than a scintilla of
evidence exists when the evidence would enable reasonable and fair-minded people
to reach different conclusions.” Id. at 578–79 (quoting Burbage v. Burbage, 447
S.W.3d 249, 259 (Tex. 2014)). “However, if the evidence is so weak that it only
10
creates a mere surmise or suspicion of its existence, it is regarded as no evidence.”
Id. at 579 (quoting Waste Mgmt. of Tex., Inc. v. Tex. Disposal Sys. Landfill, Inc., 434
S.W.3d 142, 156 (Tex. 2014)).
“When reviewing the factual sufficiency of the evidence, we examine the
entire record, considering all the evidence both in favor of and contrary to the
finding.” 4922 Holdings, LLC v. Rivera, 625 S.W.3d 316, 324 (Tex. App.—Houston
[14th Dist.] 2021, pet. denied) (citing Vast Constr., LLC v. CTC Contractors, LLC,
526 S.W.3d 709, 723 (Tex. App.—Houston [14th Dist.] 2017, no pet.)). We must
review the evidence in a neutral light. Gonzalez v. Sanchez, 717 S.W.3d 516, 527
(Tex. App.—Eastland 2025, no pet.) (citing Dow Chem. Co. v. Francis, 46 S.W.3d
237, 242 (Tex. 2001)). If we set aside a judgment on the basis that a vital finding is
not supported by factually sufficient evidence, we must detail the evidence that is
relevant to the issue and specify how the contrary evidence greatly outweighs the
evidence that supports the finding. Id. (citing Pool v. Ford Motor Co., 715 S.W.2d
629, 635 (Tex. 1986)).
When a party attacks the factual sufficiency of an adverse finding on an issue
on which it had the burden of proof, such as here, the party must demonstrate on
appeal that the adverse finding is against the great weight and preponderance of the
evidence. Francis, 46 S.W.3d at 242. However, when a party challenges the factual
sufficiency of the evidence to support a finding on an issue for which it did not have
the burden of proof at trial, we will set aside the finding only if the evidence in
support of the finding is so weak or contrary to the great weight and preponderance
of the evidence as to be clearly wrong and manifestly unjust. Gonzalez, 717 S.W.3d
at 527 (citing Pool, 715 S.W.2d at 635); Cowan v. Worrell, 638 S.W.3d 244, 254
(Tex. App.—Eastland 2022, no pet.).
11
2. Breach of Contract, Substantial Performance, and the Proper Measure
of Damages
To prevail on a breach-of-contract claim, a party must establish: (1) the
existence of a valid contract; (2) performance or tendered performance by the
plaintiff; (3) breach of the contract by the defendant; and (4) damages to the plaintiff
because of the defendant’s breach. Caprock Inv. Corp. v. Montgomery, 321 S.W.3d
91, 99 (Tex. App.—Eastland 2010, pet. denied). Breach-of-contract damages may
be direct, consequential, or both. SM Energy Co. v. Buzzard Roost Farms, Inc., 727
S.W.3d 525, 550 (Tex. App.—Eastland 2025, no pet.) (citing Signature Indus.
Servs., LLC v. Int’l Paper Co., 638 S.W.3d 179, 186 (Tex. 2022)). The appropriate
measure of damages for a breach-of-contract claim is the benefit of the bargain
denied to the injured party; its purpose is to restore the injured party to the economic
position he would have enjoyed had the contract been performed. Id. at 551 (citing
Mays v. Pierce, 203 S.W.3d 564, 577 (Tex. App.—Houston [14th Dist.] 2006, pet.
denied)).
Generally, a contracting party who is in default cannot maintain a suit for
breach. Dobbins v. Redden, 785 S.W.2d 377, 378 (Tex. 1990). But the doctrine of
substantial performance “allows a party to a contract, who is himself in breach but
who nevertheless substantially completed performance, to recover damages for that
performance.” Tacon, 889 S.W.2d at 670 (emphasis added) (citing Dobbins, 785
S.W.2d at 378). In the context of a contractual dispute between a subcontractor and
a contractor, substantial performance is an equitable doctrine “that was adopted to
allow a [subcontractor or] contractor who has substantially completed a construction
contract to sue on the contract rather than being relegated to his cause of action for
quantum meruit.” Kelly v. Tracy, No. 01-18-00913-CV, 2022 WL 2837335, at *6
(Tex. App.—Houston [1st Dist.] July 21, 2022, no pet.) (mem. op.) (quoting
Vance v. My Apartment Steak House, 677 S.W.2d 480, 482 (Tex. 1984)); see
12
Atkinson v. Jackson Bros., 270 S.W. 848, 850 (Tex. Comm’n App. 1925, holding
approved).
In such cases, although the contractor is permitted to sue on the contract, his
recovery is reduced by the cost of curing those defects for which he is responsible.
4922 Holdings, 625 S.W.3d at 329 (citing Vance, 677 S.W.2d at 482). It is the
plaintiff contractor’s burden to plead and prove his entitlement to recovery under a
theory of substantial performance. Kelly, 2022 WL 2837335, at *6 (citing Carr v.
Norstok Bldg. Sys., Inc., 767 S.W.2d 936, 940 (Tex. App.—Beaumont 1989, no
writ)). In that context, substantial performance is regarded as a condition precedent
to the right to sue on a contract. Id. (citing Atkinson, 270 S.W. at 850).
3. Application
Raitz contends that because “every case involving a disputed construction
defect amounts to either a case of substantial performance . . . or no substantial
performance,” the doctrine of substantial performance is inapplicable to a breach-
of-contract claim in which the suing contractor did not breach the agreement. See
Tacon, 889 S.W.2d at 670; Emerson Constr. Co., Inc. v. Ranger Fire, Inc., No. 03-
09-00567-CV, 2013 WL 4817551, at *5–6 (Tex. App.—Austin Aug. 29, 2013, no
pet.) (mem. op.).
The jury found that Sanchez did not breach the Iredell agreement. Because it
is undisputed that Sanchez did not offer any evidence of the cost of remedial repairs
for that project, if the doctrine of substantial performance did apply, the evidence
would be legally insufficient to support the jury’s finding. Mullins, 724 S.W.3d at
578 (citing City of Keller, 168 S.W.3d at 827); Francis, 46 S.W.3d at 242. Whether
the doctrine applies turns on whether Sanchez breached that agreement. Tacon, 889
S.W.2d at 670; see Emerson Constr., 2013 WL 4817551, at *5–6.
Although it is undisputed that the Iredell slab was defective, causation was a
contested issue at trial. Raitz contends that because Sanchez stated in a text that he
13
“left a bad finish” on the Iredell project, that he would not seek the remaining balance
for that project, and that he attempted to repair the slab himself, he admitted to
breaching the agreement. Sanchez argues that Raitz’s evidence does not establish
that the jury’s finding is against the great weight and preponderance of the evidence
because (1) there is substantial evidence that the defects in the slab were caused by
the defective concrete that Raitz supplied for the project, and (2) Sanchez explained
in his trial testimony that his text admission was a desperate attempt to negotiate
payment for the Woodlands project, not a true admission of fault.
There was an abundance of evidence presented that the concrete mix was
defective, and the cause of the problems that were associated with the Iredell slab.
Sanchez testified that the concrete mix repeatedly clogged the pump truck and that
the volumetric trucks continuously experienced issues and delays, which resulted in
“cold joints” in the slab and a crumbling finish. Rodriguez similarly testified to the
clogging and mixing problems with the trucks, and he also blamed the concrete mix
for causing these problems. Rodriguez testified that he had never seen properly
mixed concrete cause the crumbling that occurred with the Iredell slab. He also sent
a video of the contents of the pump truck: a large “clump” that had failed to set into
concrete even after hours of remaining in the truck’s pipes. Meanwhile, Casey
asserted that it was not possible for the volumetric trucks to produce such a “clump”
or mix the concrete so poorly, but he did not offer any evidence to support these
assertions. And although Sanchez texted that he would not charge Raitz for the
Iredell project and that he left a bad finish on the slab, he explained that he made
those statements out of desperation to convince Raitz to pay him for the Woodlands
project and in an attempt to preserve a business relationship between them, and that
the concrete mix was the cause of the defects in the slab.
The jury was free to credit, weigh, believe, and disbelieve all, some, or none
of the testimony and evidence presented. Gonzalez, 717 S.W.3d at 535 (citing
14
Golden Eagle Archery, Inc v. Jackson, 116 S.W.3d 757, 761 (Tex. 2003)). Sanchez
admitted fault in texts that he sent to Raitz but testified at trial that the admissions
were a negotiation technique and were not true. Likewise, Sanchez and Rodriguez
testified that the concrete mix was deficient and would not set properly, although
Casey testified to the contrary because he claimed that his volumetric trucks were
computer-operated and preprogrammed, and a bad mix would have triggered an
automatic shutdown. Conflicting evidence such as this falls within the jury’s
province to resolve, and therefore the jury’s findings on that point should not be
disturbed. Id. (citing City of Keller, 168 S.W.3d at 807, 822, 827).
We conclude that the evidence before us supports the jury’s finding that
Sanchez did not breach the Iredell agreement, and that this evidence was not so weak
or against the great weight and preponderance of the evidence as to be clearly wrong
and manifestly unjust. Id. (citing Pool, 715 S.W.2d at 635). Thus, because the
evidence is factually sufficient to support the jury’s finding, the doctrine of
substantial performance is not applicable to this case, and Sanchez bore no burden
to establish the cost of remedial repairs for the Iredell slab. Further, because there
is more than a scintilla of evidence to support the jury’s finding, we conclude that
the evidence is legally sufficient as well. Mullins, 724 S.W.3d at 578–79.
Accordingly, we overrule Raitz’s first issue.
B. The Exclusion of Casey’s Testimony was not Error
In its second issue, Raitz contends that the trial court abused its discretion
when it erroneously excluded Casey’s testimony on the cost of remedial repairs on
the grounds that expert testimony was required and Raitz did not designate an expert
witness to testify on this subject.
Even if the trial court’s decision to exclude Casey’s testimony—regarding the
cost of repairs for the Iredell slab on the basis that Raitz did not designate Casey as
an expert witness—was erroneous, and we do not hold that it was, any such error
15
was harmless. If a trial court abuses its discretion and erroneously admits or
excludes evidence, we must determine whether the error “probably caused the
rendition of an improper judgment.” TEX. R. APP. P. 44.1(a)(1); Campbell v.
Hendershot Equip. Co., Inc., 717 S.W.3d 494, 515 (Tex. App.—Eastland 2025, pet.
denied). We review the entire record to determine whether an error is harmful.
Campbell, 717 S.W.3d at 515 (citing Gunn, 554 S.W.3d at 668–69). Whether an
erroneous exclusion of evidence probably caused the rendition of an improper
judgment is “a judgment call entrusted to the sound discretion [and] good sense of
the reviewing court from an evaluation of the whole case.” City of Stephenville v.
Belew, 692 S.W.3d 347, 361 (Tex. App.—Eastland 2024, pet. denied) (quoting First
Emps. Ins. Co. v. Skinner, 646 S.W.2d 170, 172 (Tex. 1983)).
Raitz argues that even if Casey’s testimony did not support a jury’s finding
on damages, it would have shown that Sanchez breached the contract and Raitz did
not. Raitz contends that this excluded evidence was pertinent to “a key issue that
was properly part of Sanchez’s case in chief.”
Casey testified during Raitz’s offer of proof that, based on his personal
knowledge and perception of the jobsite after the pour, the Iredell slab was not
finished correctly and required repairs by grinding and applying an overlay and an
epoxy finish. However, Casey was permitted to present similar testimony to the
jury—that, in his opinion, the concrete mix in the Iredell project was not defective
and was not the cause of the slab’s defects. The remainder of Casey’s testimony
during the offer of proof concerned the cost of remedial repairs and their
reasonableness and necessity. That constituted evidence of damages, not liability,
and the jury foreclosed any consideration of Raitz’s alleged damages when they
found that Sanchez did not breach the Iredell agreement. See Mitchell v. Bank of
Am., N.A., 156 S.W.3d 622, 627 (Tex. App.—Dallas 2004, pet. denied) (holding that
because the jury’s finding of no liability was supported by sufficient evidence, the
16
exclusion of any evidence on the issue of damages was harmless because it could
not have resulted in the rendition of an improper judgment).
We conclude that any error in excluding Casey’s testimony was harmless.
Accordingly, we overrule Raitz’s second issue.
C. The Refusal to Submit Raitz’s Requested Jury Instruction was not Error
In its third issue, Raitz argues that the trial court abused its discretion when it
refused to submit Raitz’s requested jury instruction on the cost of repairs issue, again
because, according to Raitz, the trial court failed to require Sanchez to prove up the
costs of remedial damages under the “substantial performance” doctrine.
As Sanchez points out, no evidence was presented to the jury on the
reasonable and necessary cost of repairs. In this regard, it is error to submit a
question for which there is no evidence. See Horton v. Kansas City S. Ry. Co., 692
S.W.3d 112, 137 (Tex. 2024) (citing Harris Cnty. v. Smith, 96 S.W.3d 230, 236 (Tex.
2002)); see also TEX. R. CIV. P. 278 (“The court shall submit the questions,
instructions and definitions . . . which are raised by the written pleadings and the
evidence.”). And again, even if the trial court erred, any error could not have resulted
in the rendition of an improper judgment. See TEX. R. APP. P. 44.1(a)(1); Mitchell,
156 S.W.3d at 627 (“It is well established in Texas that no recovery is allowed unless
liability has been established. In the absence of liability, the question of damages
becomes immaterial.” (citing Turner v. Lone Star Indus., Inc., 733 S.W.2d 242, 246
(Tex. App.—Houston [1st Dist.] 1987, writ ref’d n.r.e.))); see also Shupe v.
Lingafelter, 192 S.W.3d 577, 579 (Tex. 2006) (observing that an error is harmless
“when the findings of the jury in answer to other issues are sufficient to support the
judgment” (quoting Boatload of Houston, Inc. v. Bailey, 609 S.W.2d 743, 750 (Tex.
1980))); City of Brownsville v. Alvarado, 897 S.W.2d 750, 752 (Tex. 1995) (A jury
question may be immaterial, and therefore the refusal of its submission is harmless,
17
“when its answer can be found elsewhere in the verdict or when its answer cannot
alter the effect of the verdict.”).
Here, the jury’s finding that Sanchez did not breach the Iredell agreement
precluded any damage finding in favor of Raitz for the Iredell project and thus
rendered Raitz’s proposed jury question immaterial. See Mitchell, 156 S.W.3d at
627; see also Shupe, 192 S.W.3d at 579; Alvarado, 897 S.W.2d at 752.
Consequently, we conclude that the trial court did not err when it refused to submit
Raitz’s proposed jury instruction. See TEX. R. APP. P. 44.1(a)(1).
Accordingly, we overrule Appellant’s third issue.
D. The Refusal to Grant a Pleading Amendment was not an Abuse of
Discretion
In its fourth issue, Raitz contends that the trial court abused its discretion when
it denied Raitz’s motion for leave to amend its pleadings to specifically deny that
Sanchez presented a demand to Raitz for the Iredell project under Chapter 38 of the
Civil Practice and Remedies Code. See TEX. CIV. PRAC. & REM. CODE ANN.
§ 38.002(2) (West 2015).
We review a trial court’s ruling on a motion for leave to file an amended
pleading for an abuse of discretion. Lower Valley Water Dist. v. Danny Sander
Constr., Inc., 657 S.W.3d 404, 408 (Tex. App.—El Paso 2022, no pet.). Under
Rule 63 of the Texas Rules of Civil Procedure, a trial court must grant a party leave
to amend its pleadings unless the party opposing the amendment presents evidence
of surprise or prejudice, or the proposed amendment asserts a new cause of action or
defense and is thus prejudicial on its face and the opposing party asserts a timely
objection. Id. at 409 (citing Greenhalgh v. Service Lloyds Ins., Co., 787 S.W.2d
938, 939 (Tex. 1990)); see TEX. R. CIV. P. 63. “However, when surprise or prejudice
is demonstrated, either through evidence presented by the objecting party or on the
face of a pleading asserting a new cause of action or defense, then the decision to
18
grant or deny the motion lies within the sound discretion of the trial court.” Danny
Sander Constr., 657 S.W.3d at 409 (citing Hardin v. Hardin, 597 S.W.2d 347, 349–
50 (Tex. 1980)).
To recover attorney’s fees in a suit on a written contract, a plaintiff must plead
and prove that the presentment of a contract claim was made to the opposing party,
and the opposing party failed to tender performance. See CIV. PRAC. & REM.
§§ 38.001–002; Sandberg v. STMicroelectronics, Inc., 600 S.W.3d 511, 532 (Tex.
App.—Dallas 2020, pet. denied) (citing Jones v. Kelley, 614 S.W.2d 95, 100 (Tex.
1981)); Belew v. Rector, 202 S.W.3d 849, 856–57 (Tex. App.—Eastland 2006, no
pet.). The claimant bears the burden of pleading and proving that he made a
presentment of the claim to the opposing party. Tex. Black Iron, Inc. v. Arawak
Energy Int’l Ltd., 566 S.W.3d 801, 824 (Tex. App.—Houston [14th Dist.] 2018, pet.
denied) (citing Ellis v. Waldrop, 656 S.W.2d 902, 905 (Tex. 1983)). No particular
form of presentment is required; it may be done orally or in writing and need not be
done by a party’s counsel. See Belew, 202 S.W.3d at 857. Further, merely filing a
breach-of-contract claim is insufficient. Id. However, if a plaintiff pleads that all
conditions precedent have been met and the defendant fails to affirmatively deny
presentment, the plaintiff is not obligated to produce specific evidence of
presentment. Id.
Although Raitz contends that its proposed amendment would have merely
cured a pleading defect, the assertion of the failure to satisfy a condition precedent
is an affirmative defense. See Danny Sander Constr., 657 S.W.3d at 408–10; Belew,
202 S.W.3d at 857. The assertion of a new defense is prejudicial on its face. 1 Danny 0F
Sander Constr., 657 S.W.3d at 409 (citing Greenhalgh, 787 S.W.2d at 939); see
The parties apparently argued this motion in chambers before the trial court denied it on the record.
1
Although the trial transcript does not specifically show that Sanchez objected, it is apparent that the motion
was contested on prejudice grounds.
19
TEX. R. CIV. P. 63. Moreover, Sanchez alleged in his pleadings that all conditions
precedent were satisfied, over three years before Raitz filed its request for a pleading
amendment and asserted, for the first time, its failure-to-satisfy-conditions-
precedent defense. We conclude that the trial court did not abuse its discretion when
it denied Raitz’s motion for leave to amend its pleading. See Danny Sander Constr.,
657 S.W.3d at 408–10; Belew, 202 S.W.3d at 857.
Accordingly, we overrule Raitz’s fourth issue.
E. The Evidence is Sufficient to Support the Attorney’s Fee Award
In its fifth issue, Raitz contends that there is insufficient evidence to support
the jury’s attorney’s fee award. Specifically, Raitz claims that the fee award requires
a remand or remittitur because: (1) there was legally insufficient evidence presented
that such a disproportionate fee shifting award was warranted; (2) evidence of the
attorney’s fees should have be