AHA Mechanical Contractors, LLC v. Shelby County Board of Education
CourtCourt of Appeals of Tennessee
Date FiledJuly 15, 2026
DocketW2025-01107-COA-R3-CV
JudgeJudge Steven W. Maroney
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
07/15/2026
IN THE COURT OF APPEALS OF TENNESSEE
AT JACKSON
April 21, 2026 Session
AHA MECHANICAL CONTRACTORS, LLC v. SHELBY COUNTY
BOARD OF EDUCATION
Appeal from the Chancery Court for Shelby County
No. CH-21-1403-1 Melanie Taylor Jefferson, Chancellor
___________________________________
No. W2025-01107-COA-R3-CV
___________________________________
This appeal requires us to determine whether the trial court erred in granting
Appellee/Shelby County Board of Education’s motion for summary judgment on its breach
of contract claim against Appellant/Contractor. Because disputes of material fact and
ambiguities arising therefrom exist, the trial court’s grant of summary judgment is
reversed.
Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court
Reversed and Remanded
STEVEN W. MARONEY, J., delivered the opinion of the court, in which J. STEVEN
STAFFORD, P.J., W.S., and CARMA DENNIS MCGEE, J., joined.
Scott A. Frick, Memphis, Tennessee, for the appellant, AHA Mechanical Contractor, LLC.
Jamie L. Morton, Memphis, Tennessee, for the appellee, Shelby County Board of
Education.
OPINION
I. Background
A. Contract Formation and Scope
On or about February 11, 2020, Appellee Shelby County Board of Education
(“SCBE”) published Invitation for Bid No. 03022020 (“IFB”) related to HVAC
replacement at Riverview K-8 School (the “Riverview Project”). The IFB included the
Scope of Work for the Riverview Project. In relevant part, Section 3.0 of the Scope of
Work states:
3.0 SCOPE OF WORK
The SCBE requests bids for Riverview K-8 HVAC Replacements. Replace
existing cooling tower with new to match capacity, 500-ton, 1 440 GPM.
Replacement shall include structural base, associated piping, and associated
accessories such as by-pass valves. Concrete base shall be reviewed and
verified to meet load & current code criteria. . . .
Appellant AHA Mechanical Contractors (“Contractor”) submitted a bid on the
Riverview Project, which bid SCBE accepted. The Riverview Project is governed by a
Facilities Services Agreement signed by both parties (the “Contract”). The Contract bears
the insignia of SCBE on its first page, and it appears undisputed in the record that the
Contract was drafted by SCBE.
The Contract incorporates, by reference, several documents related to the Riverview
Project, including the IFB and the Scope of Work. Paragraph 37 of the Contract requires
that, “Contractor will observe and comply with all applicable local, state, and federal laws,
ordinances, and regulations . . . .” Paragraph 15 expressly permits SCBE to terminate the
Contract for cause if, among other reasons, Contractor substantially violates any provision
of the Contract. In such case, the Contract provides for liquidated damages and an award
of SCBE’s reasonable attorneys’ fees, costs, and expenses arising from such termination
of the Contract.
B. Communications Regarding the Concrete Base
The instant appeal arises from the parties’ dispute concerning the Scope of Work
language, “Concrete base shall be reviewed and verified to meet load & current code
criteria.” The SCBE asserts that this language requires Contractor to obtain a review and
verification from a structural engineer. As discussed further below, the Contract does not
define the term “load,” nor does it specify which “current code criteria” are applicable.
After executing their Contract, the parties engaged in communication, via letters,
emails, and in-person discussions, concerning the requirements regarding the concrete
base. From our review, at the time the parties entered their Contract, the only existing
“concrete base” was the original base on which the old HVAC was constructed, which
remained after that system was dismantled so that the new HVAC system could be installed
by Contractor. As discussed below, Contractor subsequently made modifications to the
existing concrete base.
-2-
After SCBE notified Contractor that it would require an engineer’s verification that
the concrete base was “load” and “code” compliant, Contractor requested that its engineer,
Mr. Marshall Davis, provide same. However, on October 20, 2020, Mr. Davis declined to
write an engineer’s letter that would address the concrete base for the cooling tower,
stating:
We have some concerns with how the slab was done. We do not feel
comfortable writing a letter with the current as-built condition. The main
concern is the overturning of the cooling tower during a high wind or seismic
event. For us to write a letter we would require additional modification;
however, another engineer may be willing to write a letter for the as-built
condition.
Nonetheless, on October 29, 2020, Mr. Davis prepared a letter for Contractor,
stating, “The as-built condition meets the overall design intent.” The parties dispute
whether Mr. Davis’ “as-built condition” statement satisfies the “[c]oncrete base shall be
reviewed and verified to meet load & current code criteria” requirement of the Contract.
SCBE argues, and the trial court found, that, although Mr. Davis’ October 29, 2020 letter
states that the “as-built condition meets the overall design intent,” it does not address the
concrete base or state whether the concrete base was ever reviewed and verified to meet
load and current code criteria before any modifications were made to it.
SCBE sent at least three letters to Contractor requesting that Contractor comply with
its alleged contractual obligation to provide an engineer’s verification that the concrete
base would meet all load and code criteria. Although Contractor responded to these
demands, none of the responses contained an engineer’s opinion.
C. Notices of Default and Termination of the Contract
On January 15, 2021, SCBE sent a letter terminating the Contract. The January 15th
letter stated, in relevant part:
Contractor is in default of its obligations under the Construction Contract for
failure to perform the Work in accordance with the Contract Documents,
including without limitation Contractor’s failure to provide verification that
the concrete base will meet load and current code criteria as required by the
Scope of Work set forth in [the IFB]. Further, as expressly stated in the letter
dated July 8, 2020, the engineer engaged by Contractor to review the cooling
tower support frame based his opinion of the frame’s sufficiency upon the
assumption that “[t]he new cooling tower support frame will be installed on
a new concrete foundation designed by others at the existing cooling tower
location.” Owner obtained an approved structural design for the new concrete
cooling tower at no cost to Contractor. Nonetheless, Contractor has not
-3-
agreed to install a new concrete foundation that can be confirmed and verified
by a licensed professional to meet load and code criteria as required by the
IFB and has failed to perform the Work in accordance with the Contract
Documents.
In response to SCBE’s letter terminating the Contract, Contractor’s attorney sent a
letter to SCBE on January 28, 2021, stating, in relevant part:
[SCBE] does not have either a factual or legal basis for terminating the
[Contract] . . . . All work performed by [Contractor] on the [Riverview]
Project was performed in full compliance with the specifications included in
the [IFB]. The current dispute is directly attributable to the lack of proper
specifications developed by [SCBE] for what it apparently intended for this
Project. In addition, various field modifications to the installation that were
not contained in the specifications were installed as a direct result of requests
made by [SCBE] representatives who are managing the Project on behalf of
[SCBE].
[SCBE] has made demands upon my client for various certifications
by an engineer as a direct result of the failure of [SCBE] to provide
specifications in the [IFB] that it has deemed necessary subsequent to the
execution of the [Contract]. At all times pertinent material hereto,
[Contractor] has endeavored to meet the demands of [SCBE] despite the fact
that those demands fall outside of the scope of work contained in the
[Contract] and the specifications for the Project.
Following termination of the Contract, the Riverview Project was completed by
Victor Hall Construction, LLC. Substantial completion of the Riverview Project occurred
on August 31, 2021, and final completion did not occur until at least September 2021.
D. Post-Termination Litigation
On October 8, 2021, Contractor filed suit against SCBE, claiming it unlawfully
terminated the Contract. On December 10, 2021, SCBE filed an answer and a counterclaim
against Contractor, seeking to recover $61,540.00 in temporary cooling expenses resulting
from Contractor’s alleged breach of the Contract, plus reasonable attorneys’ fees
recoverable thereunder. On February 9, 2024, SCBE filed a motion for summary judgment
as to the Contractor’s claim and its counterclaim for breach of contract. Contractor
opposed the motion, which was heard on May 13, 2024.
On May 28, 2024, the trial court entered its initial order granting SCBE’s motion
for summary judgment. On June 26, 2024, Contractor filed a motion to alter or amend the
May 28th order. In its motion, Contractor argued, inter alia, that SCBE had not submitted
sufficient proof to establish the reasonableness of its attorneys’ fees. Following a hearing
-4-
on September 11, 2024, the trial court entered an order on December 10, 2024, requiring
SCBE to provide a statement of the work performed and one or two declarations from local
attorneys supporting the reasonableness of the attorney’s fees. Otherwise, Contractor’s
motion was denied.
SCBE provided the statement of work performed and the declarations as ordered by
the trial court. Contractor then moved for hearing on the question of attorney’s fees. The
trial court granted the motion for hearing, and both parties filed supplemental memoranda
regarding SCBE’s attorney’s fee award. On June 27, 2025, the trial court entered an
Amended Order Granting the School Board’s Motion for Partial Summary Judgment and
Final Judgment. Therein, the trial court reduced the hourly rate provided by SCBE’s
attorneys, stating:
While the Court finds that the rate of $400.00 per hour is reasonable for the
legal work performed . . . the Court is concerned about compensating [SCBE]
twice for the same work. Consequently, the court is awarding attorney’s fees
to [SCBE] at the rate of $310.00 per hour, reduced by the rate of $90.00 per
hour to account for the attorneys’ salaries paid by [SCBE]. Accordingly, the
Court awards [SCBE] attorney’s fees in the amount of $52,421.00 which is
comprised of 169.1 hours of legal work at $310.00 per hour.
Contractor filed a timely notice of appeal.
II. Issues
Contractor raises the following issues for review as stated in its brief:
1. Whether the Trial Court erred in granting summary judgment in favor of
Shelby County Board of Education.
2. Whether the Trial Court erred in granting summary judgment in favor of
Shelby County Board of Education on its claim for attorney’s fees, and
whether the amount of attorney’s fees awarded was an abuse of discretion by
the Trial Court.
In the posture of Appellee, SCBE raises the following additional issues for review
as stated in its brief:
1. Whether the chancery court erred in amending its Order Granting
Summary Judgment in favor of the School Board to reduce the hourly rate
by which the contractual attorney fee award was calculated to account for the
salaries paid by the School Board to its in-house attorneys; and
2. Whether this Court should award appellate attorneys’ fees to the School
Board based upon the terms of the Riverview Contract and remand this
-5-
matter to the chancery court for determination of the appropriate amount of
appellate attorneys’ fees to be awarded to the School Board.
III. Standard of Review
The grant or denial of a motion for summary judgment is a matter of law, which we
review de novo with no presumption of correctness. See Rye v. Women’s Care Ctr. of
Memphis, MPLLC, 477 S.W.3d 235, 250 (Tenn. 2015); Dick Broad. Co. of Tenn. v. Oak
Ridge FM, Inc., 395 S.W.3d 653, 671 (Tenn. 2013) (citing Kinsler v. Berkline, LLC, 320
S.W.3d 796, 799 (Tenn. 2010)). As such, this Court must “make a fresh determination of
whether the requirements of Rule 56 of the Tennessee Rules of Civil Procedure have been
satisfied.” Rye, 477 S.W.3d at 250. As the Tennessee Supreme Court has explained
concerning the requirements for a movant to prevail on a motion for summary judgment
pursuant to Tennessee Rule of Civil Procedure 56:
[W]hen the moving party does not bear the burden of proof at trial, the
moving party may satisfy its burden of production either (1) by affirmatively
negating an essential element of the nonmoving party’s claim or (2) by
demonstrating that the nonmoving party’s evidence at the summary judgment
stage is insufficient to establish the nonmoving party’s claim or defense. We
reiterate that a moving party seeking summary judgment by attacking the
nonmoving party’s evidence must do more than make a conclusory assertion
that summary judgment is appropriate on this basis. Rather, Tennessee Rule
56.03 requires the moving party to support its motion with “a separate
concise statement of material facts as to which the moving party contends
there is no genuine issue for trial.” Tenn. R. Civ. P. 56.03. “Each fact is to be
set forth in a separate, numbered paragraph and supported by a specific
citation to the record.” Id. When such a motion is made, any party opposing
summary judgment must file a response to each fact set forth by the movant
in the manner provided in Tennessee Rule 56.03. “[W]hen a motion for
summary judgment is made [and] . . . supported as provided in [Tennessee
Rule 56],” to survive summary judgment, the nonmoving party “may not rest
upon the mere allegations or denials of [its] pleading,” but must respond, and
by affidavits or one of the other means provided in Tennessee Rule 56, “set
forth specific facts” at the summary judgment stage “showing that there is a
genuine issue for trial.” Tenn. R. Civ. P. 56.06. The nonmoving party “must
do more than simply show that there is some metaphysical doubt as to the
material facts.” Matsushita Elec. Indus. Co. [v. Zenith Radio Corp.], 475
U.S. [574,] 586, 106 S. Ct. 1348 [(1986)]. The nonmoving party must
demonstrate the existence of specific facts in the record which could lead a
rational trier of fact to find in favor of the nonmoving party. . . . [A]fter
adequate time for discovery has been provided, summary judgment should
be granted if the nonmoving party’s evidence at the summary judgment stage
-6-
is insufficient to establish the existence of a genuine issue of material fact for
trial. Tenn. R. Civ. P. 56.04, 56.06. The focus is on the evidence the
nonmoving party comes forward with at the summary judgment stage, not on
hypothetical evidence that theoretically could be adduced, despite the
passage of discovery deadlines, at a future trial.
Rye, 477 S.W.3d at 264-65.
To the extent that we are required to review the trial court’s interpretation of the
parties’ Contract, the Tennessee Supreme Court has instructed that the “cardinal rule [in
interpreting contracts] . . . is to ascertain the intention of the parties and to give effect to
that intention, consistent with legal principles.” Frizzell Constr. Co. v. Gatlinburg, LLC,
9 S.W.3d 79, 86 (Tenn. 1999) (quoting Bob Pearsall Motors, Inc. v. Regal Chrysler-
Plymouth, Inc., 521 S.W.2d 578, 580 (Tenn. 1975)). “A determination of the intention of
the parties ‘is generally treated as a question of law because the words of the contract are
definite and undisputed, and in deciding the legal effect of the words, there is no genuine
factual issue left for a jury to decide.’” Kafozi v. Windward Cove, LLC, 184 S.W.3d 693,
698 (Tenn. Ct. App. 2005) (quoting Planters Gin Co. v. Fed. Compress & Warehouse Co.,
78 S.W.3d 885, 890 (Tenn. 2002)). Therefore, issues of contract interpretation are
reviewed de novo. See Dick Broad. Co., 395 S.W.3d at 659.
IV. Analysis
To determine whether summary judgment was proper, we must decide whether the
disputed contractual language is ambiguous, and, if so, whether any ambiguity can be
resolved as a matter of law. However, we first note the submission of extensive parol
evidence by both parties in their respective statements of undisputed material facts.
A. Parol Evidence Submitted by the Parties
As noted above, the parties’ dispute arises from the following language as set out in
the Scope of Work section of their Contract, i.e., “Concrete base shall be reviewed and
verified to meet load & current code criteria.” SCBE asserts that Contractor breached this
requirement insofar as it did not tender an engineer’s report verifying that the concrete base
for the HVAC unit met “load & current code criteria.”
1. SCBE’s Statement of Undisputed Material Facts
In support of its motion for summary judgment, SCBE filed a statement of
undisputed material facts (and supporting Exhibits, discussed infra).1 In relevant part,
1
Unless otherwise indicated, all grammar and emphases are reproduced as they appeared in the
-7-
SCBE’s statement of undisputed material facts provided:
10. On June 29, 2020, [SCBE] sent an email to Contractor requesting
“Engineers letter regarding the cooling tower foundation” [. . . Exhibit C].
11. On July 8, 2020, Contractor provided to [SCBE] a letter (“First Engineer
Letter”) signed by Marshall F. Davis of engineering firm Davis Patrikios
Criswell. [. . . Exhibit D].
12. The First Engineer Letter stated that the engineering firm was asked to
review the cooling tower support frame to determine if the frame capacity
was sufficient for support of the new cooling tower. [Id.]
***
14. On October 8, 2020, [SCBE] notified Contractor that Contractor had not
complied with its contractual obligation to provide verification that the
concrete base would meet load and current code criteria (“First Notice of
Default”) [. . . Exhibit E].
15. Also on October 8, 2020, [SCBE] notified Contractor in an email that it
required Contractor’s strict compliance with that provision, expressly stating
that, if Contractor intended to install the new cooling tower on the existing
concrete base, [SCBE] “is requiring that the concrete base be reviewed and
verified to ensure that it meets load & current code criteria.” [. . . Exhibit F]
(emphasis in original).
***
19. Ten days later, Contractor submitted an engineering letter dated October
29, 2020 that made no mention that the existing concrete base for the cooling
tower had been reviewed and verified to meet load and current code criteria
(“Second Engineer Letter”) [. . . Exhibit J].
20. Meanwhile, by mid-October 2020, Contractor had filled the concrete base
with crushed concrete and water, compacted the concrete/water mixture,
drilled holes to remove the water, and added steel frames [. . . Exhibit K].
21. Contractor’s engineer Mr. Davis declined to write an engineer letter that
would address the concrete base for the cooling tower, stating: “We have
some concerns with how the slab was done. We do not feel comfortable
writing a letter with the current as-built condition. The main concern is the
overturning of the cooling tower during a high wind or seismic event. For us
to write a letter we would require additional modification; however, another
engineer may be willing to write a letter for the as-built condition.” [Exhibit
original submissions of the parties.
-8-
K . . .].
22. Following a telephone consultation with . . . Contractor on November 9,
2020, on November 11, 2020[, SCBE] sent a letter . . . requesting that
Contractor provide an engineer letter verifying that the concrete base would
meet all load and code criteria (“Third Notice of Default”) [. . . Exhibit L].
23. A week later Contractor sent [SCBE] a letter dated November 19, 2020[,]
purporting to include an “Engineer’s Response” to issues raised by [SCBE],
but Contractor’s letter does not identify the name of the engineer [. . . Exhibit
M].
24. At the time Contractor submitted the November 19, 2020 letter to
[SCBE], Contractor’s engineer had already informed Contractor that it could
not write an engineer letter that the concrete foundation would meet load and
current code criteria. [Exhibit K . . . Exhibit M].
25. On January 6, 2021, [SCBE] sent Contractor a Final Demand to Cure
Default wherein [SCBE] demanded “that Contractor state in writing whether
it intends to comply with its obligations by performing the Work as described
in [SCBE’s] December 10th letter and providing the required verifications
by a licensed professional.” (“Final Demand”) [. . . Exhibit N].
26. The Final Demand required that the Contractor supply the requested
statement of intent to [SCBE] on or before 5:00 p.m. on Friday, January 8,
2021. [Id.]
27. Contractor could not obtain an engineer letter from Mr. Davis verifying
that the concrete base would meet all load and code criteria to be able to
supply it to [SCBE]. [January 12, 2021 email between Contractor and Mr.
Davis . . . Exhibit O].
28. On January 15, 2021, [SCBE] issued a Letter of Termination of
Riverview Contract . . . (“Notice of Termination”) [. . . Exhibit P].
SCBE’s statement of undisputed material facts references Exhibits C, D, E, F, J, K,
L, M, N, O, P, and these Exhibits were made attachments to SCBE’s statement of
undisputed material facts. In relevant part, the Exhibits included:
Exhibit C—this June 29, 2020 email, sent from SCBE to Contractor requests the
following: “Please provide the following as soon as they are available for the
Riverview K8 Cooling Tower Replacement: . . . Engineers Letter regarding the
cooling tower foundation.”
Exhibit D—this July 8, 2020 letter from Contractor’s engineer, Mr. Davis, i.e.,
“First Engineer Letter,” provides:
DPC, Inc. [i.e., Davis, Patrikios, Criswell engineers, Mr.
Davis’ firm] was asked to review the cooling tower support
frame provided by the equipment manufacturer . . . to
-9-
determine the frame capacity is sufficient for support of the
new cooling tower. The new cooling tower support frame will
be installed on a new concrete foundation designed by others
at the existing cooling tower location. . . .
Exhibit E—October 2020 letter from SCBE to Contractor, i.e. “First Notice of
Default,” stating:
In the letter dated July 8, 2020, Marshall F. Davis states that
DPC Inc., . . . was requested to review the cooling tower
support frame provided by the equipment manufacturer to
determine if the frame capacity is sufficient for support for the
new cooling tower. The letter states, “The new cooling tower
support frame will be installed on a new concrete foundation
designed by others at the existing cooling tower location”
[emphasis in original] . . . . The new concrete foundation design
from a licensed structural engineer has not been received for
review, comment, and/or approval. . . .
Before any work will be able to progress, AHA
Mechanical will complete the following:
1. Provide a report from a licensed structural engineer stating
that the existing concrete base/foundation will meet the load
criteria of the new cooling tower and associated structural
supports . . . . This report from a licensed structural engineer
may also include recommendations or details for modifications
to the existing concrete base/foundation to accept and support
the new structural supports.
2. Provide a detail from a licensed structural engineer for the
new concrete foundation to comply with the July 8, 2020 letter
from DPC Engineers that will support the new cooling tower
support frame as well as current adopted code criteria that
includes, but is not limited to, seismic and wind load criteria.
This request will be waived if Item #1 has been executed.
3. Provide documentation, i.e, compaction tests, from a
licensed geotechnical testing agency that demonstrates that the
loose fill that is currently in place at the existing concrete base
meets the compaction requirements for the new concrete slab.
The existing concrete base foundation must be prepped for new
concrete slab installation per standard construction practices.
This includes the removal of any debris such as redundant
metals that include the existing steel angles and existing steel
supports. Concrete slabs greater than 4” shall be steel
- 10 -
reinforced. Unless directed by a licensed structural engineer,
the steel reinforcement must tie into the existing concrete base
walls by steel reinforcing dowels epoxied into the existing base
walls at depths determined by a structural engineer or separated
by an expansion material around the perimeter. It is highly
recommended to engage a licensed structural engineer
regarding this matter to obtain proper direction.
Exhibit F—this October 8, 2020 email from Mr. Floyd Gene Sides, Jr., the
Director of Construction for SCBE, to Contractor provides, in part:
From the discussions today and the scheduled concrete pour
statement in your email response below, would it be incorrect
in stating that AHA Mechanical is installing the new cooling
tower and new steel support frame on the existing concrete
base? If so, it should be noted and brought to your attention
that this installation is not in compliance with your engineer’s
letter regarding installation. The letter from your engineer
states that the new cooling tower support frame will be
installed on a new concrete foundation designed by others
[emphasis in original]. Who is AHA Mechanical having design
this new concrete foundation? Have the details been provided
to [SCBE] for review, comment, and approval? This is the
reason for the allowance request for the engineering fee of
$5,000,00 in the solicitation.
If AHA Mechanical is intending to use the existing concrete
base, [SCBE] is requiring that the concrete base be reviewed
and verified to ensure that it meets load & current code criteria
[emphasis in original]. To assist in clarifying what the district
means by this request, the following information is being
provided:
The “load” is defined as the weight of the new cooling
tower, new structural steel frame supports, and any other new
components associated with the installation including the
anchor bolt attachments. The “current code criteria” is in
regards to the existing concrete base meeting current codes. As
you may be aware, Shelby County Code Enforcement requires
that all new HVAC equipment installations must meet the
current adopted building code. In addition to this, any existing
appurtenances that the new equipment is being attached or
installed upon must be brought up to current code as well or
confirmed that the existing appurtenances meet the current
- 11 -
code [emphasis in original]. This includes Section 1601
“Seismic” of the International Building Code since Memphis
is classified as being in a Zone D seismic zone which in simpler
terms means very active.
As part of best construction practices, most firms or
companies would engage a licensed structural engineer to
make this confirmation on their behalf with any
recommendations or improvements due to the significant
liability. This significant liability includes accountability of the
company installing the new cooling tower will be held liable
for any failure or compromise to the existing concrete base due
its inability to support the load of the new cooling tower, new
structural steel support frame, and associated attachments. This
will also include liability due to failure of the existing concrete
base during a seismic or severe wind event since modifications
were not implemented to the foundation prior to the installation
of the new equipment. From our experience and relationship
with Shelby County Code Enforcement, Shelby County Code
Enforcement will only accept or consider valid the written
confirmations from state licensed architects or engineers.
With all that stated, please provide the documentation
showing that the existing concrete base has been confirmed
that it meets the current adopted codes and will support the
weight and load of the new cooling tower, the new structural
steel support frame, and provide adequate opportunity for the
anchor bolt attachments as required in the letter from your
engineer.
This documentation does not have to be from a structural
engineer but shall include language that states AHA
Mechanical Contractors will take full and complete
responsibility and liability in regards to the existing concrete
base and its ability to meet the load criteria of the new
installation as well as meets the current adopted building code
requirements for such installation.
Exhibit J—this October 29, 2020 letter from Mr. Davis. i.e., “Second Engineer
Letter,” restates verbatim the information from his July 8, 2020 letter set out
above, with the exception of the following language, which is omitted from the
October 29 letter: “DPC, Inc. has reviewed the frame for the structural support
of the tower and the frame is sufficient.” Rather, the October 29th letter states:
DPC has required additional attachment points of the frame to
the new foundation, designed by others, to prevent overturning
- 12 -
of the cooling tower. The additional required attachments are
as follows:
• 4” x 6” x 3/8” x l’-0” clip angles long leg vertical at 4
locations w/ (2) 5/8” dia. Titen HD’s or equal with 4” min.
embedment into the existing conc. wall. The angles can be
welded to the beam bottom flange or bolted. If bolting use (2)
¾” bolts and provide long slotted holes in the clip angles. Clip
angles shall be finished same as the steel frame;
• Weld the exterior bottom beam flange to the column cap
plates, all locations 4” x 3/16” min. fillet weld;
• All welds shall be painted with a cold galvanizing paint or
equal.
DPC, Inc. has reviewed photos of the as-built condition with
the additional required attachments. The as-built condition
meets the overall design intent.
Exhibit K—October 19 and 20, 2020 emails between Latisha Rhodes,
“Estimator” for Contractor, and Mr. Davis:
[From Ms. Rhodes to Mr. Davis, October 19 at 9:35 a.m.— “We did use the
existing base and filled with crushed concrete, it was then filled with water and
then compacted, then drilled se[e]p holes in the walls to remove the water and
added 4” steel columns schedule 80 and added 4000 psi concrete with fiber and
steel added, in which the steel frame will be set on with 8” anchors for steel
frame support.”
[From Mr. Davis to Ms. Rhodes, October 19 at 12:59 p.m.]— “Please
provide the following: • You added steel columns, what do they attach to/bear
on? Just to confirm you did not reuse the existing steel columns? • Was the
reinforcing used in the slab wire mesh [or] welded wire fabric? • How thick is
the slab? • How much concrete is over the column cap plates? • What are the
8”0 steel anchors? How many? Where are they located?”
[From Ms. Rhodes to Mr. Davis, October 20 at 8:50 a.m.]— “Are you going
to be going to Riverview . . . today to look at foundation? Asking so I can have
my guy meet you there. The anchor bolts will not be in until Wednesday.”
[From Mr. Davis to Ms. Rhodes October 20 at 3:16 p.m.]— “We have
reviewed the previously provided information for the Riverview K8 school
from emails and taken the information into consideration from the phone call
on 10-20-20. We have some concerns with how the slab was done. We do not
feel comfortable writing a letter with the current as-built condition. The main
concern is the overturning of the cooling tower during a high wind or seismic
event. For us to write a letter we would require additional modification;
however, another engineer may be willing to write a letter for the as-built
- 13 -
condition.”
Exhibit L—this November 11, 2020 letter from Mr. Sides to Contractor states:
From the consultation meeting held Monday November 9,
2020 at 1:00 p.m., [SCBE] has agreed to provide additional and
more specific details regarding the clarifications of the current
work in progress at Riverview K-8 School. . . .
The intent of these requests is to ensure [SCBE] will
obtain a final product that is completed effectively and
efficiently with standard construction practices to meet current
applicable codes that will result in a finished product with
minimal to zero long-term issues specifically related to the
existing cooling tower foundation and its modifications.
The following specific confirmations are being requested in
written format:
1. Confirmation from a structural engineer that the existing
concrete base in its original condition prior to the current
modifications and without its current modifications will meet
the load of the new cooling tower and structural support frame
and comply with any applicable codes. This was the original
requirement of the solicitation.
2. Confirmation and approval from the Contractor’s structural
engineer that the existing modifications completed by the
Contractor to the existing concrete base meet the criteria of the
letters from the structural engineer, Davis Patrikios Criswell,
dated July 8, 2020 and October 29, 2020. The specific
confirmations include:
A. Confirmation from their structural engineer that the new
composite fill installed by the Contractor in the existing
concrete base meets applicable codes in regards to type,
compaction, and moisture content specific to this installation
as this is a modification to the existing concrete base. Fill type
can be determined by a lift ticket from the fill supplier. []
B. Confirmation from their structural engineer that the new
composite fill installed by the Contractor will support the new
concrete slab as installed as this is considered a modification
to the existing concrete base.
C. Confirmation and approval from their structural engineer
that the thickness of the new concrete slab installed by the
- 14 -
Contractor meets the requirement in the engineer’s letter dated
July 8, 2020 for the required eight-inch (8”) minimum
embedment of the anchor bolts. Standard construction
practices require a ten (10”) inch to twelve (12”) thick slab to
acquire an eight-inch (8”) embedment.
D. Confirmation from their structural engineer that the new
concrete slab installed by the Contractor does not require steel
reinforcement for the condition that it is currently installed
specific to applicable codes for this installation. See
International Mechanical Code Section 908.4
E. Confirmation from their structural engineer that the new
concrete slab installation is not required to be tied into the
existing concrete base as this is a modification to the existing
concrete base. See international Mechanical Code Section
908.4 []
F. If tie-ins to the existing concrete base are not required,
confirmation from their structural engineer that expansion
material is not required for movement between two (2) separate
structural components specific to the new concrete slab and the
existing concrete base wall as this is a modification and impact
to the existing concrete base. See international Mechanical
Code Section 908.4 []
G. Confirmation and approval from their structural engineer
that the new concrete slab as installed without control joints by
the Contractor will perform and not crack with the existing
metal grate support steel angles and existing structural beam
that are encased within the new concrete slab as this is
considered a modification to the existing concrete base. []
H. Confirmation and approval from their structural engineer
that the new steel post and metal plates installed by the
Contractor in the fill of the existing concrete base meet the
applicable codes in regards to seismic (lateral load) and wind
uplift as this is considered a modification to the existing
concrete base. This is specifically in reference to the anchoring
method, if implemented, of the steel posts to the existing
concrete base under the unknown fill type. See International
Mechanical Code Section 908.4 []
I. Confirmation from their structural engineer that the existing
reinforced concrete base slab will be able to support the current
foundation modificatio