Big Iron Auction Co. v. Harder Capital
CourtNebraska Supreme Court
Date FiledJuly 31, 2026
DocketS-25-429
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
Nebraska Supreme Court Online Library
www.nebraska.gov/apps-courts-epub/
07/31/2026 08:20 AM CDT
- 918 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
Big Iron Auction Company, a Nebraska corporation,
appellee, v. Harder Capital, LLC, a Nebraska
limited liability company, and Ryan M. Harder,
an individual, appellants.
___ N.W.3d ___
Filed July 31, 2026. No. S-25-429.
1. Injunction: Equity. An action for injunction sounds in equity.
2. Equity: Appeal and Error. On appeal from an equity action, an appel-
late court decides factual questions de novo on the record.
3. Jurisdiction: Appeal and Error. The question of appellate jurisdiction
is a question of law.
4. Judgments: Appeal and Error. An appellate court reviews questions of
law independently of the lower court’s conclusion.
5. Jurisdiction: Appeal and Error. Before reaching the legal issues
presented for review, it is the duty of an appellate court to determine
whether it has jurisdiction over the matter before it.
6. Injunction: Damages. In the absence of any statute authorizing the
court to assess damages in the injunction suit, upon the dissolution of
the injunction, the court has no authority to do so; the party aggrieved
must resort to an independent action upon the bond.
7. Jurisdiction. Parties cannot confer subject matter jurisdiction upon a
judicial tribunal by either acquiescence or consent, nor may subject
matter jurisdiction be created by waiver, estoppel, consent, or conduct
of the parties.
8. Jurisdiction: Appeal and Error. If the court from which a party
appeals lacked jurisdiction, then the appellate court acquires no
jurisdiction.
9. Jurisdiction. Subject matter jurisdiction refers to the power of a tribunal
to hear and determine a case in the general class or category to which
the proceedings in question belong and to deal with the general subject
matter involved.
- 919 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
10. Constitutional Law: Courts: Jurisdiction. Both chancery and com-
mon law jurisdiction are conferred upon the district court by the
Nebraska Constitution.
11. Courts: Jurisdiction: Legislature: Appeal and Error. The Legislature
has provided the district court with general, original, and appellate
jurisdiction in all matters, both civil and criminal, except where other-
wise provided.
12. Appeal and Error. An appellate court will not consider an issue on
appeal that was not presented to or passed upon by the trial court.
13. ____. In the absence of plain error, an appellate court considers only
claimed errors which are both assigned and discussed.
14. Arbitration and Award. Courts are obliged to enforce the parties’
agreement to arbitrate according to its terms.
15. ____. An arbitrator’s power derives from the parties’ agreement.
16. Arbitration and Award: Federal Acts. After an arbitral award has
issued, a court having jurisdiction may confirm, vacate, or modify
such an award under 9 U.S.C. § 9, § 10, or § 11 (Reissue 2018) of the
Federal Arbitration Act.
17. Actions: Appeal and Error. When it applies, the law‑of‑the‑case doc-
trine operates to preclude reconsideration of substantially similar, if not
identical, issues at successive stages of the same suit or prosecution.
18. Arbitration and Award. The purpose of arbitration is the quick
resolution of disputes and the avoidance of the expense and delay
associated with litigation. In serving that purpose, a court gives strong
deference to the arbitrator because when parties agree to arbitration,
they agree to accept whatever reasonable uncertainties might arise
from the process.
19. Injunction: Damages. Damages for the wrongful obtaining and issu-
ance of an injunction or restraining order are confined to just and
adequate compensation for the actual loss which is the natural and
proximate result of the restraint imposed.
20. Injunction: Damages: Attorney Fees. The necessary and reason-
able expenses for attorney fees expended or incurred in resisting or
procuring the dissolution of an order of injunction wrongfully issued
are recoverable as an element of damages, but, when the right to an
injunction is not the main issue of the case, such damages are limited
to the expenses incurred in securing the dissolution of the injunction,
as distinguished from the expenses incurred in the trial of the principal
issues involved.
21. ____: ____: ____. It is only where a trial of the principal issues
involved is necessary to dispose of an injunction that attorney fees for
- 920 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
the trial of the case are proper to be allowed as damages caused by an
injunction wrongfully issued.
22. ____: ____: ____. A recovery of attorney fees for the trial of a case
cannot be allowed as an element of damages for an injunction wrong-
fully obtained, if the injunction proceedings be only auxiliary to the
main case.
Appeal from the District Court for Hall County: Andrew C.
Butler, Judge. Affirmed as modified.
Jared J. Krejci, of Smith, Johnson, Allen, Connick & Hansen,
for appellants.
Justin D. Eichmann and Keith A. Harvat, of Houghton
Bradford Whitted, P.C., L.L.O., and Jeffrey C. Jarecki, of
Jarecki Sharp & Petersen, P.C., L.L.O., for appellee.
Funke, C.J., Cassel, Stacy, Papik, Freudenberg,
Bergevin, and Vaughn, JJ.
Cassel, J.
INTRODUCTION
This appeal presents a novel intersection between arbi-
tration and long‑established law governing damages for an
improperly granted injunction. In this complicated civil action
partially referred to arbitration, an auction service company’s
former agent appeals from an order overruling a motion for
damages, including attorney fees and expenses, under the
injunction undertaking statute. 1 We first address jurisdiction
and settle the standard of review. We then reach the key dis-
pute: whether the arbitral award effectively dictated the out-
come of the agent’s motion, as the district court concluded.
Because it did regarding all damages except attorney fees and
expenses, we affirm the court’s order as modified.
1
See Neb. Rev. Stat. § 25‑1067 (Reissue 2016).
- 921 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
BACKGROUND
Parties’ Relationship and Agreement
Big Iron Auction Company (Big Iron) provides auction
services. Between 2009 and 2023, Big Iron engaged Harder
Capital, LLC, and Ryan M. Harder (collectively Harder) as
an independent sales representative (ISR). As an ISR, Harder
represented Big Iron’s brand services and products in exchange
for commissions earned on auction sales arranged by Harder on
Big Iron’s online auction platform.
The parties defined their relationship in writing. The
operative ISR agreement contained two sections bearing on
this case.
One section—paragraph 11—set forth restrictive covenants,
including a noncompete clause. The clause prohibited the ISR
from soliciting the business of any of Big Iron’s customers
and from being a sales representative for a competitor for 2
years following termination of the agreement.
The other key section—paragraph 16—addressed dispute
resolution. It stated that the parties agreed to arbitrate their
claims and that the Federal Arbitration Act would govern the
proceedings. It conferred upon the arbitrator “exclusive author-
ity to resolve any dispute relating to the interpretation, appli-
cability, enforceability[,] or formation” of the ISR agreement.
The dispute resolution section also addressed the scope of
the matter to be arbitrated, including three rather long sen-
tences from which we capture pertinent language.
The first sentence spoke broadly. It stated that the parties
“mutually consent to the resolution by arbitration of all claims
or controversies (‘claims’), past, present or future, whether or
not arising out of the [ISR] agreement (or its termination), that
[Big Iron] may have against [Harder] or that [Harder] may
have against [Big Iron].”
The other two narrowed the scope. One stated, “The only
claims that are arbitral are those that, in the absence of this
Agreement, would have been eligible for court action under
- 922 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
applicable state or federal law.” Then, in a sentence specify-
ing claims “not covered,” the other one excluded “claims by
[Big Iron] or by [Harder] for temporary or permanent restrain-
ing orders or preliminary or permanent injunctions (‘equitable
relief’) in cases in which such equitable relief would be other-
wise authorized by law and any relief by [Big Iron] for claims
related to claims under paragraph[] 11.”
In October 2023, Harder terminated engagement as an ISR
for Big Iron. Harder began selling auction services using a dif-
ferent online platform in apparent violation of the restrictive
covenants in the ISR agreement.
Complaint, Motion to Compel Arbitration,
and Temporary Injunction
Big Iron filed a complaint against Harder in district court.
It set forth causes of action for breach of contract, injunc-
tive relief, and tortious interference. Big Iron requested an
injunction prohibiting Harder from interfering with Big Iron’s
employee and customer relationships.
Harder moved to compel arbitration regarding the counts
alleging breach of contract and tortious interference. The court
held a hearing, where a question arose.
The court asked how paragraph 16’s provisions—one giving
the arbitrator exclusive authority to resolve any dispute relat-
ing to the interpretation, applicability, enforceability, or forma-
tion of the agreement—could be reconciled with the exclusion
language relating to paragraph 11. Big Iron’s counsel stated,
“[T]here isn’t any question the equitable relief issue is an issue
for this Court to decide today” and that whether to send “the
other legal remedies to an arbitrator for determination, I will
leave that to the discretion of the Court.” The court stated that
it was ruling on the temporary injunction and that the issue “is
specifically carved out not for an arbitrator.”
The court entered an order sustaining in part the motion
to compel arbitration. The court’s order required the par-
ties to “submit each of their claims and defenses, other than
- 923 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
[Big Iron’s] claim for injunctive relief, to arbitration pursuant
to the terms and conditions found in paragraph 16” of the ISR
agreement. The order also specified that the arbitration would
include “‘any dispute relating to the interpretation, applica-
bility, enforceability[,] or formation of [the ISR Agreement],
including but not limited to any claim that all or any part of
[such] Agreement is void or voidable.’”
The court also sustained in part Big Iron’s motion for a
temporary injunction. It precluded Harder from violating the
restrictive covenants in the ISR agreement. To prevent any
injury to a third party, the temporary injunction included an
exception for auction listings that Harder currently had on
the competing platform. However, any proceeds payable to
Harder were to be deposited into a trust account until further
order of the court.
The court set the amount of the undertaking required by
§ 25-1067 for entry of the requested temporary injunction at
$300,000. With respect to a bond or undertaking, the record
contains only a letter to the judge’s bailiff stating that Big
Iron enclosed a check in accordance with the court’s order for
remittance of bond.
During the interval between the order compelling arbitra-
tion and the resolution of the arbitration proceedings, each
party sought relief from the district court concerning the
temporary injunction. Harder moved to vacate or modify the
temporary injunction. Big Iron filed an application for an
order to show cause, alleging that Harder had willfully vio-
lated the injunction. Following a hearing, the court overruled
these motions.
Arbitration Proceeding
Harder filed an answer and counterclaim in the arbitra-
tion proceeding. With respect to the count of the complaint
seeking injunctive relief, Harder stated, “This claim is not
subject to arbitration.” For its counterclaim, Harder alleged
a cause of action for breach of contract. Harder asserted that
- 924 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
a glitch on Big Iron’s platform was a substantial problem and
that Harder terminated the ISR agreement primarily because
of the glitch and Big Iron’s failure or inability to resolve
it. Harder alleged that after terminating the agreement, Big
Iron refused to pay Harder approximately $22,000 in unpaid
earned commissions.
In December 2024, the arbitration tribunal entered a final
decision and order. The arbitrator determined that the restric-
tive covenants were unenforceable. With regard to damages,
the arbitrator determined that the funds currently in trust
should be paid to Harder. It stated: “The only other damages
are the commissions that were made on sales that occurred
while Harder was still an ISR, but were not paid because of
the alleged breach of the restrictive covenants.” The arbitrator
calculated that amount to be $19,405.91.
Using language upon which the parties now focus, the arbi-
trator then stated:
There are no other recoverable damages that could be
awarded to Harder . . . based on the invalidation of the
restrictive covenants. Measuring those damages would
be too speculative. Obviously, the 1099s are not a basis
for calculating damages because those numbers represent
gross revenue not net revenue. In essence, Harder’s status
would be equivalent to starting a new business. Awarding
damages for a startup business are very speculative
and have generally not been allowed by the Nebraska
Supreme Court.
The arbitrator determined that the parties should be respon-
sible for their own share of the “fees and expenses of arbitra-
tion.” It explained:
While Harder . . . is a prevailing party on the enforce-
ability of the restrictive covenants, there are aspects of
the dispute in which Big Iron was a prevailing party, in
particular any potential damages for the “glitch.” I also
think this ruling is consistent with Nebraska law where
- 925 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
parties generally are required to pay their own fees and
expenses regardless of the outcome.
Return to District Court
In early December 2024, Harder filed two motions with the
district court. One, an ex parte motion to vacate the temporary
injunction, was based on the determination by the arbitrator
that the restrictive covenants were invalid. The court imme-
diately vacated the temporary injunction. The other motion
sought to assess damages, costs, and fees for the wrongful
injunction. In January 2025, Harder filed a motion and applica-
tion to confirm the arbitral award.
Following a hearing on the two unresolved motions (dam-
ages and confirmation), the court entered an order confirm-
ing the arbitral award on March 10, 2025. Pursuant to the
award, the court entered a judgment of $19,405.91 in favor
of Harder.
Months later, on May 28, 2025, the court entered an order
denying the motion to assess damages, costs, and fees for the
wrongful injunction. The court stated that once an arbitral
award is confirmed, “claims that were or could have been
addressed in arbitration are barred by res judicata” and that
“where a . . . confirmed arbitration award resolves all issues
arising from the wrongful enforcement, that award may have
preclusive effect on collateral bond claims—particularly when
the arbitrator’s decision includes findings that address or fore-
close further damages.”
The court observed that the arbitrator made findings as to
damages, fees, and costs. The court stated that the arbitrator
used “broad and preclusive” language clearly conveying that
there were no other recoverable damages based on the invali-
dation of the restrictive covenants. The court reasoned that
the arbitrator’s language did not appear to limit the damages
and that a plain reading of the language showed the dam-
ages included all forms of damages resulting from the invalid
attempt to enforce the covenant.
- 926 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
The court addressed Harder’s claim that the arbitrator went
beyond the scope of the arbitration clause. The court stated:
Even if [Harder is] correct that the Arbiter’s finding
was outside the scope of the ISR Agreement’s arbitra-
tion clause or that damages were not squarely before the
Arbiter, [Harder] should have sought to modify or vacate
this portion of the Award, because the language of the
Award demonstrates the Arbiter made findings related to
those damages.
The court found that because the issues of damages, fees,
costs, and expenses were all decided by the arbitrator in the
award—which the court confirmed at Harder’s request—“any
additional assessment of damages and fees by the Court would
be tantamount to a vacatur or modification of the Award con-
trary to the provisions of the Nebraska [Uniform Arbitration
Act] and [the Federal Arbitration Act].” The court ordered
the district court clerk’s office to hold the $300,000 in bond
proceeds until the appeal time had run or until further order of
the court. It stated that if no appeal was timely taken, the dis-
trict court clerk should distribute $19,405.91 and any accrued
interest to Harder.
Harder appealed, and we moved the appeal to our docket. 2
We directed the parties to submit supplemental briefs regarding
the potential application of one of our prior decisions. 3 They
did so, and we have considered their submissions.
ASSIGNMENTS OF ERROR
Harder assigns four errors that challenge the denial of
its motion to assess damages, costs, and fees for a wrong-
ful injunction. It alleges, consolidated, that the court erred
in denying the motion, in failing to enter judgment on the
motion for $587,104.68, and in “apparently determining” that
as a result of the arbitrator’s award, the motion was barred
2
See Neb. Rev. Stat. § 24-1106(3) (Cum. Supp. 2024).
3
See Higgins v. Adelson, 131 Neb. 820, 270 N.W. 502 (1936).
- 927 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
by claim or issue preclusion even though preclusion was not
raised as an affirmative defense.
STANDARD OF REVIEW
The parties disagree regarding our scope of review.
According to Harder, the case began primarily for breach of
contract, but Harder, noting the referral to arbitration and the
temporary injunction, proposes an equity standard. Big Iron
argues for a standard applicable to decisions vacating, modify-
ing, or confirming an arbitral award.
As we discuss below, our precedent on damages upon an
injunction undertaking had become somewhat muddled. If an
independent action for damages upon an injunction undertak-
ing had been asserted, we would have applied the standard for
the bench trial of a law action. 4
[1] But after the law issues (breach of contract and tortious
interference) were referred to arbitration, all that remained
was an action for injunction. An action for injunction sounds
in equity. 5 After the arbitration concluded, Harder simultane-
ously sought dissolution of the injunction and damages upon
the undertaking. Thus, it raised a law claim by motion within
the equity proceeding. 6
Although Harder later sought confirmation of the arbitral
award, the award was confirmed and no appeal was taken
within 30 days thereafter. 7 Thus, all that remained was the
motion for damages, fees, and expenses on the injunction
undertaking.
4
See id. See, also, Burbank v. Evnen, ante p. 65, 32 N.W.3d 612 (2026)
(stating standard).
5
Charter West Bank v. Riddle, 314 Neb. 263, 989 N.W.2d 428 (2023).
6
See Schmid v. Simmons, 311 Neb. 48, 970 N.W.2d 735 (2022) (reciting
equitable cleanup doctrine).
7
See Neb. Rev. Stat. § 25-2620(a)(3) (Reissue 2016) (appeal may be taken
from order confirming award). See, also, Kremer v. Rural Community Ins.
Co., 280 Neb. 591, 788 N.W.2d 538 (2010).
- 928 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
[2-4] On appeal from an equity action, an appellate court
decides factual questions de novo on the record. 8 The ques-
tion of appellate jurisdiction is a question of law. 9 An appel-
late court reviews questions of law independently of the lower
court’s conclusion. 10
ANALYSIS
Jurisdiction of Claim for Damages
on Improper Injunction
[5] Before reaching the legal issues presented for review, it
is the duty of an appellate court to determine whether it has
jurisdiction over the matter before it. 11 We do so now.
[6] Long ago, we stated that in the absence of any statute
authorizing the court to assess damages in the injunction
suit, upon the dissolution of the injunction, the court has no
authority to do so; the party aggrieved must resort to an inde-
pendent action upon the bond. 12 Then, as now, the “bond”
was the “undertaking” required by § 25-1067—which must
be “give[n]” before an injunction can become operative in
order to “secure to the party enjoined the damages he [or
she] may sustain, if it be finally decided that the injunction
ought not to have been granted.” A respected commentator
opines consistently. 13 Litigants in another early case followed
a similar course. 14
This principle derived from ancient equity practice.
According to the rules of the high court of chancery in England,
a court of equity cannot, when it dissolves an injunction,
8
Goldie v. McNeil & Co. Builders, ante p. 84, 32 N.W.3d 626 (2026).
9
WRK v. Wiegert, 320 Neb. 822, 30 N.W.3d 832 (2026).
10
Martens v. BB’s Childcare, ante p. 335, 34 N.W.3d 393 (2026).
11
Id.
12
Higgins v. Adelson, supra note 3.
13
John P. Lenich, Nebraska Civil Procedure § 18:18 at 877 (2026) (“separate
action” required).
14
See Williams v. Hallgren, 149 Neb. 621, 31 N.W.2d 737 (1948).
- 929 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
give judgment at the same time against the obligors, but
merely orders dissolution, leaving the obligee to proceed at
law against the sureties if he sustains damage by the delay
occasioned by the injunction. 15 We applied this principle,
stating that “‘in the absence of positive legislation a court of
equity has no power to afford a remedy upon the bond in the
injunction suit.’” 16
No such statutory change followed.
But our recent decisions, upon which Harder relies, departed
from that principle. In 1997, applying a different statute, 17
which must be read together with yet another statute, 18 and
without discussing our earlier case law, we reversed an injunc-
tion given below and entertained in this court a motion of
the bond’s principal for the bond’s exoneration. 19 Although
we denied the motion, we “remanded [the cause] to the dis-
trict court for the determination of any damages that may
have been sustained by [the party improperly enjoined] as
a result of the injunction issued below.” 20 In other words,
in 1997, we relied upon a supersedeas bond statute, rather
than § 25-1067, the injunction undertaking statute. The inapt
statutory citation and unobserved precedent tainted our 1997
decision. This decision was the authority upon which we
relied in 2007, when we reversed a permanent injunction
and remanded the cause to the district court “with directions
to determine in the first instance whether [the enjoined par-
15
See Bein et al. v. Heath, 53 U.S. 168, 13 L. Ed. 939 (1851).
16
Higgins v. Adelson, supra note 3, 131 Neb. at 829, 270 N.W. at 507
(quoting 2 James L. High & Shirley T. High, Treatise on the Law of
Injunctions (4th ed. 1905)).
17
See Neb. Rev. Stat. § 25-1079 (Reissue 2016) (establishing requirements
for supersedeas bond authorized by preceding section).
18
See Neb. Rev. Stat. § 25-1078 (Reissue 2016) (authorizing supersedeas
bond to keep injunction effective after order dissolving or modifying).
19
See Robertson v. School Dist. No. 17, 252 Neb. 103, 560 N.W.2d 469
(1997).
20
Id. at 113, 560 N.W.2d at 477.
- 930 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
ties were] entitled to recover . . . damages from [the bond
principal] under the injunction bond or otherwise,” 21 which, in
turn, served as the basis for our 2009 decision that damages
were not limited to the bond amount. 22
Here, other irregularities occurred below. Section 25-1067,
unlike the general appeal supersedeas statute, 23 does not autho-
rize a cash deposit. Nonetheless, Big Iron deposited cash and
the record does not show that Harder raised any objection. Nor
does the record show any direct written undertaking by Big
Iron, as specified in the statutory language. 24 Here also, Harder
apparently raised no objection.
[7,8] But despite all that, neither party objected to proceed-
ing against the cash deposit in the injunction suit. Nor does
either party assert error in this regard on appeal. Of course,
parties cannot confer subject matter jurisdiction upon a judicial
tribunal by either acquiescence or consent, nor may subject
matter jurisdiction be created by waiver, estoppel, consent, or
conduct of the parties. 25 And if the court from which a party
appeals lacked jurisdiction, then the appellate court acquires
no jurisdiction. 26
[9-11] The district court had subject matter jurisdiction.
Subject matter jurisdiction refers to the power of a tribunal
to hear and determine a case in the general class or category
to which the proceedings in question belong and to deal
with the general subject matter involved. 27 Both chancery
21
Koch v. Aupperle, 274 Neb. 52, 69-70, 737 N.W.2d 869, 882 (2007).
22
Koch v. Aupperle, 277 Neb. 560, 763 N.W.2d 415 (2009).
23
See Neb. Rev. Stat. § 25-1916 (Reissue 2016) (must execute bond with
surety, deposit U.S. Government bonds, or in lieu thereof make cash
deposit).
24
See § 25-1067. See, also, 3 Louis Lightner, Nebraska Forms Annotated
§ 3862 (1951).
25
Martens v. BB’s Childcare, supra note 10.
26
Id.
27
Lopez v. Catholic Charities, 315 Neb. 617, 998 N.W.2d 31 (2023).
- 931 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
and common law jurisdiction are conferred upon the district
court by the Nebraska Constitution. 28 And the Legislature
has provided the district court with “general, original and
appellate jurisdiction in all matters, both civil and crimi-
nal, except where otherwise provided.” 29 Whether Harder’s
damage claim arose in equity, under the common law, or by
operation of § 25-1067, subject matter jurisdiction was vested
in the district court.
[12,13] Two principles then apply. An appellate court will
not consider an issue on appeal that was not presented to or
passed upon by the trial court. 30 And in the absence of plain
error, an appellate court considers only claimed errors which
are both assigned and discussed. 31 It necessarily follows that
by failing to raise the matter in the district court and by
assigning no error thereto here, the parties have forfeited any
error by the district court in entertaining equitable jurisdiction
over a legal claim for damages for the improperly granted
injunction. Because the district court had subject matter juris-
diction, we have jurisdiction of this appeal.
Parties’ Arguments
At its heart, the parties’ legal dispute is simple. Harder con-
tends that the damages it sought for wrongful injunction were
“different” from the damages rejected by the arbitrator for
invalidation of the restrictive covenants. 32 Big Iron disagrees,
characterizing them as the “exact same damages.” 33
Harder further argues: The arbitrator had no authority over
equitable claims and issues pertaining to temporary injunc-
tions. Wrongful injunction damages were not raised or ripe at
28
See id.
29
Neb. Rev. Stat. § 24-302 (Reissue 2016).
30
Aguilar v. Valdez-Mendoza, 318 Neb. 402, 16 N.W.3d 130 (2025).
31
In re Trust of Rosenberg, 273 Neb. 59, 727 N.W.2d 430 (2007).
32
Brief for appellant at 29.
33
Brief for appellee at 24.
- 932 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
the time of the arbitration proceeding. Issue and claim preclu-
sion did not apply. The causal mechanisms were different. Big
Iron never raised preclusion as an affirmative defense.
Big Iron points to the breadth of the ISR agreement. It
highlights Harder’s failure to seek vacatur or modification of
the arbitral award and its actions and statements in seeking
confirmation of the award’s entirety. Big Iron also focuses on
the award’s language regarding harm from enforcement of the
invalid restrictive covenants. And it asserts that the arguments
regarding issue or claim preclusion were not presented to the
district court.
We disagree with Big Iron that arguments regarding issue
or claim preclusion were not presented to or passed upon
by the district court. Harder’s reply brief in support of its
motion to assess damages touched on the issue, and the district
court’s order stated that “claims that were or could have been
addressed in arbitration are barred by res judicata.” To the
extent Harder complains about preclusion not being pled as an
affirmative defense, we observe that it was Harder that elected
to proceed on motions and without pleadings. We also note that
our pleading rules contemplate supplemental pleadings “setting
out any transaction, occurrence, or event that happened after
the date of the pleading to be supplemented.” 34 We express no
opinion regarding the applicability of that procedure except to
note that it might have provided a mechanism for pleading or
failing to plead issue or claim preclusion.
Before we turn to the matter not resolved by arbitration,
we must consider the award’s effect, including any preclusive
effect, on the issues.
Effect of Arbitration
[14-16] Courts are obliged to enforce the parties’ agree-
ment to arbitrate according to its terms. 35 An arbitrator’s
34
Neb. Ct. R. Pldg. § 6-1115(d) (rev. 2025).
35
Stolt-Nielsen S. A. v. AnimalFeeds Int’l Corp., 559 U.S. 662, 130 S. Ct.
1758, 176 L. Ed. 2d 605 (2010).
- 933 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
power derives from the parties’ agreement. 36 And as the U.S.
Supreme Court recognized, after an arbitral award has issued,
a court having jurisdiction may confirm, vacate, or modify
such an award under 9 U.S.C. § 9, § 10, or § 11 (2018) of the
Federal Arbitration Act. 37
The ISR agreement provided for the resolution of all claims
between the parties, including future claims. The agreement
stated that arbitration did not cover claims for restraining
orders or injunctions or any relief by Big Iron for “claims
related to claims” under certain paragraphs, including para-
graph 11 on restrictive covenants. The agreement gave the
arbitrator “exclusive authority to resolve any dispute relating to
the interpretation, applicability, enforceability[,] or formation
of this Agreement, including but not limited to any claim that
all or any part of this Agreement is void or voidable.”
In a section of the arbitral award on damages, the arbitrator
made two findings; but only the second one matters here. The
first determined the amount of commissions to which Harder
was entitled on sales that Big Iron claimed were in violation of
the restrictive covenants. That amount, included in the district
court’s judgment, is not disputed on appeal.
The second finding stated that “[t]here are no other recov-
erable damages that could be awarded to [Harder] based on
the invalidation of the restrictive covenants.” The arbitrator
characterized such damages as “speculative.” He explained
that “1099s” were not a proper basis for calculating damages
and that “Harder’s status would be equivalent to starting a
new business.”
In seeking damages for the wrongful injunction in district
court, Harder explained its calculation for its request of over
$500,000. It based its calculation on its 1099 tax form for the
36
See City of Omaha v. Professional Firefighters Assn., 309 Neb. 918, 963
N.W.2d 1 (2021).
37
See Jules v. Andre Balazs Properties, ___ U.S. ___, 146 S. Ct. 1209, 224
L. Ed. 2d 708 (2026).
- 934 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
year 2023 (divided by 10, for the 10 months of auction sales
that year), plus the $19,405.91 that the arbitrator determined
should have been paid to Harder (which Harder also divided
by 10). Then it added those two monthly amounts and multi-
plied that number by 12 months.
We are not persuaded that, in this regard, the arbitrator’s
determination of damages “based on the invalidation of the
restrictive covenants” somehow differs from damages for
enforcement of the restrictive covenants by means of the tem-
porary injunction.
To try to avoid this problem, Harder relies on exclusionary
language in paragraph 16. It quotes the language excluding
“claims by [Big Iron] or by [Harder] for temporary or perma-
nent restraining orders or preliminary or permanent injunctions
(‘equitable relief’) in cases in which such equitable relief
would be otherwise authorized by law.” Essentially, Harder
maintains that a damage claim for an improper injunction is
part of a claim for restraining orders or injunctions.
Beyond the strained nature of Harder’s argument, at least
two flaws doom it. First, as our discussion of jurisdiction
demonstrates, an action on an injunction undertaking is a
separate claim at law and not part of the proceeding in equity
for injunction. But perhaps more important, the argument con-
flicts with the remainder of the agreement’s sentence, which
excludes only “any relief by [Big Iron] for claims related to
claims under paragraph[] 11.” It does not exclude any relief
by Harder. Thus, Harder’s claim for relief relating to dam-
ages from an invalid restrictive covenant was not excluded—
stated affirmatively, the broad agreement to arbitrate applied to
Harder’s claim for damages.
But even if the arbitrator somehow exceeded his authority,
Harder forfeited that argument. At least two avenues to chal-
lenge the award were available.
First, under 9 U.S.C. § 10(a)(4), Harder could have sought
an order from the district court “vacating the award . . . where
- 935 -
Nebraska Supreme Court Advance Sheets
321 Nebraska Reports
BIG IRON AUCTION CO. v. HARDER CAPITAL
Cite as 321 Neb. 918
the arbitrator[] exceeded [his] powers.” A party seeking relief
under § 10(a)(4) bears a heavy burden; it is not enough to
show that the arbitrator committed an error. 38 The sole ques-
tion for a court reviewing an arbitral award is whether the
arbitrator, even arguably, interpreted the parties’ contract, not
whether the arbitrator got its meaning right or wrong. 39 Harder
did not pursue this course.
Nor did Harder avail itself of the other possibility—to
seek modification or correction under 9 U.S.C. § 11(b),
applicable where “the arbitrator[ has] awarded upon a matter
not submitted.”
Instead, Harder sought confirmation of the arbitral award
under 9 U.S.C. § 9. The district court granted confirma-
tion and entered judgment against Big Iron for the total sum
awarded to Harder by the arbitrator. Under 9 U.S.C. § 13
(2018), “The judgment so entered shall have the same force
and effect, in all respects, as . . . a judgment in an action; and
it may be enforced as if it had been rendered in an action in
the court in which it is entered.”
[17] Upon Harder’s motion to confirm the award (and in
the absence of any request to vacate, modify, or correct the
award), the district court had no option but to enter judgment
confirming the arbitral award. That judgment then became the
law of the case. Unlike the doctrines of claim pr