Vogtscapes, Inc. v. Nemaha County
CourtNebraska Court of Appeals
Date FiledJune 23, 2026
DocketA-25-481
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
Nebraska Supreme Court Online Library
www.nebraska.gov/apps-courts-epub/
06/30/2026 08:08 AM CDT
- 329 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
Vogtscapes, Inc., and Nebraska Digging
Services LLC, appellants, v. Nemaha
County, Nebraska, appellee.
___ N.W.3d ___
Filed June 23, 2026. No. A-25-481.
1. Summary Judgment: Appeal and Error. An appellate court reviews
the district court’s grant of summary judgment de novo, viewing the
record in the light most favorable to the nonmoving party and drawing
all reasonable inferences in that party’s favor.
2. ____: ____. An appellate court affirms a lower court’s grant of summary
judgment if the pleadings and admitted evidence show that there is no
genuine issue as to any material facts or as to the ultimate inferences
that may be drawn from the facts and that the moving party is entitled to
judgment as a matter of law.
3. Contracts. The interpretation of a contract and whether the contract is
ambiguous are questions of law subject to independent review.
4. Summary Judgment. Summary judgment is proper when the pleadings
and the evidence admitted at the hearing disclose that there is no genu-
ine issue as to any material facts or as to the ultimate inferences that
may be drawn from those facts and that the moving party is entitled to
judgment as a matter of law.
5. Summary Judgment: Evidence. The evidence that may be received on
a motion for summary judgment includes depositions, answers to inter-
rogatories, admissions, stipulations, and affidavits.
6. Summary Judgment. In the summary judgment context, a fact is mate-
rial only if it would affect the outcome of the case.
7. Contracts: Intent. The interpretation given a contract by the parties
themselves while engaged in the performance of the contract is one of
the best indications of the true intent of the parties and, ordinarily, that
construction of the contract should be enforced.
8. Contracts. The parties to a contract may avoid a provision where their
words, acts, or conduct amount to a waiver, modification, rescission,
- 330 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
abrogation, or abandonment of the provision, or the party claiming the
benefit of the provision is estopped to rely on it.
Appeal from the District Court for Nemaha County: Julie D.
Smith, Judge. Reversed and remanded for further proceedings.
Tevyn L. Waddell and Craig F. Martin, of Lamson Dugan &
Murray, L.L.P., for appellants.
Jeffery R. Kirkpatrick, of Governmental Law, L.L.C., for
appellee.
Riedmann, Chief Judge, and Bishop and Welch, Judges.
Welch, Judge.
INTRODUCTION
Vogtscapes, Inc., and Nebraska Digging Services LLC
(Nebraska Digging) (collectively Appellants) appeal from
the Nemaha County District Court’s order granting Nemaha
County’s motion for summary judgment and dismissing
Appellants’ complaint with prejudice. Appellants contend
that the district court erred in granting summary judgment in
favor of Nemaha County when genuine issues of material fact
existed. For the reasons stated herein, we reverse, and remand
for further proceedings.
STATEMENT OF FACTS
Background
This appeal arises out of a construction dispute between
Nemaha County and Appellants. Nemaha County retained
Vogtscapes as a general contractor to replace a county road
bridge with a concrete box culvert (the Project). Nemaha
County retained Mainelli Wagner & Associates, Inc. (Mainelli
Wagner), to serve as the engineer for the Project, and
Vogtscapes subcontracted with Nebraska Digging to per-
form dirt work associated with the Project. In connection
with the dirt work, Nebraska Digging contends that Nemaha
County and Mainelli Wagner requested that Nebraska Digging
- 331 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
relocate a dirt stockpile created during the initial grading
and excavation process. In short, at the end of the Project,
Appellants claimed the work performed in relocating the
stockpile constituted additional work on the Project for which
Nebraska Digging was entitled to additional compensation
over and above its original contract price. Nemaha County
refused Appellants’ claim on the basis that relocating the dirt
stockpile did not constitute additional work, that it was work
contemplated as part of the original contract price, and that
Appellants failed to obtain a written change order in order to
seek additional compensation.
Contract
The contract between Vogtscapes and Nemaha County estab-
lished that the contract price was $752,311 “with no additions
or deletions, except by written change order as set forth in the
Contract Documents.” It is undisputed that no written change
orders were ever executed in connection with the Project.
Notably, the contract contained several other provisions rel-
evant to this appeal.
• Vogtscapes was retained to perform the “work” on the Project.
• The “work” itself was to be completed “according to the
Contract Documents, including the Standard Specifications
and any Standard Plans.”
• The Project plans, specifications, and drawings were prepared
by Mainelli Wagner.
• Mainelli Wagner was separately required to provide “general
supervision and direction of the Work and [would] decide
any questions that [arose] with reference to the intent of the
Contract Documents and compliance therewith.”
• The contract provided that “[Mainelli Wagner] is the agent
of [Nemaha County] only to the extent provided in the
Contract Documents or when specifically authorized to act on
[Nemaha County’s] behalf.”
• Vogtscapes, as the contractor, was responsible for “construc-
tion means or methods to successfully perform the Work;
- 332 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
supervision or coordination of the Work in accordance with
the Contract Documents; or any health or safety precautions
required by any regulatory agency, industry standards, or
common sense.”
• The earthwork section of the contract provided that “[e]xca-
vation and backfill required by the Work will be considered
subsidiary to items for which direct payment is made.”
Work on the Project
In connection with the summary judgment proceedings,
Appellants supplied the following facts:
• Mainelli Wagner designated Dean Britt to serve as construc-
tion inspector for the Project.
• Michael Weiss, a member of the Nemaha County Board
of Commissioners, was in regular communication with
Vogtscapes and Mainelli Wagner.
• Keith Sunderman served as the project manager for
Vogtscapes.
• Vogtscapes subcontracted with Nebraska Digging to perform
dirt work on the Project.
• Tyler Rosenow, a 50-percent owner of Nebraska Digging, rep-
resented Nebraska Digging on issues concerning the Project
and concerning issues relevant to the litigation regarding
the Project.
• The contract stated that “Contractor to coordinate with County
during construction for a location of stockpile onsite for
unused embankment after excavation. County will haul off
excess embankment from site after construction is completed.”
• In accordance with that provision, Rosenow met with Weiss
and the designated project superintendent at the beginning
of the Project to get approval for the location of the relevant
dirt stockpile.
• During that discussion, the participants were made aware that
there would be a significant amount of excess dirt left over at
the end of the Project.
- 333 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
• The location designated for the original stockpile was autho-
rized by Weiss and the project superintendent even though
its location was on top of an area that was going to have a
driveway constructed later during the Project.
• The location chosen for the stockpile was due to logistical
constraints on where the dirt was capable of being placed
within the boundaries of the Project.
• The parties were made aware that the stockpile would be in
the way during later stages of the Project.
• Later in the Project, on the first day that Nebraska Digging
began backfilling dirt from the stockpile, Rosenow raised
concerns and made numerous inquiries to Britt and Weiss con-
cerning the plan for excess dirt left over from that stockpile.
• A meeting was held in October 2023 to address the aforemen-
tioned concern, among other issues.
• During the October 2023 meeting attended by Britt, Weiss,
Sunderman, and Rosenow, the parties agreed and acknowl-
edged that the excess dirt stockpile was an obstruction to
completion of the Project and needed to be moved.
According to Rosenow’s rendition of the facts from this
meeting, the following discussions and resolutions ensued:
• Rosenow suggested that the stockpile could be moved to
the location of another nearby stockpile, which would clear
the impediment to completing the Project and which Rosenow
claimed would be more cost effective than other solutions.
• Rosenow claimed that Britt rejected his suggestion and
directed him to relocate and “waste” dirt in multiple areas.
• Rosenow raised the need for a written change order for the
additional work to relocate the stockpile, but Weiss and Britt
rejected submitting a written change order because it would
require a board meeting and would hold up progress on
the Project.
• Rosenow claimed that, as an alternative, Britt informed him
the additional work associated with moving the stockpile
would be documented as an overrun on the Project and
instructed Rosenow to track the number of truckloads used
- 334 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
to complete the additional dirt work with the understanding
that the number of truckloads would be used to determine the
overrun payment.
• Sunderman likewise testified that Britt indicated at this meet-
ing that the relocation of the stockpile would constitute
and be paid as an overrun and that a change order was not
required because it would hold up the Project.
• Rosenow claimed that Britt instructed him to “waste” dirt
within the Project in such a way that would add an addi-
tional 2 feet to the driveway, make the “ditch bottoms” 5 feet
instead of 8 feet, build up the areas around the box culvert,
and move some of the dirt from the original stockpile to
other areas outside the Project boundaries based upon agree-
ments obtained by Mainelli Wagner and Nemaha County with
nearby landowners.
• Rosenow claimed that this work was beyond the original
scope of the Project and that Nemaha County and Mainelli
Wagner were aware that such work constituted a change to
the original engineering plans.
• Rosenow asserted that as a result of the meeting, Nebraska
Digging began tracking the number of truckloads hauled to
complete the excess work, which tracking was not done pre-
viously in relation to the Project.
• After completing the work and supplying the number of
truckloads, Britt emailed Nebraska Digging, asking them
what they thought was a fair price for the additional work.
• In response, Nebraska Digging requested $12 per cubic yard
to correspond with the unit price under the original contract.
• Appellants were ultimately denied compensation for the work
associated with moving the stockpile.
In response to Rosenow’s version of events, Nemaha County
presented the following:
• Britt agreed that the stockpile had to be moved because it
was impeding construction progress and that he took part in
the October 2023 meeting but asserted that his information on
- 335 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
where to move the stockpile was merely a suggestion on how
to “waste” the dirt without impacting the Project.
• Britt asserted that the ultimate decisions on the stockpile’s
location related to the means and methods of the construction,
which was Vogtscapes’ responsibility, and it was not within
the scope of his authority under the contract to dictate the
locations of the stockpile.
• Britt testified that he proposed the plan governing where to
“waste” dirt and obtained approval from Mainelli Wagner on
the proposed changes to “waste” more dirt so that there was
less dirt to haul away.
• Britt acknowledged that he discussed relocating the dirt and
the opportunity to charge for it as an overrun but that was
only in the event it was agreed upon.
• Britt testified that despite his discussions with Appellants,
he was not authorized to approve extra expenses and there
was never an agreement reached on the price and quantity of
material excavated or moved. Britt acknowledged engaging
in numerous email discussions and conversations involving
the parties regarding the payment for the placement of the
excess dirt.
• Britt stated that once he received the pay application and
email from Rosenow about charging $12 per cubic yard as
provided in the unit cost on the summary of quantities form,
he believed that the price was too high for compensation.
• Weiss stated in his affidavit, “I never told anyone that Nemaha
County would pay more than the total contract amount for
Vogtscapes . . . to move the dirt stockpile that was in a loca-
tion that blocked the completion of the project.” He then
stated, “I did not have the authority to agree that Nemaha
County would pay more than the contracted amount without
a vote by the full County Board.”
• Weiss testified in his deposition that he “walked off” during
the October 2023 meeting and only learned of the plan to
move the stockpile and the plan to “waste dirt” through Britt,
who informed him of the plan reached.
- 336 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
• Weiss acknowledged that Britt came up with some ideas on
how to “waste dirt within the [P]roject” and that Britt then
got approval from Mainelli Wagner for those ideas and then
gave Nebraska Digging the go ahead to implement the ideas.
• Weiss stated that Britt informed him that they were not going
to do a written change order.
• Weiss testified in his deposition that when Britt informed him
of the plan to waste dirt, Weiss said two things: “[W]hatever
you decide and I’m not paying any extra money.” However,
Weiss stated that he was not involved in any conversations
with Nebraska Digging or Vogtscapes about extra payment
on the Project.
• Weiss acknowledged that changes were made to the original
engineering plans in order to waste more dirt so that there
would be less dirt to haul away.
• Weiss acknowledged that Britt was authorized to make
changes to the engineering plans so long as he had authoriza-
tion from Mainelli Wagner.
• Weiss testified that Rosenow should have never placed
the stockpile in the original location at the start of the
Project and that regardless of any extra work performed by
Nebraska Digging, the contract price was set by Vogtscapes
based on its proposal, knowing that variables may arise and
that Nemaha County did not have a separate contract with
Nebraska Digging.
Pleadings
After the dispute arose between the parties following
the Project’s completion on the total contract price to be
paid, Appellants filed a complaint against Nemaha County
in the district court alleging claims for breach of contract,
“Prompt Pay Act,” and equitable relief. The complaint alleged
facts as laid out above. Appellants further alleged that the
additional cost to relocate the stockpile was approximately
$92,470.80 plus interest, based on the total yardage moved
and the standard unit price of $12 per cubic yard. Appellants
- 337 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
alleged that their payment requests were denied by Nemaha
County. Appellants further alleged they entered into a common
interest/joint claims prosecution agreement wherein Vogtscapes
agreed to allow Nebraska Digging to prosecute the claims
on Vogtscapes’ behalf and that Appellants complied with the
Political Subdivision Tort Claims Act.
In its answer, Nemaha County admitted that it entered
into a contract with Vogtscapes to complete the Project; that
Vogtscapes entered into a separate subcontract with Nebraska
Digging for the performance of some dirt work; that Nemaha
County’s engineer was responsible for the supervision of the
Project; that the parties participated in a meeting to discuss
a change order to move the dirt stockpile; that Appellants
requested payment from Nemaha County, which Nemaha
County denied; that Nemaha County informed Nebraska
Digging that it would not pay them for dirt moving that was
necessitated by Nebraska Digging’s piling dirt in an unau-
thorized location; and either that Vogtscapes had performed
all the necessary obligations and conditions precedent under
the contract with Nemaha County or that such obligations
or conditions had been waived. Nemaha County generally
denied the remaining allegations but specifically denied that
it directed Nebraska Digging to perform additional work or
that it entered into an oral agreement for Nebraska Digging to
move the stockpile and agreed to pay Nebraska Digging as an
overrun to the total excavation price.
Motion for Summary Judgment
Nemaha County filed a motion for summary judgment alleg-
ing that there was no genuine issue of material fact and that it
was entitled to judgment as a matter of law. During the hearing
thereon, the district court received evidence, including affida-
vits from Britt, Weiss, and an attorney representing Appellants;
depositions of Britt, Weiss, Sunderman, and Rosenow; the con-
tract between Vogtscapes and Nemaha County; and the parties’
briefs in support of their respective arguments.
- 338 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
The record reveals the parties do not dispute that they
entered into a valid contract, that a dirt stockpile created
during the course of the Project was required to be relocated
in order for the Project to be completed, or that Vogtscapes
successfully completed the Project. The only dispute relates
to the total amount Appellants are entitled to under the con-
tract for the work performed. Nemaha County argued that the
contract was a lump-sum contract and specifically stated that
the full amount to be paid under the contract was $752,311
and that “no additions or deletions, except by written change
order as set forth in the Contract,” were permitted. Nemaha
County asserted that no written change orders were approved
for the contract; Appellants did not submit any written change
orders for Nemaha County to consider; the excavation, dirt
moving, grading, and backfill operations were all an intrin-
sic part of the lump-sum contract; Appellants were request-
ing payment in excess of the agreed contractual amount and
therefore the “Prompt Pay Act” did not apply; and Appellants
were not entitled to any equitable relief.
In their brief in opposition to summary judgment, Appellants
argued that the parties orally agreed to modify the contract,
the “Prompt Pay Act” applied to the additional work com-
pleted by Appellants, Nemaha County was unjustly enriched
by the additional work completed to Appellants’ detriment,
and genuine issues of material fact existed as to whether the
additional work performed was within the contract or was a
modification. In support of their argument, Appellants offered
evidence, including the pleadings and transcripts from the
depositions of Britt, Weiss, Sunderman, and Rosenow.
District Court Order
On May 30, 2025, the district court entered an order grant-
ing Nemaha County’s motion for summary judgment and dis-
missing Appellants’ complaint. The district court found that
the contract was not ambiguous and controlled the outcome
of the motion for summary judgment, that removal of the dirt
- 339 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
stockpile was work contemplated by the contract, that the
excavation and backfill were subsidiary to items for which
direct payment was made and not paid separately, that Nemaha
County did not change or add to the Project, and that even if
the work was outside the scope of the contract, Appellants did
not submit a written change order for Nemaha County to con-
sider. Appellants have now timely appealed from the district
court’s order.
ASSIGNMENT OF ERROR
Appellants’ assignments of error can be consolidated into
the following issue: The district court erred in granting sum-
mary judgment in favor of Nemaha County when genuine
issues of material facts existed.
STANDARD OF REVIEW
[1,2] An appellate court reviews the district court’s grant
of summary judgment de novo, viewing the record in the
light most favorable to the nonmoving party and drawing all
reasonable inferences in that party’s favor. D&M Roofing &
Siding v. Distribution, Inc., 319 Neb. 707, 24 N.W.3d 850
(2025). An appellate court affirms a lower court’s grant of
summary judgment if the pleadings and admitted evidence
show that there is no genuine issue as to any material facts or
as to the ultimate inferences that may be drawn from the facts
and that the moving party is entitled to judgment as a matter
of law. Id.
[3] The interpretation of a contract and whether the con-
tract is ambiguous are questions of law subject to independent
review. DH-1, LLC v. City of Falls City, 305 Neb. 23, 938
N.W.2d 319 (2020).
ANALYSIS
Appellants assign that the district court erred in grant-
ing summary judgment in favor of Nemaha County. More
specifically, Appellants contend that summary judgment was
improper when genuine issues of material fact existed as to
- 340 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
whether the contract’s written change order provision had been
waived and whether there was an oral modification of the con-
tract and underlying engineering plans.
[4-6] Summary judgment is proper when the pleadings
and the evidence admitted at the hearing disclose that there
is no genuine issue as to any material facts or as to the ulti-
mate inferences that may be drawn from those facts and that
the moving party is entitled to judgment as a matter of law.
Humphrey v. Smith, 311 Neb. 632, 974 N.W.2d 293 (2022).
The evidence that may be received on a motion for summary
judgment includes depositions, answers to interrogatories,
admissions, stipulations, and affidavits. Id. In the summary
judgment context, a fact is material only if it would affect the
outcome of the case. Id.
Appellants do not dispute that the contract contains a
written change order provision that required changes to be
approved by Nemaha County and Mainelli Wagner. However,
Appellants assert that a question of fact exists concerning
whether Nemaha County waived the change order provision
and authorized the additional work performed by Nebraska
Digging. Appellants further assert that a question of fact exists
as to whether the requested or suggested changes to the con-
tract by Mainelli Wagner amounted to a modification of the
contract requiring additional work for additional compensa-
tion. Appellants contend that, because these issues are factual
issues that the district court was not permitted to resolve at the
summary judgment stage, the district court improperly granted
summary judgment in favor of Nemaha County.
Here, the district court found that the relocation of the dirt
stockpile was within the scope or contemplated by the express
terms of the contract; Nemaha County did not propose a
change to the design of the Project, nor did Nemaha County
add to the Project; and if Vogtscapes felt that the dirt work
was outside the scope of the contract, the contract pro-
vided a procedure by which additional work or labor could
be accounted for by submitting a change order, but that
- 341 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
Appellants failed to submit any change order for Nemaha
County to consider.
Appellants contend that the court erred in making factual
determinations for purposes of summary judgment regarding
whether the relocation of the stockpile was extra or additional
work authorized pursuant to an oral modification and whether
the lack of a written change order to account for the additional
work was due to a waiver by Nemaha County.
A similar issue was raised in D. K. Meyer Corp. v. Bevco,
Inc., 206 Neb. 318, 292 N.W.2d 773 (1980). In that case, the
trial court found in favor of a subcontractor, D. K. Meyer
Corp. (Meyer), for additional work performed on the con-
tract notwithstanding its failure to procure a written change
order from the contractor, Bevco, Inc., prior to performing
the additional work. Bevco assigned error to the trial court’s
determination, which the Nebraska Supreme Court framed and
explained as follows:
Bevco contends that error was committed by the lower
court because the work was performed by Meyer without
its first receiving a written change order pursuant to the
contract entered into by Bevco and Meyer. Said contract
was a “Standard Sub-Contract Agreement,” which
provided in relevant part: “[T]hat no extra work shall be
allowed or changes made by the Sub-Contractor, or paid
for by the Contractor unless and until authorized by the
Contractor or his superintendent in writing before the work
and/or changes are begun.” It is undisputed that a written
change order for the modifications performed was never
given to Meyer. However, we conclude that the failure
to obtain a written change order does not bar Meyer’s
recovery herein. In Griffin v. Geneva Industries, Inc.,
193 Neb. 694, 696-97, 228 N.W.2d 880, 882 (1975), we
stated: “It is well-established that the parties to a contract
may avoid such a provision where their words, acts, or
conduct amount to a waiver, modification, rescission,
abrogation, or abandonment of the provision, or the party
- 342 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
claiming the benefit of the provision is estopped to rely
on it. Annotation, 2 A. L. R. 3d 620.”
D. K. Meyer Corp., 206 Neb. at 321, 292 N.W.2d at 775.
In finding that the parties waived the written change order
provision in the contract in relation to the record before it, the
Nebraska Supreme Court held:
The record sustains the conclusion that the parties
herein ignored the provision of the contract requiring
a written change order prior to the modification of the
project. “The interpretation given a contract by the parties
themselves while engaged in the performance of the
contract is one of the best indications of the true intent
of the parties and, ordinarily, that construction of the
contract should be enforced.”
Id. at 322, 292 N.W.2d at 775. In support of that finding, the
Nebraska Supreme Court stated:
All parties to the construction project agreed that modifi-
cations were necessary for the completion of the project,
which modifications were performed by Meyer, without
objections by Bevco. While it is not clear from the record
which party specifically authorized the modifications, it
is, however, apparent from the evidence adduced at trial
that the parties, including Meyer and Bevco, inferen-
tially agreed to the modifications. Meyer incurred addi-
tional expenses in performing the modifications in a total
amount of $ 3,891.40.
Id. at 320, 292 N.W.2d at 774-75.
In reviewing the evidence provided by Appellants in a
light most favorable to them, as we must in performing
a summary judgment analysis, we reach a similar conclusion
here. On this record, Rosenow established that prior to plac-
ing the original dirt stockpile in its location, he consulted
with Weiss regarding the stockpile’s placement, and obtained
approval for it, due to logistical concerns associated with
where the stockpile could be placed within the boundaries of
the Project. At that time, Rosenow indicated Weiss was aware
- 343 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
that the stockpile’s placement would be in the way of future
progress of the Project, and that excess dirt would be left
over after backfilling was complete. Once Nebraska Digging
began backfill work, Rosenow again indicated that excess dirt
would remain in the stockpile and commissioned a meeting
to discuss how the stockpile would be managed in order to
complete the Project.
At an October 2023 meeting, attended by Britt, Weiss,
Sunderman, and Rosenow, Rosenow was instructed that the
remaining dirt in the stockpile needed to be moved, and
the parties discussed different options associated with mov-
ing it. Rosenow suggested moving the dirt to another nearby
stockpile, a more economical option, but that option was
rejected by Britt, who instructed Rosenow to move the dirt to
several different locations. Notably, at that meeting, Rosenow
asserted that he believed that the work constituted additional
work under the contract for which Nebraska Digging was enti-
tled to additional compensation. As such, he proposed submit-
ting a written change order for the additional work associated
with relocating the stockpile. According to Rosenow, the par-
ties at the meeting acknowledged that the work constituted an
“overrun” on the Project and that they did not want progress
to be hindered by a change order process. As such, Rosenow
asserted that Britt told him to move the dirt as he instructed,
track the number of truckloads of dirt hauled, and submit
the additional work as a project overrun for which Nebraska
Digging would be paid. And the engineering plans were
changed to designate how Nebraska Digging was directed to
move or “waste” the dirt. As a result, Nebraska Digging per-
formed the work and began tracking the number of truckloads
hauled to submit for payment. After submitting a payment
request, Nebraska Digging was ultimately denied payment on
the basis that Nemaha County contended that the work did
not constitute a project overrun and that Appellants failed to
obtain a written change order as required by the contract.
- 344 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
We recognize that Nemaha County presents a somewhat
different version of facts. Those facts include Weiss’ statement
that he did not approve the original location of the stockpile
and that he did not meaningfully participate in the October
2023 meeting or suggest the work constituted an overrun or
would be paid. And Britt acknowledges there was a discussion
about a change order at the meeting but claims that he did not
have the authority to unilaterally agree to a contract change or
overrun and felt more was required to effect a contract change
that was never adequately pursued.
But, in construing these facts in a light most favorable to
Appellants, we determine there remained material issues of
fact that precluded summary judgment here. First, the district
court found that the contract unambiguously provides that the
relocation work was contemplated under the original agree-
ment. That conclusion is disputable here. The contract most
certainly did include all dirt work, but that dirt work required
Nebraska Digging to excavate and backfill, with the “County
[to] haul off excess embankment from site after construction
is completed.” And the only reason the stockpile had to be
relocated was due to its logistical placement, which placement
was authorized by Weiss in advance of such placement as
required by the contract.
[7] Regardless, there was evidence presented that during
the course of the Project, Rosenow took the position that the
relocation was additional work as he construed the contract,
and Britt, who was designated as an agent of Nemaha County
to decide questions that “[arose] with reference to the intent of
the Contract Documents and compliance therewith,” appeared
to agree with that interpretation, had the engineering plans
modified, and instructed Rosenow to treat the additional work
as a Project “overrun” and to bill for it. And as the Nebraska
Supreme Court stated in D. K. Meyer Corp. v. Bevco, Inc.,
206 Neb. 318, 322, 292 N.W.2d 773, 775 (1980): “‘The inter-
pretation given a contract by the parties themselves while
engaged in the performance of the contract is one of the best
- 345 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
indications of the true intent of the parties and, ordinarily,
that construction of the contract should be enforced.’” At a
minimum, there remained a triable issue of fact as to whether
Mainelli Wagner, as agent for Nemaha County, interpreted the
contract to deem the work additional work during the per-
formance of the contract.
[8] Second, the district court found that even if the work
constituted “additional work,” Appellants failed to procure a
written change order as required by the contract. But as stated
in D. K. Meyer Corp., 206 Neb. at 321, 292 N.W.2d at 775:
“‘It is well-established that the parties to a contract may avoid
such a provision where their words, acts, or conduct amount to
a waiver, modification, rescission, abrogation, or abandonment
of the provision, or the party claiming the benefit of the provi-
sion is estopped to rely on it.’”
Here, under Appellants’ version of the facts, after request-
ing to submit a written change order following Britt’s inter-
pretation that the relocation work constituted an overrun on
the Project, Rosenow was told not to submit a written change
order as it would slow down the Project, but that Nebraska
Digging would be paid for the additional loads and to begin
tracking them. This alleged representation was made during
the October 2023 meeting attended by Weiss and Britt and,
according to Rosenow, provided the reason Nebraska Digging
moved forward with the additional work without obtaining a
written change order. Again, on this record, we find Appellants
presented a genuine issue of material fact as to whether
Nemaha County waived the written change order provision
and orally agreed to modify the contract to pay Appellants for
the additional work on the Project.
During oral argument, counsel for Nemaha County asserted
that neither Britt nor Weiss had authority to bind Nemaha
County to a contract modification. Stated differently, counsel
argues that neither Britt nor Weiss had authority to waive the
written change order provision under the contract or com-
mit Nemaha County to paying for additional work under the
- 346 -
Nebraska Court of Appeals Advance Sheets
34 Nebraska Appellate Reports
VOGTSCAPES, INC. v. NEMAHA COUNTY
Cite as 34 Neb. App. 329
contract. But these issues were not addressed by the trial
court. Instead, the court found that the contract, as written,
unambiguously provided that the relocation work was not
additional work and found that Appellants failed to pursue a
written change order as required under the contract. As we
stated above, a factual question remains as to whether, dur-
ing the course of the construction contract, the parties agreed
that the stockpile relocation work did constitute additional
work, waived the written change order provision, and agreed
to additional compensation for the work performed. And a
factual question remains as to what authority, if any, Britt
and Weiss had to bind Nemaha County to the alleged waiver
and contract modification. For instance, under the terms of
the contract, among other things, the contract provides that
“[Mainelli Wagner] is the agent of [Nemaha County] only
to the extent provided in the Contract Documents or when
specifically authorized to act on [Nemaha County’s] behalf.”
On this record, there remains a triable issue of fact regarding
what authority both Britt and Weiss had on behalf of Nemaha
County to bind Nemaha County to the specified contract
modifications, in addition to whether the modifications were
ever made.
CONCLUSION
For the reasons stated above, we reverse the order of the
district court and re