Christopher Cates and Joy Cates v. Ken Sarbu Construction Company, Inc.
CourtDistrict Court of Appeal of Florida
Date FiledSeptember 10, 2026
Docket5D2023-3395
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
FIFTH DISTRICT COURT OF APPEAL
STATE OF FLORIDA
_____________________________
Case No. 5D2023-3395
LT Case No. 2020-CA-000147
_____________________________
CHRISTOPHER CATES and JOY
CATES,
Appellants/Cross-Appellees,
v.
KEN SARBU CONSTRUCTION
COMPANY, INC.,
Appellee/Cross-Appellant.
_____________________________
On appeal from the Circuit Court for Nassau County.
Eric C. Roberson, Judge.
Peter E. Nicandri and Pierce N. Giboney, of Milam Howard
Nicandri & Gillam, P.A., Jacksonville, for Appellants/Cross-
Appellees.
David H. Willis and Jonathan B.B. Lucas, of Willis Lucas Law
Group, P.A., Jacksonville Beach, for Appellee/Cross-Appellant.
September 10, 2026
PER CURIAM.
Christopher and Joy Cates (the “Cates”) and Ken Sarbu
Construction Company, Inc., (“Sarbu Construction”) sued each
other after disputes arose about Sarbu Construction’s work on the
Cates’ home. After a bench trial, the trial judge awarded Sarbu
Construction $9,596.00 in damages arising from a change order to
the main construction contract; the trial judge ruled, however, that
neither party had proven a breach of any other contractual
responsibilities. Based on this award, the trial judge concluded
that Sarbu Construction was the prevailing party in the litigation.
Both parties appealed.
We affirm the award of damages. As we read the record, the
trial court found that the Cates breached their obligations under
the change order. We reverse, however, the finding that Sarbu
Construction was the prevailing party in the litigation because the
trial judge applied an incorrect test. See Corley v. Rivertown, Inc.,
863 So. 2d 1244, 1246 (Fla. 5th DCA 2004) (“The test to determine
the prevailing party provides that the party that prevailed on the
significant issues tried before the court is the prevailing party
entitled to an award of attorney’s fees.”). The trial judge shall
apply the correct test on remand. We affirm as to all other issues
raised on appeal.
AFFIRMED in part, REVERSED in part, and REMANDED for
further proceedings.
JAY, C.J., and EISNAUGLE, J., concur;
MAKAR, J., concurs in part and dissents in part, with opinion.
_____________________________
Not final until disposition of any timely and
authorized motion under Fla. R. App. P. 9.330 or
9.331.
_____________________________
2
Case No. 5D2023-3395
Lt. Case No. 2020-CA-000147
MAKAR, J., concurring in part and dissenting in part.
This case involves a dispute about costly repairs to balconies
on a private residence. Christopher and Joy Cates (the “Cateses”)
hired Ken Sarbu Construction Company, Inc. (“Sarbu
Construction”), to remove and replace the balconies on their luxury
home in an exclusive neighborhood on Amelia Island, Florida. The
parties agreed the job would take approximately ten weeks, but
was still incomplete six months after the building permit was
issued, which caused the relationship between the parties to break
down. Independently, and later through their legal counsel, the
Cateses expressed their discontent and told Sarbu Construction
that workers were no longer allowed on the property to perform
work. At the time, Sarbu Construction had reconstructed the
balconies, finished work on an executed change order, and
completed various other aspects of the job. Several items, however,
remained incomplete.
As a result, Sarbu Construction filed a claim of lien for the
labor, services, and materials that it claimed remained unpaid. In
the final payment affidavit, Ken Sarbu, the President of Sarbu
Construction, swore that “[a]ll work to be performed under the
contract has been fully completed[.]” Sarbu Construction then filed
a breach of contract claim and sought to foreclose on the
construction lien.
The Cateses filed counterclaims for breach of contract, a
fraudulent lien, and negligence. They moved for final summary
judgment as to both parties’ lien claims and prevailed. The trial
court found that the lien was fraudulent and subsequently
discharged Sarbu Construction’s claim of lien.
A bench trial was held to resolve the remaining claims. The
trial court ultimately found that neither party had met its burden
of proof for their breach of contract claims. The trial court
determined that the greater weight of the evidence did not favor
either side and that it was a “dead tie” as to which party breached
the agreement. Even so, the trial court found that the change order
3
executed by the parties was “something different,” and awarded
Sarbu Construction $9,596.00 for the substantial performance of
that work. The Cateses were awarded nothing.
Both parties sought rehearing, in relevant part, to be named
the prevailing party for the purpose of an award of attorney’s fees.
The trial court entered an order finding Sarbu Construction the
prevailing party.
In this appeal and cross-appeal, the parties raise numerous
issues in their extensive briefs. First, the Cateses challenge the
trial court’s monetary award to Sarbu Construction. The trial court
made no finding that the Cateses breached the agreement with
Sarbu Construction, including the change order. Rather, it found
neither party met its burden of proof that the other had committed
a breach. Based on well-established caselaw, the proper “measure
of damages in a suit by a contractor against an owner for breach of
contract when the contract has not been fully completed is either
quantum meruit or the contractor’s lost profit together with the
reasonable cost of labor and materials incurred in good faith in
partial performance of the contract.” Fid. & Deposit Co. of Md. v.
Accel, Inc., 354 So. 2d 424, 426 (Fla 4th DCA 1978) (emphasis
added). The trial court’s finding that neither party met their
burden of proof means no breach was established, particularly
when the main contract defined change orders as part of the
overall contract. Sarbu Construction, which did not claim relief
under a quantum meruit theory, was not entitled to damages
without an explicit finding of breach of the change order.
In addition, Sampley Enterprises, Inc. v. Laurilla, 404 So. 2d
841, 842 (Fla. 5th DCA 1981), states that the “measure of damages
is the amount which the innocent party would have received if the
contract had been performed, less any deductions for expenses not
yet incurred.” (Emphasis added). Sarbu Construction attempts to
assert that it is the “innocent party” because the Cateses did not
prove that it breached the contract. But Sarbu Construction,
likewise, failed to prove that the Cateses breached the contract;
therefore, neither party can be said to be the breaching party. The
trial court’s award of damages to Sarbu Construction is thereby
unsupportable.
4
Second, the Cateses challenge the trial court’s finding that
Sarbu Construction was the prevailing party under the lien
statute, which applies a “significant issue” test under the caselaw.
Although neither party proved a breach of contract—the most
significant claims in the litigation—the trial court nonetheless
concluded that Sarbu Construction was the prevailing party
because it was awarded damages. The trial court narrowly focused
on only the net award of damages, which was a much smaller
amount in comparison to what each party sought. It thereby did
not undertake the broader task under the “significant issue” test,
which was to consider all relevant factors. As our supreme court
has said:
The overall purpose of section 713.29 and attorneys’
fee statutes in general is to discourage rather than
encourage needless litigation. Consistent with this
purpose, we conclude that a trial court has the discretion
to make a determination that neither party has prevailed
on the significant issues in litigation after a thorough
examination of all the factors, including the issues
litigated, the amount of the claim of lien versus the
amount recovered on the lien, the existence of setoffs and
counterclaims by the homeowner, and the amounts offered
by either party to resolve the issues prior to the litigation,
assuming that those negotiations were not otherwise
confidential either by agreement or statute.
Trytek v. Gale Indus., Inc., 3 So. 3d 1194, 1203 (Fla. 2009)
(emphasis added). Applying the proper test—and considering that
an award of damages to Sarbu Construction was unsupportable
where no breach was proven—this is the rare case where neither
party is the prevailing party.
In summary, I would reverse the award of damages to Sarbu
Construction but agree that the trial court applied the incorrect
test to determine a prevailing party. On the facts of this case, and
the trial court’s ruling that neither party proved a breach of
contract, a remand for entry of an order finding no prevailing party
is warranted. See Snyder v. Davis, 426 So. 3d 882, 883 (Fla. 4th
DCA 2025) (“Only in rare instances—when the outcome is truly a
draw—may a court find no prevailing party.”).
5