MAPP v. Floor and Decor
CourtCourt of Appeals for the Fifth Circuit
Date FiledAugust 6, 2026
Docket25-30536
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
Case: 25-30536 Document: 56-1 Page: 1 Date Filed: 08/06/2026
United States Court of Appeals
for the Fifth Circuit
____________ United States Court of Appeals
Fifth Circuit
FILED
No. 25-30536 August 6, 2026
____________
Lyle W. Cayce
MAPP, L.L.C., Clerk
Plaintiff—Appellee,
versus
Floor and Decor Outlets of America, Incorporated,
Defendant—Appellant.
______________________________
Appeal from the United States District Court
for the Eastern District of Louisiana
USDC No. 2:24-CV-444
______________________________
Before Southwick, Graves, and Wilson, Circuit Judges.
Leslie H. Southwick, Circuit Judge:
Floor and Decor Outlets of America seeks enforcement of its
contractual discretion to elect that a claim brought by its former contractor,
MAPP, L.L.C., be arbitrated. The district court denied F&D’s motion to
compel arbitration, and this appeal followed. We agree with the district court
that, under Louisiana law, the clause is adhesionary and unenforceable.
AFFIRMED.
Case: 25-30536 Document: 56-1 Page: 2 Date Filed: 08/06/2026
No. 25-30536
FACTUAL AND PROCEDURAL BACKGROUND
In June 2022, Floor and Decor Outlets of America, Inc. (“F&D”), a
national flooring retailer, contracted with MAPP, L.L.C., a Louisiana
construction management company, for the building of an F&D retail store
in Metairie, Louisiana. The construction agreement was memorialized in a
Master Agreement Between Owner and Contractor (“the Agreement”).
In November 2022, F&D sent a notice to MAPP terminating the
Agreement because of schedule delays in the project. Three days later,
Michael Polito, the CEO of MAPP, emailed a number of F&D personnel
asserting that MAPP’s conduct had not constituted a breach of contract and
requesting that the termination be canceled. An F&D executive responded
that the company’s counsel would contact MAPP. Communications
continued until December, when Polito sent a letter to F&D demanding over
three million dollars for the work performed through the termination date.
F&D did not respond.
In January 2023, MAPP sued F&D in the United States District
Court for the Middle District of Louisiana under the Louisiana Private Works
Act (“LPWA”). 1 F&D moved to compel arbitration and transfer venue to
the Eastern District of Louisiana. The district court granted the motion to
transfer and denied the motion to compel without prejudice. In the new
district court, F&D again moved to compel arbitration, arguing that the
Agreement had an express arbitration provision that covered MAPP’s claim.
The relevant language in the Agreement’s arbitration provision is this:
_____________________
1
The LPWA secures the obligations of construction project owners to contractors,
among others, for the price of their work through a “privilege on an immovable.” La.
R.S. § 9:4801; Golden Nugget Lake Charles, L.L.C. v. W.G. Yates & Sons Constr. Co., 850
F.3d 231, 233 (5th Cir. 2017).
2
Case: 25-30536 Document: 56-1 Page: 3 Date Filed: 08/06/2026
No. 25-30536
Any disputed Claims that cannot be decided by confidential
negotiation or mediation may, in the sole discretion of Owner,
be decided by arbitration in accordance with the Construction
Industry Arbitration Rules of the American Arbitration
Association then in effect.
The district court found that F&D had not complied with the
Agreement’s dispute resolution procedure, “which sets forth several steps
that must be taken before F&D can request arbitration.” Thus, according
to the district court, MAPP’s claim was outside the ambit of the arbitration
clause. The district court denied F&D’s motion to compel. F&D timely
appealed.
DISCUSSION
“We review de novo a ruling on a motion to compel arbitration.”
Kubala v. Supreme Prod. Servs., Inc., 830 F.3d 199, 201 (5th Cir. 2016). The
Federal Arbitration Act (“FAA”), Pub. L. No. 68-401, 43 Stat. 883 (1925),
enacted by Congress in 1925, governs this dispute. The Supreme Court has
instructed that the FAA establishes two principles for courts to apply: first,
that “arbitration is a matter of contract,” and second, that there is a “liberal
federal policy favoring arbitration.” AT&T Mobility LLC v. Concepcion, 563
U.S. 333, 339 (2011) (quotation marks and citations omitted).
This court follows two steps to determine whether a motion to compel
arbitration should be granted: (1) “we ask if the party has agreed to arbitrate
the dispute” and if so, (2) “we then ask if ‘any federal statute or policy
renders the claims nonarbitrable.’” Sherer v. Green Tree Servicing LLC, 548
F.3d 379, 381 (5th Cir. 2008) (quoting JP Morgan Chase & Co. v. Conegie ex
rel. Lee, 492 F.3d 596, 598 (5th Cir. 2007)). The parties do not assert that
any federal statute or policy bars the proposed arbitration, so we do not
address the second step. See id.
3
Case: 25-30536 Document: 56-1 Page: 4 Date Filed: 08/06/2026
No. 25-30536
The “first step itself contains two questions: (1) is there a valid
agreement to arbitrate the claims and (2) does the dispute in question fall
within the scope of that arbitration agreement.” Id. The district court
considered both issues, then denied the motion on the basis that F&D’s
failure to initiate arbitration properly left the dispute outside the scope of the
arbitration clause. We apply a different analysis, concluding there was not a
valid arbitration agreement, and need not reach whether the dispute was
within the scope of the agreement. Our decision affirms on different grounds
than those relied on by the district court, which is appropriate under our de
novo review. See Price v. Valvoline, L.L.C., 88 F.4th 1062, 1065 (5th Cir.
2023).
I. Validity of the Agreement to Arbitrate
To compel arbitration, there must be a valid agreement between the
parties to arbitrate. We do not apply the “the federal policy favoring
arbitration when addressing ambiguities” to the question of “whether a valid
agreement exists.” Sherer, 548 F.3d at 381. Under Section 2 of the FAA,
“[a] written provision in any maritime transaction or a contract evidencing a
transaction involving commerce to settle by arbitration . . . shall be valid,
irrevocable, and enforceable, save upon such grounds as exist at law or in
equity for the revocation of any contract.” 9 U.S.C. § 2. Generally applicable
rules of state law “such as fraud, duress, or unconscionability, may be applied
to invalidate arbitration agreements,” as such grounds may be used to
invalidate any contract. Doctor’s Assocs., Inc. v. Casarotto, 517 U.S. 681, 687
(1996). “Courts may not, however, invalidate arbitration agreements under
state laws applicable only to arbitration provisions.” Id. Statutes singling out
arbitration clauses with more demanding rules are invalid. Id.
One generally applicable defense against the validity of a contract
under Louisiana law is adhesion. Aguillard v. Auction Mgmt. Corp., 2004-
4
Case: 25-30536 Document: 56-1 Page: 5 Date Filed: 08/06/2026
No. 25-30536
2804 (La. 6/29/05), 908 So. 2d 1, 9–11. “A contract is one of adhesion when
either its form, print, or unequal terms call into question the consent of the
non-drafting party and it is demonstrated that the contract is unenforceable,
due to lack of consent or error, which vitiates consent.” Id. at 11. The district
court addressed without deciding, and the parties continue to press before
this court, the issue of whether the arbitration clause at issue in this case is
adhesionary.
MAPP argues that the lack of mutuality in the arbitration clause —
under the contract, F&D may compel MAPP to arbitrate its claims against
F&D, but MAPP cannot compel F&D to arbitrate its claims against MAPP
— is enough to make it adhesionary under Louisiana law, and therefore
invalid. F&D disagrees that the provision lacks mutuality.
The contested arbitration provision provides that “[a]ny disputed
Claims that cannot be decided by confidential negotiation or mediation may,
in the sole discretion of Owner, be decided by arbitration.” F&D contends,
imaginatively, that this reflects mutuality because “upon F&D’s election to
arbitrate, MAPP’s and F&D remaining disputed claims must be arbitrated
without regard for which party is asserting a [c]laim.” We disagree. The text
of the provision reveals F&D has the sole discretion to choose which
disputed claims to elect to arbitrate.
Given these unilateral rights, we examine whether the contract is one
of adhesion. The goal under Louisiana law is to make a finding of whether a
“party truly consented to the contract terms.” Duhon v. Activelaf, LLC,
2016-0818 (La. 10/19/16), 411 So. 3d 605, 613.
Duhon provides the test for adhesion. There, the Louisiana Supreme
Court considered the validity of a non-mutual arbitration clause in a risk
agreement signed by the patrons of an indoor trampoline park. Id. at 606.
The clause mandating arbitration applied only to the patrons, leaving the
5
Case: 25-30536 Document: 56-1 Page: 6 Date Filed: 08/06/2026
No. 25-30536
trampoline park with complete discretion. Id. at 608. Mindful of the FAA,
the court drew from “general state contract principles” in assessing the
provision. Id. at 610. The court applied four adhesion factors gleaned from
its precedent: “(1) the physical characteristics of the arbitration clause, (2)
the distinguishing features of the arbitration clause, (3) the mutuality of the
arbitration clause, and (4) the relative bargaining strength of the parties.” Id.
at 611 (citing Aguillard, 908 So. 2d at 10–11). Two factors counseled in favor
of finding it adhesionary: (1) the physical characteristics of the clause, which
was “cloak[ed] within a blanket of boilerplate language regarding rules and
risks” and (2) the lack of mutuality in the clause, which “fortifie[d]” the
court’s concerns. Id. at 612. The court held the clause unenforceable. Id.
Obviously, if nothing else, the bargaining strength of visitors to a trampoline
park in deciding whether to accept an arbitration clause before entering the
park is far less than the bargaining strength of a sophisticated potential
contractor when negotiating a contract.
The Duhon court cautioned that it was not “requiring term-for-term
mutuality in an arbitration clause,” which “could risk running afoul of the
FAA.” Id. at 613. That court was clear that there is no categorical rule
barring non-mutual arbitration clauses. In evaluating arbitration clauses, a
court applying Louisiana law must consider “the context of the overall
contract and the surrounding circumstances” and “weigh[ the] several
factors.” Id. We agree that Louisiana’s approach does not single out
arbitration agreements for disfavor, as would be prohibited by Section 2 of
the FAA. We therefore will apply it here.
We examine other relevant precedent before returning to Duhon.
This court has addressed a similar question of adhesion under Louisiana law
in Iberia Credit Bureau, Inc. v. Cingular Wireless LLC, 379 F.3d 159, 171 (5th
Cir. 2004). There, the parties disputed whether a non-mutual arbitration
clause in a wireless company’s contract was enforceable against various
6
Case: 25-30536 Document: 56-1 Page: 7 Date Filed: 08/06/2026
No. 25-30536
plaintiffs, including a sheriff’s department. Iberia, 379 F.3d at 162–164, 168.
The court cited “[r]ecent Louisiana appellate cases” that had “deemed”
one-sided arbitration clauses to be “unconscionable and unenforceable.” 2
Id. at 169. The court found “serious question[s] as to the clause’s validity”
and affirmed the district court’s denial of the motion to compel arbitration.
Id. at 169, 176.
F&D relies on two Louisiana Court of Appeal decisions. In one, the
court found a contract to be enforceable even though “the [arbitration] clause
lack[ed] mutuality and there [was] an apparent disparity in the parties’
bargaining positions.” Hanlon v. Monsanto Ag Prods., LLC, 48,010 (La. App.
2 Cir. 10/9/13), 124 So. 3d 535, 544. In the other, the court held that the
mere absence of mutuality was insufficient to invalidate the agreement in
dispute. See Hoffman, Siegel, Seydel, Bienvenu & Centola, APLC v. Lee, 2005-
1491 (La. App. 4 Cir. 7/12/06), 936 So. 2d 853, 859. Significantly, both
opinions preceded Duhon.
F&D explains the divergence in outcomes in the caselaw by asserting
that two of them involved “take it or leave it” business to consumer
transactions while the other two were “business to business” transactions.
That distinction can have relevance only to the extent it is consistent with the
Duhon factor-by-factor analysis.
We now return to Duhon in order to consider the four factors it
identified. 3 We examine together the first two factors: the physical
_____________________
2
The court considered Sutton’s Steel & Supply, Inc. v. Bellsouth Mobility, Inc., 2000-
511 (La. App. 3 Cir. 12/13/00), 776 So. 2d 589 and Posadas v. The Pool Depot, Inc., 2002-
1819 (La. App. 1 Cir. 6/27/03), 858 So. 2d 611.
3
In its briefing, MAPP only asserts one factor — the lack of mutuality — as a basis
for treating the arbitration clause as adhesionary. We agree with F&D that this, alone, is
insufficient and therefore consider all four.
7
Case: 25-30536 Document: 56-1 Page: 8 Date Filed: 08/06/2026
No. 25-30536
characteristics and distinguishing features of the arbitration clause in the
contract. While the arbitration clause here is just one paragraph of many,
written in standard boilerplate in a long, single-spaced document, the
arbitration clause is legible, demarcated, and set within a wider dispute
resolution section. The provision was not hidden or “cloak[ed].” See
Duhon, 411 So. 3d at 612 (concluding that the plaintiff “did not truly consent
to the arbitration provision” when the provision was “cloak[ed]” in a
“blanket of boilerplate language”). In Aguillard, the opinion the Duhon court
relied on for the four factors, the state supreme court found that clearly
setting off and labeling the arbitration clause weighed in favor of
enforcement. Aguillard, 908 So. 2d at 16.
We have already discussed mutuality, which is the third factor. The
contract gives F&D the right to compel MAPP to arbitrate under the
contract, while denying MAPP the same right. To add to this inequity, the
contract provides that “each party shall be entitled to any attorneys’ fees
incurred by such party for any motions practice required to enforce this
provision by litigation, including any motions to compel arbitration, which
shall be awarded by the arbitrator in the form of an interim award upon
application for fees by the party enforcing this provision.” As only F&D may
enforce the provision, this seemingly symmetrical language is a one-sided
fees award to F&D for the costs of compelling arbitration. The clause would
punish only one party, MAPP, “for seeking to initiate a lawsuit.” Duhon,
411 So. 3d at 619 (Crichton, J., concurring). Under this provision, F&D
can obtain costs for the motion to compel arbitration even if it had not, at the
time of MAPP’s filing of a claim, chosen to arbitrate the dispute. This factor
supports adhesion.
Finally, the fourth factor is the bargaining position of the parties. In
Aguillard, the Louisiana Supreme Court explained that “[a]n unequal
bargaining position is evident when the contract unduly burdens one party in
8
Case: 25-30536 Document: 56-1 Page: 9 Date Filed: 08/06/2026
No. 25-30536
comparison to the burdens imposed upon the drafting party and the
advantages allowed to that party.” 908 So. 2d at 10. Inconsistent with that
explanation, the district court here stated that there “is no evidence before
the Court that there was a significant difference in bargaining power between
the parties.” According to Aguillard, the evidence is the contract itself, as it
unduly burdens one party in comparison to the burdens on the drafting party.
We examine the relevant evidence to see how well it reflects what Aguillard
stated was evident from this sort of imbalance in the contract.
To find a contractor for this project, F&D, a major retail chain,
engaged in a competitive bid process. MAPP is a local Louisiana
construction management company. Once MAPP’s bid was selected, F&D
provided a standard form contract that MAPP had no input in drafting.
Whether MAPP, after winning the bid, could have bargained for a revision
to give mutuality to the arbitration provision was not tested insofar as we can
tell from the record, but it was a local contractor seeking a national retail
chain’s business. The facts of this case further confirm what the terms of the
contract demonstrate: MAPP was in an inferior bargaining position to F&D.
Two of the four factors in the Aguillard-Duhon list support adhesion.
We consider the two supporting adhesion sufficient, as they deal with the
effect of the contract on the party forced to arbitrate. The two that do not
favor adhesion relate to whether the arbitration clause was sufficiently
obvious in the contract. Together, the evidence relevant to the four factors
demonstrates that MAPP was sufficiently aware of the unequal terms but that
it had little choice but to accept them in order to obtain the contract.
The arbitration provision was adhesionary under Louisiana law and
thus unenforceable.
AFFIRMED.
9
Case: 25-30536 Document: 56-1 Page: 10 Date Filed: 08/06/2026
No. 25-30536
Cory T. Wilson, Circuit Judge, concurring in the judgment:
I agree with the majority that we should affirm the district court’s
denial of F&D’s motion to compel arbitration, but I would do so for the same
reason the district court gave for its ruling: F&D fails to show that it complied
with the parties’ dispute resolution procedure antecedent to invoking the
arbitration clause.
The dispute resolution procedure delineated in the parties’
Agreement has a few steps. First, MAPP must submit a claim to F&D’s
Project Manager. The Project Manager then has thirty days to issue a written
decision. If MAPP disagrees with the decision, it must submit the claim for
confidential negotiation and mediation. And if negotiation and mediation do
not resolve the dispute, only then may the claim go to arbitration.
That did not happen here. After F&D terminated the Agreement,
MAPP submitted a claim to F&D. But once the ball was in F&D’s court,
F&D dropped it. As the district explained, there is no serious disagreement
that F&D’s Project Manager never provided MAPP with a written decision
on MAPP’s claim, much less within the thirty-day window specified by the
Agreement. And though some communications were exchanged between the
parties, no “confidential negotiation and mediation” ever occurred.
Therefore, as the district court concluded, whatever duty MAPP had to
arbitrate its claim was never triggered.
On appeal, F&D argues that compliance with pre-arbitration dispute
resolution procedures is a question of procedural arbitrability properly
reserved to an arbitrator. See John Wiley & Sons, Inc. v. Livingston, 376 U.S.
543, 555–57 (1964). But F&D did not raise this argument until appeal, so it
is not properly preserved. See Martco Ltd. P’ship v. Wellons, Inc., 588 F.3d
864, 877 (5th Cir. 2009). And while there is a “general rule in favor of the
arbitrator’s deciding questions of procedural arbitrability,” this court has
10
Case: 25-30536 Document: 56-1 Page: 11 Date Filed: 08/06/2026
No. 25-30536
recognized an exception when no “rational mind could conclude” that the
parties complied with the dispute resolution procedure. Gen. Warehousemen
and Helpers Union Loc. 767 v. Albertson’s Distrib., Inc., 331 F.3d 485, 488 (5th
Cir. 2003). And here, F&D plainly did not.
Moreover, because F&D’s “breach of the procedural requirement”
preceding arbitration “was clear,” id., it is not necessary to reach the knottier
question of whether the arbitration clause at issue is adhesionary under
Louisiana law. Given that it is at least somewhat uncharted as to how the
Louisiana Supreme Court would apply the four-factor test it articulated in
Duhon v. Activelaf, LLC, 2016-0818 (La. 10/19/16), 411 So. 3d 605, 611, to
the arbitration clause here, I am reticent to break new ground by doing so in
today’s case.
Albeit by a different route, I concur in the judgment.
11