James B. Martin, Inc. D/B/A Allpro Windows & Doors v. Sadie Moore
CourtDistrict Court of Appeal of Florida
Date FiledJuly 1, 2026
Docket4D2025-0517
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA
FOURTH DISTRICT
JAMES B. MARTIN, INC. d/b/a ALLPRO WINDOWS & DOORS,
Appellant,
v.
SADIE MOORE, et al.,
Appellees.
No. 4D2025-0517
[July 1, 2026]
Appeal from the County Court for the Seventeenth Judicial Circuit,
Broward County; Jennifer Wigand Hilal, Judge; L.T. Case No.
062022CC067542AXXXCE.
Richard Francis Hussey of Richard F. Hussey, P.A., Fort Lauderdale,
for appellant.
No appearance for appellees.
CONNER, J.
Appellant James B. Martin, Inc. d/b/a Allpro Windows & Doors
(“Allpro”) appeals the trial court’s denial of Allpro’s request to enforce a
construction lien on real property in which five family members have
various ownership interests. Allpro raises three issues on appeal. We
affirm the trial court’s ruling on two issues without discussion. The issue
we address is the effect a defective notice of commencement had on the
construction lien’s enforcement. After review, we affirm the trial court’s
dismissal of the count for enforcing the construction lien as to one family
member. However, as to another family member, we reverse in part the
trial court’s rulings on the counts for enforcement of a construction lien
and quiet title. We remand for further proceedings.
Background
A contract was entered into between Allpro and appellee Sadie Moore,
a life tenant living on the property, to remove and replace ten windows at
the residence where Sadie was living. Sadie’s mother, Tonette Moore, was
present when the contract was signed.
To protect the priority of construction lien rights, Allpro presented a
form notice of commencement which Sadie signed in blank (and not before
a notary). Allpro staff later filled out (and notarized) the notice of
commencement.
When the window installation was more than half completed, Sadie
contended that some of the windows were incorrect and refused to make
additional payments due under the contract.
Allpro filed a construction lien against the property which asserted that
Sadie and Brenda Johnson owned the property. 1 Allpro then filed suit for
enforcement of the construction lien, breach of contract, unjust
enrichment, and foreclosure of an equitable lien. Sadie filed a response to
the suit and a quiet title counterclaim, contending she owned the property.
After suit was filed, Allpro apparently conducted a title search on the
property and learned that, in addition to Sadie and Brenda Johnson
having an ownership interest, Tonette, Patrell Staten, and Bertram Moore
also had ownership interests. The trial court allowed Allpro to amend the
complaint to add everyone having an ownership interest as additional
defendants. A default was entered as to Johnson, Staten, and Bertram
Moore. Tonette obtained a dismissal of the construction lien foreclosure
count (Count 1) because Allpro had failed to serve a notice to owner for the
claim of lien on Tonette. Tonette was also awarded attorneys’ fees on
Count 1.
After a bench trial, the trial court entered a final judgment for Allpro on
its breach of contract count, but entered judgment for Sadie on Allpro’s
construction lien foreclosure count and Sadie’s quiet title counterclaim.
The trial court denied enforcement of Allpro’s construction lien after
finding that Allpro’s notice of commencement was defective for failure to
list all property owners. More specifically, the trial court found that
because Allpro had completed the information in the notice of
commencement after Sadie had signed the notice of commencement in
blank, Allpro effectively became Sadie’s agent, shifting the risk of error in
the notice of commencement from Sadie to Allpro. Additionally, the trial
court found that the notice of commencement was void because Allpro did
not commence work within ninety days after recording the notice of
commencement.
1 The record does not indicate when or how Allpro became aware that Brenda
Johnson owned an interest in the property.
2
After the trial court denied Allpro’s rehearing motion, Allpro gave notice
of appeal.
Appellate Analysis
Allpro initially argues the trial court erred in dismissing its construction
claim of lien against Tonette. However, Allpro did not preserve that
argument. Thus, we affirm without further discussion as to that
argument. Sunset Harbour Condo. Ass’n v. Robbins, 914 So. 2d 925, 928
(Fla. 2005) (“In order to be preserved for further review by a higher court,
an issue must be presented to the lower court and the specific legal
argument or ground to be argued on appeal or review must be part of that
presentation if it is to be considered preserved.” (quoting Tillman v. State,
471 So. 2d 32, 35 (Fla. 1985))); see also Est. of Herrera v. Berlo Indus., Inc.,
840 So. 2d 272, 273 (Fla. 3d DCA 2003) (“[I]ssues not presented in the
trial court cannot be raised for the first time on appeal.”)).
Next, Allpro argues that the trial court erred in denying enforcement of
the construction lien based on Allpro’s failure to serve all owners with a
notice to owner or the claim of lien, because: (1) Sadie held herself out as
the property’s owner in the notice of commencement, answer, and
amended answer and affirmative defenses; and (2) Allpro substantially
complied with the statutory requirements to impose and enforce a
construction lien.
As to the first argument, because Allpro completed the notice of
commencement, the trial court properly ruled that the risk of errors in the
notice of commencement shifted to Allpro. Importantly, in preparing the
notice of commencement, Allpro never asked Sadie if anyone else owned
an interest in the property.
As to the second argument, Allpro correctly argues that even if the
notice of commencement was insufficient, the trial court nonetheless
erred, because the insufficient notice of commencement does not
invalidate a properly recorded and served claim of lien, and Allpro strictly
complied with the conditions precedent to foreclose on the claim of lien as
to Sadie, who was an owner in privity with Allpro. Sasso Air Conditioning,
Inc. v. United Cos. Lending Corp., 742 So. 2d 468, 470-71 (Fla. 4th DCA
1999) (holding that although a notice of commencement was insufficient,
the construction lien was not invalid because “substantial compliance with
the notice of commencement is all that is required”). Additionally, the
defective notice of commencement merely affected the lien’s start date. See
§ 713.13(3), Fla. Stat. (2021) (“The recording of a notice of
commencement . . . gives constructive notice that claims of lien under this
3
part may be recorded and may take priority as provided in s. 713.07.”).
Generally, all construction liens relate back to the recording of the notice
of commencement. See Napolitano v. Sec. First Fed. Sav. & Loan Ass’n,
533 So. 2d 948, 949-50 (Fla. 5th DCA 1988). A defective notice of
commencement does not invalidate the recorded claim of lien; instead, it
simply means the effective date of the attachment of the lien is the date
the claim of lien is recorded in the public records (a potential loss of priority
of lien). Id. at 950 (“In the event a notice of commencement is not filed,
then such lien shall attach and take priority as of the time the claim of lien
is recorded.”).
Also, the trial court erred in denying the construction lien on the basis
that the work did not commence within ninety days of Allpro recording the
notice of commencement. We are satisfied that Allpro, by taking
measurements at the home for window sizes and ordering the windows
within ninety days after the contract was signed, commenced the
furnishing of materials and replacement of windows within that time
period. See Lacentra Trucking, Inc. v. Flagler Fed. Sav. & Loan Ass’n. of
Miami, 586 So. 2d 474, 477 (Fla. 4th DCA 1991) (holding that actual
commencement could begin through “the ascertainment of boundary
monuments and flagging and staking[.]”).
Thus, the trial court’s denial of Allpro’s enforcement of the construction
lien as to Sadie was reversible error.
Conclusion
We affirm the trial court’s dismissal of Allpro’s count for enforcement
of a construction lien as to Tonette’s interest in the real property. We also
affirm the award of attorneys’ fees and costs as to Tonette. After
determining the trial court erred in denying Allpro’s enforcement of the
construction lien as to Sadie Moore’s interest in the real property and
quieting title as to the construction lien, we reverse the trial court’s final
judgment in part and remand for further proceedings. Because Allpro’s
initial brief did not address the propriety of a construction lien as to other
persons’ ownership interests in the property, we do not address that issue.
We affirm the other issues raised on appeal without discussion.
Affirmed in part, reversed in part, and remanded for further proceedings.
LEVINE and SHEPHERD, JJ., concur.
* * *
4
Not final until disposition of timely-filed motion for rehearing.
5