Connecticut Yankee Atomic Power Company v. United States
CourtCourt of Appeals for the Federal Circuit
Date FiledSeptember 4, 2026
Docket25-1395
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
Case: 25-1395 Document: 50 Page: 1 Filed: 09/04/2026
United States Court of Appeals
for the Federal Circuit
______________________
CONNECTICUT YANKEE ATOMIC POWER
COMPANY, MAINE YANKEE ATOMIC POWER
COMPANY, YANKEE ATOMIC ELECTRIC
COMPANY,
Plaintiffs-Appellees
v.
UNITED STATES,
Defendant-Appellant
______________________
2025-1395
______________________
Appeal from the United States Court of Federal Claims
in Nos. 1:21-cv-01116-TMD, 1:21-cv-01118-TMD, 1:21-cv-
01119-TMD, Judge Thompson M. Dietz.
______________________
Decided: September 4, 2026
______________________
CATHERINE EMILY STETSON, Hogan Lovells Cadwalader
US LLP, Washington, DC, argued for plaintiffs-appellees.
Also represented by KEENAN ROARTY; KATHERINE BOOTH
WELLINGTON, Boston, MA.
DANIEL FALKNOR, Commercial Litigation Branch, Civil
Division, United States Department of Justice, Washing-
ton, DC, argued for defendant-appellant. Also represented
by LISA LEFANTE DONAHUE, AN HOANG, ELINOR JOUNG KIM,
Case: 25-1395 Document: 50 Page: 2 Filed: 09/04/2026
2 CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US
PATRICIA M. MCCARTHY, BRETT SHUMATE; BRIGHTON
SPRINGER, Office of the General Counsel, United States De-
partment of Energy, Washington, DC.
______________________
Before LOURIE, PROST, and STARK, Circuit Judges.
STARK, Circuit Judge.
This case is the latest in a series of nuclear-waste-re-
lated contract disputes between the United States and a
group of utility companies known as “the Yankees” (the
Connecticut Yankee Atomic Power Company, Maine Yan-
kee Atomic Power Company, and Yankee Electric Power
Company). The current appeal presents a single question
of contract law: can the damages caused by the govern-
ment’s continuing partial breach be offset by the Yankees’
investment gains earned by a legally mandated trust fund?
The Court of Federal Claims answered in the negative and
entered judgment in the Yankees’ favor. We reach the
same conclusion and, therefore, affirm.
I
A
Following World War II and the Manhattan Project,
the United States enacted a series of measures to promote
the civilian adoption of atomic energy. See generally Cotter
Corp., N.S.L. v. United States, 127 F.4th 1353, 1357-58
(Fed. Cir. 2025). By the 1970s, “the private sector [had]
become involved in the development of atomic energy for
peaceful purposes under a program of federal regulation
and licensing.” Duke Power Co. v. Carolina Env’t Study
Grp., Inc., 438 U.S. 59, 63 (1978). “Today, more than 50
nuclear power plants . . . produce electricity for American
homes and businesses. In all, nuclear power plants gener-
ate almost 20 percent of the electricity in America.” NRC
v. Texas, 605 U.S. 665, 669 (2025).
Case: 25-1395 Document: 50 Page: 3 Filed: 09/04/2026
CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US 3
The generation of atomic energy yields a “dangerous”
byproduct: nuclear waste. Id. at 668. This radioactive ma-
terial, also known as “spent nuclear fuel” (“SNF”), is “usu-
ally stored on site” at the power plant at which it is
produced, until it can be safely removed. Id. “In 1982, rec-
ognizing the need to protect the public and the environ-
ment by providing for the disposal of the nuclear waste
accumulating at civilian nuclear power plants around the
country, Congress enacted the Nuclear Waste Policy Act”
(“NWPA”). Maine Yankee Atomic Power Co. v. United
States, 225 F.3d 1336, 1337 (Fed. Cir. 2000) (“Yankee I”).
“The NWPA was designed to solve the national problem of
permanent disposal of spent nuclear materials.” Bos. Edi-
son Co. v. United States, 658 F.3d 1361, 1371 (Fed. Cir.
2011). Among other things, the NWPA “authorized the De-
partment of Energy (‘DOE’) to contract with nuclear power
utilities as part of its plan for a national nuclear waste dis-
posal system.” Sys. Fuels, Inc. v. United States, 818 F.3d
1302, 1303 (Fed. Cir. 2016).
Under the NWPA, “[n]uclear plant operators and utili-
ties were mandated by Congress to enter into Standard
Contracts” with DOE. Indiana Michigan Power Co.
v. United States, 422 F.3d 1369, 1372 (Fed. Cir. 2005). “For
our purposes, the bargain was this: The utilities would pay
fees into a Nuclear Waste Fund that the government set up
under the NWPA. In return, DOE committed to begin ac-
cepting and disposing of contract holders’ SNF no later
than January 31, 1998.” Energy Nw. v. United States,
641 F.3d 1300, 1302 (Fed. Cir. 2011).
Ultimately, the government’s 1998 retrieval date
proved to be overly ambitious. To date, there is no ap-
proved central repository for SNF. See NRC, 605 U.S.
at 668 (“To address the storage problem, federal law has
long designated the Yucca Mountain Nuclear Waste Repos-
itory in Nevada as the future permanent site for disposal
of spent nuclear fuel. But the Nevada project has caused
significant political controversy and has stalled.”). Hence,
Case: 25-1395 Document: 50 Page: 4 Filed: 09/04/2026
4 CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US
thus far, DOE has not disposed of a single unit of SNF from
any nuclear power plant, including those controlled by the
Yankees, and there is no current date by which it expects
to do so. J.A. 398 (“[T]he Government has not provided any
timeline for when it intends to accept the Yankees’ SNF.”);
see also Pac. Gas & Elec. Co. v. United States, 536 F.3d
1282, 1287 (Fed. Cir. 2008) (“PG&E”) (“Without a licensed
permanent repository, DOE has never built an [atomic
waste storage] facility.”). The government’s undisputed
breach of the Standard Contract forms the basis of the Yan-
kees’ long-running litigation.
B
Due to the risks entailed in the process of shutting
down nuclear power plants, beginning in 1988 the Nuclear
Regulatory Commission (“NRC”) directed all operators of
such facilities to “provide reasonable assurance that funds
will be available for the decommissioning process.”
10 C.F.R. § 50.75. NRC regulations set out several ap-
proved “methods” for providing the necessary “financial as-
surance.” Id. § 50.75(e)(1).
One option is an “external sinking fund,” more com-
monly known as a “nuclear decommissioning trust”
(“NDT”), which is “maintained by setting funds aside peri-
odically in an account segregated from [plant operator] as-
sets and outside the administrative control of [such
operator] . . . in which the total amount of funds would be
sufficient to pay decommissioning costs at the time perma-
nent termination of operations is expected.”
Id. § 50.75(e)(1)(ii). The power plant operators are re-
quired to raise the funds necessary for these NDTs from
the end-consumers of the electricity they generate (“rate-
payers”), via payments made to wholesale purchasers of
the nuclear energy produced by the plant (“wholesalers”).
Federal Energy Regulatory Commission (“FERC”) regula-
tions permit the funds to be invested for gain, but mandate
that “after decommissioning has been completed, the util-
ity shall return the excess [fund] amount to ratepayers.”
Case: 25-1395 Document: 50 Page: 5 Filed: 09/04/2026
CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US 5
18 C.F.R. § 35.32(a)(7). Until then, gains generated by the
NDTs may be used “to fund the costs of decommissioning
the nuclear power plant to which the [NDT] relates, and to
pay administrative costs and other incidental expenses, in-
cluding taxes, of the [NDT].” Id. § 35.32(a)(6).
C
In 1983, the Yankees executed the Standard Contract
with DOE, thereby obtaining the right to operate nuclear
power plants in Maine, Connecticut, and Massachusetts.
See Yankee Atomic Elec. Co. v. United States, 536 F.3d
1268, 1271 (Fed. Cir. 2008) (“Yankee II”). Pursuant to the
Standard Contract, DOE became contractually obligated to
retrieve and dispose of the Yankees’ SNF in exchange for a
fee. See id. By law, the Yankees are not permitted to dis-
pose of SNF themselves, so even today they continue to re-
tain – and securely store – significant quantities of nuclear
waste on site. See generally Indiana Michigan, 422 F.3d
at 1374.
As further required, each of the Yankees established
an NDT, funded by the ratepayers in the three states.
Since then, the ratepayers’ contributions to the NDTs have
totaled $405 million. On top of that, the NDTs have re-
turned investment earnings of $339 million since 2009, in-
cluding nearly $185 million during the five-year period
that is the subject of this appeal, 2017 through 2021 (the
“Claim Period”).
While the Yankees have paid the removal fees required
under the Standard Contract, DOE has yet to uphold its
part of the bargain. “In 1994, [DOE] announced that it
could not begin disposing of nuclear waste by January 31,
1998, as the [Standard] [C]ontract required, because the
repository it planned to build to store the waste would not
be available.” Yankee I, 225 F.3d at 1337. This breach is
ongoing and has led to four prior rounds of litigation, cul-
minating in decisions from this court and the Court of Fed-
eral Claims holding that DOE has partially, and
Case: 25-1395 Document: 50 Page: 6 Filed: 09/04/2026
6 CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US
repeatedly, breached the Standard Contract. 1 These judg-
ments have also awarded damages to the Yankees adding
up to nearly $500 million. See id. at 1343; Yankee II,
536 F.3d at 1271; Yankee Atomic Elec. Co. v. United States,
679 F.3d 1354, 1357-58 (Fed. Cir. 2012) (“Yankee III”). Of
that amount, approximately $396 million has been distrib-
uted back to the ratepayers.
The Yankees ceased producing nuclear power by 1996
and completed decommissioning of their power plants by
the end of 2007. The parties agree that, but for the govern-
ment’s breach of the Standard Contract, the Yankees
would have been defunct by 2010, and, in that event, the
NDTs would also have been terminated and their holdings
distributed to ratepayers. See J.A. 1757-58 (“During this
claim period, each Yankee utility has maintained its corpo-
rate existence only due to the SNF stored at its site.”). At
this point, the Yankees continue to exist solely to store
SNF. In the meantime, the NDTs continue to be held in
trust for the ratepayers.
1 Because the government insists it someday intends
to perform, DOE’s breach is only a “partial” one, which has
precluded the courts from determining the Yankees’ final
damages amount. See Indiana Michigan, 422 F.3d at 1376
(“If the breach is partial only, the injured party may re-
cover damages for nonperformance only to the time of trial
and may not recover damages for anticipated future non-
performance.”) (internal quotation marks omitted). The on-
going nature of the breach, combined with the Tucker Act’s
six-year statute of limitations, has resulted in these SNF
cases being litigated in five-year installments (e.g., the
2017-21 Claim Period). See id. at 1378 (“[The utility] must
bring any future actions for damages related to DOE’s
breach of the Standard Contract within six years of incur-
ring such damages.”).
Case: 25-1395 Document: 50 Page: 7 Filed: 09/04/2026
CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US 7
In the nearly 20 years since the decommissioning of
their plants, the Yankees have undertaken various efforts
to accommodate the long-term storage of SNF at their sites
until DOE finally performs under the Standard Contract.
For example, in a previous claim period, the Yankees “con-
structed an on-site dry-storage facility, otherwise known as
an Independent Spent Fuel Storage Installation (‘ISFSI’).”
Consol. Edison Co. of N.Y. v. Entergy Nuclear Indian Point
2, LLC, 676 F.3d 1331, 1334 (Fed. Cir. 2012). An ISFSI is
essentially a large concrete pad on which steel casks con-
taining SNF are placed. There are many costs attendant
to maintaining an ISFSI, including those mandated by reg-
ulation, “such as physical security and radiation monitor-
ing expenses.” 26 C.F.R. § 1.468A-1(b)(6)(i).
During the current Claim Period, the Yankees’ ISFSI-
related expenses ran to $145 million. As has been permit-
ted by NRC, FERC, and Internal Revenue Service regula-
tions for nearly 20 years, the Yankees used the NDTs to
pay these expenses. J.A. 396 (“The NDTs are the funding
source that the Yankees use to pay for their ISFSI-related
costs.”). Meanwhile, the Yankees’ NDTs’ earned nearly
$185 million in investment gains during the Claim Period.
The Yankees filed this lawsuit against DOE in the
Court of Federal Claims in March 2021, seeking full reim-
bursement of the $145 million they spent on SNF. The gov-
ernment did not contest liability. It did, however, seek to
offset the damages it owes by the investment gains earned
from the NDTs ($185 million), which would reduce the
damages it would have to pay to zero. The parties filed
cross-motions for partial summary judgment on “the issue
of whether investment earnings on the Yankees’ [NDTs]
should be considered in the calculation of damages.” J.A.
2.
On February 21, 2024, the Court of Federal Claims
granted summary judgment to the Yankees. Thereafter,
the court entered the parties’ stipulated $145 million judg-
ment in favor of the Yankees, subject to the government’s
Case: 25-1395 Document: 50 Page: 8 Filed: 09/04/2026
8 CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US
right to appeal. The government timely appealed. We have
jurisdiction under 28 U.S.C. § 1295(a)(3).
II
“We review the Court of Federal Claims’ grant of sum-
mary judgment de novo.” Richardson v. United States,
110 F.4th 1375, 1380 (Fed. Cir. 2024). The court “shall
grant summary judgment if the movant shows that there
is no genuine dispute as to any material fact and the mo-
vant is entitled to judgment as a matter of law.”
RCFC 56(a).
III
We begin by setting out several principles of contract
law pertinent to our analysis. First, “the traditional dam-
ages remedy under contract law is compensatory in na-
ture.” Cmty. Health Choice, Inc. v. United States, 970 F.3d
1364, 1375 (Fed. Cir. 2020). “That is, the disappointed
promisee is generally entitled to an award of money dam-
ages in an amount reasonably calculated to make him or
her whole.” Id. (internal quotation marks omitted). “One
way to achieve that end is to give the nonbreaching party
‘expectancy damages,’ i.e., the benefits the nonbreaching
party expected to receive in the absence of a breach.” Oliva
v. United States, 961 F.3d 1359, 1362 (Fed. Cir. 2020) (in-
ternal quotation marks omitted); see also S. Cal. Fed. Sav.
& Loan Ass’n v. United States, 422 F.3d 1319, 1334
(Fed. Cir. 2005) (“Expectation damages give the non-
breaching party the benefit of his bargain by putting him
in as good a position as he would have been in had the con-
tract been performed.”).
An important caveat, however, is that “the non-breach-
ing party should not be placed in a better position through
the award of damages than if there had been no breach.”
Bluebonnet Sav. Bank, F.S.B. v. United States, 339 F.3d
1341, 1345 (Fed. Cir. 2003) (emphasis added); see also
LaSalle Talman Bank, F.S.B. v. United States, 317 F.3d
1363, 1371 (Fed. Cir. 2003) (“[I]t is a fundamental tenet of
Case: 25-1395 Document: 50 Page: 9 Filed: 09/04/2026
CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US 9
the law of contract remedies that an injured party should
not be put in a better position than had the contract been
performed.”) (internal quotation marks omitted). Thus, “a
plaintiff suing for breach of contract is not entitled to a
windfall.” Cmty. Health, 970 F.3d at 1375 (internal quota-
tion marks and alterations omitted); see also White v. Delta
Constr. Int’l, Inc., 285 F.3d 1040, 1043, 1046 (Fed. Cir.
2002) (vacating “windfall” award).
Second, “the non-breaching party is expected to take
reasonable steps to mitigate his or her damages.” Cmty.
Health, 970 F.3d at 1375. Relatedly, “there must be a re-
duction in damages” paid by the breaching party “equal to
the amount of benefit that resulted from the mitigation ef-
forts that the non-breaching party in fact undertook.” Id.
at 1376. However, and key here, the breaching party is not
entitled to a reduction of damages for benefits obtained by
the non-breaching party’s engagement in activities that are
“not properly viewed as actions in mitigation.” LaSalle,
317 F.3d at 1374.
Third, “[a] breach of contract may prevent a loss as well
as cause one.” Cmty. Health, 970 F.3d at 1376 n.10 (inter-
nal quotation marks omitted). “Thus, where the defend-
ant’s wrong or breach of contract has not only caused
damage, but has also conferred a benefit upon [the] plain-
tiff which he would not otherwise have reaped, the value of
this benefit must be credited to [the] defendant in as-
sessing the damages.” Kansas Gas & Elec. Co. v. United
States, 685 F.3d 1361, 1367 (Fed. Cir. 2012) (internal quo-
tation marks omitted); see also LaSalle, 317 F.3d at 1371
(“[T]he actual profits earned [by the non-breaching party]
must be credited against [its] projected lost profits.”).
The government argues that the Yankees’ use of NDT
gains to pay their breach-induced ISFSI costs mitigated
the Yankees’ damages. To award the Yankees’ damages on
top of their own successful mitigation efforts would, the
government continues, result in a windfall, in violation of
bedrock contract law. The government further insists it is
Case: 25-1395 Document: 50 Page: 10 Filed: 09/04/2026
10 CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US
entitled to a credit for the NDTs’ investment gains – bene-
fits it contends the Yankees only received by virtue of its
breach – that would fully offset what it owes the Yankees
for the Claim Period. The Yankees counter that the gains
earned in the NDTs are not sufficiently related to the gov-
ernment’s breach to be credited or counted as mitigation.
The Court of Federal Claims sided with the Yankees. We
do as well, for the reasons we explain in the next sections.
IV
To obtain the offset it seeks, the government must
carry its burden of proving that the Yankees’ use of NDT
funds constitutes a mitigation activity. See Westfield Hold-
ings, Inc. v. United States, 407 F.3d 1352, 1370 (Fed. Cir.
2005) (“[When] the government want[s] an offset, it [is] the
government’s burden to prove [it] . . . .”). It has failed to do
so, for two independent reasons. First, the government has
not shown that the NDTs, even with their investment
gains, have reduced or avoided any loss suffered by the
Yankees. Second, the government has failed to prove that
the NDTs are sufficiently connected to the government’s
breach. We address both failings below.
A
To constitute mitigation – and, therefore, be eligible for
offset against damages – the non-breaching party’s activi-
ties must be part of its “efforts to avoid damages.” Indiana
Michigan, 422 F.3d at 1375 (emphasis added). Hence,
“mitigation costs” are those that are “incurred in a reason-
able effort to avoid loss caused by a breach.” Old Stone
Corp. v. United States, 450 F.3d 1360, 1368 (Fed. Cir. 2006)
(emphasis added); see also Restatement (Second) of Con-
tracts § 347 cmt. d (“[The non-breaching party’s] cost
avoided is subtracted from the loss in value caused by the
breach in calculating his damages.”); id. § 350 (“Avoidabil-
ity as a Limitation on Damages”).
Case: 25-1395 Document: 50 Page: 11 Filed: 09/04/2026
CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US 11
We have applied this proposition in the specific context
of SNF cases. See, e.g., Kansas, 685 F.3d at 1366 (“The in-
jured party is limited to damages based on his actual loss
caused by the breach. If he . . . sustains a smaller loss than
might have been expected, his damages are reduced by the
loss avoided.”) (internal quotation marks and citation omit-
ted); Dairyland Power Co-op. v. United States, 645 F.3d
1363, 1372 (Fed. Cir. 2011) (“[A] non-breaching party’s re-
covery can in some cases be offset to account for costs it
avoided because of the breach.”). In both Yankee II and III,
for example, we considered “the expenses [the Yankees]
might have avoided” as part of their claim for reimburse-
ment of the costs of their mitigation efforts. Yankee II,
536 F.3d at 1273; see also Yankee III, 679 F.3d at 1361
(“The Yankees agreed to reduce their breach world ISFSI
costs by the estimated future cost of transferring SNF from
their wet pools to DOE in the nonbreach world, on the
ground these expenses were avoided because of the
breach.”).
Our mitigation inquiry in the SNF context focuses on
“direct savings that reduce the damages claim.” Kansas,
685 F.3d at 1366. We have, for example, found that a nu-
clear plant operator’s “decision to pursue higher enrich-
ment fuel assemblies” was “part and parcel of [its]
mitigation efforts,” because it “produced a real-world bene-
fit[:] . . . a savings of hundreds of thousands of dollars per
cycle.” Id. at 1367 (internal quotation marks omitted); see
also Cmty. Health, 970 F.3d at 1377 (“By enhancing the
racks to accommodate high-enrichment fuel assemblies,
the plaintiffs mitigated the government’s breach in a way
that produced a benefit.”) (internal quotation marks and
alterations omitted). In other SNF cases, we determined
that “a reduction in the share of wet storage and decom-
missioning fees paid” were “costs that were avoided,” re-
sulting in a credit to the government as mitigation. Bos.
Edison, 658 F.3d at 1369; see also Yankee III, 679 F.3d at
1362 (deeming “Yankee Atomic’s wet storage pool costs and
NRC fees” as mitigation expenditures). We have likewise
Case: 25-1395 Document: 50 Page: 12 Filed: 09/04/2026
12 CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US
approved treating “off-site storage” costs as “mitigation
damages” when non-breaching utilities worked around the
government’s breach by investing in external storage ar-
rangements. PG&E, 668 F.3d at 1353. These types of un-
dertakings, which avoid costs or yield “savings realized by
the plaintiff as a result of the breach,” are illustrative of
mitigation efforts in the SNF context. Cmty. Health,
970 F.3d at 1376 n.10 (internal quotation marks and alter-
ations omitted).
Here, by contrast, the government fails to identify any
of the Yankees’ costs that have been reduced or avoided as
a result of the government’s failure to collect the Yankees’
nuclear waste. It does not, for instance, contend that any
of the Yankees’ “spent fuel management cost[s]” have
abated or diminished, J.A. 396; that the Yankees have
fewer “radiation monitoring expenses,” 26 C.F.R. § 1.468A-
1(b)(6); or that they pay less for “security, analyses, [or] li-
censing” because of the NDTs’ investment gains. J.A. 1413.
To the contrary, it is undisputed that these costs have con-
tinued to mount. Instead, the government points to a
source of funds the Yankees can use to pay those (unmiti-
gated) costs: the NDTs and their investment returns. But
nothing about the availability of this funding pool de-
creases, in any amount, the costs associated with storing
SNF at a nuclear facility. In other words, that the money
is available to pay for expenses is not the same as those
expenses diminishing.
In urging us to reach a different conclusion, the govern-
ment relies heavily on our decision in LaSalle, 317 F.3d
at 1372. There, we held that the government was entitled
to a damages offset where its non-breaching counterparty,
a regional thrift savings bank, had mitigated its damages
by arranging to be purchased by a third-party bank. This
“substitute transaction,” we found, allowed the thrift to
continue operating and, ultimately, generate profits, which
had to be credited against the projected losses stemming
Case: 25-1395 Document: 50 Page: 13 Filed: 09/04/2026
CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US 13
from the government’s breach (for failing to undertake var-
ious measures to prevent the bank from entering receiver-
ship). Id. at 1371-72. The government compares “the
continued maintenance of the NDTs and the reimburse-
ments the Yankees received from the investment gains” to
that “substitute transaction.” Open. Br. at 28.
The government misreads LaSalle. Our holding there
was that the “reduction of loss through a substitute trans-
action is generally a direct mitigation of damages.” Id.
at 1373 (emphasis added); see also id. at 1372 (“If the non-
breaching party makes an especially favorable substitute
transaction, so that he sustains a smaller loss than might
have been expected, his damages are reduced by the loss
avoided as a result of that transaction.”) (emphasis added;
internal quotation marks and alterations omitted). In
other words, the core principle of LaSalle is that mitigation
efforts can result in an offset of breach of contract damages
when they reduce or avoid loss – a conclusion exemplified
by the long line of precedent discussed above.
Because no such reduction or avoidance of loss has
been shown here, we conclude that the NDTs’ investment
gains do not constitute a “mitigation activity” and, there-
fore, cannot be credited against the damages owed by the
government for its breach of contract.
B
There is a second reason that the NDTs’ investment
gains do not constitute mitigation activity: they are not a
direct consequence of DOE’s breach.
The “general rule,” applicable here, is “when there is a
direct relation, in time and in subject matter, between the
breach and mitigating events, the damages are reduced ac-
cordingly.” LaSalle, 317 F.3d at 1371-74. “[U]nrelated
events and remote consequences,” however, “do not reduce
the liability of the wrongdoer for the losses caused by the
wrong.” Id. at 1373; see also Kansas, 685 F.3d at 1366
(“Damages do not extend to remote consequences of the
Case: 25-1395 Document: 50 Page: 14 Filed: 09/04/2026
14 CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US
breach.”). The burden is on the breaching party to prove
that the non-breaching party’s actions are directly related
to the breach such that they constitute mitigation.
See LaSalle, 317 F.3d at 1373-74. The government has not
met its burden here.
The relationship between the NDTs’ earnings and
DOE’s breach is temporally remote. Each of the Yankees’
NDTs was established by 1984, more than a decade before
DOE’s breach began in 1998. When they were created, the
NDTs were for decommissioning the Yankees’ plants, a
process the Yankees completed by 2010. Of course, when
it became clear that the government could not honor its
SNF retrieval obligations in the early 2000s, the applicable
regulations were amended to expand the scope of “decom-
missioning” to include SNF storage and ISFSI-related
costs. The Yankees have used their NDTs solely for those
purposes ever since. But none of this more recent history
changes the fact that the NDTs were created prior to DOE’s
breach.
The government counters that this reasoning ignores
the partial, ongoing nature of its breach. It insists that
“[t]he operative point in time for determining the NDTs’
temporal relation to the breach is not when the fund was
established. It is during the claim period when the Yan-
kees’ damages accrued, and the Yankees received reim-
bursements for their ongoing spent fuel storage costs from
the NDTs.” Reply Br. at 1. The government cites no au-
thority that supports this assertion, and we reject it.
Nor has the government shown the required direct re-
lationship in subject matter between its breach and the
NDTs’ profits. The Yankees’ NDTs and their investment
gains, on the one hand, and DOE’s failure to take the Yan-
kees’ SNF, on the other, are not “reasonably directly re-
lated.” LaSalle, 317 F.3d at 1366 (“[M]itigation is limited
to actions reasonably directly related to the breach and its
proximate consequences.”). The Yankees created the NDTs
because the NWPA required them to do so; they continue
Case: 25-1395 Document: 50 Page: 15 Filed: 09/04/2026
CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US 15
to hold the NDTs, in trust for the ratepayers, because var-
ious statutes and regulations require them to keep doing
so. See, e.g., 10 C.F.R. § 50.75; 18 C.F.R. § 35.32(a)(6)-(7).
The investment gains earned by the NDTs during the
Claim Period are simply a “remote consequence” – a favor-
able one, to be sure – of DOE’s breach of contract. LaSalle,
317 F.3d at 1372; see also Hughes Commc’ns Galaxy, Inc.
v. United States, 271 F.3d 1060, 1072 (Fed. Cir. 2001) (re-
coupment of money from third parties was “too remote” to
be “type of mitigation” that “reduce[s] [non-breaching
party’s] damages”). Hence, they are not mitigating activi-
ties that may be offset against the damages owed by the
government to the Yankees. LaSalle, 317 F.3d at 1371
(“[I]t is improper to credit the wrongdoer with the profits
that the non-breaching party was able to achieve, through
no action by the wrongdoer, in mitigating the damages
caused by the breach.”). 2
V
The government warns that affirming the Court of Fed-
eral Claims judgment for the Yankees results in an im-
proper windfall, placing the Yankees “in a better position
2 We disagree with the Court of Federal Claims’ de-
termination that the requisite “direct relationship” needed
for the NDTs’ to constitute mitigation activity is further de-
feated by the fact that the NDTs are (i) subject to unpre-
dictable market forces and (ii) managed by a third party
investment professional. These factors do not necessarily
render the relationship between the Yankees’ activities
and DOE’s breach to be too remote. Indeed, we have pre-
viously rejected this proposition in the SNF context. See
Kansas, 685 F.3d at 1368 (holding that credit against con-
tract damages owed to operator of nuclear plant may be ap-
propriate even when “plaintiff’s earnings resulted from
uncertain market forces over time”).
Case: 25-1395 Document: 50 Page: 16 Filed: 09/04/2026
16 CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US
than they would have enjoyed had DOE performed.” Open.
Br. at 21. We disagree.
Although the funds in the NDTs (including their in-
vestment gains) are available to the Yankees as an interim
source to cover the costs incurred due to the government’s
breach, these monies are essentially a loan to the Yankees;
the Yankees are not entitled to keep them. The NDTs con-
sist entirely of funds provided by the ratepayers, and it is
the ratepayers to whom the holdings of the NDTs will be
returned when DOE at last completes performance under
the Standard Contract. See 18 C.F.R. § 35.32(a)(7). When
the Yankees draw on the NDTs to cover breach-related
costs, they are, in effect, borrowing against a fund that be-
longs to the ratepayers. The damages awarded here will
simply serve to pay the ratepayers back. Reducing this
damages award to zero, as the government asks us to do,
would leave the NDTs – and, ultimately, the ratepayers –
$145 million worse off than they should be.
In these circumstances, this is no windfall to either the
Yankees or the ratepayers. The victims of the govern-
ment’s breach are by no means “better off” as a result of
that breach. Instead, they are being restored to the posi-
tion they would have occupied had the breach never oc-
curred. The affirmed judgment requires the government to
reimburse the Yankees for having paid, using the rate-
payer-contributed NDT funds, the costs imposed on the
Yankees by the government’s breach of contract. It does
not provide any windfall to them. 3
3 The government emphasizes that the Yankees rec-
ord the NDTs as “assets” on their financial statements,
which also disclose that the NDTs contain sufficient funds
to cover 15 years of projected ISFSI costs, without any “spe-
cific expectation of the Yankees receiving a damages award
from the Government’s breach of the Standard Contract.”
Open. Br. at 9 (quoting J.A. 398). That does not alter the
Case: 25-1395 Document: 50 Page: 17 Filed: 09/04/2026
CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US 17
VI
One final point further convinces us that the NDTs’
gains are not a mitigation effort: the logical consequences
that would follow were we to hold otherwise. Were we to
rule that the government is entitled to a credit against
damages owed when the NDTs generate investment gains,
we would have to similarly conclude that the Yankees are
entitled to collect greater damages in any claim period in
which the NDTs experience investment losses. 4
The NDTs and their investments are either mitigation
activities or they are not. See Hughes, 271 F.3d at 1072
(holding that same activity cannot be mitigation only when
profitable for non-breaching party, as this “would destroy
[the] symmetry between [the] reduction and escalation of
damages”). If they are, as the government insists, then the
government could offset the investment gains against the
damages it owes for the current Claim Period, but only at
the cost of having to add to the damages owed if, during
another period, the NDTs experience investment losses.
The government has not agreed to accept this risk. At
oral argument, it suggested that it might owe such addi-
tional damages when it finally performs and this litigation
fundamental reality that the NDTs are held in trust for the
Yankees’ ratepayers, who, but for the damage caused by
the government’s breach, would have their principal con-
tributions to the NDTs returned to them as well as the in-
vestment gains realized by the NDTs.
4 In that circumstance, the government might also
be liable to pay other “fair and reasonable” mitigation ex-
penses, such as third-party investment manager fees. Cit-
izens Fed. Bank v. United States, 474 F.3d 1314, 1321 (Fed.
Cir. 2007); see also J.A. 948 (“Investment income [from the
NDTs] is used to pay the trustee and investment manage-
ment expenses of administering the Trust[s].”).
Case: 25-1395 Document: 50 Page: 18 Filed: 09/04/2026
18 CONNECTICUT YANKEE ATOMIC POWER COMPANY v. US
concludes. See Oral Arg. at 1:30-3:30. 5 But it strongly im-
plied it would never pay for the NDTs’ investment losses
during any period of partial breach. If, as seems to be the
case, the government refuses responsibility for losses in the
NDTs, it cannot benefit when those same NDTs happen to
enjoy gains. J.A. 7 (“Just as the Yankees may not ask for
increased damages should their NDT investments yield
losses, the government may not ask for reduced damages
due to gains in the Yankees’ NDTs.”); see also Dominion
Res., Inc. v. United States, 641 F.3d 1359, 1365 (Fed. Cir.
2011) (observing that nuclear utility “cannot ask for in-
creased damages should its investment of [funds] return
less than [expected], and the government cannot ask for a
reduction in damages should [the] investments return
more”). The proper result, then, is to deny the government
an offset against the damages it owes for DOE’s breach.
VII
We have considered the government’s remaining argu-
ments and find them unpersuasive. Accordingly, for the
foregoing reasons, we affirm the judgment of the Court of
Federal Claims.
AFFIRMED
5Available at https://www.cafc.uscourts.gov/oral-ar-
guments/25-1395_07072026.mp3.