Charles and Anna Silla v. Q&R Home Improvements, LLC, and Robert Koseyan
CourtNew Jersey Superior Court Appellate Division
Date FiledNovember 2, 2026
DocketA-3137-24
StatusUnpublished
๐ฐ News Coverage: Read the LAWS.com news report on this case
Full Opinion
NOT FOR PUBLICATION WITHOUT THE
APPROVAL OF THE APPELLATE DIVISION
This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the
internet, this opinion is binding only on the parties in the case and its use in other cases is limited . R. 1:36-3.
SUPERIOR COURT OF NEW JERSEY
APPELLATE DIVISION
DOCKET NO. A-3137-24
CHARLES and ANNA SILLA,
Plaintiffs-Respondents,
v.
Q&R HOME IMPROVEMENTS,
LLC, and ROBERT KOSEYAN,
Defendants-Appellants.
_____________________________
Submitted September 30, 2026 โ Decided November 2, 2026
Before Judges Smith and Vinci.
On appeal from the Superior Court of New Jersey, Law
Division, Monmouth County, Docket No. L-2528-22.
Hegge & Confusione, LLC, attorneys for appellants
(Michael Confusione, of counsel and on the brief).
Ronal L. Lueddeke, attorneys for respondents (Karri
Lueddeke, on the brief).
PER CURIAM
Defendants Q&R Home Improvements, LLC (Q&R) and Robert Koseyan
appeal from a June 4, 2025 amended order for judgment entered in favor of
plaintiffs Charles and Anna Silla following a bench trial at which the court found
defendants violated the New Jersey Consumer Fraud Act (CFA), N.J.S.A. 56:8-
1 to -227, in connection with a series of home-improvement contracts.1 We
affirm.
I.
We summarize the facts developed during the bench trial on March 17,
2025. Plaintiffs, who primarily reside in New York, own a second home in
Neptune. Q&R provides various home improvement services to residential
property owners and Koseyan is the owner of Q&R. Plaintiffs contacted
Koseyan to do a "total renovation" of the interior of their Neptune home.
On May 14, 2022, the parties entered into a contract for a "bathroom
remodel" (May 14 contract). The May 14 contract provided defendants would
"demoli[sh the] entire bathroom stripped down to the framing beams
and . . . subflooring," install bathroom fixtures, "[i]nstall moisture resistant
1
Defendants also appealed from orders entered on July 9, 2024, September 8,
2023, and November 3, 2023. Defendants did not brief any arguments relating
to those orders, and any such arguments are therefore waived. Green Knight
Cap., LLC v. Calderon, 469 N.J. Super. 390, 396 (App. Div. 2021).
A-3137-24
2
drywall," and "[i]nstall new bathroom vinyl." The contract stated "[p]lumbing
configuration to be unchanged. Electrical configuration to be unchanged." The
total price for the services included in the May 14 contract was $11,500, which
plaintiffs paid in full before any work began.
Also on May 14, plaintiffs executed a "change order" (May 14 change
order) for additional work. This work included "[g]eneral yard clean up,"
"[t]rench[ing] electrical to [the] rear yard," "paint[ing the] interior of [the]
house," "replac[ing] all hot water baseboard units," "[s]and[ing] [the] entire
hardwood flooring throughout [the] house," and "[r]emov[ing] and install[ing]
new ceiling fans." The total price for the services included in the May 14 change
order was $13,650, which plaintiffs paid in full before the work was completed.
On May 28, 2022, the parties executed a second change order (May 28
change order) for additional work, including "[i]nstall[ation of] kitchen
cabinets . . . [b]ase cabinets . . . wall cabinets . . . [c]ountertops . . . [a] stainless
[steel] sink . . . [and a] backsplash." The price for that work in the kitchen was
$18,500. The May 28 change order also included "[d]emolition of . . . flooring
to existing floor beams," "[i]nstall[ation of] floor insulation," "[i]nstall[ation of]
vinyl thermal pane windows," "[i]nstall[ation of a]luminum roof sealer,"
"[p]aint[ing the] entire exterior of house and garage," and "[p]aint[ing the] entire
A-3137-24
3
interior of house and garage." The total price for the services included in the
May 28 change order was $47,000. Plaintiffs paid $35,000 toward the work
included in the May 28 change order before the work was completed.
On June 16, 2022, the parties executed another change order (June 16
change order), which included "[s]upply/install[ation of three] exterior [half]
lite doors," "re-install[ation of] existing storm doors," "[r]emoval of all job
related debris," "[s]upply/install[ation of] prefinished flooring throughout [the]
entire house," and "install[ation of] underlayment barrier throughout the entire
house." The total price for the services included in the June 16 change order
was $12,500, which plaintiffs paid in full.
The total price for all the work included in the May 14 contract and the
change orders was $84,650. As of June 17, 2022, plaintiffs paid Q&R a total of
$72,650. Defendants failed to complete the work and left the job site by early
July 2022.
On September 16, 2022, plaintiffs filed a complaint against defendants
alleging: (1) violations of the CFA; (2) breach of contract; (3) negligence; and
(4) violation of the Contractors' Registration Act (CRA), N.J.S.A. 56:8-136
to -152. Plaintiffs demanded a jury trial. On November 14, 2022, defendants
answered. In August 2023, defendants' first counsel moved to withdraw, which
A-3137-24
4
the court granted on September 8, 2023. On December 20, 2024, new counsel
entered an appearance for defendants. On March 17, 2025, the court conducted
a bench trial.
Anna Silla testified defendants "began the work." They "strip[ped] off the
floors . . . and put [in] the new one."2 Defendants "also changed the
windows . . . without doing the sides" and "insulated the whole house."
However, defendants did not finish the bathroom, finish the kitchen, buy
[plaintiffs] any kitchen cabinets, paint, install countertops, install a tile
backsplash, install any appliances, paint the exterior of the home, or install any
portion of the bathroom.
Anna testified Koseyan "said he [was] going . . . to finish . . . two months
from . . . May 14." She "expected that the work would be done at some point in
July." Anna testified that when plaintiffs were at the home they "were sleeping
in the garage because there [was] no water, no bathroom." They also used
restaurant bathrooms to relieve themselves and "wash" themselves.
Anna testified that plaintiffs' "communications fell off with . . . Koseyan"
and they "ke[pt] calling him. No answer. [They] texted him. No answer. He
2
Because plaintiffs share a common surname, we refer to them by their first
names. No disrespect is intended.
A-3137-24
5
just ignore[d them]. That[ was] it. Like, gone." Plaintiffs introduced numerous
text messages and phone records to corroborate Anna's testimony.
Plaintiffs eventually hired their neighbor who was a licensed contractor,
Eddie Knee of EBK's Total Construction LLC, who finished the renovations.
Plaintiffs paid Knee at least $62,167 for his work.
Knee testified that when he first visited the home in July or August 2022,
he observed plaintiffs "needed a bathroom done and a kitchen done . . . and a
bunch of miscellaneous stuff." He stated Koseyan had installed "[s]heetrock"
and "a new floor" in the kitchen. Knee "gutted the walls" in the kitchen because
"by code . . . there [were] not enough [electrical] outlets." Knee "t[ook] the
[s]heetrock down," "install[ed] the cabinets and countertops," and "re-
[s]heetrock[ed]."
In the bathroom, Knee testified defendants had installed "the shower pan"
and the "walls [were] ready for tile." Knee testified the bathroom was not
finished, but some of the work was "salvageable in [his] opinion." Knee
"took . . . apart" some of the previous work that was not done "the way he [does]
it." He "did[ not] take apart things that [he] could use" and was able to use the
"walls" defendants installed. Knee worked on "the hot water baseboards" in the
bathroom "because, while they were renovating it, [the baseboards] . . . had to
A-3137-24
6
be taken out and moved and [he] put that in and then a couple [of] new covers. "
He also "replaced the diverter valve" for the shower.
In the living room, Knee "finish[ed the s]heetrock" and there were "some
spots that needed to be spackled" and there was "a little strip off the
bottom . . . that [he] had to put on." Knee testified that "when [he] turned the
heat on, it did[ not] work" and he had to replace the "gas valve" and "the pump
that circulates the water." Knee needed to use outside professionals such as
electricians, plumbers, and heating, ventilation, and air conditioning (HVAC)
specialists for some of the work.
Koseyan testified that defendants completed a portion of the work they
agreed to do. Specifically, they removed and replaced the floors, removed and
reinstalled insulation and sheetrock, painted the roof with a waterproof material,
removed a set of steps in the rear of the house, and painted the ceilings and
interior other than the kitchen and bathroom. Koseyan claimed some of the work
he did was not included in his contract and change orders with plaintiffs,
including demolition and removal of "a structure in the back" of the property,
grading the back yard, reframing a wall in the bathroom, and replacing beams,
floor joists, and insulation as a result of water damage.
A-3137-24
7
Koseyan testified that the work was delayed because, after defendants
started work, plaintiffs said they "wanted to reconfigure" the kitchen and change
"where everything had to go." That reconfiguration would have entailed
electrical and plumbing work he could not do. He told plaintiffs he "needed a
licensed electrician" and a "licensed plumber" to do that work. Koseyan also
told plaintiffs he needed an HVAC professional to change the baseboard heating
elements "if they really want[ed] the heat to work properly in the house."
According to Koseyan, plaintiffs did not want to pay for the additional
electrical and plumbing work, which "interfered with the completion of the
project." Defendants continued the outside work while they were "waiting to
understand how [plaintiffs] wanted . . . to configure . . . the kitchen and the
bathroom." Charles "was the point person" and "he just was taking his time
getting back to [Koseyan]." Koseyan claimed defendants completed "probably
about [eighty-five] percent" of the work they agreed to do.
Koseyan admitted defendants did not finish the bathroom work and did
not "refund any portion of the $11,500" plaintiffs paid Q&R in connection with
the May 14 contract. He also admitted defendants did not do all of the work
included on the May 14 change order. Defendants did not "trench the electrical,"
"paint[] the bathroom," or "replace all hot water baseboard units." Defendants
A-3137-24
8
also did not sand the hardwood flooring because it was replaced with laminate
flooring. Defendants did not refund any portion of the $13,650 plaintiffs paid
Q&R for the work included on the May 14 change order.
With respect to the May 28 change order, Koseyan admitted defendants
did not install the kitchen cabinets, base cabinets, countertops, sink, or
backsplash. Q&R was "paid for this change order," but defendants did not
refund any portion of the $18,500 plaintiffs paid for the work in the kitchen that
was not completed. Defendants also did not paint the exterior of the house
because "the color was[ not right]." Defendants did not refund any portion of
the $7,200 plaintiffs paid for the exterior painting work.
On March 19, 2025, the court entered final judgment in favor of plaintiffs,
supported by an oral decision. The court found "there could be no legitimate
argument that defendant[s] did not breach the contract as [they] admitted
receiving monies from the . . . plaintiffs for work admittedly not performed and
[they have] not offered to refund any of that money." The court determined
"[t]he only real question is the extent of damages . . . and whether or not it
ultimately results in a finding of a violation of the [CFA]."
The court rejected defendants' claim that plaintiffs were not entitled to a
refund because they did work that was not included in the contract and change
A-3137-24
9
orders. The court found Anna's testimony that defendants did not complete any
additional work "was credible . . . and . . . consistent with all the evidence, or
lack thereof, to the contrary." It noted "there was no documentary evidence of
any kind, no corroborating witness testimony, no photographs, no receipts,
nothing . . . that would explain, articulate, or provide reference for the work that
allegedly was performed."
The court also rejected defendants' claim that they did not abandon the job
because plaintiffs failed to advise him how to proceed with the configuration of
the bathroom and kitchen. It found "again, [defendants] provided no
documentation or communication between [them] and the plaintiffs indicating
that [they were] waiting [for] this crucial information before [they] could
proceed."
The court found Anna "testified that they never intended to change the
layout of either the bathroom or the kitchen, which is why the initial contract
specifically state[d] that the configuration of the plumbing and electrical in the
bathroom would remain unchanged." Her testimony was "once again consistent
with the documentary evidence" and "[t]he fact that the kitchen and bathroom
were ultimately finished by . . . [K]nee . . . in their original configuration
clearly furthers the credibility of . . . plaintiff[s] in this regard."
A-3137-24
10
In addition, plaintiffs produced "numerous text exchanges with
[Koseyan] . . . as well as a telephone call log, all of which support [their]
contention that at no time did [defendants] ever even infer that the reason for
not continuing the work . . . was due to plaintiffs' failure . . . to
advise . . . defendant[s] about any changes or reconfigurations of . . . the
rooms." The court concluded "defendant[s'] argument as to why
[they] . . . cancelled [their] work in or about July . . . 2022 and did not return to
the property . . . to not be credible."
The court determined defendants committed unlawful business practices
as defined in the CFA by violating numerous provisions of the Home
Improvement Practice Regulations (HIPR), N.J.A.C. 13:45A-16.1 to -16.2. The
court found defendants violated N.J.A.C. 13:45A-16.2(a)(6)(v), which prohibits
a contractor from having a consumer make "final payment on the contract before
the home improvement is completed in accordance with the term[s] of the
contract." The court found it was "undisputed that . . . plaintiffs paid in full for
a number of the contracts that were signed . . . prior, not only to completion, but
prior to any work being performed."
A-3137-24
11
The court found defendants violated N.J.A.C. 13:45A-16.2(a)(6)(vi),
(vii), and (viii) 3 by failing to advise plaintiffs in the "contract and change orders
which apply to the bathroom and kitchen" they "did not perform [electrical or
plumbing work]" and the work defendants contend plaintiffs wanted done
"necessarily involve[d] either the plaintiffs going out and finding their own
electrician and plumber or [defendants] contracting with an electrician or
plumber for an additional cost." "None of which [was] reflected in writing in
3
Those sections provide it is unlawful to:
vi. Misrepresent or fail to disclose that the offered or
contract price does not include delivery or installation,
or that other requirements must be fulfilled by the buyer
as a condition to the performance of labor, services, or
the furnishing of products or materials at the offered or
contract price;
vii. Mislead the prospective buyer into believing that
the down payment or any other sum constitutes the full
amount the buyer will be obligated to pay;
viii. Misrepresent or fail to disclose that the offered or
contract price does not include all financing charges,
interest service charges, credit investigation costs,
building or installation permit fees, or other
obligations, charges, cost or fees to be paid by the
buyer.
[N.J.A.C. 13:45A-16.2(a)(6)(vi), (vii), and (viii).]
A-3137-24
12
any of the documents provided" and "defendant[s] knew or should have known
that additional expenses beyond those contemplated in the contract and change
orders would be required."
The court found defendants violated N.J.A.C. 13:45A-16.2(a)(7)(ii) and
(iii)4 by failing to set forth any "timeframes, start[,] or end dates . . . in any of
the written documents." Defendants also failed to advise plaintiffs in writing of
"the basis for any delays" including that the cause of the delay allegedly was
"out of [their] control because [they were] waiting on information from the
plaintiffs." The court also found defendants violated N.J.A.C. 13:45A-
4
Those sections provide it is unlawful to:
ii. Fail to begin or complete work on the date or within
the time period specified in the home improvement
contract, or as otherwise represented, unless the delay
is for reason of labor stoppage; unavailability of
supplies or materials, unavoidable casualties, or any
other cause beyond the seller's control. Any changes in
the dates or time periods stated in a written contract
shall be agreed to in writing; or
iii. Fail to give timely written notice to the buyer of
reasons beyond the seller's control for any delay in
performance, and when the work will begin or be
completed.
[N.J.A.C. 13:45A-16.2(a)(7)(ii) and (iii).]
A-3137-24
13
16.2(a)(12)5, which "is sort of a catchall" based on the same conduct that
violated the other more specific regulations.
The court found plaintiffs proved they suffered "ascertainable loss" "due
to defendant[s'] violations of the [HIPR] and therefore the CFA" that
"stem[med] from defendants' undisputed failure to . . . complete the promised
work . . . and . . . refund any monies to plaintiffs despite" failing "to complete
the work . . . plaintiffs paid for." It determined "[p]laintiffs'
damages . . . consist of monies paid for items not performed which subsequently
had to be performed by their secondary contractor."
The court awarded plaintiffs damages in the amount of $36,621 based on
what they paid for "work that was not performed." With respect to the May 14
5
That section provides:
12. Home improvement contract requirementsโ
writing requirement: All home improvement contracts
for a purchase price in excess of $500.00, and all
changes in the terms and conditions thereof shall be in
writing. Home improvement contracts which are
required by this subsection to be in writing, and all
changes in the terms and conditions thereof, shall be
signed by all parties thereto, and shall clearly and
accurately set forth in legible form and in
understandable language all terms and conditions of the
contract, . . .
[N.J.A.C. 13:45A-16.2(a)(12).]
A-3137-24
14
contract, for which plaintiffs paid the full amount of $11,500, the court gave
defendants "credit . . . for demolition done and the installation of the shower
pan" in the amount of $1,500, "leaving damages on the [May 14] contract in the
amount of $10,000." The court awarded damages in the amount of $11,650 on
the May 14 change order. It determined plaintiffs paid the full $13,650 due for
that change order but gave defendants a "credit . . . in the amount of $2,000" for
painting and yard cleanup that was done.
On the May 28 change order, the court awarded damages in the amount of
$13,700. It reasoned that plaintiffs paid a total of $35,000 toward the May 28
change order, but defendants performed some of the work included in that
change order totaling $21,300, leaving a balance owed to plaintiffs of $13,700.
The court also awarded plaintiffs $940 for the "electrical work . . . to add outlets
to the kitchen to make it up to code which would have been within the scope of
work required for [the] kitchen renovation" and $331 for installation of "ceiling
fans, which were part of defendant[s'] contracted obligations." The court then
trebled the damage award pursuant to the CFA, for a total award of $109,863,
and awarded plaintiffs attorneys' fees and costs.6 The court dismissed plaintiffs'
6
The court also found Koseyan individually liable pursuant to the CFA.
Defendants did not brief any arguments relating to that aspect of the June 4,
A-3137-24
15
"breach of contract claim as duplicative." It also dismissed plaintiffs' CRA
claim.
Plaintiffs subsequently moved for attorneys' fees in the amount of $26,140
and costs in the amount of $622.84, supported by an affidavit of services in
accordance with Rule 4:42-9(b). Plaintiffs' counsel certified she devoted 49.8
hours to the case, and her hourly billing rate was $550 per hour. Defendants
opposed the application, arguing only that "$475 per hour is appropriate as a
rate in this case," which "would bring the fee application to a more fair and
reasonable $23,655."
On June 3, 2025, the court granted plaintiffs' application in an oral
decision. The court "note[d] [defendants did] not oppose or attempt to
distinguish in any way the number of hours spent" but it "did review those as
well." It found "the rate of $550 per hour . . . [was] certainly well within the
range of a reasonable and customary fee . . . and the requested fee [was] fair and
reasonable." The court then reviewed "the affidavit of service[s] in its entirety"
and addressed each of the factors set forth in Rule of Professional Conduct
(RPC) 1.5(a). It found "the total hours expended were 49.8" and none of the
2025 judgment. Any such arguments are, therefore, waived. Green Knight Cap.,
LLC, 469 N.J. Super. at 396.
A-3137-24
16
time expended was "unnecessary, overstated, duplicative, or otherwise
improper." The court granted plaintiffs' application and awarded attorneys' fees
in the amount of $26,140, plus costs in the amount of $622.84. On June 4, 2025,
the court entered an amended order for judgment. This appeal followed.
II.
On appeal, defendants argue, the "failure to hold a jury trial, which both
parties demanded in their pleadings, was harmful error." Defendants did not
raise this argument in the trial court.
Defendants also argue the court "misapplied the [CFA's] causal
connection and ascertainable loss requirements." Specifically, they contend the
court "erred in awarding treble damages under the [CFA] because . . . plaintiffs
failed to prove that there was a causal relationship between the unlawful
practices under the CFA and the claimed" ascertainable loss.
Relatedly, defendants argue "[t]he damages in this case . . . should have
been measured by the extra money . . . plaintiffs had to pay . . . [Knee] . . . to
perform the work that . . . defendant[s] . . . promised to accomplish but did not."
They contend the court's $36,621 damage award "generally applies the proper
measure for expectation damages" and should be "affirmed" as "breach-of-
contract damages, not CFA damages."
A-3137-24
17
Defendants also argue the court's award of attorneys' fees was excessive
because it did not "separat[e] which portion[s] of the fees resulted from proving
the [CFA] violations โ which were recoverable โ and which resulted from the
breach of contract claim, which were not."
III.
Defendants' claim that the court deprived them of their right to a jury trial
is raised for the first time on appeal. Generally, we "will decline to consider
questions or issues not properly presented to the trial court when an opportunity
for such a presentation is available 'unless the questions so raised on appeal go
to the jurisdiction of the trial court or concern matters of great public interest. '"
Nieder v. Royal Indem. Ins. Co., 62 N.J. 229, 234 (1973) (quoting Reynolds
Offset Co. v. Summer, 58 N.J. Super. 542, 548 (App. Div. 1959)). Because
defendants failed to raise this argument in the trial court, it is waived.
Even if we considered defendants' argument, we are convinced it is
without merit. Rule 4:35-1(d) provides, in relevant part, that:
When trial by jury has been demanded as provided by
this rule, the trial of all issues so demanded shall be by
jury, unless all parties or their attorneys, by written
[consent] and filed stipulation or oral stipulation made
in open court and entered on the record, consent to trial
by the court without a jury.
[Ibid.]
A-3137-24
18
It has long been the rule that the right to a jury trial may be waived. See
Guber v. Peters, 149 N.J. Super. 138, 139 (App. Div. 1977) (holding that the
defendants waived their right to a jury trial requested in their initial pleadings
by failing to press that right to the court thereafter). Waiver is a
"voluntary . . . relinquishment of a known right" evidenced by a clear,
unequivocal, and decisive act from which an intention to relinquish the right can
be based. Sroczynski v. Milek, 197 N.J. 36, 63-64 (2008) (Rivera-Soto, J.,
concurring) (quoting Knorr v. Smeal, 178 N.J. 169, 177 (2003)). At times, a
waiver may be implied by conduct or acquiescence. Guber, 149 N.J. Super. at
140.
Plaintiffs contend defendants expressly waived their right to a jury trial at
a pretrial conference, and the trial transcript supports that claim. At the outset
of the trial, the court stated the "matter [was] before the [c]ourt for a bench trial."
Defense counsel, accompanied by Koseyan, did not object, confirmed
defendants did not have any objections to plaintiffs' proposed trial exhibits,
waived the opportunity to make an opening statement, and proceeded with the
bench trial. We are convinced, based on the record, that defendants expressly
waived their right to a jury trial prior to trial as plaintiffs contend, or implicitly
waived that right through their statements and conduct at the time of trial.
A-3137-24
19
IV.
We are unpersuaded by defendants' claim that the court incorrectly found
plaintiffs established a causal connection between the HIPR and CFA violations
and their ascertainable loss. Our review of a final determination made following
a bench trial is "subject to a limited and well-established scope of review."
Seidman v. Clifton Sav. Bank, S.L.A., 205 N.J. 150, 169 (2011). We do not
disturb a trial court's findings of fact unless "convinced that those findings and
conclusions [a]re 'so manifestly unsupported by or inconsistent with the
competent, relevant and reasonably credible evidence as to offend the interests
of justice.'" Griepenburg v. Twp. of Ocean, 220 N.J. 239, 254 (2015) (quoting
Rova Farms Resort v. Invs. Ins. Co. of Am., 65 N.J. 474, 484 (1974)). "To the
extent that the trial court's decision constitutes a legal determination, we review
it de novo." D'Agostino v. Maldonado, 216 N.J. 168, 182 (2013).
The CFA's private cause of action "requires a plaintiff to prove three
elements: '1) unlawful conduct by defendant; 2) an ascertainable loss by
plaintiff; and 3) a causal relationship between the unlawful conduct and the
ascertainable loss.'" Id. at 184 (quoting Bosland v. Warnock Dodge, Inc., 197
N.J. 543, 557 (2009)).
A-3137-24
20
"Unlawful conduct" is either an affirmative act, knowing omission, or
regulatory violation. See Thiedmann v. Mercedes-Benz USA, LLC, 183 N.J.
234, 245 (2005). If a contractor violates the HIPR, the first element of the CFA's
three-step analysis is satisfied. Roberts v. Cowgill, 316 N.J. Super. 33, 38-40
(App. Div. 1998).
Our Supreme Court has held "ascertainable loss" requires "that the
plaintiff suffered an actual loss." Thiedemann,183 N.J. at 248. The loss "must
be presented with some certainty demonstrating that it is capable of calculation."
Ibid.
"In addition, the CFA requires a consumer to prove that the loss is
attribut[ed] to the conduct that the CFA seeks to punish by including a limitation
expressed as a causal link." Bosland, 197 N.J. at 555. "[A] plaintiff who cannot
prove the causal link between the asserted regulatory violation and his [or her]
loss cannot find relief within the CFA." Id. at 560.
Here, defendants do not dispute the court's determination that they
violated numerous provisions of the HIPR, nor do they challenge the court's
determination of plaintiffs' ascertainable loss. Rather, they contend the court
incorrectly found a causal link between the HIPR violations and plaintiffs ' loss.
We disagree.
A-3137-24
21
There can be no serious dispute that plaintiffs' loss was causally connected
to defendants' violation of N.J.A.C. 13:45A-16.2(a)(6)(v), which prohibits a
contractor from having a consumer "make final payment on the contract before
the home improvement is completed in accordance with the terms of the
contract." That regulation is intended to protect consumers from precisely what
happened in this case. Defendants took plaintiffs' full payments for work that
was not complete and abandoned the project. Plaintiffs, who had already paid
defendants for the work, were then forced to expend tens of thousands of dollars
to complete the same work.
Nor can there be any legitimate dispute that plaintiffs' loss was causally
connected to defendants' violations of N.J.A.C. 13:45A-16.2(a)(7)(ii) and (iii).
As the court correctly found, defendants violated those regulations by failing to
set forth any "timeframes, start[,] or end dates" for the work and failing to advise
plaintiffs in writing of the "basis for any delays" including that the cause of the
delay allegedly was "out of [their] control because [they] were waiting on
information from the plaintiffs."
If, as defendants contend, their work was delayed and ultimately
abandoned because they were waiting to hear from plaintiffs, compliance with
the requirement to advise plaintiffs of the cause of the delay would have resolved
A-3137-24
22
the miscommunication. According to defendants, had plaintiffs simply
responded, they would have completed the work in a timely manner.
Compliance with the HIPR, therefore, would have prevented plaintiffs' loss.
Conversely, therefore, defendants' failure to comply with the HIPR caused
plaintiffs' loss.
There is no basis for us to disturb the court's determination that plaintiffs'
losses were caused by these and the other HIPR violations it found. We are
satisfied the court's factual findings were amply supported by competent,
credible evidence in the record and the court properly applied those facts to the
law. For the same reasons, we are convinced defendants' claim that the court
should have awarded damages for breach of contract instead of treble damages
under the CFA lacks merit.
V.
Defendants' claim that the court's award of attorneys' fees was excessive
is not persuasive. Defendants' argument that the court failed to differentiate
between fees attributable to breach of contract and the CFA violations is raised
for the first time on appeal. In the trial court, defendants only challenged
counsel's hourly billing rate and conceded the balance of the application,
including the number of hours expended. Defendants abandoned that argument
A-3137-24
23
on appeal. Because defendants' newly-minted argument was not raised in the
trial court, it is waived. Nieder, 62 N.J. at 234.
Even if we considered their argument, the court correctly determined
plaintiffs' losses resulted solely from defendants' CFA violations and dismissed
the breach of contract claim. There is, therefore, no basis to apportion fees to
anything other than the CFA claim.
We have, nevertheless, reviewed the court's award of attorneys' fees on
the merits. "We review [a] trial court's award of [attorneys'] fees and costs in
accordance with a deferential standard. Such an award 'will be disturbed only
on the rarest occasions, and then only because of a clear abuse of discretion. '"
Hansen v. Rite Aid Corp., 253 N.J. 191, 211-12 (2023) (quoting Rendine v.
Pantzer, 141 N.J. 292, 317 (1995)). We are satisfied the court properly reviewed
plaintiffs' application in accordance with Rule 4:42-9(b), RPC 1.5(a), and
applicable law, and do not find any basis to disturb the court's award of
attorneys' fees and costs.
Affirmed.