Govendo v. Micronesian Garment Inc.
CourtSupreme Court of The Commonwealth of The Northern Mariana Islands
Date FiledSeptember 10, 1991
Docket90-013
JudgeDela Cruz
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
CLERK OF COURT
SUPREME. COUR1. CNMI
FILED
FOR PUBLICATION
IN THE SUPREME COURT OF THE
COMMONWEALTH OF TBB NORTHERN MARI�A ISLANDS
KENNETH L. GOVENDO, ) APPEAL NO. 90-013
) SUPERIOR CT. NO. 89-425
Plaintiff/Appellant, )
)
vs. ) QPINION
)
MICRONESIAN GARMENT )
MANUFACTURING, INC., et al, )
)
Defendants/Appellees. )
____ )
Argued and Submitted october 4, 1990
counsel for Plaintiff/Appellant: Kenneth L. Govendo, Esq.,
pro se
P.O. Box 2377
Saipan, MP 96950
Counsel for Defendants/Appellees: Rexford C. Kosack, Esq.
P.O. Box 410
Saipan, MP 96950
BEFORE: DELA CRUZ, Chief Justice, BORJA, Justice, and ATALIG,
Special Judge.
DELA CRUZ, Chief Justice:
Kenneth L. Govendo ("Govendo11) appeals the dismissal of his
action against Micronesian Garment Manufacturing, Inc. ("MGM11 or
"the company") and the NMI Coastal Resources Management Office
272
cncRMn or "the agency") . 1 The action was dismissed for failure to
state a cognizable claim, pursuant to Com.R.Civ.P� 12{b) (6).2
I.
Under the Coastal Resources Management Act of 1983, 2 CMC §§
1.501. et seq. ("the Act"), CRM is charged with the authority to
review proposed construction projects within NMI coastal areas.3
Should a project be proposed in an "area of particular concern" or
fall within certain regulatory "major siting guidelines11,4 the CRM
permit process is triggered. In that event, construction cannot
proceed unless and until the agency issues a permit. If CRM issues
a permit, it may impose appropriate limitations upon a project.
The cont:,:oversy in this case arose from MGM 1 s proposal to
construct a garment facto:r:y on saipan.
On November 2, 1988, the company submitted an application to
the agency to construct such a factory in Susupe. In the face of
-public opposition to the proposed siting, MGM withdrew its application.
1Govendo v. Micronesian Garment Mfg., Inc., Civil Action No.
89-425, Memorandum Decision and Order of Dismissal (N.M.I. Super.
ct. April 2, 1990). CRM elected not to participate in this appeal.
2For the pertinent language of this rule, see n.s, infra.
3The agency's territorial jurisdiction includes the
Commonwealth's territorial waters and "all land areas" except
certain federally-owned lands. 2 CMC § 1513.
4See Office of Coastal Resources Management Rules and
Regulations, 7 Commonwealth Reg�ster No. 10 at 4096 et seq. (1985);
"Coastal Respurces Management Program Major Siting Guidelines",
Appellee's Exhibit E. Under the "Major Siting Guidelines," a
project meeting any one or more of certain specified criteria
(e.g., "(a] peak water demand of greater than 3,500 gallons per
day") "is presumptively a major siting unless the CRM Directors
determine otherwise by written consensus.11
273
An MGM representative subsequently notified CRM by letter
dated Januaey 31, 198
· 9, that the company proposed a new site in San
Vicente. According to the letter, MGM intended to construct a
dormitory to house forty-five workers. It planned to generate its
own electricity, rely on catchment basins and wells for water, and
to hook up to an adjacent sewer line to dispose of waste water.
Based on this information, the company inquired whether it would
have to submit an application for a permit.
In a letter dated March 8, 1989, the CRM administrator advised
MGM that, based on the company's representatiGns, the project was
not a major siting:
The water and sewer usage is below the amounts estab
lished in CRM major siting guidelines. The project will
connect to the sewer. The number of workers, forty five,
housed at the site is below the major siting guideline
figure of fifty.
As you know, however, our office continually
monitors project sites. Should any of the facts change,
CRM would have to review the project for possible
jurisdiction.
In response to an inquiry from Govendo, the agency advised him of
its decision concerning the project in a letter dated March 15,
1989: 11[t]he factory, as now represented, no longer fits within the
Major Siting Guidelines, nor is is [sic] located within an area of
particular concern . [t]herefore, CRM has no authority to
assert jurisdiction."
In a letter dated March 2 4, 1989, Govendo requested the agency
to reconsider its decision:
Simply stated, CRM is not following its own regulations
about when a project should be declared a major siting.
Although 45 workers may be living on the premises, it is
274
apparent that this factory will bring in more than 50
aliens altogether. Thus •it should be declared a
• •
major siting.
I shall file a lawsuit on April 13 · unless . CRM
declares this project to be a major siting.
The record does not indicate any response by the agency.5
on April 13, 1989, Govendo filed an action against MGM and CRM
officials in Commonwealth Superior Court.
Govendo asserted jurisdiction on several grounds, including 1
CMC § 3102 (the trial court's general jurisdictional statute), 2
CMC § 1542 (a statute permitting private actions against CRM,
examined in part II, infra) and NMI Const. Art. I § 9.6
5According to CRM "Major Siting Guidelines":
Any project which :gteets any one or more of the criteria
set forth below is presumptively a major siting unless
the CRM Directors determine otherwise by a written
consensus.
c. Employees. Employment of over 50 fulltime equivalent
employees.
Appellee's Exhibit E.
6NMI Const. Art. I, § 9 provides as follows:
Each person has the right to a clean and healthful
public environment in all areas, including the land, air,
and water. Harmful and unnecessary noise pollution, and
the storage of nuclear or radioactive material and the
dumping or storage of any type of nuclear waste within
the surface or submerged lands and waters of the Northern
Mariana Islands,. are prohibited except as provided by
law.
Govendo subsequently also claimed jurisdiction pursuant to NMI
Const. Art. X, § 9, which permits taxpayers to bring suits against
the government "to enjoin the expenditure of public funds for other
than public purposes or for a breach of fiduciary duty. 1 1 He
asserted that CRM officials breached their fiduciary duty by
allowing the MGM factory to be built without declaring it a.major
275
Govendo claimed that CRM violated statutory law and its
regula1;:ions in failing to declare the MGM factory a major siting.
Specifically, he asserted violation of 2 CMC § 1511 (a) (4), (8),
(14) and (15), which provide as follows:
(a) It is the coastal resources management policy
of the Commonwealth to:
(4) Plan for and manage any use or activity
with the potential for causing a direct and
significant impact on coastal resources.
Significant adverse impacts shall be mitigated to
the extent practicable:
. . . .
(8) Mitigate to the extent practicable adverse
environmental impacts, including those on aquifers,
beaches, estuaries and other coastal resources while
developing an efficient and safe transportation
system;
(14) Not permit, to the extent practicable,
development with the potential for causing
significant adverse impact in fragile areas such as
designated and potential historic and archeological
sites, critical wildlife habitats, beaches,
designated and potential pristine marine and
terrestrial communities, limestone and volcanic
forests, designated and potential mangrove stands
and other wetlands;
(15) Manage ecologically significant resource
areas for their contribution to marine productivity
and value as wildlife habitats, and preserve the
functions and integrity of reefs, marine meadows,
salt ponds, mangroves and other significant natural
n.6 (cont.):
siting. The trial court ruled that neither 1 CMC § 3102 nor Art.
I, § 9 conferred jurisdiction in this proceeding. It did not
address the applicability of Art. X, § 9, and this issue has not
been raised on appeal.
276
areas • • •
. . . .
Govendo also asserted violation of 2 CMC § 1 51 2(a), (i) and (j):
The Coastal R'esources Management Office has the
following powers, functions and duties:
(a) To coordinate the planning and
implementation of the coastal resources management
policies of the Commonwealth government;
(i) To ensure the consistency of permit
decisions with the coastal resources management
policies and regulations set forth in Sections 1 511
and 1 531 ;
(j) To coordinate the permit process • • •
Finally, Govendo asserted violation of CRM regulations concerning
issuance of major siting permits. He sought a declaratory judgment
to the effect that the MGM factory was a major siting, an
injunction ordering CRM to declare the factory a major siting and
to follow regulatory procedures, and a preliminary injunction
preventing MGM from building the factory until disposition of the
action.
MGM denied most of Govendo's allegations and asserted three
affirmative defenses: (1) lack of standing to bring the suit: (2)
failure to state a claim for which relief could be granted: and (3)
failure to comply with 1 CMC § 9112(b), a provision in the NMI
Administrative Procedure Act permitting judicial review of agency
action if filed within thirty days of the action.
The agency's response was similar; it asserted the first two
277
of MGM's affirmative defenses.
Immediately before trial on March 20, 1989, MGM orally moved
to dismiss Govendo's suit for lack of subject matter jurisdiction.7
The company argued that Govendo failed to establish a necessary
element of a claim for relief under the CRM private action statute,
2 CMC § 1542.
After taking the motion under advisement, the court dismissed
Govendo's action on April 2, 1990.
The SuEerior Court Decision
Construing 2 CMC § 1542 to provide the basis for both subject
matter jurisdiction and a claim for relief, the court interpreted
MGM's motion as a motion to dismiss for failure to state a claim
upon which relief could be granted. Com.R.Civ.P. 12(b) (6) .s
7Pursuant to com.R.Civ.P. 12(b) (1) (lack of jurisdiction over
subject matter) and 12(h) (3) ("[w]henever it appears by suggestion
of the parties or otherwise that the court lacks jurisdiction over
the subject matter, the court shall dismiss the action").
�his rule provides, in pertinent part:
Every defense, in law or fact, to a claim for relief
in any pleading • shall be asserted in the responsive
• •
pleading thereto if one is required, except that the
following defenses may at the option of the pleader be
made by motion:
(6) failure to state a claim upon which relief
can be granted,
A motion making any of these defenses shall be made
before pleading if a further pleading is permitted. • •
278
"There is no reason for the court not to proceed on this premise.
The fact that MGM has misnamed its motion is of no import to the
court." Memorandum Decision at 5.
In analyzing 2 CMC § 1 542, the court noted three requirements:
{1) the plaintiff must be an interested person who (2) gave CRM 30
days written notice of (3) a breach of duties "specifically imposed
by this Chapter.119 MGM conceded that Govendo met the first two
requirements but claimed that he failed to satisfy the third
requirement.
The court briefly analyzed and rejected several statutory
duties Govendo had cited to sustain his action.10 It accorded its
most detailed analysis to Govendo's claim that 2 CMC § 1 51 2(a)
(requiring the agency 11 (t]o coordinate the planning and
implementation of the coastal resources managament policies by the
9The court noted that "Chapter" refers to the entire Coastal
· Resources Management Act, 2 CMC § § 1 501 et seg. For the full text
of 2 CMC § 1 542, see part II, infra.
1011 (Govendo] cites nine 1 duties• as being breached in paragraph
eight of his complaint. A review of the cited • duties' reveals
that only three are specifically imposed by the Act."
Memorandum Decision 3.t 6, 7. The duty imposed under 2 CMC §
1512(i) to ensure the consistency of permit decisions with
statutory coastal resource management policies and regulations did
not apply because "the agency action complair.t.!.d of never• • •
progressed to the 'permit decision• stage and hence the § 1 51 2(i)
duty was never triggered." Id. at 7. The duty imposed under 2 CMC
§ 1 51 2(j) to coordinate the permit process "(requires] CRM to
ensure that all ministerial and other support services are
available" for a five-agency review board, and that 11all aspects of
the review process" are coordinated. "This section has nothing to
do with (Govendo's] cause of action. " I£. As set forth infra, the
court accorded closer analysis to Govendo's claim that CRM breached
the duty "(t]o coordinate the planning and implementation of the
coastal resources management policies by the government." 2 CMC §
1 512(a).
279
goverrm.ent") mandated that CRM enforce its regulations:
[Govendo] refers the court to 2 CMC § 1511(a) (1-23) .
This section contains 23 coastal resource management
policies of the CNMI. Using these policies as guide
lines, [Govendo] correctly cites 2 CMC § 1531 as
conferring on CRM the power to promulgate and enforce
regulations. It is at this point that infirmities begin
to appear in (Govendo's] argument. [He] concludes that
"since it is the duty of CRM to enforce its own policies
and since one of the duties is to promulgate its own
rules and regulations, CRM has the duty to enforce its
own regulations." (Govendo) utilizes a classic bootstrap
argument to reach the conclusion that a duty "specific
ally imposed" by the Act is the duty to enforce its own
regulations. This is just not so. Even if this were the
case, there is no regulation that directs CRM to declare
a garment factory a major siting. Witnout an express
grant of legislative authority, this court cannot go
beyond the specifically imposed duties of the Coastal
Resources Management Act and use the policies enumerated
in 2 CMC § 1511(a) as a bridge to graft a whole set of
new, unintended duties onto the Act.
Memorandum Decision at 8.
The court expressed the opinion that 2 CMC § 1542 provides
"the only avenue for judicial review of CRM decisions":
The limited grant of jurisdiction to the court and
the broad grant of discretionary leeway given to CRM
under the Act evidences the legislature's intent to allow
CRM to utilize its expertise in these highly specialized
regulatory matters without being second guessed by the
court.
Memorandum Decision at 9. The court thereupon granted the motion
to dismiss.
Govendo appeals.
II.
The sole issue Govendo raises on appeal is whether the trial
court erred in ruling that 2 CMC § 1542 does not permit a private
action against CRM to challenge the agency's determination that a
280
project is not a major siting.
Because the record indicates that the factory at issue had
already been constructed. at the time of trial, it is first
necessary to determine whether the appeal is barred by mootness.'t
We also deem it appropriate to scrutinize the procedural law
applied below.
Mootness
As a general rule, in order to decide a case a court must be
able to afford a petitioner the relief he or she seeks. "The duty
of this court, as of every other judicial tribHnal, is to decide
actual controversies by a judgment which can be carried into
effect, and not to give opinions upon moot questions or abstract
propositions, or to declare principles or rules of law which cannot
affect the matter in issue in the case before it." Wong v .. Board
of Regents, University of Hawaii, 616 P.2d 201, 204 (Haw. 1980) .
Courts lack jurisdiction to decide moot cases. Id t2
- ·
11The issue of mootness in the appeal of an administrative
decision may be raised sua sponte by an appellate court. Sherrill
v. Department of Transportation, 799 P.2d 836 (Ariz. 1990}.
12concerning the larger question of justiciability, we concur
with the analysis of the Supreme Court of Hawaii:
Though the courts of Hawaii are not subject to a
"cases or controversies" limitation like that imposed
upon ,the federal judiciary by Article III, § 2 of the
United States Constitution, we nevertheless believe
judicial power to resolve public disputes in a system of
government where there is a separation of powers should
be limited to those questions capable of resolution and
presented in an adversary context.
Life of the Land v. Land Use Commission of the State of Hawaii, 623
P.2d 431, 438 {Haw. 1981) . The courts of the NMI are likewise not
281
Since construction of the MGM factory has been completed, even
if we were to decide that Govendo's appeal has merit it appears
that we could not· provide him effective relief. .c1· Kona Old
Hawaiian Trails .Group v. Lyman, 734 P.2d 161, 165 (Haw. 1987)
(" (a]s long as all of the .construction authorized under the
shoraline management area • • • permit is not completed, the appeal
presents an adversity of interests and possibly affords the
appellant an effective remedy").
Nonetheless, we believe that we may properly entertain this
appeal:
[I]n exceptional situations mootness is not an obstacle
to the consideration . of an appeal. In our opinion,
"(w]hen the question involved affects the public
interest, and it is likely in the nature of things that
similar questions arising in the future would likewise
become moot before a needed authoritative determination
by an appellate court can be made, " an exception to the
rule is justified.
Id., qu9ting Johnston v. Ing, 441 P.2d 138, 140 (Haw. 1968).13 As
in Lyman, the question presented in this case is of public concern,
and, if it were to recur, would likely become moot before it could
n.12 (cont.):
subject to a "cases or controversiesil limitation, but are limited
by similar policy considerations. See Mafnas v. commonwealth, No.
90-025, slip op. at 11, 12 (N.M.I. Aug. 30, 1991) (although federal
constitutional strictures on standing are inapplicable in NMI
courts, law of standing "must be applied with some view to
realities as well as practicalities").
13 see also Alaska Transportation Commission v. Gandia, 602 P. 2d
402, 403 (Alaska 1979) quoting Doe y. state, 487 P.2d 47, 53
1
(Alaska 1971) ("[w)here the matter is one of grave public concern
and is recurrent but is capable of evading review we have 1
undertaken review even though the question may be technically
moot").
282
be determined on appeal. We shall therefore consider the merits.
Motion to Dismiss
As noted above, the trial court interpreted MGM's motion as a
motion to dismiss for failure to state a claim upon which relief
could be granted, pursuant to Com.R.Civ.P. 12(b) (6) .
When considering such a motion, the court must accept the
allegati9ns in the complaint as true and construe them in the light
most favorable to the plaintiff. Abramson v. Brownstein, 897 F.2d
389 (9th Cir. 1990) (analysis of counterpart federal rule) . 14
Dismissal is improper unless it appears beyond do11bt that the
plaintiff can prove no set of facts in support of his claim which
would entitle him to relief. Id.
We review de novo a dismissal for failure to state a claim
under com.R.Civ.P. 12(b) (6) . Id.
Govendo's Claim
Because we are reviewing a dismissal pursuant to Com.R.Civ.P.
12 (b) (6) , we must accept as true Govendo' s allegation that CRM
violated its major siting regulations. Abramson, supra.15
Govendo contends that 2 CMC § 1542 grants interested persons
14we have previously ruled that it is appropriate to consult
interpretation of counterpart federal rules when interpreting
commonwealth procedural rules: interpretation of such rules can be
highly persuasive. Tudela v. MPLC, No. 90-011 (N.M.I. June 7,
1990).
15since Govendo's letter to CRM of March 24, 1989, alleging
that the agency failed to follow its regulations was attached to
his complaint as an exhibit, it may be regarded as part of the
complaint. Com.R.Civ.P. lO(c). For the text of the "Major Siting
Guidelines" CRM allegedly violated, see footnote 5, infra.
283
the right to bring an action to compel the agency to perform not
only the duties specifically imposed under the Act, but also the
duties imposed pursuant to regulations the agency bas adopted.16
MGM disputes this claim.17
Since the language of a statute is at issue, rules of
statutory construction come into play. A basic principle · of
construction is that language must be given its plain meaning.
commonwealth y. Hasinto, No. 90-033 (N.M.I. oct. 15, 1991). When
language is clear, we will not construe it contrary to its plain
meaning. Tudela y. MPLC, No. 90-011 (N.M.I. June 7, 1990).
Two CMC § 1542 provides, in full:
Any interested person may initiate an action in the
Commonwealtb Trial Court to compel the performance of the
duties specifically imposed by this Chapter upon the
coastal Resources Management Office or any coastal
resources management regulatory agency. No action may be
brought unless 30 days written notice has been given by
the complainant to the coastal Resources Management
Office and any affected coastal resources management
regulatory agencies regarding the duties which the
complainant alleges have not been performed.
It is necessary to closely analyze the first sentence. 1
1Any
interested person" plainly confers broad standing. 11[M]ay • • •
compel the performance of • • • duties" indicates that injunctive
16we note that this case does not involve an appeal from a CRM
permit decision. k{. 2 CMC § 1541{b) (permitting aggrieved persons
to appeal joint decisions of the coastal resources management
regulatory agencies). It is, instead, an independent action.
17The company does not contest Govendo1s compliance with the
requirement under 2 CMC § 1542 that a complainant give thirty days
written notice to the agency before filing suit. In fact, the
record indicates that Govendo filed his action only twenty days
after notifying CRM of his intention to do so if the agency did not
declare the project a major siting. However, since this point has
not been raised on appeal, we will not consider it.
284
relief may be granted to require performance of a �--a
"[m]andatory obligation to perform." Black's Law Dictionary 453
(5th Ed. 1979).
Our analysis hinges upon interpretation of the clause "duties
specifically imposed by this Chapter." As enacted, this language
originally specified the term "Act" instead of "Chapter."
"Chapter" was substituted by the Law Revision Commission when the
Act was codified as chapter five of Title 2 of the Commonwealth
Code. Thus, 2 CMC § 1542 permits private actions to compel duties
"specifically imposed" by the Act.
In this context, according to the plain meaning of "specific
ally", 18 a litigant may compel performance of only those duties
that are explicitly or definitely set forth in the Act--i.e.,
statutory duties.
Given this analytical framework, the issue may be restated as
follows: does 2 CMC § 1542 grant any interested person the right to
compel CRM to enforce its major siting regulations if a
construction proposal falls within the criteria specified in•
regulations?
The answer is no. Govendo's interpretation of the right of
action permitted under 2 CMC § 1542 does not comport with the plain
·meaning of the statute. If the NMI legislature had intended to
grant interested persons the right to bring a private action to
compel CRM to perform regulatory duties, it would not have chosen
18
11The adverb •specifically' means in a specific manner;
explicitly; particularly; definitely.11 81 c.J.s. Specifically
(1977); se e also Black's Law Dictionary 1254 (5th ed. 1979).
285
language that clearly indicates that such persons may only compel
performance of statutory duties "specifically imposed" by the
Act.19
Thus, the trial court was correct in dismissing Govendo' s
action for failure to state a claim upon which relief could be
granted. It appears that CRM did not violate any statutory duty
imposed by the Act.
We are not saying that CRM or any other NMI agency is immune
from legal challenge if no means of judicial review of agency
action is provided by statute. 20 If it clearly appears that an
agency is not enforcing its regulations, limited judicial review
may be available by way of extraordinary writ.21 "It is generally
accepted th.at an action in mandamus is proper to compel
administrative agencies to exercise the powers entrusted to them,.
19While it may be tempting to cQnstrue 2 CMC § 1542 as Govendo
urges, we must apply the language according to its plain meaning,
Hasinto, supra, and may not construe it contrary to that meaning.
Tudela, supra. Only the legislature has the authority to amend the
statute.
2011Themere failure to provide specially by statute for
judicial review is certainly no evidence of intent to withhold
[review)." Holding's Little America v. Board of County Commission
ers of Laramie County, 670 P.2d 699, 703 (Wyo. 1983); see also
Johns v. Commercial Fisheries Entry Commission, 699 P.2d 334
(Alaska 1985). Preclusion of judicial review may not be inferred
except where there is a clear showing that the legislature intended
it. Morris v. Gressette, 432 U.S. 491, 97 S.Ct. 2411, 53 L.Ed.2d
506 (1977); Legal Aid Society of Alameda County v. Brennan, 608
F.2d 1319 (9th Cir. 1979), cert. den. Chamber of Commerce of United
States v. Legal Aid Society of Alameda County, 447 U.S. 921, 100
s.ct. 3010, 65 L.Ed.2d 1112 (1980).
21" ( c] ourts have inherent power to .. review the actions of
administrative agencies • by extraordinary writ."
• • State. ex
rel. Bailey v. Grande, 465 P.2d 334, 339 (Mont. 1970).
286
to perform ministerial acts and to enforce their rules and
requlations.11 Tew v. City of Topeka Police and Fire Civil Service
Commission, 697 P. 2d 1279, -1283 (Kan. 198 5 ) •
III.
For the foregoing reasons, the superior Court decision is
AFFIRMED.
f1..
Entered this /0
---- day of September, 1991.
I -
I� .l._ . 'I��I?
JOSE S. DELA CRUZ, Chief
287