Land Use Review Board v. 3643 VT Route 103, N, LLC
CourtSupreme Court of Vermont
Date FiledAugust 28, 2026
Docket25-AP-351
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
NOTICE: This opinion is subject to motions for reargument under V.R.A.P. 40 as well as formal
revision before publication in the Vermont Reports. Readers are requested to notify the Reporter
of Decisions by email at: Reporter@vtcourts.gov or by mail at: Vermont Supreme Court, 109 State
Street, Montpelier, Vermont 05609-0801, of any errors in order that corrections may be made
before this opinion goes to press.
2026 VT 39
No. 25-AP-351
Land Use Review Board Supreme Court
On Appeal from
v. Superior Court,
Environmental Division
3643 VT Route 103, N, LLC et al. May Term, 2026
Joseph S. McLean, J.
Charity R. Clark, Attorney General, and Melanie Kehne, Assistant Attorney General,
Montpelier, for Petitioner-Appellee.
Mark G. Hall and Alex Arroyo of Paul Frank + Collins PC, Burlington, for Respondents-
Appellants.
PRESENT: Reiber, C.J., Eaton, Waples, Nolan and Drescher, JJ.
¶ 1. DRESCHER, J. Because it had been in business since the early twentieth century,
a quarry in Chester, Vermont was exempt from Act 250 as a pre-existing development. After its
owner integrated the quarry into the operations of two of the owner’s nearby quarries, however,
both the district environmental commission and the Environmental Division determined the quarry
became subject to Act 250’s permitting requirements. Landowner now appeals from a judgment
of the Environmental Division holding that the quarry still requires a permit even after its
operations returned to pre-existing levels disconnected from the other quarries, and affirming the
imposition of a stop-work order by the Land Use Review Board (LURB). We affirm because the
quarry’s unpermitted and expanded commercial operation went on for years and inflicted lasting
impacts on the landscape, and because the court’s consideration of the stop-work order was a sound
exercise of discretion.
I. Background
¶ 2. The following facts are undisputed. Appellants are quarry operators Julian
Materials, LLC; Julian Development, LLC; 137 Chandler Road, LLC; 3643 VT Route 103, N.,
LLC; and others, collectively referred to here as landowner. From about 2018 to 2024, landowner
operated three quarries in Chester known as North Quarry, South Quarry, and Chandler Quarry.
¶ 3. Chandler Quarry is located on an eight-and-a-half-acre parcel, about a mile-and-a-
half from North and South Quarries. Because Chandler Quarry’s operations preceded the 1970
passage of Act 250, it had not previously been subject to Act 250’s permitting requirements. See
10 V.S.A. § 6081(b) (providing permit exemptions for developments commenced prior to June 1,
1970, but not for subsequent substantial changes). Landowner had operated Chandler Quarry since
2011, first under a lease and then as owner after acquiring it in early 2019.
¶ 4. Landowner acquired North and South Quarries in 2018. Until then, they operated
independently from Chandler Quarry. North and South Quarries occupy the same 300-plus-acre
parcel and have operated pursuant to Act 250 permits.
¶ 5. Landowner’s acquisitions of all three quarries coincided with a new business
strategy involving fabricating and processing stone “in house” at Chandler Quarry and selling
finished goods on site. Starting in 2018, landowner began trucking stone from North and South
Quarries to Chandler Quarry for processing. In 2021, landowner constructed a new building on
Chandler Quarry to house and use its newly purchased processing equipment. The building
remains standing. During this time, and until about April 2024, landowner operated Chandler
Quarry seven days a week.
2
¶ 6. LURB’s predecessor, the Natural Resources Board (NRB),1 began receiving noise
and traffic complaints from neighboring landowners related to these expanded activities. In 2022,
neighbors requested that the NRB assess whether the expanded operations at Chandler Quarry
needed a permit. The District 2 Environmental Commission issued a jurisdictional opinion (JO)
in March 2023, concluding the use of Chandler Quarry as part of the larger operations required an
Act 250 permit amendment.
¶ 7. Landowner appealed to the Environmental Division. In a March 2024 summary
judgment ruling, the court affirmed the NRB’s determination that operating Chandler Quarry in
coordination with North and South Quarries constituted a substantial change to a pre-existing
development that required an Act 250 permit.2 Landowner did not appeal this decision.
¶ 8. In June 2025, pursuant to 10 V.S.A. § 8008, LURB issued an administrative order
(AO) determining that landowner violated Act 250 in several ways, including by operating
Chandler Quarry without a permit. The AO imposed a civil penalty of $27,500 and ordered
landowner to pay expenses associated with LURB’s action. The order also directed landowner to
cease all operations, including quarrying activity at Chandler Quarry, until appropriate permits
were obtained.
¶ 9. Landowner timely requested a merits hearing before the Environmental Division
pursuant to 10 V.S.A. §§ 8008(b) and 8012. During the hearing, a quarry employee confirmed
1
As part of a legislative restructuring in 2024, the NRB was replaced by LURB. See 2023,
No. 181 (Adj. Sess.), § 2 (codifying 10 V.S.A. § 6021 and establishing LURB as a five-member
board).
2
The Environmental Division explained that Chandler Quarry previously did not qualify
as a development for Act 250 not only because it operated independently from North and South
Quarries, thereby falling below the ten-acre threshold for towns with permanent zoning bylaws,
but also because Chandler Quarry’s operations predated Act 250. Because Chandler Quarry is less
than five miles from North and South Quarries, landowner’s coordinated operation of all three
quarries increased the amount of involved land to more than ten acres, which brought Chandler
Quarry within Act 250’s definition of development. See 10 V.S.A. § 6001(3)(A)(i) (listing factors
to qualify as “development”).
3
that in 2018 landowner began using its newly purchased equipment at Chandler Quarry for
processing stone from North, South, and Chandler Quarries. According to the employee, in
response to the Environmental Division’s March 2024 determination, landowner stopped
processing stone at Chandler Quarry, sold its equipment, and conducted a “mass layoff” that
reduced the number of its employees in Chester to just three, from a high of forty-two. Whereas
before the ruling, landowner blasted, hauled, cut, and palletized stone at Chandler Quarry,
landowner after the ruling only transported stone extracted from the quarry to third-party vendors
elsewhere. According to the employee, operations at Chandler Quarry returned to at-or-below pre-
existing historical operating levels and were again separate from North and South Quarries.
¶ 10. The Environmental Division affirmed the AO. The court found that landowner had
taken steps to “decouple” Chandler Quarry from North and South Quarries following the court’s
2024 ruling. The court also found that landowner dramatically reduced quarrying activity at North
and South Quarries. Nevertheless, the court concluded that landowner’s unpermitted activities at
Chandler Quarry between 2018 and 2025 were a continuing violation of Act 250. In affirming the
AO’s stop-work order, the court did “not take this step lightly.” The court emphasized the long
duration of landowner’s continuing violations, despite direction provided to landowner by prior
orders and the unambiguous language of the permits that issued with respect to North and South
Quarries. Landowner timely appealed.
II. Analysis
¶ 11. Landowner raises two issues on appeal. First, it contends that notwithstanding the
Environmental Division’s March 2024 order affirming the JO, the court erred in concluding that
Chandler Quarry continues to be subject to Act 250 jurisdiction. Relying largely on our decision
in In re Audet, 2004 VT 30, 176 Vt. 617, 850 A.2d 1000 (mem.), landowner argues that by
returning to a pre-2018 level of activity Chandler Quarry has returned to its previous not-subject-
to-Act 250 status. Second, landowner contends that the Environmental Division abused its
4
discretion in affirming the AO’s stop-work provision because it failed to consider the economic
impact on the quarry’s employees.
A. Act 250 Jurisdiction
¶ 12. This Court reviews the Environmental Division’s factual findings deferentially
and will overturn them only if they are clearly erroneous when viewed in the light most favorable
to the prevailing party. In re Wheeler Parcel Act 250 Determination, 2025 VT 28, ¶ 14, 221 Vt.
216, 342 A.3d 836. We will not disturb the Environmental Division’s legal conclusions when
reasonably supported by its factual findings. Id. We review its resolution of legal questions,
however, de novo. In re Katzenbach A250 Permit #7R1374-1, 2022 VT 42, ¶ 11, 217 Vt. 155,
287 A.3d 36.
¶ 13. Act 250 is designed to “insure” that Vermont’s “ ‘lands and environment are
devoted to uses which are not detrimental to the public welfare and interests.’ ” In re Pilgrim
P’ship, 153 Vt. 594, 596, 572 A.2d 909, 910 (1990) (quoting 1969, No. 250 (Adj. Sess.), § 1). To
that end, the legislation imposes permitting requirements for certain large-scale projects that
implicate “values of state concern” and represents “a philosophic compromise between a desire to
protect and control all the lands and environment of the state of Vermont, and the need to avoid an
administrative nightmare.” In re Agency of Admin., State Bldgs. Div., 141 Vt. 68, 76, 444 A.2d
1349, 1352 (1982). The general rule is that “once a change of statewide impact occurs to land,
Act 250 jurisdiction attaches and it cannot be undone by later events such as a cessation of the
development activity.” Audet, 2004 VT 30, ¶ 13; see also In re Rusin, 162 Vt. 185, 191, 643 A.2d
1209, 1212 (1994) (holding that once developer took significant steps to realize his permitted
project, subsequent reduction of scope of construction did not remove project from Act 250
jurisdiction).
¶ 14. We first address landowner’s argument that its 2024 reduction of operations at
Chandler Quarry resulted in reversion to its historical Act 250 exemption. Landowner concedes
5
on appeal that, from 2018 to 2024, it operated Chandler Quarry in conjunction with its other
quarries and that by doing so, Act 250 jurisdiction attached. Landowner contends, however, that
because Chandler Quarry was previously exempt from Act 250 as a pre-existing development
under 10 V.S.A. § 6081(b), Act 250 jurisdiction dissolved when it reduced activities at Chandler
Quarry to at-or-below previous levels after the Environmental Division’s 2024 order. In
landowner’s view, returning Chandler Quarry to its pre-2018 operations, and “decoupling” it from
the North and South Quarries, rendered the Environmental Division’s March 2024 order no longer
applicable.
¶ 15. Landowner relies heavily on our decision in Audet. 2004 VT 30. In that case, a
landowner who repaired and sold vehicles on two contiguous parcels in Worcester purchased a
third parcel one-third of a mile away and proposed building a home on it. Neighbors successfully
opposed that plan before the selectboard. To retaliate, landowner began using the third parcel to
store junked cars and other debris from his business. He told neighbors he planned to be a “bad
neighbor” and to build a garage on the parcel that would increase traffic in the area. Id. ¶ 3. He
“graded, filled and graveled portions” of the parcel. Id. In response, the neighbors requested a
jurisdictional opinion from the district environmental commission. The commission determined
that Act 250 jurisdiction was triggered under 10 V.S.A. § 6001(3)(A)(ii) because, as in this appeal,
see supra, ¶ 7 n.2, the proximity and addition of the third parcel to the landowner’s other two
caused the combined size of the three parcels to exceed Act 250’s jurisdictional threshold. The
landowner thereafter ceased using the third parcel in any way connected to his business and
petitioned the environmental board for a declaration that Act 250 jurisdiction did not apply because
the third parcel was not being used as part of his business.
¶ 16. We affirmed the board’s decision that the third parcel did not require an Act 250
permit. Id. ¶ 10. Although jurisdiction was “technically” triggered when the landowner started
using the third parcel in association with his business, he “changed his plans and ceased the use”
6
once “faced with the prospect of having to obtain an Act 250 permit.” Id. ¶ 14. We held that when
the landowner abandoned that use shortly after the district environmental commission informed
him that Act 250 would apply, “the environmental board could find that no further Act 250
jurisdiction existed at that point, so long as [the landowner’s] change of plans was made in good
faith and occurred without any sort of construction, physical change to the land or other ongoing
impact that would require Act 250 review.”3 Id. To hold otherwise, we explained, would
permanently impose Act 250 jurisdiction simply because the use of the land temporarily changed.
Id.
¶ 17. Chandler Quarry is different. Here, landowner unlawfully operated Chandler
Quarry in coordination with North and South Quarries for over five years. During that time,
landowner materially increased quarrying activity, including the use of hydraulic hammers and
blasting. It also constructed a building in connection with its operation. And after LURB ruled
that a permit was required for Chandler Quarry to operate lawfully, landowner continued to drill,
blast, and process stone as part of its coordinated multi-quarry operations. Drilling and blasting
continued at Chandler Quarry—albeit at a reduced rate and apparently independently of the other
quarries—even after the March 2024 ruling. Unlike Audet, landowner here engaged in sustained
commercially motivated jurisdiction-triggering operations that inflicted lasting impact on the
property. To hold that landowner can undo Act 250 jurisdiction simply by reducing operations
would ignore those impacts and incentivize recalcitrance.
¶ 18. Our holding does not mean Chandler Quarry is forever subject to the Environmental
Division’s Act 250 jurisdiction determination. “Any permit granted under” Act 250 “for extraction
of mineral resources,” for instance, “shall be for a specified period determined by the Board.” 10
V.S.A. § 6090(b)(1). “[A]bsent some [other] activity to trigger the statute’s application,”
3
The environmental board found that the clearing and grading of the third parcel were not
related to the landowner’s business. Id. ¶ 16 n.2.
7
jurisdiction can end when the permittee ceases operations and reclaims the parcel in compliance
with the permit’s requirements. In re Huntley, 2004 VT 115, ¶¶ 1, 3-6, 177 Vt. 596, 865 A.2d
1123 (mem.) (holding Act 250 mine permit expires upon cessation of mining and reclamation and
rehabilitation in accordance with permit requirements); accord In re Hamm Mine Act 250
Jurisdiction (Jurisdictional Op. No.2-241), 2009 VT 88, ¶¶ 17-19, 186 Vt. 590, 980 A.2d 286
(mem.) (explaining Act 250 enforcement jurisdiction continues until reclamation conditions of
mine permit are satisfied). As LURB points out, permits for earth extraction operations include
reclamation plans and other conditions to ensure environmental impacts are addressed going
forward. See 10 V.S.A. § 6086(a)(9)(E). Landowner must get a permit (or an amendment to an
existing permit) which will contain reclamation requirements, if appropriate, for Chandler Quarry.
¶ 19. Landowner also argues that the Environmental Division’s determination that Act
250 jurisdiction attached to Chandler Quarry was not supported by sufficient evidence. We decline
to address this argument. The issue was fully litigated and resolved against landowner in the
March 2024 order, which landowner did not appeal. See Nat. Res. Bd. Land Use Panel v. Dorr,
2015 VT 1, ¶¶ 10-13, 198 Vt. 226, 113 A.3d 400 (rejecting effort to relitigate prior Act 250
jurisdictional ruling in subsequent enforcement action); see also Town of Pawlet v. Banyai, 2024
VT 13, ¶¶ 8, 12, 219 Vt. 90, 315 A.3d 1008 (explaining that “court’s final judgments are conclusive
upon parties and cannot be collaterally attacked” and declining to consider landowner’s arguments
concerning prior final order that he did not appeal (quotation omitted)). We decline to review
previously decided issues that landowner opted not to appeal.
B. Stop-Work Order
¶ 20. Lastly, we turn to landowner’s claim that the Environmental Division erred in
affirming the stop-work order because it failed to consider the economic impact of the order or
landowner’s efforts to comply with the administrative penalty process. Under 10 V.S.A.
§ 8008(c), LURB may issue an AO that “directs the respondent to stop work until a permit is
8
issued, compliance is achieved, a hazard is abated, or any combination of the above.” When
issuing a stop-work order, LURB must “consider the economic effect . . . on individuals other than
the respondent.” Id. Similarly, in reviewing an AO issued by LURB, the Environmental Division
must also “consider the economic effect of the order on individuals other than the respondent.” Id.
§ 8012(b)(3). Landowner argues that the stop-work order should be reversed and vacated because
the Environmental Division failed to comply with this statutory mandate.
¶ 21. We only review whether the Environmental Division’s continued imposition of the
stop-work order constituted an abuse of discretion. See In re Beliveau NOV, 2013 VT 41, ¶ 22,
194 Vt. 1, 72 A.3d 918 (reviewing imposition of fine for zoning violation under abuse of discretion
standard); accord Fenwick v. City of Burlington, 167 Vt. 425, 432, 708 A.2d 561, 565 (1997)
(reviewing trial court’s decision not to grant injunction in zoning case for abuse of its “wide
discretion”). When the Environmental Division’s decision is grounded in the various statutory
factors and is not clearly unreasonable, we will find no abuse of discretion. Vt. Agency of Nat.
Res. v. Duranleau, 159 Vt. 233, 240, 617 A.2d 143, 147 (1992).
¶ 22. Landowner argues that the Environmental Division made “no attempt” to assess the
economic impact on the quarries’ employees in violation of § 8012(b)(3). The record indicates
otherwise. The Environmental Division explicitly cited the applicable statutory standard and
stated that it considered the economic harm of the stop-work order on the quarries’ employees.
The court accurately noted that landowner itself could have mitigated that impact by seeking an
Act 250 permit. The court reiterated it did not “take this step lightly but [felt] compelled to” affirm
the stop-work order because of the unambiguous need for a permit as expressed by the JO and
March 2024 decision; the extended duration of the continuing violations; the relatively small
number of employees; and landowner’s ability to prevent the harm.
9
¶ 23. The record demonstrates the Environmental Division reasonably considered the
statutory factors, including the economic impacts on those affected. It was not, therefore, an abuse
of discretion to affirm the stop-work order.
Affirmed.
FOR THE COURT:
Associate Justice
10