In Re APPLICATION OF ENBRIDGE ENERGY TO REPLACE AND RELOCATE LINE 5
CourtMichigan Supreme Court
Date FiledJuly 31, 2026
Docket168335, 168336, 168337, 168338, 168339, and 168346
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
Michigan Supreme Court
Lansing, Michigan
Syllabus
Chief Justice: Justices:
Megan K. Cavanagh Brian K. Zahra
Richard H. Bernstein
Elizabeth M. Welch
Kyra H. Bolden
Kimberly A. Thomas
Noah P. Hood
This syllabus constitutes no part of the opinion of the Court but has been Reporter of Decisions:
prepared by the Reporter of Decisions for the convenience of the reader. Kimberly K. Muschong
In re APPLICATION OF ENBRIDGE ENERGY TO REPLACE AND RELOCATE LINE 5
Docket Nos. 168335, 168336, 168337, 168338, 168339, and 168346. Argued March 16,
2026 (Calendar Nos. 2 and 3). Decided July 31, 2026.
These consolidated appeals involve the intersection of three legal frameworks—1929 PA
16 (Act 16), MCL 483.1 et seq. (giving the PSC primary authority to regulate pipelines in
Michigan); Michigan’s environmental protection act (MEPA), MCL 324.1701 through MCL
324.1706; and the common-law public trust doctrine—and the order of the Michigan Public
Service Commission (PSC) approving Enbridge Energy Limited Partnership’s application to
construct a tunnel under the Straits of Mackinac to house a portion of its Line 5 pipeline (the
“Replacement Project”). The PSC granted Enbridge’s predecessor approval to construct Line 5 in
1953, and the Michigan Conservation Commission also granted it an easement to construct two
20-inch pipes (referred to as the dual pipelines) located on or suspended above the lakebed across
the Straits. As part of a negotiated agreement between the state and Enbridge in 2017 through
2018, the Replacement Project contemplated the decommissioning of the dual pipelines and the
construction of a concrete-lined tunnel under the Straits’ lakebed and a new 30-inch pipe through
the tunnel. In 2018, the Legislature created the Mackinac Straits Corridor Authority (MSCA) and
authorized it to enter into an agreement to build a “utility tunnel” under the Straits. The
Department of Natural Resources granted the MSCA an easement to construct a tunnel under the
Straits, and once Enbridge completes the tunnel, the MSCA will take ownership of the tunnel and
provide Enbridge with a 99-year lease.
After Enbridge filed its application for the Replacement Project with the PSC, appellants,
Bay Mills Indian Community, Grand Traverse Band of Ottawa and Chippewa Indians, Little
Traverse Bay Bands of Odawa Indians, Nottawaseppi Huron Band of the Potawatomi,
Environmental Law and Policy Center, Michigan Climate Action Network, and For Love of Water,
intervened in the proceedings to oppose the Replacement Project. Appellees Michigan Laborers’
District Council, Michigan Propane Gas Association, and National Propane Gas Association
intervened to support the project.
The PSC referred the matter to an administrative law judge (ALJ) to conduct proceedings
and build a record. Relevant to this appeal, the parties disputed the proper scope of the PSC’s
analysis under MEPA. Enbridge filed a motion in limine seeking to exclude as legally irrelevant
various issues from the PSC’s consideration, including the construction of the utility tunnel, the
environmental impact of the tunnel construction, the public need for and continued operation of
Line 5, the current operational safety of Line 5, whether Line 5 has an adverse impact on climate
change, and the intervening parties’ climate change agendas. The ALJ granted the motion as to
all issues other than the construction of the utility tunnel, and several intervenors appealed the
ruling to the PSC. While that appeal was pending, Governor Gretchen Whitmer issued a notice of
revocation of the 1953 easement. The PSC remanded the case to the ALJ to consider the impact
of the Governor’s actions.
On remand, the ALJ reached the same conclusions as he had before. He found that the
PSC’s 1953 order had already established that Line 5 served a public need and that this finding
had no expiration date. The ALJ further concluded that Governor Whitmer’s actions could not
“be used to expand the scope of this case to include an examination or determination of the public
need for Line 5, or any aspect of its operation and safety.” The intervenors again appealed, and
the PSC largely affirmed the ALJ’s ruling. Like the ALJ, the PSC determined that its 1953
decision approving Line 5, as well as earlier Supreme Court caselaw, established that the pipeline
complied with Act 16 and that there was no expiration date for this finding. Accordingly, it
concluded that the Act 16 analysis in this case should be limited to the Replacement Project and
not the pipeline as a whole. The PSC limited its MEPA analysis “to the conduct at issue in this
case,” i.e., the Replacement Project, and refused to consider evidence of potential pollution,
impairment, and destruction of Michigan’s natural resources resulting from existing sections of
Line 5, including the danger of oil spills. It also concluded that its MEPA analysis did “not extend
to the entirety of Line 5,” but was limited to the single new pipeline and tunnel. However, the
PSC also determined that the conduct at issue included the products flowing through the new
pipeline section and allowed the introduction of evidence of the greenhouse gas emissions that
would result from the consumption of the products. The PSC also concluded that greenhouse gases
were “pollution” within the meaning of MEPA and that although the Replacement Project was
limited to the 4-mile section of the pipeline described in the application, MEPA review was
necessary because that pipeline section would involve hydrocarbons that may result in pollution.
After the presentation of additional evidence and testimony, the ALJ closed the record and
transferred the case to the PSC for a final decision. The PSC issued an order granting Enbridge
approval under Act 16 to construct the Replacement Project. It found that the requirements of both
Act 16 and MEPA were satisfied and that there were no feasible or prudent alternatives to the
Replacement Project, but it declined to consider the public trust doctrine in its analysis.
Appellants appealed the PSC’s ruling to the Court of Appeals. In a published per curiam
opinion, the Court of Appeals, M. J. KELLY, P.J., and LETICA and WALLACE, JJ., affirmed. ___
Mich App ___ (February 19, 2025) (Docket Nos. 369156, 369157, 369159, 369161, 369162,
369163, 369165, and 369231). Appellants sought leave to appeal, and the Supreme Court granted
the applications. ___ Mich ___; 25 NW3d 327 (2025) (Docket Nos. 168335 to 168339); ___ Mich
___; 25 NW3d 319 (2025) (Docket No. 168346).
In an opinion by Justice WELCH, joined by Chief Justice CAVANAGH and Justices
BERNSTEIN, BOLDEN, THOMAS, and HOOD, the Supreme Court held:
Courts must review de novo an agency’s application of MEPA, regardless of whether a
case commences in court or in administrative proceedings. MEPA requires (1) consideration of
the environmental impact factually and proximately caused by the conduct at issue, (2) a fair and
reasoned comparison of the environmental impacts of any alternatives to the conduct considered,
and (3) consideration of the conduct’s potential effects on public trust resources. The Court of
Appeals erred in this case by applying a deferential standard of review to the PSC’s decision, and
the PSC erred by (1) failing to consider whether the tunnel project will factually and proximately
cause the extension of Line 5’s operational life, potentially resulting in additional environmental
harm; (2) comparing alternatives in an inconsistent manner; and (3) failing to consider the project’s
impact on public trust resources.
1. The Court of Appeals erred by applying a deferential standard of review to the PSC’s
MEPA determination rather than analyzing de novo whether the proposed conduct satisfies MCL
324.1705(2). MEPA decisions are reviewed de novo whether they originate as an administrative
proceeding or through direct litigation in court, meaning that the reviewing court must consider
the legal issues independently and review the record without deference to prior proceedings.
Nothing in MEPA’s text implies the existence of multiple standards of review, and interpreting
the provision at issue in this case—MCL 324.1705(2)—to provide for de novo review of
administrative agencies’ MEPA determinations is consistent with both the language of MEPA as
a whole and MEPA’s purpose of spurring the development of a common law of environmental
quality through judicial decisions. The Court previously determined that MCL 324.1704(3)
requires a court to independently and nondeferentially review an agency decision after remitting a
case to that agency for administrative proceedings, and there is no meaningful difference between
MCL 324.1704(3) and MCL 324.1705(2). Regardless of how a MEPA case originates, the task
for the trial court—or agency—is the same. It must adjudicate or determine whether the “conduct”
at issue is likely to pollute, impair, or destroy the air, water, or other natural resources or the public
trust in these resources.
2. Under MEPA, harms asserted beyond the conduct itself must be examined to determine
if they are factually and proximately caused by the conduct. In this case, the PSC must apply this
framework and determine whether the Replacement Project will factually and proximately cause
Line 5’s extended lifespan and attendant harms.
In applying MEPA, the factfinder must first define the “conduct” at issue. “Conduct” under
MEPA is distinguishable from alleged environmental harms. In citizen MEPA suits, the
allegations in the plaintiff’s complaint define the conduct at issue. In administrative proceedings—
whether initiated by an agency under MCL 324.1705(2) or remitted to an agency by the court
under MCL 324.1704(2)—the subject of the proceedings is the conduct at issue under MEPA.
Here, the Replacement Project for which Enbridge sought approval in its Act 16 application was
the subject of the PSC proceedings.
Once the relevant “conduct” is established, MEPA requires courts and agencies to
determine or adjudicate whether the conduct will cause pollution, impairment, or destruction of
the air, water, or other natural resources, or the public trust in these resources. This analysis can
be broken into two steps: (1) determining which harms are at issue and (2) assessing the scope of
those harms. At the first step, the factfinder—aided by the parties—must determine what kind of
environmental risks the conduct in question poses. Under MCL 324.1705(1) and (2), the focus is
on those harms that are likely effects of the conduct. Although this concept appears broad,
MEPA’s text limits its scope by requiring both factual causation (i.e., the harm is an “effect” of
conduct) and proximate causation (i.e., the harm is “likely”). Proximate cause requires more than
speculation or conjecture, and a mere possibility is not enough to establish either but-for causation
or proximate causation. Determining the harm of the relevant conduct is a factually intensive
inquiry and does not lend itself to hard-and-fast rules; courts and agencies must use common sense
and apply basic proximate cause principles. A factfinder should not fully quantify the effects of a
risk until it determines that the risk is a result of the proposed conduct. This analysis therefore
necessitates a case-by-case inquiry that allows the courts to fashion standards in the context of
actual problems as they arise in individual cases.
Once the factfinder has determined which environmental risks are actually relevant to the
conduct, it must carry out its statutory duty to adjudicate or determine the impact of the defendant’s
conduct on the air, water, or other natural resources, and on the public trust in these resources. If
the factfinder determines that the conduct at issue poses no meaningful environmental harm, the
analysis ends, but if the factfinder determines that the environmental harms are the likely effects
of the conduct at issue, the factfinder may not permit the conduct if a feasible and prudent
alternative exists.
To accurately assess the environmental consequences of the Replacement Project, the PSC
should have determined whether the project would be the proximate cause of Line 5’s continued
operation and its alleged attendant harms. Because it did not do so, the PSC was unable to fulfill
its obligations under MEPA to determine, pursuant to MCL 324.1705(2), what pollution,
impairment, or destruction of the air, water, or other natural resources, or the public trust in these
resources, the project might cause; that is, the PSC erred by not examining whether the
Replacement Project would be the proximate cause of further environmental harms by extending
Line 5’s lifespan. For purposes of the MEPA harm analysis, Line 5’s continued operation, with
and without the Replacement Project, was a factual question, not just a legal one. The PSC also
acted inconsistently by considering greenhouse emissions from the pipeline as a whole in its harms
analysis, but declining to consider other environmental risks (like oil spills) using that same scope.
3. Once a court or an agency finds that the conduct at issue has polluted, impaired, or
destroyed or is likely to pollute, impair, or destroy the air, water, or other natural resources or the
public trust in these resources, the next step, as set forth in MCL 324.1705(2), is to determine
whether there is a feasible and prudent alternative that avoids or mitigates these environmental
effects. Determining the feasibility or prudence of an “alternative” necessarily calls for a
benchmark against which the alternative may be evaluated. That benchmark is the harm caused
by the proposed conduct. Accordingly, a meaningful examination of the alternatives cannot occur
until the impact of the relevant conduct on the air, water, or other natural resources, and on the
public trust in these resources, is determined. This analysis of environmental impacts is distinct
from the requirements that an alternative be feasible, prudent, and consistent with the public health,
safety, and welfare. Accordingly, they may be considered independently, though both bear on the
factfinder’s final decision. In addition, MCL 324.1705(2) requires that both the conduct and the
alternatives be consistent with the public health, safety, and welfare. The alternatives analysis
exists under MEPA to determine if there is a feasible and less environmentally harmful pathway
than the challenged conduct. In order for this analysis to accomplish its goals, the environmental
impact of the conduct at issue must be compared with that of the alternatives being considered.
An analysis that fails to do so will not allow a reasoned choice of alternatives.
The inconsistencies in the PSC’s comparisons did not allow for such a “reasoned choice.”
The PSC incorrectly compared the environmental effects of alternatives that would fully replace
Line 5 with the effects of the Replacement Project alone.
4. MEPA requires separate consideration of harms to public trust resources. The correct
way to define “public trust” in MEPA is by looking to the common-law public trust doctrine. The
doctrine serves to protect the waters of the Great Lakes and their submerged lands and requires
consideration of the public’s right to fish, hunt, travel through, and otherwise utilize the Great
Lakes. Just as the MEPA factfinder must assess and mitigate harm to the water and the air, so too
must it assess and mitigate harm to public trust resources. The PSC erred by failing to determine
whether the Replacement Project would pollute, impair, or destroy public trust resources.
Court of Appeals judgment reversed, PSC order vacated, and case remanded to the PSC
for further proceedings.
Justice ZAHRA, concurring in part and dissenting in part, concurred in the majority opinion
limited only to the holding that the matter should be remanded to the PSC for express findings on
the issue of public trust; otherwise, he disagreed with the conclusions reached in the majority
opinion in several respects. First, the majority opinion errs by concluding that appellate courts
review de novo administrative decisions under MEPA. The majority opinion does not provide the
PSC’s decision any degree of deference even though some level of deference is generally afforded
to administrative decision-makers because of their expertise in the regulated field. MCL
324.1705(2) plainly contemplates judicial review but does not describe the judicial review
required. However, Const 1963, art 6, § 28, requires reviewing courts to determine whether
agency orders are authorized by law and supported by competent, material, and substantial
evidence on the whole record. Applying de novo review in this case allows the majority to dismiss
the PSC’s determinations or even substitute its own beliefs for the PSC’s findings. The majority
opinion also ignores the clear differences in the text of MCL 324.1701 and MCL 324.1705 to
erroneously conclude that the Legislature did not intend for the MEPA standard to differ between
citizen suits and administrative proceedings.
Justice ZAHRA further disagreed with the majority opinion’s expanded scope of analysis
under MEPA. The majority opinion’s conclusion—that the continued operation of Line 5 is itself
a relevant adverse environmental effect of the Replacement Project—is poorly reasoned and
illogical, and it creates a moral hazard. By dismissing the PSC’s determination and expanding the
scope of review to the entirety of Line 5, the majority opinion ignores that Line 5 has already been
determined to be in the public interest, and its continued operation is the result of the authority the
state granted Enbridge’s predecessor to construct, use, and maintain Line 5, not the Replacement
Project. The majority opinion’s interpretation of “likely” effects is particularly problematic;
tenuous, remote, or peripheral environmental effects should not be considered relevant in
determining feasible alternatives to the Replacement Project. Instead, consideration of proposed
feasible alternatives must be limited to alternatives to the Replacement Project, not alternatives to
Line 5 as a whole. While the PSC erroneously considered feasible alternatives to the entirety of
Line 5, the PSC did properly consider feasible alternatives to the Replacement Project.
Finally, while the PSC did not expressly consider the public trust in its final opinion,
necessitating remand on that issue, the opinion clearly addressed the substance of the public trust
in the state’s natural resources. Justice ZAHRA additionally noted that the Department of
Environment, Great Lakes, and Energy recently granted a permit to Enbridge for the Replacement
Project, in which proceedings the public trust was expressly considered; this could aid the PSC in
independently addressing the public trust on remand.
Michigan Supreme Court
Lansing, Michigan
OPINION
Chief Justice: Justices:
Megan K. Cavanagh Brian K. Zahra
Richard H. Bernstein
Elizabeth M. Welch
Kyra H. Bolden
Kimberly A. Thomas
Noah P. Hood
FILED July 31, 2026
STATE OF MICHIGAN
SUPREME COURT
In re APPLICATION OF ENBRIDGE ENERGY
TO REPLACE AND RELOCATE LINE 5.
LITTLE TRAVERSE BAY BANDS OF
ODAWA INDIANS,
Appellant,
v No. 168335
MICHIGAN PUBLIC SERVICE
COMMISSION, MACKINAC STRAITS
CORRIDOR AUTHORITY, MICHIGAN
PROPANE GAS ASSOCIATION, NATIONAL
PROPANE GAS ASSOCIATION, and
MICHIGAN LABORERS’ DISTRICT
COUNCIL,
Appellees,
and
ENBRIDGE ENERGY LIMITED
PARTNERSHIP,
Petitioner-Appellee.
In re APPLICATION OF ENBRIDGE ENERGY
TO REPLACE AND RELOCATE LINE 5.
BAY MILLS INDIAN COMMUNITY,
Appellant,
v No. 168336
MICHIGAN PUBLIC SERVICE
COMMISSION, MACKINAC STRAITS
CORRIDOR AUTHORITY, MICHIGAN
PROPANE GAS ASSOCIATION, NATIONAL
PROPANE GAS ASSOCIATION, and
MICHIGAN LABORERS’ DISTRICT
COUNCIL,
Appellees,
and
ENBRIDGE ENERGY LIMITED
PARTNERSHIP,
Petitioner-Appellee.
In re APPLICATION OF ENBRIDGE ENERGY
TO REPLACE AND RELOCATE LINE 5.
GRAND TRAVERSE BAND OF OTTAWA
AND CHIPPEWA INDIANS,
Appellant,
v No. 168337
2
MICHIGAN PUBLIC SERVICE
COMMISSION, MACKINAC STRAITS
CORRIDOR AUTHORITY, MICHIGAN
PROPANE GAS ASSOCIATION, NATIONAL
PROPANE GAS ASSOCIATION, and
MICHIGAN LABORERS’ DISTRICT
COUNCIL,
Appellees,
and
ENBRIDGE ENERGY LIMITED
PARTNERSHIP,
Petitioner-Appellee.
In re APPLICATION OF ENBRIDGE ENERGY
TO REPLACE AND RELOCATE LINE 5.
NOTTAWASEPPI HURON BAND OF THE
POTAWATOMI,
Appellant,
v No. 168338
MICHIGAN PUBLIC SERVICE
COMMISSION, MACKINAC STRAITS
CORRIDOR AUTHORITY, MICHIGAN
PROPANE GAS ASSOCIATION, NATIONAL
PROPANE GAS ASSOCIATION, and
MICHIGAN LABORERS’ DISTRICT
COUNCIL,
Appellees,
and
3
ENBRIDGE ENERGY LIMITED
PARTNERSHIP,
Petitioner-Appellee.
In re APPLICATION OF ENBRIDGE ENERGY
TO REPLACE AND RELOCATE LINE 5.
ENVIRONMENTAL LAW & POLICY
CENTER and MICHIGAN CLIMATE ACTION
NETWORK,
Appellants,
v No. 168339
MICHIGAN PUBLIC SERVICE
COMMISSION, MACKINAC STRAITS
CORRIDOR AUTHORITY, MICHIGAN
PROPANE GAS ASSOCIATION, NATIONAL
PROPANE GAS ASSOCIATION, and
MICHIGAN LABORERS’ DISTRICT
COUNCIL,
Appellees,
and
ENBRIDGE ENERGY LIMITED
PARTNERSHIP,
Petitioner-Appellee.
In re APPLICATION OF ENBRIDGE ENERGY
TO REPLACE AND RELOCATE LINE 5.
4
FOR LOVE OF WATER,
Appellant,
v No. 168346
MICHIGAN PUBLIC SERVICE
COMMISSION, MACKINAC STRAITS
CORRIDOR AUTHORITY, MICHIGAN
PROPANE GAS ASSOCIATION, NATIONAL
PROPANE GAS ASSOCIATION, and
MICHIGAN LABORERS’ DISTRICT
COUNCIL,
Appellees,
and
ENBRIDGE ENERGY LIMITED
PARTNERSHIP,
Petitioner-Appellee.
BEFORE THE ENTIRE BENCH
WELCH, J.
These cases are about the intersection of the Great Lakes, energy transmission, and
administrative review. In particular, they concern the order of the Michigan Public Service
Commission (PSC) approving appellee Enbridge Energy Limited Partnership’s application
to construct a tunnel under the Straits of Mackinac to house a portion of its Line 5 pipeline
(the “Replacement Project”). Appellants—environmental advocacy groups and Indian
Tribes—contend that the PSC erred in its analysis of the project’s environmental effects
under the Michigan environmental protection act (MEPA). 1
1
MCL 324.1701 through MCL 324.1706 (Part 17 of the Natural Resources and
Environmental Protection Act (NREPA), MCL 324.101 et seq.). While MEPA was
5
We take this opportunity to answer several questions about MEPA’s scope and
function. First, we hold that courts must review de novo an agency’s application of MEPA,
regardless of whether a case commences in court or in administrative proceedings. Second,
we hold that MEPA requires (1) consideration of the environmental impact factually and
proximately caused by the conduct at issue, (2) a fair and reasoned comparison of the
environmental impacts of any alternatives to the conduct considered, and (3) consideration
of the conduct’s potential effects on public trust resources. Applying these holdings to the
cases at issue, we conclude that the Court of Appeals erred by applying a deferential
standard of review to the PSC’s decision, and that the PSC erred by (1) failing to consider
whether the tunnel project will factually and proximately cause the extension of Line 5’s
operational life, potentially resulting in additional environmental harm; (2) comparing
alternatives in an inconsistent manner; and (3) failing to consider the project’s impact on
public trust resources.
Accordingly, we reverse the judgment of the Court of Appeals, vacate the PSC’s
order approving the construction of the Replacement Project, and remand this matter to the
PSC for further proceedings consistent with this opinion.
I. FACTUAL BACKGROUND
The Great Lakes are the largest freshwater system on Earth. Department of
Environment, Great Lakes, and Energy, Learn About our Great Lakes
<https://www.michigan.gov/egle/public/learn/great-lakes> (accessed June 12, 2026)
originally enacted as a standalone statute, see 1970 PA 127, it was later recodified—in
essentially the same form—as part of NREPA, see 1994 PA 451. For simplicity, we use
the current citations for MEPA’s provisions throughout this opinion.
6
[https://perma.cc/7AJU-ZJKS]. “[T]he pure blue waters of these incomparable inland
seas” are “Michigan’s great natural resource[.]” Obrecht v Nat’l Gypsum Co, 361 Mich
399, 416; 105 NW2d 143 (1960). Connecting Lake Michigan and Lake Huron, the Straits
of Mackinac are a critical point in this ecosystem. As the many Indian Tribes involved in
this litigation point out, the Great Lakes and the Straits of Mackinac have nourished life in
this region for thousands of years. See generally United States v Michigan, 471 F Supp
192, 221-225 (WD Mich, 1979) (discussing the importance of fishing to the native
inhabitants of Michigan in the context of a landmark decision enforcing tribal treaty fishing
rights). The Straits, spanned by the Mackinac Bridge, are a significant natural and
commercial resource for the state and a point of pride for Michiganders.
A. LINE 5’s HISTORY
The Line 5 pipeline, operated by Enbridge, is 645 miles long and carries oil and
liquid natural gas (LNG) from Superior, Wisconsin, to Sarnia, Ontario. It is part of a larger
network of Enbridge pipelines stretching across the United States and Canada. Although
Line 5 mostly transports hydrocarbons across Michigan to eastern Canada, the line
provides crude oil to a few smaller facilities in Michigan, provides most of the Upper
Peninsula’s propane supply, and provides jet fuel to the Detroit Metropolitan Wayne
County Airport.
In 1953, Enbridge’s predecessor—Lakehead Pipe Line Company, Inc.
(Lakehead)—received approval from the PSC to construct the pipeline presently known as
7
Line 5. The Michigan Conservation Commission 2 also granted Lakehead an easement to
construct two 20-inch pipes (referred to as the dual pipelines) located on or suspended
above the lakebed across the Mackinac Straits.
This Court rejected a collateral attack on the PSC’s decision in Lakehead Pipe Line
Co, Inc v Dehn, 340 Mich 25; 64 NW2d 903 (1954). In that case, landowners challenging
the condemnation of their land along the pipeline’s path argued “that the construction and
operation of the pipe line in question here is not a purpose for which the State may grant
the power of eminent domain,” as Lakehead primarily contemplated “the transporting of
oil from Canadian oil fields to refineries in” Canada. Id. at 36. The Court rejected their
argument, noting that Lakehead “propose[d] to deliver oil to Michigan refineries and other
purchasers in this State” and holding that “the construction, maintenance and operation of
the pipe line in question” would “benefit[] the people of Michigan.” Id. at 36, 38. 3
Appellants allege that the dual pipelines, which have a daily carrying capacity of up
to 540,000 barrels and are elevated above the lakebed by supports, are vulnerable to
damage. Anchor strikes are a particular concern, as exemplified by an April 2018 strike
that dented, but did not rupture, the dual pipelines. 4 Given the fast-moving currents and
2
The Conservation Commission was the predecessor to the Natural Resources
Commission. See Westervelt v Natural Resources Comm, 402 Mich 412, 418 n 1; 263
NW2d 564 (1978) (opinion by WILLIAMS, J.).
3
Notably, the pipeline’s approval, construction, and attendant litigation all preceded the
adoption in 1963 of Michigan Constitution, Article 4, § 52—which requires the Legislature
to “provide for the protection of the air, water and other natural resources of the state”—
and the enactment of MEPA in 1970, 1970 PA 127.
4
See National Transportation Safety Board, Marine Accident Brief—Anchor Contact of
Articulated Tug and Barge Clyde S VanEnkevort/Erie Trader with Underwater Cables
and Pipelines (May 21, 2019), p 7, available at
8
connection of both Lake Michigan and Lake Huron to the Straits, if one of the pipes were
to rupture, the resulting spill would be environmentally and economically catastrophic.
B. THE REPLACEMENT PROJECT
The “Replacement Project” at issue here emerged as a result of a series of
agreements negotiated between Enbridge and Governor Rick Snyder on behalf of the state
of Michigan in 2017 through 2018. Specifically, the project involves drilling and
constructing a new, concrete-lined tunnel through the bedrock approximately 60 feet to
250 feet under the Straits’ lakebed and running a new 30-inch pipe through that tunnel.
According to the terms of Enbridge’s agreement with the state, this would allow the dual
pipelines to be decommissioned and “would essentially eliminate the risk of adverse
impacts that may result from a potential oil spill in the Straits . . . .” The project would not
change Line 5’s current carrying capacity or the service it provides. Initially, the project
contemplated that the tunnel could be used for other utilities, such as electric and broadband
lines. However, the PSC declined to approve this aspect of the project, concluding that
“Enbridge failed to demonstrate by a preponderance of the evidence that co-locating third-
party utilities in the tunnel with the Straits Line 5 replacement segment is reasonable or
safe.”
In 2018, the Legislature created the Mackinac Straits Corridor Authority (MSCA)
and authorized it to enter into an agreement to build a “utility tunnel” under the Straits.
See 2018 PA 359. Enbridge agreed to construct and maintain the tunnel and the
<https://www.ntsb.gov/investigations/AccidentReports/Reports/MAB1912.pdf> (accessed
June 12, 2026) [https://perma.cc/5DAW-95YV].
9
replacement pipeline and to deactivate the existing dual pipelines once the Replacement
Project becomes operational. For its part, the MSCA agreed to obtain the necessary
property rights for Enbridge to construct the Replacement Project. Consistent with this
goal, in December 2018, the Department of Natural Resources (DNR) granted the MSCA
an easement to construct a tunnel under the Straits. Once Enbridge completes the tunnel,
the MSCA will then take ownership of the tunnel and provide Enbridge with a 99-year
lease.
Enbridge filed an application with the PSC to move forward with the construction.
As set forth in more detail below, the PSC approved the application and the Court of
Appeals affirmed that decision, resulting in this appeal.
II. LEGAL BACKGROUND
Some initial legal background is helpful for understanding the proceedings that led
to this appeal and the positions the parties have taken. Three legal frameworks intersect in
this case: 1929 PA 16 (Act 16), MEPA, and the common-law public trust doctrine.
A. ACT 16
We begin with 1929 PA 16 (Act 16), codified at MCL 483.1 et seq., which gives
the PSC primary authority to regulate pipelines in this state. Under this framework,
pipeline operators must apply to and receive approval from the PSC in order to construct
new facilities. See MCL 483.3(1)(a); Mich Admin Code, R 792.10447(1)(c). The PSC
has set out a three-part test for determining whether to grant an application under Act 16.
It must find that “(1) the applicant has demonstrated a public need for the proposed
pipeline, (2) the proposed pipeline is designed and routed in a reasonable manner, and (3)
10
the construction of the pipeline will meet or exceed current safety and engineering
standards.” In re Application of Enbridge Energy, Ltd Partnership, order of the Public
Service Commission, entered January 31, 2013 (Case No. U-17020), p 5. See also In re
Application of Wolverine Pipe Line Co, order of the Public Service Commission, entered
July 23, 2002 (Case No. U-13225), pp 4-5.
Any party in interest who is “dissatisfied with any order of the [PSC] fixing any rate
or rates, fares, charges, classifications, joint rate or rates, or any order fixing any
regulations, practices, or services, may . . . file an appeal as of right in the Court of
Appeals.” MCL 462.26(1). The party appealing from such an order must “show by clear
and satisfactory evidence that the order of the [PSC] complained of is unlawful or
unreasonable.” MCL 462.26(8). See also In re MCI Telecom Complaint, 460 Mich 396,
427; 596 NW2d 164 (1999) (describing the deferential standards of review for certain PSC
decisions).
B. MEPA
We next turn to the environmental protections guaranteed by our state Constitution
and by statute. Article 4, § 52 of the Michigan Constitution of 1963 reads:
The conservation and development of the natural resources of the state
are hereby declared to be of paramount public concern in the interest of the
health, safety and general welfare of the people. The legislature shall provide
for the protection of the air, water and other natural resources of the state
from pollution, impairment and destruction.
Michigan’s Environmental Protection Act, 1970 PA 127, “mark[ed] the Legislature’s
response to [that] constitutional commitment . . . .” Ray v Mason Co Drain Comm’r, 393
Mich 294, 304; 224 NW2d 883 (1975). MEPA “imposes a duty on individuals and
11
organizations both in the public and private sectors to prevent or minimize degradation of
the environment which is caused or is likely to be caused by their activities.” Id. at 306. It
“prohibits pollution, destruction, or impairment of the environment unless it can be shown
that ‘there is no feasible and prudent alternative’ and that [a] defendant’s conduct ‘is
consistent with the promotion of the public health, safety and welfare in light of the state’s
paramount concern for the protection of its natural resources . . . .’ ” Id. (citation omitted;
ellipsis in Ray). Put simply, MEPA bars environmentally destructive conduct unless it can
be shown that the conduct is necessary and unavoidable. 5
MEPA “was the first legislation of its kind” and a “dramatic change” from prior
practice in environmental protection, which vested environmental enforcement in
administrative agencies without citizen participation. Id. at 304-305. Its provisions
reflected “public dissatisfaction with the existing legal and regulatory regime.” Castrilli,
Environmental Rights Statutes in the United States and Canada: Comparing the Michigan
and Ontario Experiences, 9 Vill Env’t LJ 349, 361 (1998). The belief that administrative
agencies were “too closely associated” with regulated interests and were unlikely to
provide relief motivated the decision to vest enforcement in MEPA’s citizen intervention
and lawsuit provisions. Id.; see also Ray, 393 Mich at 305 (“Not every public agency
proved to be diligent and dedicated defenders of the environment.”).
5
MEPA differs significantly from its federal analogue, the National Environmental Policy
Act (NEPA), 42 USC 4321 et seq. Unlike MEPA, “NEPA is a purely procedural statute”
and “imposes no substantive environmental obligations or restrictions.” Seven Co
Infrastructure Coalition v Eagle Co, Colorado, 605 US 168, 173; 145 S Ct 1497; 221 L Ed
2d 820 (2025). But, as will be discussed later in this opinion, notwithstanding their
differences, MEPA and NEPA have some analogous provisions.
12
The Legislature did not attempt to promulgate a specific set of substantive
environmental standards within MEPA, nor did it assign this task to an administrative
agency. See id. at 306. Instead, the Legislature set “parameters” but “left to the courts the
important task of giving substance to the standard by developing a common law of
environmental quality.” Id. Although the statute contemplates that courts may adopt
standards or procedures created by “the state or an instrumentality, agency, or political
subdivision,” courts “may . . . [d]etermine the validity, applicability, and reasonableness”
of any such standard, and “[i]f a court finds a standard to be deficient, direct the adoption
of a standard approved and specified by the court.” MCL 324.1701(2)(a) and (b). See also
Nemeth v Abonmarche Dev, Inc, 457 Mich 16, 30; 576 NW2d 641 (1998).
Against this backdrop, MEPA provides several procedural pathways to enforce its
requirements. Most notably, it creates a cause of action for private parties—and the
attorney general—to seek declaratory and equitable relief in circuit court. See MCL
324.1701(1); see also MCL 324.1702 through MCL 324.1704. But, in addition to allowing
“citizen suits,” 6 MEPA contemplates that agencies will also enforce its provisions. Section
1704 creates a mechanism for the circuit court to remit a MEPA action to an administrative
agency for a decision in the first instance. MCL 324.1704(2) through (4). MEPA also
6
Lawsuits brought under MEPA by individuals or other entities have commonly been
referred to as “citizen suits,” see, e.g., Sax & D