Save the Sound, Inc. v. FAA
CourtCourt of Appeals for the D.C. Circuit
Date FiledJuly 21, 2026
Docket24-1028
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
United States Court of Appeals
FOR THE DISTRICT OF COLUMBIA CIRCUIT
Argued December 12, 2025 Decided July 21, 2026
No. 24-1028
SAVE THE SOUND, INC.,
PETITIONER
v.
FEDERAL AVIATION ADMINISTRATION AND BRYAN BEDFORD,
IN HIS CAPACITY AS ADMINISTRATOR OF THE FEDERAL
AVIATION ADMINISTRATION,
RESPONDENTS
AVPORTS LLC AND TWEED NEW HAVEN AIRPORT
AUTHORITY,
INTERVENORS
Consolidated with 24-1029
On Petitions for Review of an Order
of the Federal Aviation Administration
Dana Hrelic argued the cause for petitioners. With her on
the briefs were James T. Shearin, Roger Reynolds, Jessica
Roberts, and Dara Illowsky.
2
Rebecca Jaffe, Attorney, U.S. Department of Justice,
argued the cause for respondents. With her on the brief were
Adam R.F. Gustafson, Assistant Attorney General, and Robert
J. Lundman and Kevin W. McArdle, Attorneys.
W. Eric Pilsk, Catherine M. van Heuven, and David J.
Monz were on the brief for intervenor Tweed New Haven
Airport Authority in support of respondents. Peter J. Kirsch
entered an appearance.
Kenneth P. Quinn and David F. Knapp were on the brief
for intervenor Avports LLC in support of respondents.
Kelley J. Halliburton was on the brief for amicus curiae
City of New Haven, Connecticut in support of respondents.
Before: SRINIVASAN, Chief Judge, WILKINS and KATSAS,
Circuit Judges.
Opinion for the Court filed by Circuit Judge KATSAS.
KATSAS, Circuit Judge: The National Environmental
Policy Act requires federal agencies to prepare reports
discussing the environmental effects of major federal actions.
Its requirements are modest, purely procedural, and serve only
to facilitate informed agency decision-making. In this case, an
environmental group and a town challenge the Federal
Aviation Administration’s approval of a construction project at
a small Connecticut airport. They allege numerous NEPA
violations, but their theories would require us to override
reasonable agency judgments or explanations. Neither NEPA
nor the Administrative Procedure Act permits this, so we deny
the petitions for review.
3
I
A
NEPA requires federal agencies to prepare reports on the
environmental effects of “major Federal actions.” 42 U.S.C.
§ 4332(2)(C). The report must discuss “reasonably foreseeable
environmental effects.” Id. § 4332(2)(C)(i).
An agency may issue its report in one of two forms. When
a project does not have “reasonably foreseeable significant
effect[s]” on the environment, an agency must prepare an
environmental assessment (EA). 42 U.S.C. § 4336(b)(2). Such
an EA must “concise[ly]” set forth the agency’s reasons for
finding no significant environmental effects. Id. If a project is
expected to have significant environmental effects, the agency
must prepare a longer environmental impact statement (EIS).
Id. § 4336(b)(1). But neither an EA nor an EIS may go on
endlessly. In 2023, Congress prohibited EAs that exceed 75
pages and EISs that exceed 150 pages absent extraordinary
circumstances. Id. § 4336a(e).
In Seven County Infrastructure Coalition v. Eagle County,
605 U.S. 168 (2025), the Supreme Court stressed that courts
play a modest role in reviewing agencies’ NEPA reports. The
Court ordered a “course correction … to bring judicial review
under NEPA back in line with the statutory text and common
sense.” Id. at 184. This correction was necessary because
lower courts had “strayed and not applied NEPA with the level
of deference demanded by the statutory text” and judicial
precedent. Id. at 183. For example, the Court explained that
NEPA’s “textually mandated focus” is “the ‘proposed
action’—that is, the project at hand.” Id. at 186–87 (quoting
42 U.S.C. § 4332(2)(C) (2018)). Therefore, agencies need not
evaluate the environmental effects of a “possible future”
project or a “geographically distant” one. Id. at 187. Similarly,
4
although NEPA requires “detailed” agency reports, it does not
specify what details must be included, and it prohibits bloated
reports. Id. at 180–81 & n.3. “So the question of whether a
particular report is detailed enough in a particular case itself
requires the exercise of agency discretion—which should not
be excessively second-guessed by a court.” Id. at 181.
Summing up, the Court held that “the central principle of
judicial review in NEPA cases is deference.” Id. at 179.
Finally, the Court reiterated the settled principle that
“NEPA is a purely procedural statute” that “does not require
the agency to weigh environmental consequences in any
particular way.” Seven County, 605 U.S. at 173; see also id. at
180 (“NEPA imposes no substantive constraints on the
agency’s ultimate decision to build, fund, or approve a
proposed project.”). An agency therefore may conclude that
“other values outweigh the environmental costs” of a project,
and we must respect that determination so long as the agency
has reasonably explained it. Id. at 177–78 (cleaned up).
B
Tweed New Haven Airport is a regional Connecticut
airport managed by the Tweed-New Haven Airport Authority.
Tweed is one of the most underserved airports in the country.
In September 2021, the only airline flying there stopped doing
so. As of late 2023, only one airline had stepped in to fill the
void—a short-haul carrier called Avelo.
Tweed has no shortage of problems, but two are relevant
here. First, its only active runway is too short. At 5,600 feet,
it cannot accommodate the weight of full-capacity flights on
one of the most common passenger planes—the Boeing 737-
800. To comply with the runway’s current weight limits, Avelo
must reduce the capacity on such flights from 189 to 162 seats.
Second, Tweed’s passenger terminal is undersized and
5
outdated. The existing terminal was built as a hangar in 1980
and then converted to a passenger terminal. It is cramped,
inefficient, and prone to flooding.
To address these and other problems, the Airport Authority
prepared a Master Plan. Running over 250 pages, it laid out
proposed upgrades for the next several decades. To target the
specific problems noted above, the Authority proposed an
expansion project that would (1) extend the runway by roughly
1,000 feet to accommodate 737-800 aircraft at full capacity and
(2) build a new passenger terminal.
The Master Plan also proposed to improve Tweed’s
unusual taxiways. A taxiway is a road for planes to travel
between hangars and runways. Tweed’s taxiways have
atypical signage and acute rather than right-angle connections
to the runway. The Airport Authority proposed construction
projects to address these taxiway issues. The Authority
preliminarily projected that these taxiway upgrades would have
significant environmental effects on nearby water or wetlands.
C
The FAA bifurcates its approval process for airport
expansion projects. To start, an airport may seek conditional
approval to evaluate whether a proposed project is safe. At this
initial stage, the project is still too tentative for environmental
review. In the FAA’s words, environmental review is “not yet
needed and … not ripe for decision.” FAA Order 5050.4B
(2006) (reprinted at J.A. 762). Later, the airport may seek final
approval, which requires NEPA review.
The Airport Authority received conditional approval for
all the projects in its Master Plan, but it sought final approval
only for the runway extension and new terminal. The FAA
treated the runway extension and new terminal as a single
6
project. It did not consider the taxiway upgrades as part of this
project because the Airport Authority had not sought final
approval for those upgrades and did not expect to do so in the
next five years.
In conducting its NEPA review for the proposed runway
extension and new terminal, the FAA received over 900 public
comments on a draft EA. In response, the agency updated the
draft, prepared a final EA, and concluded that the project would
have no significant environmental effects. The FAA thus
declined to prepare a full EIS.
In its EA, the agency concluded that the project would
reduce air pollution near the airport. The FAA projected that
the number of “enplanements” at Tweed—that is, the number
of passengers expected to board flights there—would increase
from about 350,000 in 2022 to over 1.2 million in 2031. J.A.
79. The FAA attributed this expansion to increased demand
and to Avelo’s expanding service, growth the agency predicted
would occur regardless of whether the project went forward.
See id. With the runway extension, the FAA projected that
Tweed would see fewer flights with more passengers per flight
due to the use of full-capacity 737-800s. Id. at 79, 684, 710.
Without the extension, the FAA projected more flights with
fewer passengers per flight due to the reduced capacity. See id.
On balance, the agency predicted that “overall net emissions
for most pollutants” would “decrease” if the project went
forward. Id. at 684.
The FAA also evaluated flooding-related environmental
risks. It recognized that the project would require replacing
some floodplains with impervious surfaces like the expanded
concrete runway. Because impervious surfaces do not absorb
water, rainwater falling on them may carry pollutants into
nearby bodies of water. Nonetheless, the FAA found that the
7
project would have only minimal stormwater runoff effects.
For one thing, the Airport Authority would excavate other parts
of the property to create new floodplains. J.A. 29–30, 40.
Moreover, construction would include infiltration measures
allowing water to penetrate or pass man-made surfaces to reach
the soil. Id. at 31. The project also would include stormwater
detention systems to collect rainwater and prevent flooding. Id.
Finally, the FAA noted the minimal effects on nearby wetlands.
Id. at 31, 178, 734. The Airport Authority would offset any
losses by working with other regulators to create wetlands
elsewhere in the state, with preliminary plans to do so near the
Airport. Id. at 31, 39, 192, 239–40, 437–38, 443, 485.
An environmental group called Save the Sound and the
Town of East Haven, Connecticut petitioned this Court for
review of the FAA’s decision to approve the project. They
contend that the EA violates NEPA in several respects. We
have jurisdiction under 49 U.S.C. § 46110(a).
II
Courts review NEPA claims through the Administrative
Procedure Act. Gulf Restoration Network v. Haaland, 47 F.4th
795, 799 (D.C. Cir. 2022). Judicial review in NEPA cases is
especially narrow. “In reviewing the FAA’s compliance with
NEPA, our role is simply to ensure that the agency has
adequately considered and disclosed the environmental impact
of its actions and that its decision is not arbitrary or capricious.”
Cmtys. Against Runway Expansion, Inc. v. FAA, 355 F.3d 678,
685 (D.C. Cir. 2004) (cleaned up); see 5 U.S.C. § 706(2)(A)
(arbitrary-and-capricious standard). And as explained above,
Seven County repeatedly stressed more generally that “[t]he
bedrock principle of judicial review in NEPA cases can be
stated in a word: Deference.” 605 U.S. at 185.
8
III
The petitioners assert four categories of NEPA claims. We
consider each in turn.
A
The petitioners first contend that the FAA impermissibly
segmented the project by considering only the proposed
runway extension and terminal construction, but not the
possible taxiway upgrades. We disagree.
In Seven County, the Supreme Court stressed that NEPA’s
text speaks of “the ‘proposed action’—that is, the project at
hand.” 605 U.S. at 182. So, NEPA never requires an agency
to “evaluate the effects of [a] separate project.” Id. at 187. And
it gives agencies wide latitude to define the relevant project:
Even “interrelated” projects that are “close in time and place to
the project at hand” are not necessarily a single project. Id. at
190. Our review “must remain deferential,” particularly as to
the “gray area in defining the project at hand.” Id. Even if we
conclude that “NEPA would support drawing a different line,”
we must defer if the agency has drawn a “reasonable and
manageable line.” Id. (cleaned up). According to regulations
promulgated by the Council on Environmental Quality, we
police this line by considering whether possibly different
projects overlap temporally and have substantial independent
utility. See 40 C.F.R. § 1501.9(e) (2023); City of Bos.
Delegation v. FERC, 897 F.3d 241, 252 (D.C. Cir. 2018).1
1
While this litigation was pending the status of the CEQ
regulations implementing NEPA became unsettled. For one thing,
this Court concluded that the regulations are ultra vires, Marin
Audubon Soc’y v. FAA, 121 F.4th 902 (D.C. Cir. 2024), though we
later characterized our analysis as dicta, Marin Audubon Soc’y v.
9
Here, the FAA drew a reasonable line at the proposals
submitted for final approval—the runway extension and
terminal construction. For one thing, the FAA explained, the
taxiway project is temporally remote. The Airport Authority
does not plan to seek final approval for the taxiway upgrades
in the next five years. J.A. 251. Moreover, the respective
projects have substantial independent value. The runway and
terminal upgrades will provide passengers with better service,
regardless of whether the taxiways are upgraded. Id. at 104,
110. To be sure, some of the taxiway upgrades might
eventually connect to the newly added runway. However, “the
fact that other projects might foreseeably be built or expanded
in the wake of the current project does not, by itself, make the
agency responsible for addressing the environmental effects of
those other projects.” Seven County, 605 U.S. at 189.
The petitioners add that the projects must be connected
because the runway extension will require taxiway upgrades to
meet FAA safety standards. Specifically, they contend that
Tweed needs a full-length taxiway running parallel to its
runway. But as the FAA explained, the new runway complies
with its design standards with or without the taxiway upgrades.
J.A. 740. The FAA requires certain airports to adopt a full-
length taxiway to account for specific visibility conditions that
FAA, No. 23-1067, 2025 WL 374897, at *1 (D.C. Cir. Jan. 31, 2025)
(Srinivasan, C.J., concurring in the denial of rehearing en banc). For
another, the CEQ rescinded the regulations. See Removal of
National Environmental Policy Act Implementing Regulations, 91
Fed. Reg. 618 (Jan. 8, 2026). The parties agree that these
developments do not affect this case. Because it makes no difference
to the outcome here, we apply the CEQ regulations that were in effect
when the FAA issued its decision without considering any possible
complications from either Marin Audubon or the later rescission. See
Sierra Club v. FERC, 153 F.4th 1295, 1308 n.7 (D.C. Cir. 2025);
Healthy Gulf v. FERC, 132 F.4th 544, 549 n.1 (D.C. Cir. 2025).
10
are unrelated to runway length. Id. at 860. The relevant
visibility conditions are not known to be present at Tweed.
Moreover, even if they were, the FAA permits airports to
implement other safety measures instead of building a full-
length taxiway. Id. at 748, 876. So, neither the runway
expansion nor the terminal improvements required the taxiway
upgrades to go forward.
For these reasons, the FAA permissibly declined to
consider the prospective taxiway improvements as part of the
current project.
B
The second objection is a slight variation on the first. The
petitioners posit that the FAA ran afoul of NEPA’s mandate to
consider “reasonably foreseeable environmental effects” of the
proposed runway expansion and terminal construction.
42 U.S.C. § 4332(C)(i). Under the regulations in place when
the FAA approved the project, agencies had to consider
“cumulative effects” of the project—that is, those resulting
from the “incremental effects of the action when added to the
effects of other past, present, and reasonably foreseeable
actions.” 40 C.F.R. § 1508.1(g)(3) (2023). But when a future
project is in its early planning stages and the agency lacks
“information about its scope,” the project is “too preliminary
to meaningfully estimate its cumulative impacts.” City of Bos.
Delegation, 897 F.3d at 253 (cleaned up). Instead, possible
effects are better analyzed in “later projects” when they
“become better known.” Id. at 254.
Invoking the requirement to consider cumulative effects,
the petitioners rehash their argument about the taxiway
upgrades. They say the taxiway project is reasonably
foreseeable because Tweed’s current layout raises safety
concerns and the Airport Authority included blueprints for the
11
upgrades in its Master Plan. We reject this argument for the
reasons already given: The taxiway project is not required for
safety, and there is too much uncertainty surrounding whether
the Airport Authority will ever pursue it, and if so in what form.
More generally, the petitioners insist that the FAA
arbitrarily ignored reasonably foreseeable future effects by
drawing a line at projects expected to occur within five years.
The petitioners invoke Northern Plains Resource Council, Inc.
v. STB, 668 F.3d 1067 (9th Cir. 2011), where the Ninth Circuit
set aside an environmental analysis that did not consider effects
more than five years after the approval at issue. But Northern
Plains was expressly limited to “the facts presented” in that
case, which involved a project beset by decades of delay and
construction set to continue for more than five years. Id. at
1078. This case involves no comparable circumstances; the
agency estimated the project would be completed within three
years of issuing the EA. J.A. 21, 25. And whatever the merits
of Northern Plains on its facts, Seven County prevents us from
imposing on the FAA a requirement to consider the effects of
a distinct, inchoate project expected to be commenced more
than five years after the regulatory approval at issue here.
The petitioners also contend that the FAA failed to
adequately consider the effects from Avelo’s decision to
service Tweed in 2021. But the FAA did consider that decision
as part of its cumulative-effects analysis. J.A. 250, 708. The
agency factored the effects of Avelo’s activities into its
baseline model, and it then assessed how the project would
affect the baseline. Id. at 79, 399–408, 417. Indeed, the FAA
reasonably concluded that the project would reduce most
pollutants, by enabling Avelo to accommodate the same
passenger demand with fewer flights. Id. at 417, 684. The
petitioners suggest the FAA should have quantified the specific
effects from Avelo’s activities. But NEPA does not require
12
that level of detail. See Seven County, 605 U.S. at 180–81.
Instead, it is more than enough that the FAA “extensively
detailed the existing conditions” at Tweed. El Puente v. U.S.
Army Corps of Eng’rs, 100 F.4th 236, 250–51 (D.C. Cir. 2024).
C
The petitioners challenge the FAA’s prediction that the
project will not cause enplanements at Tweed to increase.
Recall that the agency projected enplanements to increase
substantially, but for reasons unrelated to the project. And
recall its prediction that the project would cause fewer flights
with more passengers per flight, thus reducing air pollution.
The petitioners initially object that the FAA failed to use
reliable data and disclose its methodology, as required by
42 U.S.C. § 4332(2)(D)–(E). Yet the FAA explained that it
based its calculations on the number of projected flights, seats
per flight, and percentage of seats filled. J.A. 83, 388–97. It
included several pages of analysis with specific numbers based
on forecasts from Avelo. Those disclosures ensured that
“relevant information is available to those participating in
agency decision-making.” Sierra Club v. FERC, 153 F.4th
1295, 1306 (D.C. Cir. 2025) (cleaned up). And they likewise
enabled the public “to understand and consider meaningfully
the factors involved.” Izaak Walton League of Am. v. Marsh,
655 F.2d 346, 368 (D.C. Cir. 1981) (cleaned up). 2
2
In their reply brief, the petitioners claim that the FAA should
have employed the methodology that the Airport Authority used in
the Master Plan. This argument is forfeited because it was not clearly
raised in the opening brief. United States v. All Assets Held at Credit
Suisse (Guernsey) Ltd., 45 F.4th 426, 434 (D.C. Cir. 2022). It is also
misguided because, as explained below, a reviewing court may rarely
if ever override an agency’s technical calculations on matters within
13
Next, the petitioners charge that the FAA ignored the
Environmental Protection Agency’s request for more details on
the enplanement projections. But the FAA did respond to
EPA’s comments, by adding almost ten pages of fine print to
the final EA. J.A. 708–14. The petitioners say this was not
enough because the FAA should have treated EPA like a
“cooperating agency” formally involved in the project. See
42 U.S.C. §§ 4336a(a)(3), 4336e(2). The petitioners do not,
and could not, contend that EPA was such a cooperating
agency. Regardless, the FAA included at least a reasonable
level of detail in the final EA, which is all we may demand of
it. See Seven County, 605 U.S. at 180–81.
The petitioners lodge several specific objections about the
economic or technical assumptions underpinning the flight
projections. Such claims are difficult to sustain given the
deferential nature of judicial review for arbitrariness, both
under the APA in general and in NEPA cases in particular.
Even before Seven County, distinguished judges on our Court
had made this point repeatedly. See, e.g., Friends of the River
v. FERC, 720 F.2d 93, 102 (D.C. Cir. 1983) (R.B. Ginsburg,
J.) (resolution of issues requiring “technical expertise ... is
properly left to the informed discretion of the responsible
federal agency”); Citizens Against Burlington, Inc. v. Busey,
938 F.2d 190, 201 (D.C. Cir. 1991) (Thomas, J.) (when
analysis “requires a high level of technical expertise, we must
defer to the informed discretion of the responsible federal
agencies” (cleaned up)); Sierra Club v. EPA, 353 F.3d 976, 991
(D.C. Cir. 2004) (Roberts, J.) (same); Cmtys. for a Better Env’t
v. EPA, 748 F.3d 333, 336 (D.C. Cir. 2014) (Kavanaugh, J.)
(noting the “extreme degree of deference to the agency when it
its expertise, let alone require a federal agency to use the
methodology of a particular non-federal entity.
14
is evaluating scientific data within its technical expertise”
(cleaned up)).
Specifically, the petitioners challenge the FAA’s
conclusion that the number of enplanements would remain
constant with or without the project. In their view, the project
will provide Tweed with more flight capacity, attracting more
passengers and potentially even more airlines. This line of
objection runs into several problems.
First, the petitioners rely on flight projections in the Master
Plan, which predated Avelo’s decision to service Tweed. By
the time the FAA had conducted its NEPA analysis, these
projections were outdated and wildly inaccurate. For instance,
the Master Plan projected at most around 114,000
enplanements in 2022, J.A. 984, but the actual number of
enplanements for that year was about 350,000, id. at 79. Under
these circumstances, the FAA reasonably used newer data.
Second, the petitioners flag possibilities that the FAA
reasonably discounted as unlikely. They argue that the runway
extension will likely attract new airlines to Tweed. But as the
FAA explained, there were “no firm proposals from other
carriers to serve” that airport. J.A. 68. And even if other
airlines did enter the market, the FAA did not expect
enplanements to change because new carriers would compete
with Avelo for a share of the same passengers. Id. at 718. We
must afford substantial deference to the FAA’s predictive
judgment about enplanements. St. John’s United Church of
Christ v. FAA, 550 F.3d 1168, 1172 (D.C. Cir. 2008); see also
Ethyl Corp. v. EPA, 541 F.2d 1, 36 (D.C. Cir. 1976) (en banc).
And even if a professional economist could contest the
agency’s conclusion, the petitioners have given us no reason to
doubt it. Along the same lines, the petitioners argue that the
runway extension will likely support new, long-distance flights
15
to the West Coast. But as the FAA explained, Avelo’s CEO
noted that the carrier had “no plans in the near term or even in
the intermediate term” to add such flights. J.A. 552. And in
any event, the FAA’s models did account for possible flights to
the West Coast. Id. at 391–92.
Third, the petitioners grasp at statements from judicial
decisions not involving the project under review. They cite a
Second Circuit decision addressing whether federal law
preempted a Connecticut statute regulating runway length.
Tweed-New Haven Airport Auth. v. Tong, 930 F.3d 65 (2d Cir.
2019). In a background sentence without citations, that Court
stated that an extension “would also allow Tweed to attract
more carriers.” Id. at 69. A general background statement in a
judicial opinion that is immaterial to the question presented is
hardly a sound basis for later overriding an agency’s
“predictive and scientific judgments” during a NEPA review
challenged in a different case. Seven County, 605 U.S. at 181.
Likewise, the petitioners cite a Ninth Circuit decision, Barnes
v. DOT, 655 F.3d 1124 (9th Cir. 2011), for the proposition that
runway upgrades tend to induce more passenger demand. But
Barnes faulted the FAA for failing to consider whether a new
runway would increase demand at an airport operating at its
maximum acceptable capacity. Id. at 1128, 1136–38. That
case has little to say about whether, on this record, the FAA
reasonably concluded that the extension of an existing runway,
at an airport operating well below its maximum acceptable
capacity, would likely increase overall demand.
Because the FAA’s enplanement projections were
reasonably supported and explained, we reject the petitioners’
various challenges to them.
16
D
Finally, the petitioners fault the FAA for failing to
adequately consider environmental effects related to flooding,
runoff, and wetlands. Again, we disagree.
The petitioners assert that the project, which requires
replacing some floodplains with impervious surfaces, will
likely increase nearby flooding. However, the FAA reasonably
explained that the Airport Authority would offset the loss of
floodplains by excavating lands around the airport to create
new ones and by taking various other mitigating measures.
J.A. 29–30, 40, 241–47. In fact, the FAA laid out far more
detailed mitigation plans than the ones at issue in the main case
on which the petitioners rely. See Wyo. Outdoor Council
Powder River Basin Res. Council v. U.S. Army Corps of
Eng’rs, 351 F. Supp. 2d 1232, 1252 (D. Wyo. 2005).
Similarly, the petitioners argue that the FAA failed to
analyze the effects of stormwater pollution on nearby surface
waters and wetlands. They claim that the FAA failed to give
sufficient detail about mitigation measures, but the agency
thoroughly considered this issue. It mentioned stormwater
detention and filtering systems that Tweed would install at the
new terminal, noted construction plans to allow for rainwater
infiltration, and pointed to a state permitting program that
Tweed has complied with and must continue to satisfy. J.A.
31, 39, 178, 192, 698–99, 729, 744. This case is thus easily
distinguishable from American Rivers v. FERC, 895 F.3d 32
(D.C. Cir. 2018), where we faulted an agency for not discussing
mitigation in any detail, leaving it “as TBD.” Id. at 54 (cleaned
up). Furthermore, the FAA explained, this project was
designed to minimize any effect on wetlands. In particular, it
avoided nearly half of the relevant wetlands and directly
affected largely low-value, inland wetlands comprised of
17
grasses in areas of Tweed that had been filled with artificial
materials in the 1930s. J.A. 30–31, 103, 234–35, 423–24, 431.
Though some commenters speculated that the project may
prevent additional wetlands from forming naturally, the FAA
discounted that possibility as “very unlikely” given the location
of the project and the existing wetlands. Id. at 728. We cannot
say that this predictive, technical judgment was unreasonable.
Despite these measures, the petitioners fault the agency for
failing to consider indirect effects on nearby tidal wetlands.
But an agency has broad latitude to decide “how far to go in
considering indirect environmental effects from the project at
hand.” Seven County, 605 U.S. at 182. And here, the FAA
reasonably explained its view that there would be no such
effects. According to the petitioners, if inland wetlands cannot
soak up pollutants in stormwater, tidal wetlands will face
increased damage. The FAA rejected this contention and
explained that mitigation measures would substitute for the
inland wetlands’ minor, relevant function. J.A. 235, 437–38.
Finally, the petitioners claim that the FAA failed to
consider the full benefits the wetlands provide. The FAA
explained that the wetlands at issue are largely low-quality
ones. J.A. 31, 191, 235. Only one wetland has any nutrient-
related functions, and it had already been filled with unnatural
construction materials. Id. at 235, 688, 702. Further, the FAA
emphasized that Tweed must coordinate with state regulators
to mitigate the project’s wetlands effects. Id. at 437–38. The
petitioners again say this analysis was light on details. Yet the
FAA undertook to coordinate with state regulators to ensure
“no-net-loss” of wetlands, and it gave specifics about
preliminary locations and strategies. This substantive
undertaking, made after considering the relevant
environmental considerations, well exceeds the process and
deliberation that NEPA requires.
18
IV
In sum, the FAA reasonably defined the project, addressed
its possible environmental effects, discussed measures the
Airport Authority would take to mitigate such effects, and
concluded the project would have no significant environmental
effects. An agency can always include more detail and more
robust explanations in its EA or EIS. But as we recently
explained, “the era of searching NEPA review is over.” Sierra
Club, 153 F.4th at 1311. Under Seven County, we must
determine only whether the agency acted within a broad range
of reasonableness. Because the FAA did so here, we deny the
petitions for review.
So ordered.