Carteret Business Partnership, Inc. v. New Jersey Department of Environmental Protection
CourtNew Jersey Superior Court Appellate Division
Date FiledJuly 30, 2026
DocketA-0951-24
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
NOT FOR PUBLICATION WITHOUT THE
APPROVAL OF THE APPELLATE DIVISION
SUPERIOR COURT OF NEW JERSEY
APPELLATE DIVISION
DOCKET NO. A-0951-24
APPROVED FOR PUBLICATION
July 30, 2026
CARTERET BUSINESS APPELLATE DIVISION
PARTNERSHIP, INC.,
Petitioner-Appellant,
v.
NEW JERSEY DEPARTMENT
OF ENVIRONMENTAL
PROTECTION,
Respondent-Respondent.
___________________________
Argued June 4, 2026 – Decided July 30, 2026
Before Judges Mawla, Marczyk and Puglisi.
On appeal from the New Jersey Department of
Environmental Protection.
Dominic J. Aprile argued the cause for appellant
(Bathgate Wegener & Wolf, PC, attorneys; William J.
Wolf and Daniel J. Carbone, on the briefs).
Elizabeth Delahunty, Deputy Attorney General,
argued the cause for respondent (Jennifer Davenport,
Attorney General, attorney; Janet Greenberg Cohen,
Assistant Attorney General, of counsel; Elizabeth
Delahunty, on the brief).
Scott E. Reiser argued the cause for intervenor
Township of Woodbridge (Javerbaum Wurgaft Hicks
Kahn Wikstrom & Sinins, attorneys; Scott E. Reiser
and Steven J. Eisenstein, of counsel and on the brief).
The opinion of the court was delivered by
MARCZYK, J.A.D.
Petitioner Carteret Business Partnership, Inc. (CBP) appeals from the
New Jersey Department of Environmental Protection's (DEP) November 18,
2024 final agency decision, which reversed the administrative law judge's
(ALJ) initial decision and granted the DEP's motion for summary decision.
The primary issue on appeal is whether the DEP has authority under N.J.A.C.
7:14A-22.8(a)(3)(v) to consider a treatment works approval (TWA) application
that lacks consent from the receiving wastewater treatment plant. We
conclude the DEP reasonably interpreted the regulation to require the receiving
wastewater treatment plant's consent as a mandatory prerequisite to
considering a TWA application, such that it was precluded from considering
CBP's application. Accordingly, we affirm.
I.
A. Background.
This appeal arises from the DEP's denial of CBP's TWA application to
construct and operate two gravity sanitary sewer laterals to service a sixty -
four-unit mixed-use development in the Borough of Carteret. The proposed
A-0951-24
2
development would discharge effluent into Carteret's municipal wastewater
conveyance system, which connects to the Township of Woodbridge's
wastewater conveyance system. Ultimately, the wastewater would be
conveyed into the Middlesex County Utilities Authority's (MCUA) wastewater
treatment plant. Pursuant to a 1987 agreement, Woodbridge permits Carteret
to use its sewer system to transport sewage to the MCUA.
CBP submitted the TWA application to the DEP in November 2022,
which included a WQM-003 Consent Form (Consent Form) pursuant to
N.J.A.C. 7:14A-22.8(a)(3). The Consent Form included two required
signatures from Carteret, evidencing its consent and certification to the
application, in Sections A and B, respectively titled "Consent by Governing
Body" and "Certification by Wastewater Conveyance System Owner."
However, the Consent Form lacked the MCUA's signature in Section C, titled
"Certification by Wastewater Treatment Facility Owner." In an email attached
to CBP's application, the MCUA explained it would not endorse the
application because it was "administratively incomplete," as it lacked
Woodbridge's endorsement "to convey sanitary sewer flows through [its]
collection system to [the] MCUA." CBP noted Woodbridge would not agree
to convey the wastewater to the MCUA and consent to CBP's TWA application
A-0951-24
3
because of an "intermunicipal pecuniary conflict" between Carteret and
Woodbridge.
In a November 7, 2022 letter, CBP requested the DEP approve the
application pursuant to N.J.A.C. 7:14A-22.8(a)(3)(v), despite the fact it was
missing the MCUA's signature on the Consent Form. On November 14, 2022,
the DEP erroneously provided a notice of administrative completeness to CB P,
however, it subsequently advised CBP Section C of its Consent Form was
missing a mandatory signature. In a December 21, 2022 letter, CBP
acknowledged the MCUA's signature was still missing but reiterated its
request the DEP approve its application, again asserting the agency had the
authority to do so under N.J.A.C. 7:14A-22.8(a)(3)(v)(5).
In February 2023, the DEP denied the TWA application. It reasoned it
lacked the authority to issue the permit because the MCUA—the wastewater
treatment facility owner—had not executed the Consent Form to certify the
wastewater would be treated and the plant was following the New Jersey
Pollution Discharge Elimination System (NJPDES) permit requirements. The
DEP explained:
[The] MCUA has notified this office that they will not
endorse and provide consent until . . . Woodbridge
provide[s] . . . consent as [the] "Wastewater
Conveyance System Owner." The wastewater flow
from this project will be conveyed to the MCUA for
A-0951-24
4
treatment using [a] downstream sewage conveyance
system, owned and operated by . . . Woodbridge.
CBP challenged the denial and requested an adjudicatory hearing. 1 In
October 2023, the matter was referred to the OAL for a hearing before an ALJ.
Woodbridge moved to intervene, which the ALJ granted. In April 2024, the
DEP moved for summary decision. CBP opposed the motion.
B. The ALJ's Initial Decision.
On July 8, 2024, the ALJ issued an initial decision, finding the DEP had
authority to consider CBP's TWA application pursuant to N.J.A.C. 7:14A -
22.8(a)(3)(v)(5). She rejected the agency's interpretation the regulation does
not apply when the wastewater treatment facility owner is the entity
withholding consent. The ALJ reasoned the agency's interpretation was
inconsistent with the regulation's language, "which require[s] the []DEP to step
in to make a decision when the affected municipality, the sew[er]age authority,
and/or the treatment facility owner refuse[s] to do so." She noted the Law
Division had also reviewed the regulation and determined the DEP should
1
In February 2023, prior to the DEP's denial of its application, CBP filed a
verified complaint in lieu of prerogative writs in the Law Division, seeking an
order compelling the MCUA to consent to its TWA application. The court
subsequently granted a motion to transfer venue to the Office of
Administrative Law (OAL). See Carteret Bus. P'ship v. Twp. of Woodbridge,
No. L-0674-23 (Law Div. Apr. 18, 2023) (order at 2). However, the matter
was already before the OAL pursuant to CBP's hearing request regarding the
DEP's denial of its TWA application.
A-0951-24
5
administratively resolve the issue, as CBP had asked the agency to do. The
ALJ also emphasized the regulation states the DEP "shall" consider the reasons
for the lack of consent in determining whether to approve an application.
Although the affected parties had not disclosed their reason for denying
consent, the ALJ found the agency had the authority to compel such
disclosure.
Alternatively, if the TWA regulations preclude consideration without the
MCUA's consent, the ALJ determined the DEP should instruct CBP how to
proceed without consent. Accordingly, the ALJ denied the DEP's motion for
summary decision, granted summary decision in favor of CBP, and ordered the
agency to consider CBP's TWA application on its merits. The DEP filed
exceptions to the ALJ's decision, and CBP and Woodbridge filed responses.
C. The DEP's Final Agency Decision.
On November 18, 2024, the DEP Commissioner issued a final agency
decision, reversing the ALJ's initial decision and granting the DEP's motion for
summary decision. He found the ALJ's initial decision failed to follow the
plain meaning of N.J.A.C. 7:14A-22.8(a)(3)(v)(5) and "improperly imposed
requirements on [the] DEP that are not set forth in the TWA regulations."
Thus, the Commissioner concluded the DEP lacked authority under the
regulation to review CBP's TWA application without the MCUA's consent.
A-0951-24
6
The Commissioner determined summary decision was appropriate, and
the interpretation of N.J.A.C. 7:14A-22.8(a)(3)(v)(5) could be resolved as a
matter of law. Indeed, "all parties agree[d] that [the] MCUA, the wastewater
treatment facility owner, did not sign [the] DEP's [Consent F]orm as part of
CBP's TWA application and that Woodbridge would also not sign the form as
a wastewater conveyance system owner." He reasoned N.J.A.C. 7:14A-
22.8(a)'s plain text, structure, history, and administrability does not allow the
DEP to review a TWA application without the wastewater treatment facility
owner's consent.
The Commissioner found although N.J.A.C. 7:14A-22.8(a)(3)(v) "sets
out an alternate path for an applicant that cannot get consent as required by
N.J.A.C. 7:14A-22.8(a)(3), a review of N.J.A.C. 7:14A-22.8(a)(3)(v)(1)
through (5) clearly reveals that . . . path is limited only to when an 'affected
municipality' or 'affected sewerage authority' withholds such consent."
(Citations reformatted). Accordingly, he reasoned the receiving wastewater
treatment plant's consent is mandatory because it is not mentioned in those
subsections, and the DEP would have included it had the agency intended to
carve out an exception for obtaining its consent.
The Commissioner also found the regulatory history of N.J.A.C. 7:14A -
22.8 clearly showed the DEP's intent to require the receiving treatment plant
A-0951-24
7
owner's consent. He determined the ALJ's decision was "therefore contrary to
the applicable TWA regulations and undermine[d the] DEP's purpose in
requiring consent from the wastewater treatment facility owner to protect
public health and maintain the integrity of New Jersey's waters." Citing 41
N.J.R. 142(a) (Jan. 5, 2009), the Commissioner explained it was the
wastewater treatment facility owner's responsibility, not the DEP's, to ensure
the facility can accept the additional flow from the project and continue to
comply with its NJPDES permit. He found that interpretation also aligned
with the TWA program's general policy and purpose, as outlined in N.J.A.C.
7:14A-22.1(b). Accordingly, the Commissioner determined, "[c]onsent from
the owner of the receiving wastewater treatment plant is a non-negotiable
requirement in a TWA application and cannot be waived."
The Commissioner further found the ALJ's initial decision failed to
apply the "appropriate deferential standard to [the] DEP's interpretation and
implementation of its rules." He noted the ALJ erred in finding the DEP was
required to direct CBP on how to move forward if the agency lacked the
regulatory authority to review its TWA application. The Commissioner
reasoned "no regulatory requirement in N.J.A.C. 7:14A-22.8 or in any other
TWA regulation . . . requires [the] DEP to undertake such action." He
explained:
A-0951-24
8
The reasons why [the] MCUA does not wish to
consent are irrelevant to this issue of regulatory
interpretation and[,] thus, there is no need to delve
into the record regarding Woodbridge's position
and/or contractual relationship with Carteret regarding
sewer conveyance and cost-sharing of improvement
projects. At the end of the day, [the] MCUA has
refused to consent to CBP's TWA application, and as a
result[,] N.J.A.C. 7:14A-22.8(a)(3)(v)(5) does not
permit [the] DEP to move forward with reviewing
and/or approving CBP's application. [The] DEP has
no regulatory responsibility to interject itself into a
dispute between two municipalities.
[(Citation reformatted).]
II.
CBP argues the DEP deprived it of administrative justice by refusing to
consider all relevant elements of its TWA application and the reasons the
MCUA and Woodbridge denied consent. It asserts the Commissioner failed to
appreciate relevant facts and discounted relevant evidence in reaching the
agency's final decision. CBP challenges the Commissioner's statements the
DEP "did not rely on the reasons Woodbridge or [the] MCUA provided for not
providing consent," and "[t]he reasons for Woodbridge's refusal to consent . . .
are outside the scope of th[e] decision." It contends those statements are
contrary to N.J.A.C. 7:14A-22.8(a)(3)(v)(5), which states the agency "shall
review the reasons for the lack of consent," and "[a]ny such reasons shall be
considered." Thus, CBP avers the DEP made a "purely technical decision
A-0951-24
9
devoid of any expert opinion or analysis of the application itself," making its
final decision "incomplete, injurious to the interests of justice and due process,
and contrary to established practice and precedent."
CBP further argues the Commissioner erred in not considering
Woodbridge's reasons for withholding consent to its application, given the
MCUA's denial rested "solely" upon its refusal to consent. It asserts the
Commissioner failed to address the ALJ's interpretation of the regulations and
the DEP's obligations, "which placed Woodbridge at the center of the case,"
and instead relied on "a literal, restrictive, and inflexible" interpretation,
contrary to federal case law, the administrative code, and the DEP's own
documents.
CBP claims, pursuant to the operational definitions in N.J.A.C. 7:14A -
22.1, both Woodbridge and the MCUA can be categorized as "an affected
sewerage entity and a treatment works owner." Thus, it contends a full and
fair review of its application should have included an investigation into "the
relevance and validity" of the reason Woodbridge, as "an affected municipality
or sewerage authority," failed to consent, which, in turn, caused the MCUA to
deny consent. CBP asserts the DEP ignored its duty to engage in necessary
fact-finding, it failed to consider all relevant evidence, dismissed the MCUA's
A-0951-24
10
and Woodbridge's reasons for not consenting as immaterial, and declined to
review its application on the merits.
Relying on Saginaw Broadcasting Co. v. Federal Communications
Commission, 96 F.2d 554 (D.C. Cir. 1938), CBP asserts the Commissioner
ignored his obligation to act as a factfinder, as he refused to address facts in
the record and further investigate the matter to reach a just conclusion. It
contends the DEP's failure to consider all facts in the record permitted
Woodbridge to exceed its authority as a municipality by controlling CBP's
access to a sewer line. CBP contends the DEP's "strict interpretation of the
regulations . . . violated the established doctrine[s] of flexibility and fairness"
and resulted in a "rigid" final agency decision in violation of N.J.A.C. 1:1 -
1.3(a), and the DEP failed to use its equitable powers to approve CBP's
application.
CBP claims Woodbridge changed its position several times, which alone
warrants the DEP's consideration in evaluating its TWA application.
Moreover, it argues the DEP considered immaterial facts and "interject[ed]
itself into the irrelevant intermunicipal dispute" between Woodbridge and
Carteret, allowing Woodbridge to "become the sole arbiter of administrative
control over access to public works," contrary to its regulatory obligations. It
contends the DEP failed in its obligation to coordinate between municipalities
A-0951-24
11
and identify alternatives to maximize sewer capacity by refusing to get
involved in the dispute. CBP asserts N.J.A.C. 7:14A-22.8(a)(3)(v)(5) was
written to allow the DEP to review the reasons for lack of consent and to
determine whether to issue a permit even when consent is withheld. It
emphasizes the regulation's plain language includes options of approving or
denying an application following a "review [of] the reasons for the lack of
consent or denial" by the "affected municipality or sewerage authority" insofar
as "such reasons shall be considered by the [DEP] in determining whether to
issue a [TWA]."
CBP further argues N.J.A.C. 7:14A-22.8(a) is ambiguous about what
happens when the receiving treatment plant owner refuses to provide consent
for a TWA application, emphasizing it does not expressly prohibit the DEP
from issuing a TWA when a treatment plant owner or conveyance system
operator withholds consent. CBP asserts the regulation's plain text does not
support the DEP's position it must deny an application as administratively
incomplete in such cases. It further maintains the DEP has the authority to
review the reasons for lack of consent and issue a TWA if those reasons are
not justified. CBP claims Carteret has already paid for the necessary sewer
capacity, and Woodbridge's refusal to provide consent is rooted in an unrelated
political dispute.
A-0951-24
12
Review of an administrative agency's final determination is limited. In
re Carter, 191 N.J. 474, 482 (2007). We will uphold an agency's decision
"unless there is a clear showing that it is arbitrary, capricious, or unreasonable,
or that it lacks fair support in the record." Stein v. Dep't of L. & Pub. Safety,
458 N.J. Super. 91, 99 (App. Div. 2019) (quoting J.B. v. N.J. State Parole Bd.,
229 N.J. 21, 43 (2017)). In evaluating whether the decision was arbitrary,
capricious, or unreasonable, we examine:
(1) whether the agency's action violates express or
implied legislative policies, that is, did the agency
follow the law; (2) whether the record contains
substantial evidence to support the findings on which
the agency based its action; and (3) whether in
applying the legislative policies to the facts, the
agency clearly erred in reaching a conclusion that
could not reasonably have been made on a showing of
the relevant factors.
[In re Stallworth, 208 N.J. 182, 194 (2011) (quoting In
re Carter, 191 N.J. at 482-83).]
Courts are "obliged to give due deference to the view of those charged
with the responsibility of implementing legislative programs." In re
Reallocation of Prob. Officer, 441 N.J. Super. 434, 444 (App. Div. 2015)
(quoting In re N.J. Pinelands Comm'n Resol., 356 N.J. Super. 363, 372 (App.
Div. 2003)). Thus, we "give substantial deference to an agency's interpretation
of the statute it is charged with carrying out, as well as to the interpretation the
agency itself gives to its own regulations." Fedor v. Nissan of N. Am., Inc.,
A-0951-24
13
432 N.J. Super. 303, 320 (App. Div. 2013). Deference is due "because 'a state
agency brings experience and specialized knowledge to its task of
administering and regulating a legislative enactment within its field of
expertise.'" US Bank, N.A. v. Hough, 210 N.J. 187, 200 (2012) (quoting In re
Election L. Enf't Comm'n Advisory Op., 201 N.J. 254, 262 (2010)).
Nevertheless, courts will not defer to an agency's interpretation of its
own regulations if that interpretation is "plainly unreasonable." Ibid. (quoting
In re Election, 201 N.J. at 262). If a court "is satisfied after its review that the
evidence and the inferences to be drawn therefrom support the agency head's
decision, then it must affirm even if the court feels that it would have reached
a different result." Campbell v. N.J. Racing Comm'n, 169 N.J. 579, 587
(2001) (quoting Clowes v. Terminix Int'l, Inc., 109 N.J. 575, 588 (1988)).
"Accordingly, it is 'a rare day when an agency cannot give a plausible
interpretation for one of its own regulations.'" In re Eastwick Coll. LPN-to-
RN Bridge Program, 225 N.J. 533, 542 (2016) (quoting US Bank, 210 N.J. at
203-04).
On a de novo review of an agency's interpretation of one of its
regulations, "[w]e interpret a regulation in the same manner that we would
interpret a statute." Ibid. (alteration in original) (quoting US Bank, 210 N.J. at
199). Our "paramount goal" is to determine the intent of the drafter, which can
A-0951-24
14
generally be "found in the actual language of the enactment." US Bank, 210
N.J. at 199. We will not "rearrange the wording of the regulation, if it is
otherwise unambiguous, or engage in conjecture that will subvert its plain
meaning." Ibid. "Should the plain language analysis yield more than one
plausible interpretation of the regulation, a reviewing court may consider
extrinsic sources, including 'the long-standing meaning ascribed to the
language by the agency charged with its enforcement.'" In re Eastwick, 225
N.J. at 542 (quoting Bedford v. Riello, 195 N.J. 210, 222 (2008)). "If,
however, the regulation's 'language is clear, then the interpretative process will
end without resort to extrinsic sources.'" Ibid. (quoting Bedford, 195 N.J. at
222). "In short, we must construe the regulation as written." US Bank, 210
N.J. at 199.
Summary decisions under N.J.A.C. 1:1-12.5 are governed by
"substantially the same [standard] as that governing a motion under Rule 4:46-
2 for summary judgment in civil litigation." L.A. v. Bd. of Educ. of Trenton,
221 N.J. 192, 203 (2015) (quoting Contini v. Bd. of Educ. of Newark, 286 N.J.
Super. 106, 121 (App. Div. 1995)). We must determine "whether the
competent evidential materials presented, when viewed in the light most
favorable to the non-moving party in consideration of the applicable
evidentiary standard, are sufficient to permit a rational factfinder to resolve the
A-0951-24
15
alleged disputed issue in favor of the non-moving party." Brill v. Guardian
Life Ins. Co. of Am., 142 N.J. 520, 523 (1995).
N.J.A.C. 7:14A-22.8(a), in pertinent part, provides:
Persons who propose to build, install, or modify
treatment works that require the [DEP]'s approval
pursuant to this subchapter, shall submit the following
information and documents in the manner prescribed
in this subchapter:
....
3. A resolution and/or written
statement of consent from the affected
municipality, sewerage authority, owner
of the receiving treatment plant,
owner/operator of the wastewater
conveyance system into which the project
will directly connect, and district sludge
management lead planning agency (if
applicable, see (a)(3)(ii) below) or
completion of the [DEP]'s [Consent
Form].
....
iii. Written statements of
consent from the affected
sewerage authority shall
contain a certification
concerning the plant's
compliance with applicable
NJPDES permit requirements.
iv. A written statement of
consent from the
owner/operator of the
conveyance system must
A-0951-24
16
certify that the conveyance
system has adequate
conveyance capacity as
defined in N.J.A.C. 7:14A-
1.2, to convey the additional
flow.
[(Emphases added) (citations reformatted).]
N.J.A.C. 7:14A-22.8(a)(3)(v), in turn, states:
If an applicant is unable to obtain the required written
statement of consent, then the applicant may choose to
follow the procedures stated in (a)(3)(v)(1) through
(5) below. . . .
(1) The affected sewerage authority or
municipality shall submit a written
statement of consent to the application or
submit written comments to the [DEP]
within [sixty] days of the request for
consent. Prior to the expiration of the
[sixty-]day period to respond [to] a
request for a written statement of consent,
the municipality or sew[er]age authority
may request a [thirty-]day extension for
review of a request for consent.
(2) Any document issued by a sewerage
authority or municipality which is
tentative, preliminary, or conditional
approval shall not be considered a
statement of consent.
(3) When the affected sewerage
authority or municipality does not consent
to a project, it shall state all reasons for
rejection or disapproval in a resolution
and send a certified copy of the resolution
to the [DEP].
A-0951-24
17
(4) When the affected municipality or
sewerage authority expressly denies a
request for a written statement of consent
for a project, the permit application may
be determined by the [DEP] to be
incomplete for processing; or in the
alternative, the [DEP] may review the
reasons for denial. Any such reasons shall
be considered by the [DEP] in
determining whether to issue a [TWA] or
sewer connection approval in accordance
with this subchapter.
(5) When the affected municipality or
sewerage authority does not issue either a
written statement of consent or a denial of
the request for consent, the [DEP], upon
receipt of proof that the applicant has
delivered to the affected agency a written
request for a written statement of consent,
shall review the reasons for the lack of
consent or denial, if known on the basis of
reasonably reliable information. Any
such reasons shall be considered by the
[DEP] in determining whether to issue a
[TWA] or sewer connection approval in
accordance with this subchapter.
[(Emphases added) (citation reformatted).]
The Commissioner's interpretation of N.J.A.C. 7:14A-22.8(a) in the
DEP's final agency decision was reasonable and entitled to deference. See US
Bank, 210 N.J. at 200. His reading of the plain language of the regulation
logically differentiated between an "affected municipality or sewerage
authority" and a "receiving wastewater treatment plant" in finding N.J.A.C.
A-0951-24
18
7:14A-22.8(a)(3)(v) does not provide an "alternate path" for approval of TWA
applications lacking the owner of the receiving wastewater treatment plant's
consent. N.J.A.C. 7:14A-22.8(a)(3)(v)(5) expressly states it applies when an
"affected municipality or sewerage authority does not issue either a written
statement of consent or a denial of the request for consent," but it does not
mention the receiving wastewater treatment plant's owner. As the
Commissioner found, the receiving wastewater treatment plant is not expressly
mentioned anywhere in N.J.A.C. 7:14A-22.8(a)(3)(v)(1) to (5). Furthermore,
the plain language of N.J.A.C. 7:14A-22.8(a)(3) requires consent from the
owner of the receiving wastewater treatment plant—here, the MCUA. In the
absence of such consent, the DEP sensibly interpreted the regulations in
concluding it was not authorized to review CBP's TWA application.
"If a regulation includes particular language in one section but omits it
in another, 'it is generally presumed that [the state agency] acts intentionally
and purposely in the disparate inclusion or exclusion.'" Est. of Campagna v.
Pleasant Point Props., LLC, 464 N.J. Super. 153, 176 (App. Div. 2020)
(alteration in original) (quoting N.J. Div. of Child Prot. & Permanency v.
R.L.M., 236 N.J. 123, 148 (2018)) (finding regulations, which made a
prospective owner or operator's criminal history a basis to deny licensure, but
did not contain any comparable provisions about the significance of a
A-0951-24
19
prospective resident's criminal history, signified there was no codified duty to
perform criminal background checks of prospective residents). As the
Commissioner reasoned, had the DEP intended to carve out an exception to
obtaining the receiving wastewater treatment plant's consent, as it did for an
"affected municipality or sewerage authority," it would have expressly stated
so in N.J.A.C. 7:14A-22.8(a)(3)(v)(5). See J.H. v. R & M Tagliareni, LLC,
239 N.J. 198, 215 (2019) ("Had the [Department of Community Affairs]
determined that radiators required covering, the agency possessed the
knowledge and expertise to include them in N.J.A.C. 5:10-14.3(d)'s language,
and [the agency] could have very easily done so."). Accordingly, we are
unpersuaded by CBP's arguments and conclude the regulation's plain language
and structure support the DEP's interpretation it did not have the authority to
review the reasoning behind the MCUA's or Woodbridge's lack of consent.
The Commissioner's finding the DEP intended to mandate the owner of a
receiving wastewater treatment plant's consent based on the regulatory history
was reasonable. In the DEP's January 5, 2009 response to a comment, it
explained the agency's purpose in requiring the owner of the receiving
treatment plant's consent:
The TWA program does not allocate flow capacity for
projects subject to TWA. This is the responsibility of
the owner of the receiving wastewater treatment plant
and owner/operator of the wastewater conveyance
A-0951-24
20
system into which the project will directly connect.
Subject to meeting all other administrative and
technical requirements, TWAs can be processed for
approval, as long as the owner of the receiving
wastewater treatment plant and owner/operator of the
wastewater conveyance system into which the project
will directly connect consent to the additional flow
anticipated from the project. Such consent is one of
the TWA administrative requirements found in
N.J.A.C. 7:14A-22.8(a)(3).
[41 N.J.R. 142(a), 171-72 (Jan. 5, 2009) (response to
comment 195) (emphases added) (citation
reformatted).]
Accordingly, the regulatory history expressly states the owner of the
receiving wastewater treatment plant's consent is an "administrative
requirement[]," implying the DEP cannot approve a TWA application lacking
such consent. See ibid. The Commissioner's interpretation is supported by the
TWA program's purpose to place the responsibility on "the sewerage authority
and/or treatment plant owner/operator to implement timely corrective actions
and to ensure that additional connections to the treatment works do not result
in [violations of their DEP permits or the overflow of conveyance systems]."
N.J.A.C. 7:14A-22.1(b).
Given it was undisputed the MCUA did not sign the Consent Form
attached to CBP's application, the DEP was not required to engage in
additional fact-finding or review the MCUA's or Woodbridge's reasoning for
their withholding consent. Accordingly, we affirm the DEP's November 18,
A-0951-24
21
2024 final agency decision and hold it reasonably interpreted its regulations to
require the consent of the owner of the receiving wastewater treatment plant as
a prerequisite to it considering a TWA application. Its findings were not
arbitrary, capricious, or unreasonable, and we discern no basis to disturb its
decision.
To the extent we have not specifically addressed any remaining
arguments CBP raised, we conclude they lack sufficient merit to warrant
discussion in a written opinion. R. 2:11-3(e)(1)(E).
Affirmed.
A-0951-24
22