Olurotimi Phillips and Jacqueline Phillips v. Lyons Heritage Tampa, L L C
CourtDistrict Court of Appeal of Florida
Date FiledJune 17, 2022
Docket2D21-0816
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
DISTRICT COURT OF APPEAL OF FLORIDA
SECOND DISTRICT
OLUROTIMI PHILLIPS and
JACQUELINE PHILLIPS,
Appellants,
v.
LYONS HERITAGE TAMPA, LLC,
Appellee.
No. 2D21-816
June 17, 2022
BY ORDER OF THE COURT:
Upon consideration of Appellants Olurotimi and Jacqueline
Phillips's motion for the issuance of a written opinion pursuant to
Florida Rule of Appellate Procedure 9.330(a)(2)(D), filed on
December 6, 2021,
IT IS ORDERED that the motion for the issuance of a written
opinion is granted to the extent that the opinion dated December 3,
2021, is withdrawn and the attached opinion is substituted
therefor. Appellee Lyons Heritage, LLC's opposition to Appellants'
motion is noted.
I HEREBY CERTIFY THE FOREGOING IS A
TRUE COPY OF THE ORIGINAL COURT ORDER.
MARY ELIZABETH KUENZEL, CLERK
2
DISTRICT COURT OF APPEAL OF FLORIDA
SECOND DISTRICT
OLUROTIMI PHILLIPS and
JACQUELINE PHILLIPS,
Appellants,
v.
LYONS HERITAGE TAMPA, LLC,
Appellee.
No. 2D21-816
June 17, 2022
Appeal from the Circuit Court for Pinellas County; George M.
Jirotka, Judge.
James C. Patterson of Harder Law Group, Lutz, for Appellants.
Chris K. Ritchie and J. Michael Grimley, Jr., of Galloway, Johnson,
Tompkins, Burr & Smith, PLC, Pensacola; and Adam Bild and Tim
Brown of Bild Law, Lutz, for Appellee Lyons Heritage Tampa, LLC.
ROTHSTEIN-YOUAKIM, Judge.
Olurotimi and Jacqueline Phillips appeal the trial court's order
granting Lyons Heritage Tampa, LLC's motion to compel arbitration.
Because the racial discrimination claims in the Phillipses' fifth
amended complaint are subject to arbitration pursuant to the
contract between the parties ("the Building Agreement"), we affirm.
Background
The Phillipses contracted with Lyons Heritage to build their
home. The Building Agreement included a dispute resolution
clause ("the arbitration clause"), which provided, in pertinent part:
16. Resolving Disputes: Controversies, claims or
disputes arising out of, from or relating to this Agreement
(including any claims under the Limited Warranty), shall
be settled by binding arbitration in accordance with the
Construction Industry Arbitration Rules of the American
Arbitration Association ("AAA") and the Federal
Arbitration Act (Title 9 of United States Code), using a
single arbitrator and judgment rendered by the arbitrator
may be confirmed, entered and enforced by the Circuit
Court of the Thirteenth Judicial Circuit, Hillsborough
County, Florida, the court having exclusive jurisdiction.
Each party shall bear its own costs and legal fees for the
arbitration. Exclusive venue for such arbitration
proceedings shall be in Tampa, Florida. Florida law shall
apply when construing this Agreement and in connection
with the resolution of any dispute between the parties.
A dispute did, in fact, arise, and the Phillipses sued Lyons
Heritage in state court, alleging violations of §§ 1981 (providing that
"[a]ll persons" have "the same right . . . to make and enforce
contracts. . . as is enjoyed by white citizens") and 1982 (providing
that "[a]ll citizens" have the "right . . . to inherit, purchase, lease,
2
sell, hold, and convey real and personal property") of Title 42 of the
United States Code. In Count I of the operative fifth amended
complaint, the Phillipses sought damages for Lyons Heritage's
allegedly racially motivated refusal to complete construction of the
home. The Phillipses alleged:
The delay of over three and one-half years in the home
construction suffered by the Phillips[es] cannot be
entirely construction related and must, therefore, be
attributed at least, in no small part, to the fact that
Lyons [Heritage] simply did not wish to finish the
Phillips[es]' home and have a mixed race couple move
into the area.
The complaint included general allegations that one of Lyons
Heritage's project managers had told the Phillipses, "We do not like
doing business with people like you . . . you people just want
handouts" and that Lyons Heritage's president had stated that the
Phillipses were not like the company's "usual customers."
In Count II, the Phillipses alleged that racial discrimination
also motivated Lyons Heritage to take certain measures to block the
Phillipses from accessing their property. The Phillipses alleged that
they had initiated arbitration with respect to the denial of access to
the property and that an arbitrator had ordered Lyons Heritage to
return access to the Phillipses. The Phillipses alleged that by the
3
time Lyons Heritage had blocked their access to their property, they
had already paid $500,000 pursuant to the Building Agreement.
They also alleged that Lyons Heritage had continued to block their
access to the property in violation of an arbitration award.
After unsuccessfully moving to dismiss the complaint, Lyons
Heritage moved for an extension of time to file an answer, which the
trial court granted. Rather than filing an answer, however, Lyons
Heritage moved to compel arbitration, arguing that the Phillipses'
racial discrimination claims were subject to arbitration pursuant to
the arbitration clause in the Building Agreement. The trial court
granted the motion, and the Phillipses timely appealed the order.
Analysis
We review de novo the order compelling arbitration. Stacy
David, Inc. v. Consuegra, 845 So. 2d 303, 306 (Fla. 2d DCA 2003).
"In determining whether a dispute is subject to arbitration, courts
consider at least three issues: (1) whether a valid written
agreement to arbitrate exists; (2) whether an arbitrable issue exists;
and (3) whether the right to arbitration was waived." Id. (citing
Seifert v. U.S. Home Corp., 750 So. 2d 633, 636 (Fla. 1999)).
4
The Phillipses argue that no valid written agreement to
arbitrate exists because a requirement that they arbitrate their
claims would violate public policy. Specifically, they argue that it
would improperly require them to forfeit their rights to (1) a jury
trial, (2) punitive damages, and (3) attorney's fees and costs.
As our sister court has observed, however, "All arbitration
agreements waive the parties' right to a jury trial as a means of
dispute resolution." See Hobby Lobby Stores, Inc. v. Cole, 287 So.
3d 1272, 1276 (Fla. 5th DCA 2020) (citing Fi-Evergreen Woods, LLC
v. Est. of Robinson, 172 So. 3d 493, 497 (Fla. 5th DCA 2015)). That
the right to a jury trial in this case arises out of federal law renders
it no less subject to knowing and voluntary waiver, and there is no
dispute that the Phillipses knowingly and voluntarily agreed to
arbitrate all disputes arising out of or relating to the Building
Agreement.
Moreover, the Phillipses will not forfeit any rights to punitive
damages and attorney's fees and costs in arbitration. As an initial
matter, the fifth amended complaint does not make any claim for
punitive damages, and in any event, the Phillipses do not point to
any provision in the arbitration clause that limits their right to such
5
a recovery. Instead, their argument that they will forfeit the right to
recover punitive damages appears to be based solely on an
assumption that resolving their dispute through arbitration will
somehow eliminate that right. But when a party agrees to arbitrate
a statutory claim, it "does not forgo the substantive rights afforded
by the statute; it only submits to their resolution in an arbitral,
rather than a judicial, forum." Gilmer v. Interstate/Johnson Lane
Corp., 500 U.S. 20, 26 (1991) (quoting Mitsubishi Motors Corp. v.
Soler Chrysler-Plymouth, Inc., 473 U.S. 614, 628 (1985)). To the
extent that the Phillipses may be entitled to punitive damages
against Lyons Heritage, nothing would prevent an arbitrator from
awarding such relief. See id.; see also § 682.11(1), Fla. Stat. (2021)
("An arbitrator may award punitive damages or other exemplary
relief if such an award is authorized by law in a civil action
involving the same claim and the evidence produced at the hearing
justifies the award under the legal standards otherwise applicable
to the claim.").
The Phillipses argue further that the requirement that each
party bear its own costs and legal fees for the arbitration is in
derogation of their statutory right to prevailing party fees in their §§
6
1981 and 1982 actions. See 42 U.S.C. § 1988(b) (2022) (granting
courts discretion to award a reasonable attorney's fee to a party
that prevails in any action seeking to enforce §§ 1981 and 1982).
And Lyons Heritage correctly acknowledges that a fees provision
that eliminates the statutory right to prevailing party attorney's fees
violates public policy. See Hochbaum v. Palm Garden of Winter
Haven, LLC, 201 So. 3d 218, 221 (Fla. 2d DCA 2016) ("[A]n
arbitration agreement that limits the statutory remedy of attorneys'
fees violates public policy."); see also Flyer Printing Co. v. Hill, 805
So. 2d 829, 833 (Fla. 2d DCA 2001) (affirming the circuit court's
refusal to compel arbitration pursuant to the parties' agreement
because the arbitration agreement required the appellee to bear half
the fees and costs associated with the arbitration in contravention
of her statutory right to seek a full award of fees and costs under
certain civil rights statutes).
Lyons Heritage argues, however, that the fee provision is
severable from the rest of the arbitration clause and, therefore,
requiring arbitration of the claims pursuant to the arbitration
clause would not violate public policy. We agree. First, the
Building Agreement as a whole includes a severability clause, which
7
states: "Should any term or provision of this document be ruled
invalid or unenforceable by an arbitrator or a court of competent
jurisdiction, the remainder of this document shall nonetheless
stand in full force and effect."1
Moreover, both the Building Agreement as a whole and the
arbitration clause in particular specifically provide that Florida law
applies. And under Florida law, an invalid or unenforceable
provision is severable from an agreement so long as the provision
does not strike at the heart, or the essence, of the agreement. See
Shotts v. OP Winter Haven, Inc., 86 So. 3d 456, 459 (Fla. 2011).
Here, the attorney's fees and costs provision is severable from the
rest of the arbitration agreement because it does not go to the
essence of that agreement. See 4927 Voorhees Rd., LLC v.
Tesoriero, 291 So. 3d 668, 671 (Fla. 2d DCA 2020) (rejecting the
plaintiff's argument that the parties' arbitration agreement violated
public policy because its fees and costs provision eliminated the
plaintiff's statutory right to prevailing party fees and holding that
1 The severability clause is included in the "Mold and Chemical
Disclosure and Disclaimer," which by its terms has been "appended
to and made a part of the Building Agreement or Home Purchase
Agreement."
8
the provision was severable because it did not go to the essence of
the arbitration agreement, which was the "selection of a forum in
which to resolve disputes as an alternative to litigation in court"),
review denied, No. SC20-528, 2021 WL 50180 (Fla. Jan. 6, 2021);
see also Hochbaum, 201 So. 3d at 223 ("Here, the offending
provision deals only with attorneys' fees. The provision does not
require the arbitration to be conducted in accordance with certain
rules, and it does not limit the compensatory or punitive damages
that Hochbaum may recover in arbitration."). In addition, Florida
law permits arbitrators to grant attorney's fees when authorized by
law. See § 682.11(2) ("An arbitrator may award reasonable attorney
fees and other reasonable expenses of arbitration if such an award
is authorized by law in a civil action involving the same claim or by
the agreement of the parties to the arbitration proceeding.").
We therefore conclude that the Building Agreement includes a
valid written agreement to arbitrate because the offending provision
that eliminates the Phillipses' statutory rights to prevailing party
fees is severable from the rest of the arbitration clause. Because
that provision is severable, the trial court on remand shall strike it
from the arbitration clause. See Hochbaum, 201 So. 3d at 223
9
(affirming order compelling arbitration but remanding with
instructions to strike the provision that requires the parties to bear
their own attorney's fees because such a provision violated the
statutory right to prevailing party fees under section 415.1111,
Florida Statutes).
Next, the Phillipses argue that an arbitrable issue does not
exist because their §§ 1981 and 1982 claims fall outside the scope
of the arbitration clause. That clause, however, extends to any
disputes "arising out of, from, or relating to [the Building]
Agreement." (Emphasis added.) The words "relating to" indicate
that the clause is intended to be broad in scope and "include those
claims that are described as having a 'significant relationship' to the
contract—regardless of whether the claim is founded in tort or
contract law." See Jackson v. Shakespeare Found., Inc., 108 So. 3d
587, 593 (Fla. 2013) (citing Seifert, 750 So. 2d at 637–38). A claim
has a significant relationship to the contract if it "presents
circumstances in which the resolution of the disputed issue
requires either reference to, or construction of, a portion of the
contract." Id. (citing Seifert, 750 So. 2d at 638).
10
The Phillipses argue that Count I does not present an
arbitrable issue because a racial discrimination claim has nothing
to do with the construction of their home. But the label assigned to
the claim does not matter; what matters is the claim's relation to
the contract. See Seifert, 750 So. 2d at 637–38. In Count I, the
Phillipses alleged that Lyons Heritage did not complete construction
because it did not want a "mixed-race couple to live in the area."
Count I also included allegations that Lyons Heritage's construction
delays were motivated by racial discrimination.
We agree with the trial court's conclusion that the claim in
Count I relates to the contract, i.e., the Building Agreement.
Because the conduct underlying the claim is inextricably linked to
the performance of the Building Agreement, resolution of the claim
necessarily requires reference to it. Although the Phillipses allege
that various Lyons Heritage employees made racially insensitive
remarks—the resolution of which, standing alone, would not
require reference to the Building Agreement—their claim is
grounded upon allegations that Lyons Heritage's construction
delays and its failure to complete construction were motivated by
11
racial discrimination. And those allegations raise issues that
require reference to and construction of the Building Agreement.
Indeed, the very issue of whether a construction delay even
occurred requires reference to the Building Agreement. That
agreement, for example, provides that the builder will use its best
efforts to complete construction of the custom home within 330
days from the start of construction. It also envisions some
construction delays if certain events occur—for example, if the
buyer requests any changes to the construction plan, such as
changing the placement of a door or a window, the agreement
provides for a one-month construction delay. The Building
Agreement also includes a timeline of completion of construction
that is based upon a payment schedule. It states, for example, that
a payment of $76,767.30 is due once substantial completion of the
foundation is completed. It also states, "Buyer acknowledges that
Builder needs to be paid on time and Buyer agrees that if any
payment is not made to Builder within the times provided above,
Builder shall be entitled to stop all work until payment, including
interest, is made." (Emphases added.) In sum, the Building
Agreement envisioned that construction delays would result from
12
the occurrence of certain circumstances, and reference to the
contractual terms describing those circumstances would be
necessary in any claim that is premised upon a construction delay.
Our decision in Kaplan v. Kimball Hill Homes Florida, Inc., 915
So. 2d 755 (Fla. 2d DCA 2005), supports our conclusion that the
claim in Count I falls within the scope of the Building Agreement's
arbitration clause. In Kaplan, we upheld the trial court's
conclusion that the Kaplans' claims for fraud and fraudulent
inducement relating to a home construction contract were subject
to arbitration. Id. at 760. Just as in this case, the parties' home
construction contract in Kaplan included a broad arbitration clause
that required arbitration of any disputes "relating to" the contract.
Id. at 759. The fraudulent inducement claim relied upon
allegations that the home builder had made misrepresentations
about its ability to complete construction on time. Id. at 757. The
fraud claim included allegations that the home builder had failed to
disclose facts concerning the water runoff and drainage from an
adjacent property and the obstruction of a golf course view from the
home. Id. at 758.
13
In concluding that the trial court correctly ordered arbitration
on the fraud and fraudulent inducement claims, we observed that
"[t]he very issues which gave rise to the dispute are specifically
mentioned in the contract," id. at 759, and we recited the provisions
of the home construction contract that dealt with each issue, id. at
759–60. Because resolution of the fraud and fraudulent
inducement claims required reference to the home construction
contract, we concluded that the claims were within the scope of the
arbitration clause. Id. Based on that same reasoning, we also
concluded that the trial court had erred in refusing to compel
arbitration of a claim of intentional infliction of emotional distress
that was premised on the same underlying conduct. Id. at 760.
Just as in Kaplan, the claim here is subject to arbitration because
resolution of those claims requires reference to the contract.
The Phillipses argue that Seifert mandates reversal, but Seifert
is inapposite. In that case, the supreme court concluded that an
arbitration clause in an agreement for the sale of a home did not
require arbitration of a wrongful death claim. See Seifert, 750 So.
2d at 642. The incident underlying the claim occurred after the
Seiferts moved into a home that U.S. Home Corporation had
14
constructed pursuant to the sales agreement between them. Id. at
635. Mr. Seifert died following an incident in which carbon
monoxide emissions from a car in the garage of the home were
distributed into the house. Id. As the personal representative of
his estate, Mrs. Seifert sued U.S. Home for negligence. Id. In
concluding that the wrongful death claim was not subject to
arbitration, the supreme court reasoned that the resolution of the
claim did not require reference to the sales agreement. Id. at 642.
It reasoned that the claim did not have "a 'significant relationship'
to the contract because none of the allegations in the complaint
refer to or mention the sales agreement between the Seiferts and
U.S. Home." Id. at 642.
This case is distinguishable from Seifert because the claim in
Count I requires reference to the Building Agreement. The claim is
that Lyons Heritage's performance of the Building Agreement—its
construction delays and its failure to complete construction
altogether—was motivated by racial discrimination rather than by
the occurrence of other circumstances described in the Building
Agreement. Therefore, the resolution of the claim inevitably
requires reference to the Building Agreement. Indeed, that
15
resolution of the claim requires reference to the Building Agreement
is further supported by the complaint's repeated references to it.
For the same reason, the trial court correctly compelled
arbitration of the Phillipses' § 1982 claim in Count II. Resolution of
the claim likewise requires reference to the Building Agreement,
including its provisions governing the payment schedule and the
completion of construction timeline. And again, that this claim is
arbitrable is further supported by the Phillipses' repeated references
to the Building Agreement in its complaint as well as to the
previous arbitration award entered in connection with this issue.
Finally, the Phillipses argue that even if their claims are
arbitrable, Lyons Heritage waived its right to arbitrate by requesting
an extension of time to file an answer to the complaint. "It is well
settled that a party waives its right to arbitration by inconsistent
conduct." Balboa Ins. Co. v. W.G. Mills, Inc., 403 So. 2d 1149, 1150
(Fla. 2d DCA 1981) (citing Seville Condo. #1, Inc. v. Clearwater Dev.
Corp., 340 So. 2d 1243, 1245 (Fla. 2d DCA 1976)); see also Gettles
v. Com. Bank at Winter Park, 276 So. 2d 837, 839–40 (Fla. 4th DCA
1973) (holding that a party had waived its contractual right to
arbitration by filing suit and by moving to dismiss a counterclaim
16
before moving to compel arbitration). But although Lyons
Heritage's motion for extension of time to file an answer delayed its
subsequent demand for arbitration, its filing of the motion was not
inconsistent with that demand. See Audio Visual Innovations, Inc. v.
Spiessbach, 119 So. 3d 522, 527 (Fla. 2d DCA 2013) ("Whether
there is a '[w]aiver of the right [to arbitrate] does not necessarily
depend on the timing of the motion to compel arbitration, but
rather on the prior taking of an inconsistent position by the party
[demanding arbitration].' " (quoting Miller & Solomon Gen.
Contractors, Inc. v. Brennan's Glass Co., 824 So. 2d 288, 290 (Fla.
4th DCA 2002))). The request for an extension to file an answer
does not constitute a waiver "because it 'is not a substantive attack
on the merits.' " Id. (quoting Miller & Solomon Gen. Contractors, Inc.,
824 So. 2d at 291). And because Lyons Heritage did not otherwise
take any action inconsistent with its right to arbitrate, it did not
waive such right.
Conclusion
Because the claims alleged in Counts I and II of the Phillipses'
fifth amended complaint "relate to" the Building Agreement, they
fall within the scope of the valid, broad arbitration clause included
17
in that agreement. Moreover, requiring arbitration of those claims
will not require the Phillipses to forego any substantive rights to
which they are statutorily entitled. Although the provision
requiring the parties to bear their own attorney's fees offends public
policy because it contravenes the Phillipses' statutory right to
prevailing party fees, the provision is severable. Accordingly, we
affirm the order compelling arbitration but remand with
instructions to strike the attorneys' fees provision from the
arbitration clause in the Building Agreement.
Affirmed; remanded with instructions.
NORTHCUTT and VILLANTI, JJ., Concur.
Opinion subject to revision prior to official publication.
18