State ex rel. Bristolville 25 Developer, L.L.C. v. Lordstown
CourtOhio Supreme Court
Date FiledOctober 20, 2026
Docket2025-1497
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
[Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as State
ex rel. Bristolville 25 Developer, L.L.C. v. Lordstown, Slip Opinion No. 2026-Ohio-4073.]
NOTICE
This slip opinion is subject to formal revision before it is published in an
advance sheet of the Ohio Official Reports. Readers are requested to
promptly notify the Reporter of Decisions, Supreme Court of Ohio, 65
South Front Street, Columbus, Ohio 43215, of any typographical or other
formal errors in the opinion, in order that corrections may be made before
the opinion is published.
SLIP OPINION NO. 2026-OHIO-4073
THE STATE EX REL . BRISTOLVILLE 25 DEVELOPER, L.L.C., ET AL. v. T HE
VILLAGE OF LORDSTOWN ET AL .
[Until this opinion appears in the Ohio Official Reports advance sheets, it
may be cited as State ex rel. Bristolville 25 Developer, L.L.C. v. Lordstown,
Slip Opinion No. 2026-Ohio-4073.]
Mandamus—Village lacks clear legal duty to proceed with review of data-center
developer’s site plan because it is subject to ordinance placing a temporary
moratorium on issuing of any new permits, as well as receipt and processing
of permit applications, for proposed data centers—Relators have not shown
a clear legal right to have developer’s site plan reviewed under
premoratorium zoning ordinance—Gibson v. Oberlin and Fairmount Ctr.
Co. v. Arnold distinguished—Writ denied.
(No. 2025-1497—Submitted August 4, 2026—Decided October 20, 2026.)
IN MANDAMUS.
__________________
SUPREME COURT OF OHIO
The per curiam opinion below was joined by KENNEDY, C.J., and FISCHER,
DEWINE, BRUNNER, DETERS, HAWKINS, and SHANAHAN, JJ.
Per Curiam.
{¶ 1} Relators, Bristolville 25 Developer, L.L.C. (“Bristolville”) and
BHGH Properties, L.L.C., seek a writ of mandamus to compel respondents, the
Village of Lordstown and its planning-and-zoning administrator, Kellie D. Bordner
(collectively, “the village”), to perform duties under the Lordstown Codified
Ordinances in effect on October 20, 2025. We previously granted an alternative
writ. 2025-Ohio-5682. In addition to their evidence and merit briefing, relators
have filed a motion for leave to file rebuttal evidence and a motion asking us to take
judicial notice of actions taken by the Lordstown Village Council since the merit
briefing concluded in this case.
{¶ 2} We deny relators’ motion for leave to file rebuttal evidence and grant
their motion for judicial notice. And because relators have not shown a clear legal
right to the relief they seek in this case, we deny the writ.
I. FACTUAL AND PROCEDURAL BACKGROUND
{¶ 3} Bristolville acquires and develops real property for construction of
large-scale data centers throughout the United States. In February 2025,
Bristolville agreed to purchase from BHGH Properties a parcel of real property
located in Lordstown on which Bristolville seeks to construct a data center. The
property is zoned for industrial use.
A. Site-Plan Review under the Lordstown Ordinance and Overview Process
{¶ 4} Before an applicant may request a zoning permit for new construction
in Lordstown, local law requires projects to undergo a “Site Plan Review” overseen
by Lordstown’s Planning and Zoning Office. Chapter 1115 of the Lordstown
Codified Ordinances sets forth the site-plan-review process. Subject to exceptions
2
January Term, 2026
not applicable here, “[n]o permit for the construction . . . of any building shall be
given . . . except in conformity with a site plan approved by the Planning
Commission.” Lordstown Cod.Ord. 1115.02, available at Village of Lordstown,
Codified Ordinances of Lordstown, OH,
https://codelibrary.amlegal.com/codes/lordstown/latest/lordstown_oh/0-0-0-15997
(accessed Sept. 17, 2026) [https://perma.cc/2SVE-YFYX].
{¶ 5} To explain the preliminary steps to submitting a site plan for approval
by the Planning Commission, the Lordstown Planning and Zoning Office provides
to prospective zoning-permit applicants a two-page document titled “Overview of
Lordstown Village Site Plan Review Process” (“the Overview”). The Overview
details four steps in the process.
{¶ 6} Under “step one,” a zoning-permit applicant must submit to the
Planning and Zoning Office drafts of a narrative outline of the project and a
“site/plot plan identifying property size, setbacks from all property lines to the
proposed facility . . . , and other project details.” Once the applicant submits these
draft materials, “the Village of Lordstown will begin the process of engaging the
Village Engineer(s) on the project.” The village engineer will then prepare and
provide to the developer a “work authorization,” which the developer must sign and
return to Lordstown as an acknowledgment of the developer’s responsibility to
reimburse Lordstown for the village engineer’s fees related to the project. When
the signed work acknowledgment is received, the village council will approve the
village engineer’s engagement on the project.
{¶ 7} Once the village council approves the village engineer’s engagement
on the project, the Overview process moves on to “step two,” the “pre-application
meeting” required by Lordstown Cod.Ord. 1115.04(a). Under step two, before the
pre-application meeting, the developer must submit detailed project information,
including a preliminary-planning-evaluation form, a site-plan-review form, utility
plans, a storm-water-management plan, hazard/safety plans, and approvals from
3
SUPREME COURT OF OHIO
other regulatory entities. The Overview contemplates that after submission of these
draft materials, a pre-application meeting will occur and should include “everyone
from the Village team & everyone from the Developer’s team.”
{¶ 8} Following the pre-application meeting, “step three” of the Overview
contemplates that the village engineer and planning-and-zoning administrator will
each provide written comments on the proposed site plan, identifying deficiencies
or additional information that is needed. Other Lordstown department heads may
also provide feedback for the developer to address. The developer is required in
step three to address all comments, questions, and concerns “by providing revised
drafts, responses, & updates.”
{¶ 9} Once the site-plan details have been fully addressed and the draft site-
plan documents updated, the Overview process proceeds to final submission of the
site plan under “step four.” Final site-plan documents are submitted to Lordstown’s
planning-and-zoning administrator and must “address all revisions, questions,
concerns or comments from the pre-application meetings & any individual
department discussions/meetings.” The applicant must file a copy of the final site
plan with the planning-and-zoning administrator for approval by the Planning
Commission. Lordstown Cod.Ord. 1115.04(a).
{¶ 10} Upon the developer’s filing of the final site plan, the Planning
Commission “shall review the site plan pursuant to the site plan review guidelines
set forth in [Lordstown Cod.Ord.] 1115.05.” Lordstown Cod.Ord. 1115.04(c). If
the Planning Commission approves the final submission, the applicant may file an
application for a zoning permit for the Planning and Zoning Office’s approval. Id.
No construction may begin until the zoning permit has been issued. Lordstown
Cod.Ord. 1115.02.
B. Bristolville Initiates the Site-Plan-Review Process
{¶ 11} On October 20, 2025, Bristolville initiated the site-plan-review
process set forth in the Lordstown Codified Ordinances. On that date, in
4
January Term, 2026
accordance with step one of the Overview, Bristolville hand-delivered to the
Planning and Zoning Office “the required narrative outline of the project and a
site/plot plan, among other things.” Bristolville also emailed a copy of these draft
materials to Bordner and Village Solicitor Matthew Ries the same day. The next
day, Bordner sent an email to Bristolville, informing them that
since the Planning & Zoning Committee previously recommended
a ban on data centers within the Village of Lordstown, which is now
before Village Council, having just gone through second reading,
the Planning & Zoning Office would not be able to proceed until
Council makes a decision on the ban at the next Council meeting.
{¶ 12} Bristolville responded to Bordner a week later, asking her to proceed
with the site-plan-review process in accordance with the Lordstown Codified
Ordinances because data centers were still permitted under Lordstown’s zoning
ordinances.
C. Lordstown Passes Ordinance Prohibiting Data Centers
{¶ 13} Six days later, on November 3, the Lordstown Village Council
passed Ordinance No. 57-2025, which would prohibit any data center within the
corporate boundaries of Lordstown.1 Village of Lordstown,
https://www.lordstown.com/wp-content/uploads/57-2025.pdf (accessed Sept. 17,
2026) [https://perma.cc/NU3M-YY2U]. The ordinance further provided that “[n]o
1. The ordinance defined “data center” as “a facility, used for the storage, management, and
dissemination of digital data, which houses computer, telecommunication, and/or network
equipment, systems, servers, appliances, and other associated components related to digital data
operations, and/or facility designed or modified to house networked computers and data and
transaction processing equipment and related infrastructure support equipment, including but not
limited to server farms, cloud computing hubs, and colocation centers.” Id. at § 1, Village of
Lordstown, https://www.lordstown.com/wp-content/uploads/57-2025.pdf (accessed Sept. 17, 2026)
[https://perma.cc/NU3M-YY2U].
5
SUPREME COURT OF OHIO
zoning permit, building permit, or certificate of occupancy shall be issued for any
use that meets the [ordinance’s] definition of a data center.” Id. at § 2b. The
ordinance was explicitly inapplicable to any data-center facility already existing or
under construction as of the ordinance’s effective date. Id. at § 8. The village
council passed the ordinance as an emergency measure, id. at § 9, and the ordinance
was to take effect on December 3, 2025, see R.C. 731.29.
{¶ 14} Two days later, notwithstanding the village council’s passage of
Ordinance No. 57-2025, Bordner forwarded Bristolville’s October 20 draft site-
plan materials to Christopher Kogelnik, the village engineer, for his review. On
November 12, Ries emailed Bristolville’s counsel a letter responding to
Bristolville’s October 28 letter to Bordner. Ries denied that the village was refusing
to proceed with a site-plan review and stated that Bordner had been working with
Kogelnik to review Bristolville’s draft submission. Ries offered to schedule a
meeting with Bristolville to discuss issues that Kogelnik had identified in his initial
review, but Ries indicated that “the proposed project w[ould] likely be prohibited
by Village of Lordstown’s Ordinance No. 57-2025, which prohibits the
establishment and operation of data centers” in Lordstown.
D. Relators File this Action; Lordstown Repeals the Ban
{¶ 15} After receiving Ries’s letter, relators commenced this action. In their
complaint, relators ask for a writ of mandamus “directing Respondents . . . to follow
Lordstown Codified Ordinance 1115 by accepting, reviewing, and acting upon
Bristolville’s Submission and to do so throughout the Site Plan Review Process
under the Village’s applicable laws in effect as of October 20, 2025, when no data
center ban was in effect in the Village.” The complaint named Ries, Bordner, and
Lordstown as respondents. The village filed a motion to dismiss relators’ petition
under Civ.R. 12(B)(6) for failure to state a valid claim for relief in mandamus. We
granted the motion as to Ries; as to Border and Lordstown, we denied the motion,
6
January Term, 2026
ordered them to file an answer, and granted an alternative writ, setting a schedule
for the parties to submit evidence and merit briefs. 2025-Ohio-5682.
{¶ 16} Before we issued our order granting an alternative writ, the village
council repealed Ordinance No. 57-2025 before it was to take effect. In its place,
the council unanimously passed an ordinance placing a temporary moratorium on
the issuing of any new permits, as well as the receipt and processing of applications
for permits, for proposed data centers in Lordstown. Lordstown Ord. No. 1-2026,
§ 2, available at Village of Lordstown, https://www.lordstown.com/wp-
content/uploads/1-2026.pdf (accessed Sept. 17, 2026) [https://perma.cc/48BU-
9QWX]. The moratorium was effective for up to 180 days and was to expire on
July 4, 2026. See id. Under the terms of the moratorium, the village’s obligations
to conduct site-plan reviews or to act on any application for a permit for a data
center were suspended “during the time when th[e] moratorium shall be in effect.”
Id. at § 3. As a result of the council’s enactment of the moratorium, the process for
reviewing Bristolville’s site plan did not move forward.
{¶ 17} On June 15, before the expiration of the moratorium, the village
council passed an ordinance extending it for an additional 180 days. See Lordstown
Ord. No. 29-2026, available at Village of Lordstown,
https://www.lordstown.com/wp-content/uploads/29-2026-1.pdf (accessed Sept.
17, 2026) [https://perma.cc/NT5M-5JSU].
II. EVIDENTIARY MOTIONS
A. Motion for Leave to File Rebuttal Evidence
{¶ 18} Relators filed a timely motion for leave to file rebuttal evidence
under S.Ct.Prac.R. 12.06(B), asking to file proposed Exhibits JJ through OO along
with the authenticating affidavit of their counsel. Relators state that the proposed
exhibits consist entirely of public records and that most were obtained from
Lordstown through a public-records request. The village opposes the motion.
7
SUPREME COURT OF OHIO
{¶ 19} Relators’ proposed rebuttal evidence consists of documents relating
to the site-plan review and zoning-permit application to construct industrial
structures on property owned and developed by a nonparty to this case. According
to relators, this rebuttal evidence is relevant in this case to respond to the village’s
arguments that Bristolville has not yet applied for a zoning permit and that the
Overview is but “an informal aid and roadmap” for the site-plan-review process.
The rebuttal evidence relating to the site-plan review and zoning application of
another developer for a different project, say relators, demonstrate that the village
follows the Overview generally but refuses to do so with respect to Bristolville’s
project.
{¶ 20} Rebuttal evidence “is that given to explain, refute, or disprove new
facts introduced into evidence by the adverse party; it becomes relevant only to
challenge the evidence offered by the opponent, and its scope is limited by such
evidence.” State v. McNeill, 1998-Ohio-293, ¶ 44. We have discretion in
determining whether to allow rebuttal evidence. Id.
{¶ 21} We deny relators’ motion. The village has argued in its merit brief
that Lordstown Cod.Ord. Ch. 1115 governs the site-plan review and zoning-permit
process. And while the Overview is an informal aid for the village and developers,
the village noted, the Overview “does not take the place of the Village’s
ordinances.” Whether the village followed the Overview with respect to the site-
plan review and zoning-permit applications of a third party does not refute the
village’s position that the ordinances—not the Overview—set forth the legal duty
enforceable in mandamus. See State ex rel. Shie v. Ohio Adult Parole Auth., 2022-
Ohio-270, ¶ 11 (“An internal policy of an agency does not create a legal duty
enforceable in mandamus”).
{¶ 22} Relators’ argument that the proposed rebuttal evidence responds to
the village’s argument that Bristolville has not yet applied for a zoning permit also
lacks merit. Under Lordstown Cod.Ord. 11154.04(c), an application for a permit
8
January Term, 2026
may not be submitted until the site-plan review has been completed. Relators’
proposed rebuttal evidence does not refute the village’s contention in this regard.
If anything, the proposed evidence corroborates the village’s position; that is, it
demonstrates that a third party completed the site-plan process before submitting
its application for a zoning permit.
{¶ 23} For these reasons, we deny relators’ motion for leave to file rebuttal
evidence.
B. Motion for Judicial Notice
{¶ 24} Relators have also filed a motion asking us to take judicial notice of
(1) a notice of a public hearing and a proposed version of Lordstown Ordinance
No. 29-2026, which was ultimately enacted, extending the data-center moratorium
through 2026, and (2) a copy of Lordstown Ordinance No. 16-2026, by which
Lordstown entered into an agreement under which consultant Brian Frantz would
assist Lordstown in amending its Planning and Zoning Code to, according to
relators, “creat[e a] conditional use permit process” and “specifically provide for
regulations related to data centers.” The village opposes the motion.
{¶ 25} Under Evid.R. 201(B), courts may take judicial notice of a fact that
is “not subject to reasonable dispute” in that it is “capable of accurate and ready
determination by resort to sources whose accuracy cannot reasonably be
questioned.” Judicial notice may be taken at any stage of the proceeding before the
court. Evid.R. 201(F).
{¶ 26} We grant relators’ motion for judicial notice. The existence of the
notice and ordinances is not subject to reasonable dispute; indeed, they are publicly
available on Lordstown’s website. See Agenda Public Hearing: June 15, 2026,
available at Village of Lordstown, https://www.lordstown.com/wp-
content/uploads/June-15-2026-Public-Hearing.pdf (accessed Sept. 17, 2026)
[https://perma.cc/NMH5-APCZ]; Lordstown Ord. No. 29-2026, available at
Village of Lordstown, https://www.lordstown.com/wp-content/uploads/29-2026-
9
SUPREME COURT OF OHIO
1.pdf (accessed Sept. 17, 2026) [https://perma.cc/NT5M-5JSU]; Lordstown Ord.
No. 16-2026, available at Village of Lordstown, https://www.lordstown.com/wp-
content/uploads/16-2026.pdf (accessed Sept. 17, 2026) [https://perma.cc/Y67X-
T26P]. Moreover, municipal ordinances and facts that are noted in public records
are the sort of facts of which we have taken judicial notice in mandamus actions.
See, e.g., State ex rel. Ohio Republican Party v. FitzGerald, 2015-Ohio-5056, ¶ 18
(taking judicial notice of announcements posted on county government’s website);
State ex rel. Herdman v. Franklin Cty. Bd. of Elections, 1993-Ohio-24, ¶ 9 (taking
judicial notice of a village ordinance).
III. ANALYSIS
{¶ 27} To be entitled to a writ of mandamus, relators must establish by clear
and convincing evidence a clear legal right to the relief they requested, a clear legal
duty on the part of the village to provide that relief, and the lack of an adequate
remedy in the ordinary course of the law. State ex rel. A.N. v. Cuyahoga Cty.
Prosecutor’s Office, 2021-Ohio-2071, ¶ 9.
{¶ 28} In attempting to carry their burden to show a clear legal right and
duty enforceable in mandamus, relators rely on Lordstown Cod.Ord. Ch. 1115,
which sets forth the process that developers and Lordstown officials must follow
for the submission, review, and—ultimately—approval of a site plan for new
construction in Lordstown. In addition, relators ask that the village perform its site-
plan-review duties “under [Lordstown]’s applicable laws in effect as of October 20,
2025,” the date on which relators submitted their draft site-plan-review materials.
In their merit brief, relators clarify that they ask for the site-plan review to be
conducted under Lordstown’s applicable laws in effect before the village council
enacted the data-center moratorium.
10
January Term, 2026
A. The Village’s Threshold Arguments
1. Declaratory Judgment and Prohibitory Injunction
{¶ 29} The village argues that relators’ mandamus action is a disguised civil
action for a declaratory judgment, over which this court lacks original jurisdiction.
The village contends that relators’ true object is not a writ of mandamus but, rather,
a declaratory judgment that the village’s action on Bristolville’s site-plan review
will be governed by local law in effect on October 20, 2025, the date on which
Bristolville submitted its draft site-plan documents. To be sure, relators have done
little to disguise their desire that we declare that they have a vested right to proceed
with the site-plan process based on the law as it existed on October 20, 2025, before
the village council passed the moratorium on data centers. Nonetheless, we reject
the village’s argument.
{¶ 30} The fact that a mandamus complaint contains a declaratory-
judgment component is not fatal. “What distinguishes a proper mandamus
complaint from an improper one is not whether the relator is seeking declaratory
judgment as part of the complaint but whether the complaint seeks to prevent or
compel official action.” (Emphasis in original.) State ex rel. Ethics First–You
Decide Ohio Political Action Commt. v. DeWine, 2016-Ohio-3144, ¶ 10. In this
case, relators are asking us to compel the village to comply with its alleged duty to
implement and abide by Lordstown’s site-plan-review process and to move forward
with Bristolville’s site-plan submission. This is true even though relators are
demanding that the site-plan submission be reviewed under Lordstown’s applicable
laws in effect as of October 20, 2025 (when Bristolville submitted its draft site-plan
documents) or, at the latest, as of January 4, 2026 (before the data-center
moratorium went into effect). Even though the requested relief would, in effect,
prohibit the enforcement of the moratorium, such a circumstance does not change
the character of the relief relators requested. “The fact that adjudicating [a] case
requires [a] court also to prohibit [an] official from acting under the current version
11
SUPREME COURT OF OHIO
of [a law] is ‘only ancillary’ and does not alter the fundamental nature of the relief
sought.” Id. at ¶ 11, quoting State ex rel. Zupancic v. Limbach, 58 Ohio St.3d 130,
133 (1991); see also State ex rel. Pike Cty. Convention & Visitor’s Bur. v. Pike Cty.
Bd. of Commrs., 2021-Ohio-4031, ¶ 14 (holding that the relator stated a valid
mandamus claim for performance of an official act “even though the requested
relief would, in effect, prohibit the enforcement of . . . more recent county
resolutions”).
{¶ 31} We therefore reject the village’s contention that we lack subject-
matter jurisdiction over relators’ action.
2. This Action Is Not Moot
{¶ 32} The village also argues that this case is moot, emphasizing the
language of relators’ prayer for relief in their complaint. In the complaint, relators
request a writ of mandamus “directing Respondents . . . to follow Lordstown
Codified Ordinance 1115 by accepting, reviewing, and acting upon Bristolville’s
Submission and to do so throughout the Site Plan Review Process under the
Village’s applicable laws in effect . . . when no data center ban was in effect in the
Village.” (Emphasis added.) Because the data-center ban that relators’ complaint
refers to was repealed, the village argues, the mandamus action is moot. And even
though a moratorium on data centers is in effect, the village contends, the
moratorium does not inform the issue whether the village will ultimately grant or
deny a permit for Bristolville’s project.
{¶ 33} The repeal of the data-center ban is not a proper basis for dismissing
this case as moot. The gravamen of relators’ action is that the village is not moving
forward with the site-plan-review process as set forth in Lordstown Cod.Ord. Ch.
1115. Indeed, relators’ requested relief is no different now than before the ban was
repealed: they seek a writ of mandamus compelling the village to perform the duties
set forth in the Lordstown Codified Ordinances for reviewing and acting on
12
January Term, 2026
Bristolville’s site-plan submission. The repeal of the data-center ban does not moot
relators’ pursuit of this relief.
3. The Requested Act Has Not Been Performed
{¶ 34} The village next argues that the writ should be denied because the
village is already performing the act that relators are asking this court to compel
through a writ of mandamus. A writ of mandamus will not issue to compel an act
that a respondent has already performed. State ex rel. Kirk v. Burcham, 1998-Ohio-
224, ¶ 7. The village argues that relators are attempting to use a mandamus action
to expedite the site-plan-review process rather than to compel the performance of a
duty required by law.
{¶ 35} We are unpersuaded by the village’s argument. The evidence before
us shows that the village began the site-plan-review process under the Lordstown
Codified Ordinances and the Overview utilized by the village in administering
Lordstown Cod.Ord. 1115.04. However, that process halted on January 5, 2026,
when the village council enacted the moratorium on data centers. The moratorium
expressly suspended any obligation by the Planning and Zoning Office or any
Lordstown official to act on an application for a zoning permit or conduct a site-
plan review for data centers. Lordstown Ord. No. 1-2026, § 3, available at Village
of Lordstown, https://www.lordstown.com/wp-content/uploads/1-2026.pdf
(accessed Sept. 17, 2026) [https://perma.cc/48BU-9QWX]. And in accordance
with the moratorium, the council also voted not to approve the village engineer’s
proposed work authorization, which is required before the site-plan-review process
can proceed. Relators are therefore seeking a writ of mandamus to compel an act
that has not yet been performed—namely, reviewing Bristolville’s site plan. See
State ex rel. Martin Marietta Materials, Inc. v. Trenton, 2024-Ohio-6054, ¶ 28-30
(12th Dist.) (granting writ of mandamus ordering a city to act on a site-plan
application under the process set forth in the city’s code). Therefore, we reject the
village’s argument that it is performing the act sought to be compelled.
13
SUPREME COURT OF OHIO
B. Relators’ Mandamus Claim
{¶ 36} Relators rely on Lordstown Cod.Ord. 1115.04 as the source of the
purported clear legal right and duty they seek to enforce in mandamus. Because
Lordstown Cod.Ord. 1115.04(c) states that the Planning Commission “shall review
the site plan” under the site-plan-review guidelines, relators argue, the village has
a duty to complete the site-plan review and act on Bristolville’s submission. For
its part, the village contends that Bristolville does not have a vested legal right to
have the village move forward with the site-plan review and that, in any event,
Bristolville has an adequate remedy in the ordinary course of the law through an
administrative appeal.
{¶ 37} Lordstown’s site-plan-review process has been placed on hold as it
relates to the construction of data centers. Lordstown’s village council enacted a
moratorium on “the granting/issuing of any new permits, as well as the receipt and
processing of applications for permits” under the Lordstown Codified Ordinances.
Lordstown Ord. No. 1-2026, available at Village of Lordstown,
https://www.lordstown.com/wp-content/uploads/1-2026.pdf (accessed Sept. 17,
2026) [https://perma.cc/48BU-9QWX]; Lordstown Ord. No. 29-2026 (extending
the moratorium), available at Village of Lordstown,
https://www.lordstown.com/wp-content/uploads/29-2026-1.pdf (accessed Sept.
17, 2026) [https://perma.cc/NT5M-5JSU]. The moratorium “suspends any
obligations or requirements to act . . . upon an application for a permit and/or in the
site plan review approval process for Data Centers, during the time when th[e]
moratorium shall be in effect.” Lordstown Ord. No. 1-2026, § 3; Lordstown Ord.
No. 29-2026, § 3. As long as a duly enacted moratorium ordinance is in effect, the
village does not have a clear legal duty to proceed with a review of Bristolville’s
site plan, unless the moratorium is unenforceable as to Bristolville’s submission.
See State ex rel. Purdy v. Clermont Cty. Bd. of Elections, 1997-Ohio-278, ¶ 11-15
14
January Term, 2026
(determining that a clear legal right enforceable in mandamus would exist if a
statute blocking the requested relief were declared unconstitutional).
{¶ 38} Relators contend that the village must move forward with the site-
plan-review process for Bristolville’s proposed data center because the moratorium
does not apply to Bristolville’s site-plan submission. Relators argue that they have
“a vested legal right” to have the project reviewed under Lordstown’s zoning
ordinances “as they existed before the Village enacted the moratorium.”
{¶ 39} In invoking their “vested legal right,” relators rely first on Gibson v.
Oberlin, 171 Ohio St. 1 (1960). In Gibson, a building inspector refused to issue a
building permit for construction of a 12-suite apartment building. After the city’s
appellate process upheld the building inspector’s decision, the owner appealed to the
court of common pleas. While the appeal was pending, the city amended its zoning
ordinances to make the owner’s proposed apartment building an impermissible use.
Id. at 2. The common pleas court determined that the law in existence at the time of
the permit application controlled and that the property owner therefore was entitled
to the permit. On appeal, however, the court of appeals reversed, determining that
the amended ordinances applied to the owner’s permit application.
{¶ 40} The property owner appealed to this court, which framed the issue as
“whether the issuance of a building permit is governed by the law in effect at the time
of the application for such permit or is governed by an amendment to such law
enacted during the pendency of litigation.” Id. We held that although property
owners have no vested right in the continuance of any particular regulation, “once
regulations have been established, and so long as such regulations are in force, the
state and its subdivisions are as much bound as the people to abide by such
regulations.” Id. at 5. Accordingly, we reversed the court of appeals’ judgment, id.
at 6, holding that “[w]here a property owner complies with all the legislative
requirements for the procurement of a building permit and his proposed structure falls
within the use classification of the area in which he proposes to build it, he has a right
15
SUPREME COURT OF OHIO
to such permit, and there is a duty on the part of the officer charged therewith to issue
it,” id. at paragraph one of the syllabus. Such an owner’s right to the permit becomes
“vested . . . upon the filing of the application for the permit.” Id. at 6. Based on this
principle, relators argue that Bristolville is entitled to have the village move forward
with the site-plan review for Bristolville’s proposed data center without regard to the
moratorium.
{¶ 41} Relators misapply Gibson. That case stands for the proposition that
the property owner must have complied with all the legislative requirements for
procuring a permit as of the date the owner applied for the permit. Id. at paragraph
two of the syllabus. Bristolville cannot avoid Lordstown’s data-center moratorium
under this rule, however, because it has not yet applied for a permit to begin
construction, much less met all legislative requirements for obtaining such a permit.
Under the Lordstown Codified Ordinances, the Planning Commission’s approval of
a site plan is a necessary, preliminary step to obtaining a zoning permit. Lordstown
Cod.Ord. 1115.02 and 1115.04(c). Bristolville is essentially asking to apply a vested-
rights rule to the site-plan review process. But under Gibson, Bristolville does not
have a vested right to the application of any particular zoning ordinance until it has
met the legislative requirements to obtain a permit.
{¶ 42} Relators also contend that this court’s holding in State ex rel.
Fairmount Ctr. Co. v. Arnold, 138 Ohio St. 259 (1941), cuts in their favor. In
Fairmount Ctr., a property owner obtained a permit to construct a commercial
building, but the permit expired before construction began. After the permit’s
expiration, the city council introduced an ordinance to rezone the owner’s property
to residential use. Id. at 260. The council simultaneously passed an emergency
ordinance that prohibited the issuance of a building permit during the pendency of
any legislation that would, if adopted, prohibit any use covered by the desired permit.
Id. After the passage of the emergency ordinance, the property owner applied for a
second permit to construct the same building for which the first permit had expired.
16
January Term, 2026
The city’s building inspector refused to issue the second permit. Id. at 261. The
owner would have been entitled to the second permit but for the emergency
ordinance. Id.
{¶ 43} The owner then filed an action for a writ of mandamus in the court of
appeals, seeking an order compelling the building inspector to issue the second
permit. While that action was pending, the city passed the ordinance to rezone the
owner’s property. The court of appeals denied the writ, and the owner appealed to
this court, challenging both the rezoning ordinance and the “stop-gap” emergency
ordinance that prohibited the issuance of the permit while the zoning-amendment
ordinance was pending. Id. at 261. On appeal, this court framed the issue as whether
the city had “the right, by stop-gap ordinance, to hold off [the owner] until it could
put into effect an ordinance rezoning [the owner’s] property.” Id. We held that the
stop-gap ordinance was invalid because it had not been adopted in accordance with
Section 4366-11 of the General Code, which required, among other things, that the
proposed zoning change be submitted to the planning commission for report and to
hold a public hearing on whether the change should be made. Id. at 264-265.
Accordingly, we reversed the judgment of the court of appeals and remanded the case
for further proceedings. Id. at 266.
{¶ 44} Relators argue that Fairmount Ctr. supports their position that
Lordstown’s data-center-moratorium ordinance may not be applied to suspend the
village’s site-plan review of the Bristolville project. They argue that in Fairmount
Ctr., this court applied the prohibition on retroactive laws in Article II, Section 28 of
the Ohio Constitution to the stop-gap ordinance. Likening the stop-gap ordinance in
Fairmount Ctr. with Lordstown’s moratorium ordinance, relators contend that the
moratorium cannot stop the village from moving forward on Bristolville’s site plan.
{¶ 45} As with Gibson, relators misapply Fairmount Ctr. In that case, the
property owner would have been entitled to a construction permit but for the city’s
passage of the stop-gap ordinance. Id. at 261. In contrast, here, as explained above,
17
SUPREME COURT OF OHIO
Bristolville has not satisfied the requirements for obtaining a permit. Moreover,
contrary to relators’ argument, we did not hold that the stop-gap ordinance in
Fairmount Ctr. was invalid as a retroactive law under Article II, Section 28 of the
Ohio Constitution. “Irrespective of whether this section is a limitation upon a
municipal council,” we held, “the retroactive effect given to [the rezoning ordinance]
by the emergency enactment of [the stop-gap ordinance] deprive[d] [the property
owner] of its property rights without due process of law.” Id. at 266. In this case,
however, the moratorium is not giving retroactive effect to any zoning change,
because relators—unlike the property owner in Fairmount Ctr.—have no entitlement
to a permit even under the premoratorium law.
{¶ 46} Under a close reading of the cases, neither Gibson nor Fairmount Ctr.
supports relators’ request for a writ of mandamus ordering the village to move
forward on Bristolville’s site-plan submission. In both of those cases, the relief
sought by the property owner was the issuance of a building permit that had been
denied notwithstanding the property owner’s having satisfied the legislative
requirements for obtaining the permit under the zoning laws in effect at the time of
application. In contrast, here, Bristolville has not met the legislative requirements
for obtaining a permit and therefore has no vested right to enforcement of any
particular zoning ordinance.
{¶ 47} Relators also contend that they should enjoy a vested right to
Lordstown’s premoratorium zoning ordinance as a matter of public policy. They
argue: “To hold that Bristolville’s right to proceed under then-existing law does not
vest until after the Planning Commission approves the site plan . . . would eliminate
all protection that a zoning applicant has against changes in law throughout the
application process, as only projects that comply with any new such laws could be
deemed vested.” Relators further argue that a ruling in the village’s favor may
encourage localities to engage in dilatory tactics similar to what they say the village
has employed here.
18
January Term, 2026
{¶ 48} The remedy for relators’ policy concern, however, is not a writ of
mandamus. Even if we agreed with Bristolville’s policy argument, “[c]ourts cannot
create the legal duty that is enforceable in mandamus; the creation of a duty
enforceable in mandamus is a legislative and not a judicial function,” State ex rel.
Vermilion Campaign Commt. for Jean A. Anderson v. Lorain Cty. Bd. of Elections,
2025-Ohio-3250, ¶ 33. And in this case, relators have not shown a legislatively
created right or duty enforceable in mandamus. Un