Full Opinion

SIXTH DISTRICT COURT OF APPEAL STATE OF FLORIDA _____________________________ Case No. 6D2025-0106 Lower Tribunal No. 2021-CA-010091 _____________________________ SUSAN ZIMMERMAN and TOM ZIMMERMAN, Appellants, v. CARLOS R. DIEZ-ARGUELLES, Appellee/Cross-Appellant, v. GARLAND W. KNIGHT, Jr., Cross-Appellee. _____________________________ Appeal from the Circuit Court for Orange County. John E. Jordan, Judge. November 25, 2026 STARGEL, J. Appellants, Susan Zimmerman and Tom Zimmerman, appeal the amended final judgment entered in favor of Appellee/Cross-Appellant, Carlos R. Diez- Arguelles, following a nonjury trial. The underlying lawsuit arose after Diez- Arguelles and his wife hired Madison Construction, Inc. to design and build a custom home in Tampa. The project ultimately fell through before construction could begin. Diez-Arguelles sued Madison’s principals, the Zimmermans, and Madison’s qualifying agent,1 Cross-Appellee Garland Knight, seeking to recover all preconstruction deposits. The trial court found the Zimmermans liable for fraudulent misrepresentation and violating the Florida Deceptive and Unfair Trade Practices Act (“FDUTPA”) and awarded nearly all of Diez-Arguelles’s claimed damages. However, the court found that he failed to prove any claims against Knight. On appeal, the Zimmermans challenge the judgment entered against them, raising issues relating to venue, the enforceability of an arbitration clause, and whether an integration clause precluded the fraudulent misrepresentation and FDUTPA claims. Diez-Arguelles cross-appeals, challenging the trial court’s judgment in favor of Knight on the fraudulent misrepresentation and FDUTPA claims. As discussed below, we conclude that the trial court’s pretrial ruling concerning the enforceability of the arbitration clause provision was in error. Thus, we reverse as to the fraudulent misrepresentation and FDUTPA counts against the Zimmermans and remand for further proceedings. We reject the Zimmermans’ other 1 See generally § 489.119(2), (3)(a), Fla. Stat. (2020) (requiring that for a business organization to engage in contracting, it must have a “qualifying agent,” who is “certified or registered under this part in order for the business organization to operate in the category of contracting in which the qualifying agent is certified or registered”). 2 arguments, as well as the arguments raised in Diez-Arguelles’s cross-appeal, without further discussion. I. Madison is a luxury custom home builder in Tampa, Florida. Garland Knight ran the company for twenty-two years before selling his ownership interest in 2015 to his daughter, Susan Zimmerman, and her husband, Tom Zimmerman. Knight considered himself retired following the sale, but he remained Madison’s qualifying agent pursuant to his contractor’s license. Knight testified that he continued to work for the business on an unpaid basis because he enjoyed it. However, his role was limited to reviewing the company’s overall finances, and he only reviewed construction plans occasionally. Neither Susan Zimmerman nor Tom Zimmerman is a licensed contractor. In May 2020, Diez-Arguelles’s wife, Maria Tejedor, reached out to Madison about building a custom home on a waterfront property in Tampa.2 Diez-Arguelles and Tejedor met with Tom Zimmerman on multiple occasions and exchanged numerous emails about the project. Diez-Arguelles alleges that the Zimmermans made three fraudulent misrepresentations during this process: (1) that the Zimmermans were themselves licensed contractors; (2) failing to disclose that 2 While Diez-Arguelles was technically the only named plaintiff in this action, the claimed damages pertained to Diez-Arguelles and Tejedor equally. 3 Madison’s licensed contractor, Knight, would not be personally supervising, directing, and managing the project; and (3) that Madison’s in-house design professional was a licensed architect when he was not. The Zimmermans denied making the alleged misrepresentations. In July 2020, Diez-Arguelles and Tejedor entered into a “Design Agreement” with Madison that began the custom home design-build process. The Design Agreement included a nonrefundable design fee, which Diez-Arguelles and Tejedor paid, that would be credited towards the cost of construction. Diez-Arguelles and Tejedor went on to execute a “Construction Contract” in November 2020. The Construction Contract identified Diez-Arguelles and Tejedor as “Owner” and Madison as “Contractor.” It contained a total price of $2,775,000 and called for a ten percent nonrefundable deposit that worked out to $257,500 after crediting the design fee. Diez-Arguelles and Tejedor paid the deposit the day they signed the contract. Pursuant to the Design Agreement and Construction Contract, Madison worked on the project into mid-2021. During this process, Tejedor exchanged several emails with Madison regarding her desired changes to the initial design. In July 2021, Tom Zimmerman emailed Diez-Arguelles and Tejedor telling them to look out for a DocuSign from an employee of Madison. The message with the DocuSign stated that it included updated plans, an updated draw schedule, and 4 updated pricing – though the contents of the DocuSign were not available for trial. While the parties dispute what exactly was in the DocuSign, it is undisputed that there was at least some degree of price increase and that Diez-Arguelles and Tejedor refused to sign anything. Over the next two months, Diez-Arguelles sent multiple letters to Madison requesting an accounting and demanding that Madison either begin construction under the contract terms or return their deposit. Madison sent correspondence declaring Diez-Arguelles and Tejedor in default, and, after calculating the amount due to be returned under the Construction Contract, mailed a $150,875.37 check to Diez-Arguelles and Tejedor. II. On October 18, 2021, Diez-Arguelles filed suit in Orange County, naming Knight as the only defendant. Knight moved to dismiss for improper venue and failure to comply with the Construction Contract’s arbitration provision. After the case was transferred to Orange County Business Court, Diez-Arguelles amended his complaint to add the Zimmermans as defendants. The amended complaint asserted claims against the three defendants for theft (Count I), statutory civil theft under section 772.11, Florida Statutes (2021) (Count II), and conversion (Count III). All three defendants moved to dismiss the amended complaint for improper venue and failure to comply with the arbitration provision. The defendants attached a copy of 5 the Construction Contract, which contained the arbitration provision and was signed by Diez-Arguelles and Tejedor, as well as by Tom Zimmerman on behalf of Madison. After Diez-Arguelles failed to timely respond to the motion to dismiss, the defendants filed a “Notice of Fully Briefed Motion” pursuant to the rules of Orange County Business Court. The next day, Diez-Arguelles filed: (1) his “Reply to Defendants’ Notice of Fully Briefed Motion” and (2) his response in opposition to the motion to dismiss. Diez-Arguelles then filed a request for oral argument on the motion to dismiss, which the defendants opposed. The trial court denied oral argument and entered an order denying the motion to dismiss, finding, among other things, that there was “presently a genuine dispute as to the enforceability of the arbitration provision.” Diez-Arguelles subsequently filed a second amended complaint adding counts for fraudulent misrepresentation (Count IV) and violation of FDUTPA (Count V), to which the defendants filed an answer raising the same affirmative defenses. After a nonjury trial, the trial court entered a final judgment in favor of Diez-Arguelles on Count IV and in favor of the defendants on the remaining claims. Diez-Arguelles moved for rehearing on Count V, while Knight moved for rehearing as to his liability for any fraudulent misrepresentations made by the Zimmermans. The trial court granted Knight’s motion, resulting in his exoneration from liability, and set 6 argument on Diez-Arguelles’s motion. Diez-Arguelles sought rehearing of the order granting Knight’s rehearing motion. Following a hearing, the trial court entered an amended final judgment replacing and superseding the initial final judgment. The amended final judgment found that Diez-Arguelles had met his burden to prove Counts IV and V against the Zimmermans but that he had failed to prove those claims against Knight. The amended final judgment awarded Diez-Arguelles damages totaling $126,624.63. The trial court’s ruling in favor of all three defendants on Counts I, II, and III was unchanged. III. A trial court’s ruling on a motion to compel arbitration, as with the interpretation of a contract in general, is reviewed de novo. Costello v. Olson, 379 So. 3d 536, 538 (Fla. 6th DCA 2023) (first citing Murphy v. Courtesy Ford, LLC, 944 So. 2d 1131, 1134 (Fla. 3d DCA 2006); and then quoting Rose v. Steigleman, 32 So. 3d 644, 645 (Fla. 1st DCA 2010)). Three fundamental elements must be considered when determining whether a dispute is required to be submitted to arbitration: (1) whether a valid written agreement to arbitrate exists; (2) whether an arbitrable issue exists; and (3) whether the right to arbitration has been waived. Jackson v. Shakespeare Found., Inc., 108 So. 3d 587, 593 (Fla. 2013). “The intent of the parties to a contract, as manifested in the plain language of the arbitration 7 provision and contract itself, determines whether a dispute is subject to arbitration.” Id. Courts generally favor arbitration provisions and will aim to resolve any ambiguities in favor of arbitration. Id. The Construction Contract includes a mediation/arbitration provision 3 that provides, in pertinent part: 23. MEDIATION/ARBITRATION. 23.1 Owner, on behalf of Owner and all residents or other occupants of the Property, including minor children, and Contractor, hereby specifically agree that any and all disputes: (i) arising in connection with the Construction Contract, the 2-10 Home Buyers Warranty, or any dealing between Owner and Contractor; (ii) arising in connection with any representations alleged to have been made by Contractor or one of Contractor’s representatives; (iii) arising in connection with any claimed defect in or to the Property; (iv) arising in connection with any personal injury or property damages alleged to have been sustained by Owner, any residents or other occupants of the Property, or in the Property or the community in which the Property is located, if applicable; or (v) arising in connection with any issues of formation, validity, or enforceability of this section, (individually, a “Dispute” and collectively, the “Disputes”) shall be governed by this section. All Disputes shall first be submitted to mediation, and if not settled during mediation, shall thereafter be submitted to binding arbitration. Agreeing to mediation and arbitration as set forth in this section constitutes Owner’s waiver of Owner’s right to a jury trial. .... 3 While this provision requires disputes be submitted to mediation first and, if not settled at mediation, then to arbitration, we refer to it as the “arbitration provision” for the sake of brevity and to align with the terminology used in the parties’ briefs. 8 23.5 This section shall inure to the benefit of, and be enforceable by, Contractor’s subcontractors, agents, vendors, suppliers, design professionals, insurers, and any other person alleged to be responsible for any defect in or to the Property. 23.6 This section shall be deemed to be a self-executing arbitration agreement. Any disputes concerning the interpretation or the enforceability of this Construction Contract, including without limitation, its revocability or voidability for any cause, the scope of arbitrable issues, and any defense based upon waiver, estoppel or laches, shall be decided by the arbitrator. A. Delegation Clause As a preliminary matter, the Zimmermans argue that the trial court should have left the “gateway” question of arbitrability to the arbitrator pursuant to the arbitration provision’s delegation clause. See Rent-A-Ctr., W., Inc. v. Jackson, 561 U.S. 63, 68-69 (2010) (“[P]arties can agree to arbitrate ‘gateway’ questions of ‘arbitrability,’ such as whether the parties have agreed to arbitrate or whether their agreement covers a particular controversy.”); United Healthcare of Fla., Inc. v. N. Broward Hosp. Dist., 403 So. 3d 876, 878 (Fla. 4th DCA 2025) (“Just as contracting parties are free to agree to arbitrate the merits of a dispute, they are likewise free to arbitrate the question of arbitrability.” (citing Airbnb, Inc. v. Doe, 336 So. 3d 698, 703 (Fla. 2022))). But see UATP Mgmt., LLC v. Barnes, 320 So. 3d 851, 859 (Fla. 2d DCA 2021) (“A delegation clause cannot bind a party who did not agree to the contract in which it is contained.”). 9 We conclude, however, that the Zimmermans waived enforcement of the delegation clause by failing to raise it in the proceedings below. See Angels Senior Living at Connerton Ct., LLC v. Gundry, 210 So. 3d 257, 258-59 (Fla. 2d DCA 2017) (holding that court did not err in refusing to consider delegation clause, which defendant failed to raise in its initial motion or at the hearing and only later raised in an unauthorized second motion); see also Bodine v. Cook’s Pest Control Inc., 830 F.3d 1320, 1324 (11th Cir. 2016) (“A delegation clause operates as a defense that the defendant must raise in order to rely upon it. . . . When the defendant does not properly raise the delegation clause and the plaintiff suffers prejudice as a result, the defendant has waived the delegation clause[,] and the court must determine whether the arbitration agreement is enforceable.” (citations omitted)). While the Zimmermans acknowledge that the motion to dismiss did not mention the delegation clause, they suggest that the trial court erred by failing to hold a hearing where they could have addressed the issue, which they contend deprived them of the opportunity to develop a full record. However, because the Zimmermans were the ones who, admittedly, objected to oral argument on the motion, they cannot now be heard to complain that the court’s failure to hold a hearing deprived them of the ability to make a record. See Volusia Cnty v. Niles, 445 So. 2d 1043, 1048 (Fla. 5th DCA 1984) (“Under the doctrine of invited error, a party cannot successfully complain of error for which he is himself responsible, or 10 of rulings that he has invited the trial court to make.”). Accordingly, we reject their attempt to excuse the failure to raise the delegation clause below. 4 B. Arbitrability Turning to the question of arbitrability, Diez-Arguelles’s only argument below against submitting the case to arbitration was that the defendants were non- signatories to the Construction Contract. He did not dispute that the Zimmermans were in a representative capacity when they made the alleged misrepresentations nor did he dispute that Tom Zimmerman was acting in a representative capacity when he signed the Construction Contract on behalf of Madison. As such, the trial court should have proceeded from the beginning as though any action “arising in connection with the Construction Contract” and involving the Zimmermans was subject to the arbitration provision contained therein. The trial court, however, denied the motion to dismiss based in part on its determination that there was a dispute as to the enforceability of the arbitration provision. We conclude that this was error. Based on the record, there is no question 4 To the extent the Zimmermans also argue that their failure to raise the delegation clause should be excused because Florida law precludes multiple motions to compel arbitration or motions for rehearing or reconsideration of such motions, see Wegner v. Schillinger, 921 So. 2d 854, 855 (Fla. 4th DCA 2006), we note that the Zimmermans and their counsel were on notice of this fact before filing the motion to dismiss. 11 that the Zimmermans were acting as agents of Madison, and therefore, they were entitled to enforce the arbitration provision by its terms. Section 23.5 of the arbitration provision states: “This section shall inure to the benefit of, and be enforceable by, Contractor’s subcontractors, agents, vendors, suppliers, design professionals, insurers, and any other person alleged to be responsible for any defect in or to the Property.” (emphasis added). This provision establishes that the Zimmermans, as Madison’s agents, were intended third-party beneficiaries of the contract and, specifically, the arbitration provision. See Koechli v. BIP Int’l, Inc., 870 So. 2d 940, 944 (Fla. 1st DCA 2004) (“Florida and federal courts have recognized that a non-signatory can compel arbitration by a signatory to an arbitration agreement . . . when the non-signatory is an intended third party beneficiary of the contract in question.” (citations omitted)); Tech. Aid Corp. v. Tomaso, 814 So. 2d 1259, 1261 (Fla. 5th DCA 2002) (“[A]rbitration provisions are binding on the parties to the covenant, as well as on intended, third-party beneficiaries of the contract provided that the parties clearly express, or the contract itself expresses, an intent to primarily and directly benefit the third party.”); see also Qubty v. Nagda, 817 So. 2d 952, 957 (Fla. 5th DCA 2002) (holding that defendant who was not a third-party beneficiary of contract was still entitled to enforce arbitration agreement under principles of agency). 12 Diez-Arguelles argues that the Zimmermans are not covered by Section 23.5 because the instant lawsuit does not involve claims “for any defect in or to the Property.” We disagree. Basic principles of construction dictate that the phrase “alleged to be responsible for any defect in or to the Property” as contained in Section 23.5 only modifies the last item in the series – “any other person” – and not the preceding items. See State ex rel. Owens v. Pearson, 156 So. 2d 4, 6 (Fla. 1963) (“[F]ollowing an enumeration in a series, a qualifying phrase will be read as limited to the last of the series when it follows that item without a comma or other indication that it relates as well to those items preceding the conjunction.”); see also Kasischke v. State, 991 So. 2d 803, 811 (Fla. 2008) (explaining that under the doctrine of the last antecedent, “relative and qualifying words, phrases and clauses are to be applied to the words or phrase immediately preceding, and are not to be construed as extending to, or including, others more remote.” (quoting City of St. Petersburg v. Nasworthy, 751 So. 2d 772, 774 (Fla. 1st DCA 2000))). There is nothing else in the arbitration provision that indicates that Section 23.5 was intended to afford beneficiary status to Madison’s agents only in disputes concerning alleged defects to the property. Accordingly, having concluded that there was a valid written arbitration provision, and there being no claim that the arbitration provision had been waived, the only remaining question is whether Diez-Arguelles’s claims fall within the scope 13 of the arbitration provision. See Beck Auto Sales, Inc. v. Asbury Jax Ford, LLC, 249 So. 3d 765, 768 (Fla. 1st DCA 2018) (noting that even when a non-signatory is entitled to enforce an arbitration provision, “the non-signatory can compel arbitration only if the dispute at issue ‘falls within the scope of the arbitration clause.’” (quoting Kroma Makeup EU, LLC v. Boldface Licensing + Branding, Inc., 845 F.3d 1351, 1355 (11th Cir. 2017))). As explained more fully below, we conclude that they do. The Florida Supreme Court has recognized two basic types of arbitration provisions: “(1) provisions with language and application narrow in scope, and (2) provisions with language and application broad in scope.” Jackson, 108 So. 3d at 593 (citing Seifert v. U.S. Home Corp., 750 So. 2d 633, 636-37 (Fla. 1999)). While a narrow arbitration provision typically requires arbitration for claims or controversies “arising out of” the subject contract, a broad arbitration provision typically requires arbitration for claims or controversies “arising out of or relating to” the subject contract. Id. “The addition of the words ‘relating to’ broadens the scope of an arbitration provision to include those claims that are described as having a ‘significant relationship’ to the contract—regardless of whether the claim is founded in tort or contract law.” Id. (citing Seifert, 750 So. 2d at 637-38). The arbitration provision here requires, among other things, arbitration of disputes (i) “arising in connection with the Construction Contract, the 2-10 Home 14 Buyers Warranty, or any dealing between Owner and Contractor” and (ii) “arising in connection with any representations alleged to have been made by Contractor or one of Contractor’s representatives.” (emphasis added). This language is broad in scope. See Pro-Play Games, LLC v. Roger, 390 So. 3d 146, 151 (Fla. 3d DCA 2024) (construing provision that required arbitration of “a dispute aris[ing] out of or in connection with this Agreement” as broad in scope (alteration in original)); see also J.J. Ryan & Sons, Inc. v. Rhone Poulenc Textile, S.A., 863 F.2d 315, 321 (4th Cir. 1988) (holding that arbitration clause “which provides for arbitration of ‘[a]ll disputes arising in connection with the present contract’ must be construed to encompass a broad scope of arbitrable issues”). Whether a claim falls within the scope of a broad arbitration provision depends on “whether a ‘significant relationship’ exists between the claim and the agreement containing the arbitration clause, regardless of the legal label attached to the dispute.” Seifert, 750 So. 2d at 637-38. [A] significant relationship is described to exist between an arbitration provision and a claim if there is a “contractual nexus” between the claim and the contract. A contractual nexus exists between a claim and a contract if the claim presents circumstances in which the resolution of the disputed issue requires either reference to, or construction of, a portion of the contract. More specifically, a claim has a nexus to a contract and arises from the terms of the contract if it emanates from an inimitable duty created by the parties’ unique contractual relationship. Jackson, 108 So. 3d at 593 (internal citations omitted) (citing Seifert, 750 So. 2d at 638-39). 15 We have little difficulty concluding that there was a contractual nexus between Diez-Arguelles’s claims and the Construction Contract in this case. Throughout his pleadings, Diez-Arguelles sought to recover funds he and Tejedor delivered to the Zimmermans, as Madison’s agents, pursuant to the Construction Contract, for the purpose of commencing construction on a home. All the alleged wrongdoing, including the failure to refund the remainder of the deposit and the alleged misrepresentations concerning the licensure status of the Zimmermans and Madison’s architect, was connected to and emanated from the contractual relationship between Diez-Arguelles, Tejedor, and Madison. As a result, there was a significant relationship between the claims against the Zimmermans and the Construction Contract. IV. In sum, we hold that the trial court erred by failing to grant the motion to dismiss for failure to comply with the bargained-for arbitration provision in the Construction Contract. Therefore, we reverse the amended final judgment as to Counts IV and V against the Zimmermans and remand for the enforcement of the arbitration provision pursuant to the contract. We affirm the judgment of no liability against Knight on Counts IV and V.5 5 We affirm in all respects as to Counts I, II, and III, which have not been challenged on appeal. 16 AFFIRMED in part; REVERSED in part; and REMANDED with instructions. TRAVER, C.J., and BROWNLEE, JJ., concur. Dreck J. Angell, of O’Connor, Haftel & Angell, PLLC, Orlando, for Appellants. Carlos R. Diez-Arguelles, Orlando, pro se. No Appearance for Cross-Appellee, Garland W. Knight, Jr. NOT FINAL UNTIL TIME EXPIRES TO FILE MOTION FOR REHEARING AND DISPOSITION THEREOF IF TIMELY FILED 17