IN THE SUPERIOR COURT OF THE STATE OF DELAWARE
PERFICIENT, INC., )
)
Plaintiff, )
)
v. ) C.A No. N25C-12-584 CEB
)
SHI INTERNATIONAL CORP., )
)
Defendant. )
ORDER
This 16th day of September 2026 the Court enters the following Order:
1. Plaintiff Perficient, Inc. (“Perficient”) is a technology consulting firm
“developing, marketing, and selling its software, computer peripherals, computer
hardware, and associated IT services.” 1 Defendant SHI International Corp. (“SHI”)
0F
engaged Perficient to supply services and products to customers of SHI. 2 The “SHI-
1F
Vendor Products/Services Resale Agreement” (“the Contract”) permitted SHI to
market and resell Perficient products to SHI customers, and Perficient would invoice
such orders to SHI as the “fulfillment agent.” 3 2F
2. Perficient alleges that between October and December 2024 it provided
$347,576 in services and products to a customer of SHI. 4 In a signed writing, the
3F
1
Amend. Compl. ¶4.
2
Id.
3
Id., Ex. A.
4
Id. ¶¶6-10.
customer indicated the work had been completed and Perficient allegedly provided
the document to SHI along with an invoice. 5 4F
3. Article 7 of the Contract outlines the invoice and payment process:
“Subject to reconciliation with the terms of this Agreement and the Order, including
verification that the Product was delivered, the invoice shall be paid . . . net 45 days
after SHI’s receipt of the Vendor’s accurate invoice or Customer’s receipt of the
Products, whichever is later.” 6 5F
4. According to Perficient, an invoice for the work was provided to SHI,
but the bill remains unpaid and Perficient has “been met only with silence.” 7 6F
Perficient filed the present action for breach of contract and unjust enrichment. SHI
shortly thereafter filed this Motion to Dismiss.
5. In its motion, SHI alleges 1) the claim is not ripe because Perficient
failed to follow the dispute resolution procedures outlined in the Contract before
bringing suit in Superior Court, 2) Perficient has not stated a claim for breach of
contract because it failed to allege that payment was due and SHI was in breach, and
3) Perficient has failed to plead the elements of unjust enrichment. 8 7F
5
Id. ¶¶6-8.
6
Id., Ex. A.
7
Pl.’s Answering Br. at 6.
8
See generally Def.’s Mot. to Dismiss.
2
The Claim is Ripe
6. Article 25 of the Contract describes a process to be followed should any
claims or disputes arise between the parties. SHI characterizes Article 25 as a
“mandatory dispute resolution provision” which until completed, renders the
complaint not ripe. 9 SHI seeks dismissal under Superior Court Rule 12(b)(1) for
8F
lack of subject matter jurisdiction.
7. On a motion to dismiss under Rule 12(b)(1), courts may “assume the
truth of the factual allegations in the complaint but also consider facts beyond the
pleadings.” 10 9F
8. Perficient argues it complied with the first step of the dispute resolution
process by contacting SHI about the outstanding balance within 30 days of providing
the invoice. 11 10F The next step in the process is for “the Parties’ Contract
Representatives” to use their “best efforts” to negotiate settlement. 12 Exactly who 11F
has the onus of initiating such discussions isn’t articulated, nor is it clear how
Perficient could satisfy this step in the process in light of SHI’s silence. Taking the
allegations in the Complaint as true, SHI asks the Court to dismiss Perficient’s claim
on the basis of a contractual provision that SHI itself declined to follow.
9
Id. at 6-8.
10
Anew Ventures II, LLC v. Terra Glob. Inv. Mgmt., LLC, 2025 WL 3188312, at *3 (Del. Super. Nov. 14, 2025).
11
Amend. Compl. ¶11; Pl.’s Answering Br. at 7-8.
12
Amend. Compl., Ex. A, Article 25.
3
9. In the cases relied on by SHI, the court’s jurisdictional analysis was
limited to whether the parties attended mediation or arbitration as required by a
dispute resolution provision in the parties’ contract. 13 Here, SHI asks the Court to
12F
decline jurisdiction based upon SHI’s failure or refusal to use its best efforts to
negotiate a settlement. Assuming, as we must, the truthfulness of the allegations in
the Complaint, Perficient has sufficiently alleged that it satisfied the conditions
precedent to filing suit. SHI’s motion to dismiss pursuant to 12(b)(1) is DENIED.
Perficient Adequately Pled Breach of Contract
10. SHI next argues the breach of contract claim should be dismissed
because Perficient has failed to demonstrate that payment of the invoice was due
under the terms of the contract. 14 Exhibit B of the Complaint is a “Customer POE
13F
For ECIF Projects” which describes in detail the services provided to the customer,
the date each service was completed, and a signature from the customer. 15 14F
According to Perficient, this document was submitted to SHI as proof of the invoiced
work. 16 SHI counters that Perficient has not alleged that SHI actually received this
15F
document and therefore Exhibit B cannot be proof that “verification” was satisfied. 17 16F
13
See, e.g., Lennox Indus. Inc. v. All. Compressors LLC, 2020 WL 4596840, at *4 (Del. Super. Aug. 10, 2020)
(holding the court did not have jurisdiction over claims that were not submitted to a “Dispute Resolution
Committee” which would mediate and provide a non-binding recommendation).
14
Def.’s Mot. to Dismiss at 8-11.
15
Amend. Compl., Ex. B.
16
Id. ¶¶6-8.
17
Def.’s Mot. to Dismiss at 11.
4
11. “When considering a defendant’s motion to dismiss, a trial court should
accept all well-pleaded factual allegations in the Complaint as true, accept even
vague allegations in the Complaint as ‘well-pleaded’ if they provide the defendant
notice of the claims, draw all reasonable inferences in favor of the plaintiff, and deny
the motion unless the plaintiff could not recover under any reasonably conceivable
set of circumstances susceptible of proof.” 18 17F
12. To survive a motion to dismiss for failure to state a breach of contract,
the plaintiff must show the existence of a contract, breach of an obligation imposed
by the contract, and damages incurred from the breach. 19 Perficient has met this 18F
burden and adequately stated a claim for breach of contract. Both parties agree to
the existence of a valid contract and Perficient has provided what it claims is proof
of services rendered to a customer of SHI pursuant to that contract. The invoice and
Customer POE provide sufficient support for Perficient’s factual allegations, and it
is reasonably conceivable that Perficient is entitled to relief. Whether Exhibit B
qualifies as “verification received” is a matter of contractual interpretation not ready
for resolution at this stage of the pleadings. 20 The motion to dismiss the breach of
19F
contract claim is DENIED.
18
Cent. Mortg. Co. v. Morgan Stanley Mortg. Cap. Hldgs. LLC, 27 A.3d 531, 535 (Del. 2011).
19
VLIW Tech., LLC v. Hewlett-Packard Co., 840 A.2d 606, 612 (Del. 2003).
20
Id. at 615 (“Dismissal, pursuant to Rule 12(b)(6), is proper only if the defendants' interpretation is
the only reasonable construction as a matter of law.”) (emphasis in original).
5
The Unjust Enrichment Claim Is Dismissed
13. SHI’s final argument in its motion is that Perficient is precluded from
asserting an unjust enrichment claim due to the existence of the Contract, and even
if the claim could stand, Perficient has failed to adequately plead its elements.
14. “Before considering a claim for unjust enrichment, ‘courts will engage
in the threshold inquiry of determining whether a contract already governs the
parties’ relationship; if it does, the contract provides the measure of the plaintiff’s
right.’” 21 Thus, “‘[w]hen the complaint alleges an express, enforceable contract that
20F
controls the parties’ relationship . . . a claim for unjust enrichment’ is not
cognizable.” 22 21F
15. Perficient has not challenged the enforceability of the Contract or the
adequacy of relief afforded by it. For an unjust enrichment claim to proceed
alongside a claim for breach of contract, the plaintiff must demonstrate that there is
some right or obligation that is not subject to the contract. 23 Perficient can be made
22F
whole through SHI’s contractual promise to pay Perficient for products provided to
SHI customers. Since Perficient has not asserted any right that is not governed by
21
Wells Fargo Bank, N.A. v. Est. of Malkin, 278 A.3d 53, 69 (Del. 2022) (citing Metcap Secs. LLC v. Pearl Senior
Care, Inc., 2009 WL 513756, at *5 (Del. Ch. Feb. 27, 2009), aff'd, 977 A.2d 899, 2009 WL 2470336 (Del. Aug. 13,
2009)).
22
Textron Inc. v. Endurance Am. Ins. Co., 346 A.3d 639, 653 (Del. Super. 2025) (citing Bakerman v. Sidney Frank
Imp. Co., 2006 WL 3927242, at * 18 (Del. Ch. Oct. 10, 2006)).
23
Palisades Collection, LLC v. Unifund CCR P’rs , 2015 WL 6693962, at *8 (Del. Super. Nov. 3, 2015).
6
the Contract or raised any doubt regarding the enforceability of the Contract, the
motion to dismiss is GRANTED as to the unjust enrichment claim.
IT IS SO ORDERED.
/s Charles E. Butler
Charles E. Butler, Resident Judge
cc: All Counsel of record via File&ServeXpress