Williams Companies, Inc. v. PA PUC
CourtCommonwealth Court of Pennsylvania
Date FiledAugust 19, 2026
Docket1232 C.D. 2024
JudgeWojcik. Cohn Jubelirer. Dumas
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
IN THE COMMONWEALTH COURT OF PENNSYLVANIA
Williams Companies, Inc., :
:
Petitioner :
:
v. : No. 1232 C.D. 2024
: Argued: September 10, 2025
Pennsylvania Public :
Utility Commission, :
:
Respondent :
BEFORE: HONORABLE RENÉE COHN JUBELIRER, President Judge
HONORABLE PATRICIA A. McCULLOUGH, Judge
HONORABLE ANNE E. COVEY, Judge
HONORABLE MICHAEL H. WOJCIK, Judge
HONORABLE LORI A. DUMAS, Judge
HONORABLE STACY WALLACE, Judge
HONORABLE MATTHEW S. WOLF, Judge
OPINION BY JUDGE WOJCIK FILED: August 19, 2026
In this case of first impression, Williams, Inc. (Williams) petitions for
review the August 21, 2024 order of the Pennsylvania Public Utility Commission
(PUC) denying reconsideration and upholding its prior determination that Williams’
proposed solar photovoltaic systems, which bypass the electric distribution
company’s (EDC) distribution system and the regional transmission organization’s
(RTO) transmission system, do not meet the definition of an “alternative energy
system” and thus do not qualify for “solar renewable energy credits” (solar credits)
under the Alternative Energy Portfolio Standards Act (AEPS Act)1 as amended by
Section 2804 of The Administrative Code of 1929 (Act 40).2 Williams contends that
the PUC erred and/or abused its discretion by denying reconsideration and
concluding that its proposed solar photovoltaic systems, which will directly deliver
electricity generated to Williams’ natural gas compressor stations, do not qualify for
solar credits. Upon concluding that the PUCs interpretation of Act 40 was
erroneous, we reverse.
I. Background
Williams is an energy company with a primary focus on natural gas
infrastructure. Williams owns a subsidiary, Transcontinental Gas Pipe Line
Company, LLC (Transco), that operates the Transco natural gas pipeline, a major
interstate pipeline system that transports approximately 15% of the nation’s natural
gas. Transco operates multiple natural gas compressor stations along the pipeline,
which demand energy. Williams plans to construct two large solar photovoltaic
systems, using solar arrays with a nameplate capacity of approximately 11
megawatts each,3 to provide electricity to two of Transco’s natural gas compressor
stations located in Wyoming and Columbia Counties, Pennsylvania. The
compressor stations receive electricity from PPL Electric Utilities (PPL), an EDC;
Transco is the retail customer of record at both locations. For each project, the solar
arrays will be located on land adjacent to the compressor station and be physically
1
Act of November 30, 2004, P.L. 1672, as amended, 73 P.S. §§1648.1-1648.8.
2
Act of April 9, 1929, P.L. 177, added by the Act of October 30, 2017, P.L. 379,
71 P.S. §714.
3
This nameplate capacity is too large to net meter. See Section 2 of the AEPS Act, 73 P.S.
§1648.2 (definition of “customer-generator”); R.R. at 50a.
2
connected to the compressor station’s existing internal electric system. The solar
energy generated will flow directly into Transco’s compressor stations’ internal
electric systems to support the stations’ operations. Williams expects the entirety of
the solar generation to be consumed by the compressor stations, which will reduce
reliance on PPL for electricity.
On June 26, 2023, Williams filed a Petition for Declaratory Order with
the PUC seeking a declaration that Williams’ proposed solar photovoltaic systems
would qualify for solar credits under the AEPS Act. Reproduced Record (R.R.) at
1a-7a. In support, Williams relied on the language of Act 40 that a solar photovoltaic
system that “directly deliver[s] the electricity it generates to a retail customer of an
[EDC],” even if not interconnected to the grid, would qualify.4 Id. at 4a (quoting
Act 40, 71 P.S. §714). The PUC determined that Williams’ proposed solar
photovoltaic systems were ineligible for solar credits. Williams filed a Petition for
Reconsideration, which the PUC granted pending further review. Ultimately, the
PUC rejected Williams’ interpretation and concluded that the projects did not qualify
based on lack of connection to the grid. The PUC reasoned that when Act 40 is read
in pari materia with the AEPS Act, “alternative energy systems,” including solar
photovoltaic systems, must be connected to an EDC’s distribution system or an
RTO’s transmission system to qualify for solar credits. Thus, by decision dated
August 21, 2024, the PUC denied reconsideration and upheld its determination that
4
Interconnection is the physical connection to the grid; delivery is the transfer of electricity
to a retail customer or the grid.
3
Williams’ proposed solar photovoltaic systems are ineligible for solar credits.5 This
appeal now follows.6
II. Issue
The sole issue for our review is whether Williams’ proposed solar
photovoltaic systems, which will directly deliver the electricity to a PPL retail
customer, without grid interconnection, qualify for solar credits under the AEPS Act.
III. Discussion
A. Contentions
Williams argues that the PUC erred in concluding that its proposed
solar photovoltaic systems are not eligible for solar credits under the AEPS Act.
According to Williams, the clear and unambiguous language of Act 40 specifies that
a solar photovoltaic system qualifies for solar credits under the AEPS Act if it
“[d]irectly deliver[s] the electricity it generates to a retail customer of an [EDC].”
71 P.S. §714(1)(i) (emphasis added). The proposed solar photovoltaic systems here
will directly deliver the electricity generated to Transco’s compressor stations.
Transco is a retail customer of an EDC – PPL. Thus, Williams maintains that the
proposed systems should qualify for solar credits under the AEPS Act. According
5
The PUC noted that the reduced electric consumption by Williams due to the proposed
solar photovoltaic systems may qualify as demand-side management and would be eligible to
generate Tier II alternative energy source under the AEPS Act. PUC Opinion, 8/21/24, at 20; R.R.
at 69a.
6
We review the PUC’s denial of reconsideration for abuse of discretion. Executive
Transportation Company, Inc. v. Pennsylvania Public Utility Commission, 138 A.3d 145, 148 (Pa.
Cmwlth. 2016); J.A.M. Cab Company, Inc. v. Pennsylvania Public Utility Commission, 572 A.2d
1317, 1318 (Pa. Cmwlth. 1990). “An abuse of discretion occurs if the agency decision
demonstrates bad faith, fraud, capricious action or an abuse of power.” J.A.M. Cab, 535 A.2d at
1246.
4
to Williams, the PUC’s contrary interpretation disregards Act 40’s plain statutory
text and undermines the General Assembly’s intent to encourage in-state solar
development.
The PUC counters that Williams’ interpretation completely disregards
other interconnection requirements embedded within the AEPS Act. When Act 40
and the AEPS Act are read together, the PUC asserts that an ambiguity arises based
on the definition of “alternative energy system,” which requires grid connection.
The PUC advances that interconnection remains a prerequisite for solar credits, and
Act 40 did not alter or eliminate this requirement or create a standalone eligibility
pathway for solar credits. The PUC contends that Williams’ interpretation would
effectively result in an implied repeal of Sections 2 and 3 of the AEPS Act, 73
P.S. §§1648.2, 1648.3, which is not favored under the law, by eliminating the
requirement that qualifying systems deliver electricity to the grid. Such a reading
would allow any solar facility serving only its own load to earn solar credits, which
is contrary to the AEPS Act’s structure and intent. Because Williams’ proposed
solar photovoltaic systems will not interconnect with an EDC or RTO, they fail to
meet the statutory definition of an “alternative energy system” and cannot qualify
for solar credits under the AEPS Act.
B. Analysis
The parties’ conflicting arguments as to the meaning of Act 40
“presents a question of statutory construction, which is a pure question of law over
which our standard of review is de novo and our scope of review is plenary.”
Pennsylvania State Police v. Grove, 161 A.3d 877, 891-92 (Pa. 2017). When
interpreting a statute, we are guided by the tenets set forth in the Statutory
5
Construction Act of 1972 (SCA), 1 Pa. C.S. §§1501-1991. Under the SCA, our
paramount “objective ‘is to ascertain and effectuate the General Assembly’s intent.’”
Grove, 161 A.3d at 892 (quoting Section 1921(a) of the SCA, 1 Pa. C.S. §1921(a)).
“[A] statute’s plain language is generally the best indicator of legislative intent.”
Commonwealth v. H.D., 247 A.3d 1062, 1065 (Pa. 2021). “When the words of a
statute are clear and free from all ambiguity, the letter of it is not to be disregarded
under the pretext of pursuing its spirit.” 1 Pa. C.S. §1921(b); see H.D. 247 A.3d at
1065; Smith v. Ivy Lee Real Estate, LLC, 165 A.3d 93, 96 (Pa. Cmwlth. 2017).
“Every statute shall be construed, if possible, to give effect to all its provisions.”
1 Pa. C.S. §1921(a).
However, “if the words of a statute are not explicit but are unclear or
ambiguous, we resort to considerations other than the plain language to discern
legislative intent.” Mercury Trucking, Inc. v. Pennsylvania Public Utility
Commission, 55 A.3d 1056, 1068 (Pa. 2012); accord 1 Pa. C.S. §1921(c). Among
the matters we may consider are: the occasion and necessity for the statute; the
circumstances under which the statute was enacted; the mischief to be remedied; the
object to be attained; the consequences of a particular interpretation; the
contemporaneous legislative history; and the legislative and administrative
interpretations of such statute. 1 Pa. C.S. §1921(c); see Mercury Trucking, 55 A.3d
at 1068.
In addition, we follow “the precept that the General Assembly does not
intend a result that is absurd, impossible of execution, or unreasonable.” Mercury
Trucking, 55 A.3d at 1068 (citation and quotation omitted); accord Section 1922 of
the SCA, 1 Pa. C.S. §1922. The General Assembly does not intend to violate the
Pennsylvania Constitution, and it intends to favor the public interest as against any
6
private interest. Mercury Trucking, 55 A.3d at 1068 (citing 1 Pa. C.S. §1922(3),
(5)). The General Assembly also “intends the entire statute to be effective and
certain.” 1 Pa. C.S. §1922(2).
Further, “statutes which relate to the same persons or things are in pari
materia and must be construed together as one statute.” Mercury Trucking, 55 A.3d
at 1067 (citation and quotation omitted); accord Section 1932 of the SCA, 1 Pa. C.S.
§1932; Hommrich v. Public Utility Commission, 344 A.3d 121, 134 (Pa. Cmwlth.
2025) (holding statutes relating to the same things “must be construed together, if
possible, as one statute”). “If and to the extent to which the relevant statutes are
irreconcilable, the legislative act latest in date of final enactment . . . prevail[s].”
Mercury Trucking, 55 A.3d at 1067 (citing 1 Pa. C.S. §§ 1935, 1936). Finally,
[a]n amendment to a provision of an act is “construed as
merging into the original statute, becom[ing] a part
thereof, and replac[ing] the part amended, and the
remainder of the original statute and the amendment shall
be read together and viewed as one statute passed at one
time.” 1 Pa.C.S. §1953. The “portions of the statute which
were not altered by the amendment shall be construed as
effective from the time of their original enactment.” Id.
Mercury Trucking, 55 A.3d at 1067. With these tenets in mind, we examine the
AEPS Act and Act 40.
In 2004, the General Assembly enacted the AEPS Act requiring EDCs
and electric generation suppliers (EGSs) to obtain a certain percentage of their
electricity from “alternative energy sources.” Section 2 of the AEPS Act defines
and divides “alternative energy sources” into two tiers – Tier I and Tier II – each
with different types of energy and compliance requirements. Section 2 of the AEPS
Act, 73 P.S. §§1648.2; see Section 3(b) and (c) of the AEPS Act, 73 P.S. §1648.3(b)-
7
(c). Tier I is defined as “[e]nergy derived from: (1) Solar photovoltaic and solar
thermal energy[;] (2) Wind power[;] (3) Low-impact hydropower[;] (4) Geothermal
energy[;] (5) Biologically derived methane gas[;] (6) Fuel cells[;] (7) Biomass
energy[; and] (8) Coal mine methane.” 73 P.S. §1648.2 (emphasis added). Tier II
alternative energy sources are derived from “(1) Waste coal[;] (2) Distributed
generation systems[;] (3) Demand-side management[;] (4) Large-scale
hydropower[;] (5) Municipal solid waste[;] (6) Generation of electricity utilizing by-
products of the pulping process and wood manufacturing process, including bark,
wood chips, sawdust and lignin in spent pulping liquors[; and] (7) Integrated
combined coal gasification technology.” Id. These alternative energy sources are
alternatives to conventional fossil fuels.
Section 2 of the AEPS Act refers to the physical infrastructure used to
generate, store, and deliver alternative energy sources as “alternative energy
systems.” 73 P.S. §1648.2. Specifically, Section 2 of the AEPS Act defines
“alternative energy system” as:
A facility or energy system that uses a form of alternative
energy source to generate electricity and delivers the
electricity it generates to the distribution system of an
[EDC] or to the transmission system operated by a [RTO].
Id. (emphasis added). Delivery to an EDC or RTO presumes interconnection to the
grid.
Section 3 of the AEPS Act requires EDCs and EGSs to include a certain
percentage of electricity generated from alternative energy sources in their supply
portfolios. See Section 3 of the AEPS Act, 73 P.S. §1648.3. It sets specific tiered
requirements for renewable energy credits. Id. Specifically, Section 3(b) of the
AEPS Act requires that an increasing percentage of electric energy “sold by an
8
[EDC] or [EGS] to retail electric customers” must be generated from Tier I
alternative energy sources, which includes solar photovoltaic energy. 73 P.S.
§1648.3(b)(1). Section 3(c) of the AEPS Act similarly requires that an increasing
percentage of electric energy “sold by an [EDC] or [EGS] to retail electric
customers” must be generated from Tier II alternative energy sources. 73 P.S.
§1648.3(c).
A “retail electric customer” refers to:
A direct purchaser of electric power. The term excludes an
occupant of a building or facility where the
owners/operators manage the internal distribution system
serving such building or facility and supply electric power
and other related power services to occupants of the
building or facility; where such owners/operators are
direct purchasers of electric power; and where the
occupants are not direct purchasers.
Section 2803 of the Public Utility Code, 66 Pa. C.S. §2803; see Section 2 of the
AEPS Act, 73 P.S. §1648.2. Section 3(e) of the AEPS Act provides the framework
for the alternative energy credits program for qualifying alternative energy systems.
Section 3(e) of the AEPS Act, 73 P.S. §1648.3.
As originally enacted, under Section 4 of the AEPS Act, energy from
alternative energy sources were eligible for compliance if the energy was generated
within Pennsylvania or the service territory of an RTO that operated in Pennsylvania
(e.g., Pennsylvania-New Jersey-Maryland (PJM) Interconnection). This permitted
an out-of-state alternative energy source to qualify so long as it was within the PJM
RTO.
However, on October 30, 2017, the General Assembly amended the
AEPS Act by enacting Act 40. Act 40, which took effect immediately, imposes
stricter geographic qualifications for solar photovoltaic systems. Under Act 40, solar
9
credits used to meet Pennsylvania’s Tier I solar requirements must come from solar
photovoltaic systems that satisfy specific interconnection or delivery criteria within
Pennsylvania. 71 P.S. §714. Specifically, Act 40 established the following
qualifications:
(1) Notwithstanding [S]ection 4 of the [AEPS Act,] in
order to qualify as an alternative energy source eligible to
meet the photovoltaic share of this Commonwealth’s
compliance requirements under the [AEPS Act] and to
qualify for solar renewable alternative energy portfolio
credits, each solar photovoltaic system must do one of the
following:
(i) Directly deliver the electricity it generates to a
retail customer of an [EDC] or to the distribution
system operated by an [EDC] operating within this
Commonwealth and currently obligated to meet the
compliance requirements contained under the
[AEPS Act.]
(ii) Be directly connected to the electric system of
an electric cooperative or municipal electric system
operating within this Commonwealth.
(iii) Connect directly to the electric transmission
system at a location that is within the service
territory of an [EDC] operating within this
Commonwealth.
(2) Nothing under this section or [S]ection 4 of the [AEPS
Act] shall affect any of the following:
(i) A certification originating within the
geographical boundaries of this Commonwealth
granted prior to the effective date of this section of
a solar photovoltaic energy generator as a
qualifying alternative energy source eligible to meet
the solar photovoltaic share of this
Commonwealth’s alternative energy portfolio
compliance requirements under the [AEPS Act.]
10
(ii) Certification of a solar photovoltaic system with
a binding written contract for the sale and purchase
of alternative energy credits derived from solar
photovoltaic energy sources entered into prior to the
effective date of this section.
(3) This section shall apply to contracts entered into or
renewed on or after the effective date of this section.
(4) As used in this section, the following words and
phrases shall have the meanings given to them in this
section unless the context clearly indicates otherwise:
“Alternative energy source.” As the term “alternative
energy sources” is defined in [S]ection 2 of the [AEPS
Act].
“[EDC].” As defined in [S]ection 2 of the [AEPS Act].
Id. (italicized emphasis added; bolded emphasis removed). The legislative history
of Act 40 reflects an intent to promote in-state solar development and prevent out-
of-state solar projects from qualifying for Pennsylvania credits.
In short, Act 40 establishes three qualifying pathways for solar systems:
(i) direct delivery to a retail customer of an EDC; (ii) interconnection with a
cooperative or municipal system; or (iii) connection to the transmission system
within a Pennsylvania EDC’s territory. 71 P.S. §714(1). Subsections (ii) and (iii)
expressly require grid interconnection; subsection (i) does not. Id. Subsection (i)
qualifies a solar photovoltaic system that “directly delivers the electricity it generates
to a retail customer of an EDC.” 71 P.S. §714(1)(i). Subsection (i) does not mandate
delivery through the grid when the recipient is a retail customer of an EDC. See id.
By its plain terms, Act 40 establishes an independent pathway for solar
credit eligibility based on direct delivery. Although the AEPS Act’s definition of an
11
“alternative energy system,” requires interconnection to the grid, there is no
language in the AEPS Act that precludes a solar photovoltaic system from qualifying
based on direct delivery as set forth in Act 40. This means that a Pennsylvania
company that is a retail customer of a Pennsylvania EDC and installs a behind-the-
meter solar system to serve its own load satisfies the “direct delivery” requirement
by delivering electricity to itself. A physical interconnection to the grid is not
required under subsection (i). This interpretation fulfills the plain language of Act
40 and aligns with the legislative intent to promote in-state solar development.
Even if ambiguity or conflict exists between the AEPS Act and Act 40
regarding grid connection, the legislative intent to expand in-state solar participation
favors Williams’ reading. 1 Pa. C.S. §1921(c). In addition, Act 40, as the latest
legislative act, prevails over any conflicting provisions of the AEPS Act. See
Mercury Trucking, 55 A.3d at 1067; 1 Pa. C.S. §§1935, 1936. This interpretation
harmonizes Act 40 and the AEPS Act by allowing Act 40 to add a new compliance
pathway for direct delivery without displacing the AEPS Act’s interconnection-
based framework. Contrary to the PUC’s position, accepting the plain language of
Act 40 does not produce an absurd result. Rather, it simply creates an additional
compliance avenue that advances renewable energy goals and reduces grid demand.
IV. Conclusion
For these reasons, we conclude that the PUC’s August 21, 2024 order
denying reconsideration and upholding its determination that Williams’ solar
photovoltaic systems were not eligible for solar credits constituted an abuse of
discretion. We hold that Act 40 permits solar photovoltaic systems that directly
deliver electricity to a retail customer of an EDC to qualify for solar credits, even
12
without grid interconnection. As a result, Williams is entitled to declaration that its
proposed solar photovoltaic systems would qualify for solar credits under the AEPS
Act as amended by Act 40. Accordingly, we reverse the PUC’s order.
MICHAEL H. WOJCIK, Judge
Judge McCullough concurs in result only.
Judge Fizzano Cannon did not participate in the decision of this case.
13
IN THE COMMONWEALTH COURT OF PENNSYLVANIA
Williams Companies, Inc., :
:
Petitioner :
:
v. : No. 1232 C.D. 2024
:
Pennsylvania Public :
Utility Commission, :
:
Respondent :
ORDER
AND NOW, this 19th day of August, 2026, the order of the
Pennsylvania Public Utility Commission, dated the August 21, 2024, is
REVERSED. We DECLARE that Williams Companies, Inc.’s proposed solar
photovoltaic systems, as described herein, would qualify to generate solar renewable
energy credits under the Alternative Energy Portfolio Standards Act (AEPS Act)1 as
amended by Section 2804 of The Administrative Code of 1929 (Act 40) 2 if they
directly deliver electricity to a retail customer of an electric distribution company.
__________________________________
MICHAEL H. WOJCIK, Judge
1
Act of November 30, 2004, P.L. 1672, as amended, 73 P.S. §§1648.1-1648.8.
2
Act of April 9, 1929, P.L. 177, added by the Act of October 30, 2017, P.L. 379,
71 P.S. §714.
IN THE COMMONWEALTH COURT OF PENNSYLVANIA
Williams Companies, Inc., :
Petitioner :
:
v. : No. 1232 C.D. 2024
: Argued: September 10, 2025
Pennsylvania Public Utility :
Commission, :
Respondent :
BEFORE: HONORABLE RENÉE COHN JUBELIRER, President Judge
HONORABLE PATRICIA A. McCULLOUGH, Judge
HONORABLE ANNE E. COVEY, Judge
HONORABLE MICHAEL H. WOJCIK, Judge
HONORABLE LORI A. DUMAS, Judge
HONORABLE STACY WALLACE, Judge
HONORABLE MATTHEW S. WOLF, Judge
DISSENTING OPINION BY
PRESIDENT JUDGE COHN JUBELIRER FILED: August 19, 2026
The Majority holds that Section 2804 of The Administrative Code of 1929
(Act 40)1 creates an independent avenue for solar photovoltaic systems that are not
interconnected to the electric grid to generate solar renewable energy credits under
the Alternative Energy Portfolio Standards Act (AEPS Act).2 Consequently, the
Majority reverses a Pennsylvania Public Utility Commission (Commission) decision
that two solar photovoltaic systems proposed by Williams Companies, Inc.
(Williams) that bypass the electric grid cannot generate solar renewable energy
credits. Because I believe the Majority misinterprets Act 40 and reshapes the
1
Act of April 9, 1929, P.L. 177, as amended, added by the Act of October 30, 2017, P.L.
379, No. 40, 71 P.S. § 714.
2
Act of November 30, 2004, P.L. 1672, as amended, 73 P.S. §§ 1648.1–1648.8.
alternative energy credit scheme established by the General Assembly in the AEPS
Act, which requires interconnection with the electric grid, I respectfully dissent.
The General Assembly enacted the AEPS Act after “recogniz[ing] the need
for environmentally cleaner alternatives to fossil fuel energy production” in the
Commonwealth. Hommrich v. Pa. Pub. Util. Comm’n, 231 A.3d 1027, 1033
(Pa. Cmwlth. 2020). To accomplish this goal, Section 3(a)(1) of the AEPS Act
requires that “electricity generated from alternative energy sources,” such as solar
photovoltaic energy, comprise a certain percentage of “the electric energy sold by
an electric distribution company or electric generation supplier to retail electric
customers.” 73 P.S. § 1648.3(a)(1). To ensure compliance with this requirement,
Section 3(e)(4)(i) of the AEPS Act mandates that electric distribution companies and
electric generation suppliers “purchas[e] sufficient alternative energy credits and
submit[] documentation of compliance to the program administrator.” 73 P.S.
§ 1648.3(e)(4)(i); see also Section 2 of the AEPS Act, 73 P.S. § 1648.2 (defining
“alternative energy credit” as “[a] tradable instrument that is used to establish, verify
and monitor compliance with [the AEPS Act]”). For purposes of Section 3(e)(4),
one alternative energy credit equals “one megawatt hour of qualified alternative
electric generation.” 73 P.S. § 1648.3(e)(4)(ii); see also 73 P.S. § 1648.2 (“A unit
of credit shall equal one megawatt hour of electricity from an alternative energy
source.”). Alternative energy credits can be either “self-generated” or “purchased
along with the electric commodity or separately through a tradable instrument.” 73
P.S. § 1648.3(e)(4)(ii).
Initially, the AEPS Act did not specify who owned the alternative energy
credits generated by alternative energy sources. ARIPPA v. Pa. Pub. Util. Comm’n,
966 A.2d 1204, 1207 (Pa. Cmwlth. 2009). In 2007, the General Assembly amended
RCJ - 2
the AEPS Act to provide that unless a contract explicitly assigns the credit
differently, “the owner of the alternative energy system or a customer-generator
owns any and all alternative energy credits associated with or created by the
production of electric energy by such facility or customer.” 73 P.S. § 1648.3(e)(12).3
The AEPS Act defines “alternative energy system” as “[a] facility or energy system
that uses a form of alternative energy source to generate electricity and delivers the
electricity it generates to the distribution system of an electric distribution company
or to the transmission system operated by a regional transmission organization.”
73 P.S. § 1648.2. In turn, “customer-generator” is defined as
A nonutility owner or operator of a net metered distributed generation
system[4] with a nameplate capacity of not greater than 50 kilowatts if
installed at a residential service or not larger than 3,000 kilowatts at
other customer service locations, except for customers whose systems
are above three megawatts and up to five megawatts who make their
systems available to operate in parallel with the electric utility during
grid emergencies as defined by the regional transmission organization
or where a microgrid is in place for the primary or secondary purpose
of maintaining critical infrastructure, such as homeland security
assignments, emergency services facilities, hospitals, traffic signals,
wastewater treatment plants or telecommunications facilities, provided
that technical rules for operating generators interconnected with
facilities of an electric distribution company, electric cooperative or
municipal electric system have been promulgated by the Institute of
Electrical and Electronic Engineers and the . . . Commission.
Id. To qualify as an alternative energy system or customer-generator, the generation
system must interconnect with the electric grid in some manner. See id.; see also
Hommrich v. Pa. Pub. Util. Comm’n, 344 A.3d 121, 127 (Pa. Cmwlth. 2025).
3
Section 3(e)(12) was added by Section 2 of the Act of July 17, 2007, P.L. 114.
4
“Net metering” is “[t]he means of measuring the difference between the electricity
supplied by an electric utility and the electricity generated by a customer-generator when any
portion of the electricity generated by the alternative energy generating system is used to offset
part or all of the customer-generator’s requirements for electricity.” 73 P.S. § 1648.2.
RCJ - 3
Accordingly, the AEPS Act contemplates that only alternative energy sources
owned by alternative energy systems or customer-generators—both of which must
be interconnected to the electric grid in some manner—qualify to generate
alternative energy credits. See 73 P.S. §§ 1648.2, 1648.3(e)(12). Once alternative
energy credits are generated, “the owner or customer shall be entitled to sell, transfer
or take any other action to which a legal owner of property is entitled to take with
respect to the credits.” 73 P.S. § 1648.3(e)(12); see also 73 P.S. § 1648.2 (“The
alternative energy credit shall remain the property of the alternative energy system
until the alternative energy credit is voluntarily transferred by the alternative energy
system.”).
Also in 2007, the General Assembly amended Section 4 of AEPS Act to
expand where an alternative energy source must be located to generate the
alternative energy credits necessary to satisfy the Commonwealth’s alternative
energy portfolio requirements. Section 4 of the AEPS Act establishes three distinct
geographic options for an alternative energy source to qualify to generate alternative
energy credits:
[1] Energy derived from alternative energy sources inside the
geographical boundaries of this Commonwealth shall be eligible to
meet the compliance requirements under [the AEPS A]ct. [2] Energy
derived from alternative energy sources located outside the
geographical boundaries of this Commonwealth but within the service
territory of a regional transmission organization that manages the
transmission system in any part of this Commonwealth shall only be
eligible to meet the compliance requirements of electric distribution
companies or electric generation suppliers located within the service
territory of the same regional transmission organization. [3] For
purposes of compliance with [the AEPS A]ct, alternative energy
sources located in the PJM Interconnection, L.L.C. regional
transmission organization (PJM) or its successor service territory shall
be eligible to fulfill compliance obligations of all Pennsylvania electric
distribution companies and electric generation suppliers.
RCJ - 4
73 P.S. § 1648.4. “Energy derived from alternative energy sources located outside
the service territory of a regional transmission organization that manages the
transmission system in any part of this Commonwealth shall not be eligible to meet
the compliance requirements of [the AEPS A]ct.” Id.
A decade later, the General Assembly enacted Act 40. Act 40 amended
Section 4 of the AEPS Act to impose stricter geographic requirements for solar
photovoltaic systems to qualify to generate alternative energy credits. Relevantly,
Act 40 provides:
(1) Notwithstanding [S]ection 4 of the [AEPS Act], in order to qualify
as an alternative energy source eligible to meet the photovoltaic share
of this Commonwealth’s compliance requirements under the [AEPS
Act] and to qualify for solar renewable alternative energy portfolio
credits, each solar photovoltaic system must do one of the following:
(i) Directly deliver the electricity it generates to a retail customer
of an electric distribution company or to the distribution system
operated by an electric distribution company operating within
this Commonwealth and currently obligated to meet the
compliance requirements contained under the [AEPS Act.]
(ii) Be directly connected to the electric system of an electric
cooperative or municipal electric system operating within this
Commonwealth.
(iii) Connect directly to the electric transmission system at a
location that is within the service territory of an electric
distribution company operating within this Commonwealth.
71 P.S. § 714(1) (emphasis added).
As the Majority observes, Act 40 “imposes stricter geographic qualifications
for solar photovoltaic systems,” intending “to promote in-state solar development
and prevent out-of-state solar projects from qualifying for Pennsylvania credits.”
Williams Companies, Inc. v. Pa. Pub. Util. Comm’n, ___ A.3d ___, ___ (Pa.
RCJ - 5
Cmwlth. 2026), slip op. at 9, 11. But the Majority takes Act 40 much further. The
Majority concludes that the provision “[d]irectly deliver the electricity it generates
to a retail customer of an electric distribution company” creates “an independent
pathway” for solar photovoltaic systems that are not interconnected to the electric
grid to generate alternative energy credits. Id., slip op. at 10-12. The Majority
therefore interprets Act 40 as not merely imposing stricter geographic
requirements for solar photovoltaic systems to generate alternative energy credits
but as a sweeping amendment to the alternative energy credit scheme created by the
AEPS Act. The Majority misinterprets Act 40.
By stating “[n]otwithstanding [S]ection 4 of the [AEPS Act],” Act 40
preempts only Section 4 of the AEPS Act and does so to the extent Section 4 governs
where solar photovoltaic systems must be located to generate alternative energy
credits. As our Supreme Court has explained, “the use of ‘notwithstanding’” is “an
unambiguous expression of the General Assembly’s intent to distinguish the law
applicable to the circumstances addressed within the ‘notwithstanding’ clause
from the law applicable to the circumstances that follow that clause.” City of
Johnstown v. Workers’ Comp. Appeal Bd. (Sevanick), 255 A.3d 214, 222 (Pa. 2021)
(emphasis added); see also Pleasant Hills Constr. Co., Inc. v. Pub. Auditorium Auth.,
784 A.2d 1277, 1283 (Pa. 2001) (concluding that a “notwithstanding” clause is
“clear,” means “regardless,” and preempts the law mentioned in the clause).
Therefore, Act 40 only amends Section 4 of the AEPS Act to impose stricter in-state
requirements for solar photovoltaic systems to generate alternative energy credits.
By its plain language, Act 40 does not amend any other provision of the AEPS Act,
including Sections 2 and 3 of the AEPS Act.
RCJ - 6
Moreover, Act 40 is consistent with the alternative energy credit scheme
created by Sections 2 and 3 of the AEPS Act. Relevantly, Act 40 provides that a
solar photovoltaic system qualifies to generate alternative energy credits if the
system “[d]irectly deliver[s] the electricity it generates to a retail customer of an
electric distribution company or to the distribution system operated by an electric
distribution company.” 71 P.S. § 714(1)(i). Under Sections 2 and 3 of AEPS Act,
alternative energy sources owned by alternative energy systems or customer-
generators, which are interconnected with the electric grid, may generate
alternative energy credits. 73 P.S. §§ 1648.2, 1648.3(e)(12). An alternative energy
system “delivers the electricity it generates to the distribution system of an electric
distribution company,” whereas a customer-generator delivers the electricity it
generates to a retail customer of an electric distribution company, i.e., the customer-
generator, “to offset part or all of the customer-generator’s requirements for
electricity” by net metering. 73 P.S. § 1648.2. Accordingly, under Act 40, a solar
photovoltaic system qualifies to generate alternative energy credits if the system is
a customer-generator (i.e., “[d]irectly deliver[s] the electricity it generates to a retail
customer of an electric distribution company”) or an alternative energy system (i.e.,
“[d]irectly deliver[s] the electricity it generates . . . to the distribution system
operated by an electric distribution company”). 71 P.S. § 714(1)(i); 73 P.S.
§§ 1648.2, 1648.3(e)(12). Therefore, contrary to the Majority’s conclusion, Act 40
did not create an independent avenue for solar photovoltaic systems to generate
alternative energy credits but aligns with the alternative energy credit scheme
created by the