DSME Construction Co., Ltd.
CourtArmed Services Board of Contract Appeals
Date FiledApril 17, 2026
Docket63878
JudgeMcIlmail
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
DSME Construction Co., Ltd. ) ASBCA No. 63878
)
Under Contract No. W91QVN-23-D-0038 )
APPEARANCE FOR THE APPELLANT: Yong Eui Song, Esq.
Central IP & Law
Seoul, Korea
APPEARANCES FOR THE GOVERNMENT: Dana J. Chase, Esq.
Army Chief Trial Attorney
LTC Bruce A. Nessler, JA
CPT Natalie W. McKiernan, JA
MAJ Katharine M. Calderon, JA
Trial Attorneys
OPINION BY ADMINISTRATIVE JUDGE MCILMAIL
The parties contracted for appellant, DSME Construction Co., Ltd., to provide
maintenance and repair services at Camp Humphries and Camp Yongin, in the
Republic of Korea. The contracting officer terminated the contract for default. A
month later, rather than appealing to this Board from the termination for default,
DSME presented to the contracting officer a claim for (1) conversion of the
termination to one for the convenience of the government, and (2) payment of
approximately $2 million, including an amount for work performed prior to the
termination. Ninety-seven days after the termination of the contract for default, the
contracting officer denied DSME’s claim for conversion and money. DSME appeals
from that decision. Among the government’s positions is its affirmative defense that
the contract is void ab initio, for fraud and material misrepresentation. 1 The parties
elected to proceed without a live hearing, pursuant to Board Rule 11. 2
1
Amend. ans. at 102-03.
2
We have not considered DSME’s surreply in arriving at this opinion, as a sanction in
response to the preparation of that brief. DSME Constr. Co., Ltd., ASBCA
No. 63878, 26-1 BCA ¶ 39,026 at 190,053.
FINDINGS OF FACT
The parties entered the contract on April 13, 2023, for DSME to “[p]rovide
preventive maintenance in the critical facilities and dining facilities at Camp Humphreys
and Camp Yongin [in accordance with the Performance Work Statement (PWS)], for
3,358,244,779 South Korean Won (KRW) ($2,270,495.86),” 3 through a base period
ending December 31, 2023. 4 The contract incorporates by reference Federal Acquisition
Regulation (FAR) 52.212-4, Contract Terms and Conditions - Commercial Products and
Commercial Services (NOV 2021), which provides at paragraph (m), Termination for
cause:
The Government may terminate this contract, or any part
hereof, for cause in the event of any default by the
Contractor, or if the Contractor fails to comply with any
contract terms and conditions . . . . 5
FAR 52.212-4 further provides, at paragraph (f), Excusable delays:
The Contractor shall be liable for default unless
nonperformance is caused by an occurrence beyond the
reasonable control of the Contractor and without its fault or
negligence . . . .
According to ¶¶ 1.0 and 1.1 of the PWS, the government needed an “enhanced
maintenance program in the specific areas of heating, ventilating, and air-conditioning
(HVAC) system, electrical systems, and built-in food service equipment of [] selected
buildings,” and the contractor was to “provide all personnel, equipment, supplies,
facilities, transportation, tools, materials, supervision, and other items and non-
personal services necessary to provide maintenance and repair services for thirty-three
(33) critical facilities” at the two camps. 6 The government says that the contract’s
“full performance period” began on July 1, 2023; 7 DSME says that “contract
commencement” began on July 3, 2023. 8
The PWS provides, in ¶ 9.2.2, Cooling Towers, that “[d]ue to absence of
necessary water treatment system of the supply water flowing into the cooling towers,
the Contractor shall . . . remove sludge on . . . inside/outside of the cooling towers
3
As of April 16, 2026.
4
See R4, tab 1 at 1-3 (alteration added).
5
R4, tab 1 at 23 (emphasis added).
6
R4, tab 1a at 1-2.
7
Gov’t br. at 2.
8
App. br. at 5.
2
every other week or more frequently.” 9 Ultimately, DSME was responsible for
removing sludge at that rate from 29 cooling towers. 10 However, DSME performed
sludge removal only three times: once each from only three cooling towers. 11
On May 8, 2023, the parties modified the contract to require that DSME
inventory all equipment and submit an inventory report to the government no later
than 70 days (from an original 85 days) “once Phase-In is started.” 12 We find that the
phase-in period started on April 13, 2023, when the contract was awarded, and ended
70 days later, on June 22, 2023. 13 On August 8, 2023, the government issued a stop
work order, effective August 9, 2023. 14 DSME did not provide a complete inventory
until August 31, 2023. 15
On October 17, 2023, the contracting officer terminated the contract for
default. 16 Among the reasons that the contracting officer identified for the termination
of the contract are that DSME had not timely provided an accurate inventory list, and
had not adequately removed sludge from cooling towers. 17
On November 16, 2023, DSME submitted to the contracting officer a certified
claim asserting that “the government wrongfully and improperly terminated the
Contract,” and requesting conversion of the termination to one for the convenience of
the government and payment of 3,050,892,883 KRW ($2,062,696.47), 18 “for the work
DSME performed prior to the termination and loss and damages incurred by DSME
thereafter due to the wrongful and improper termination.” 19 On January 22, 2024, the
contracting officer issued a decision stating that:
9
R4, tab 1a at 42 § 9.2.2 (emphasis added).
10
Gov’t br. at 18 ¶ 39; app. br. at 23-24 ¶ 81.
11
Gov’t br. at 18 ¶ 39; see app. br. at 14-15 ¶¶ 37-39.
12
See R4, tab 2 at 1-3.
13
DSME agrees. App. br. at 29 ¶ 102. The government says that the phase-in period
began on April 17, 2023, and ended on June 30, 2023. Gov’t br. at 10 ¶ 22, 33,
35. That discrepancy is immaterial, because DSME did not provide a complete
inventory until August 31, 2023. App br. at 24-25 ¶¶ 84, 86.
14
R4, tab 4; gov’t br. at 23 ¶ 57; app. br. at 5 ¶ 4.
15
App br. at 24-25 ¶¶ 84, 86.
16
R4, tabs 5b, 5c.
17
See R4, tab 5c at 1, 4.
18
As of April 16, 2026.
19
R4, tab 56 at 2-3, 201, 203, tab 56zn. In its complaint at page 1, DSME alleges that
it “made the claim” on November 16, 2023. At page 3 of its answer, the
government alleges that the contracting officer received the “complete claim”
on November 20, 2023, citing page 1 of the contracting officer’s decision. But
the contracting officer’s decision states that DSME’s claim is “dated
3
the Contracting Officer has determined not to convert the
termination from [a termination for default] to [a
termination for convenience]. The Government will pay
for performance provided by DSME from 17 April 2023
thru 8 August 2023 (the stop work order date) [in
accordance with] the contract. The contracting officer has
repeatedly requested an invoice based on this amount and
does not recognize the amount as part of this claim, as it
has not been properly invoiced as of this time. 20
DSME noticed this appeal 85 days later, on April 16, 2024.
DECISION
I. Jurisdiction
Given that the contracting officer’s January 22, 2024 decision was issued
seven days after the expiration of the 90-day period within which DSME could have
timely appealed the contracting officer’s October 17, 2023 termination of the contract
for default, we invited the parties to brief the issue of our jurisdiction. DSME says that
we possess jurisdiction; the government disagrees. We find jurisdiction to entertain
the appeal.
While receipt by a contracting officer of a contractor’s request for
reconsideration of a contracting officer’s final decision does not vacate such a decision,
a contracting officer’s reconsideration of such a decision does. See Royal Int’l Builders
Co., ASBCA No. 42637, 92-1 BCA ¶ 24,684 at 123,135; see also Guardian Angels
Med. Serv. Dogs, Inc. v. United States, 809 F.3d 1244, 1249-51 (Fed. Cir. 2016).
Although the contracting officer’s January 22, 2024 decision ultimately rejects DSME’s
asserted excuses for its default, by entertaining DSME’s November 2023 claim for
conversion of the October 2023 default termination to one for the convenience of the
government along with the associated alleged monetary damages, that January 22, 2024
decision effectively reconsiders the October 2023 decision to base the termination of
the contract upon the determination that DMSE had defaulted upon its contractual
obligations. In addition, the January 22, 2024 decision acknowledges that the
government owes DSME an unspecified amount for performance, but only for the
period April 17 through August 8, 2023. This appeal challenges those determinations.
20 November 2023,” even though DSME’s claim is dated November 16, 2023.
R4, tab 6 at 1 (emphasis added), tab 56 at 1, 203. We find that the contracting
officer received DSME’s claim on November 16, 2023.
20
R4, tab 6 at 13 (alterations added).
4
Because DSME timely appealed from the contracting officer’s January 22, 2024
decision, we possess jurisdiction to entertain this appeal.
II. Equipment Inventory
DSME was to have inventoried all equipment, and submitted a report of that
inventory to the government, no later than June 22, 2023. However, DSME admits
that it did not submit what it describes as an “accurate inventory list” until August 31,
2023. 21 Because DSME failed to inventory all equipment and submit a report of such
inventory no later than June 22, 2023, DSME defaulted.
Now it’s up to DSME to demonstrate that its default is excused. See HK&S
Constr. Holding Corp., ASBCA No. 60164, 19-1 BCA ¶ 37,268 at 181,352. DSME
offers several excuses: that the government did not provide an inventory list until
April 26, 2023; that the government-provided inventory list was inaccurate; that the
government impeded access to at least some buildings; and that the government did
not respond to DSME’s June 7, 2023 inventory list. 22 We are unpersuaded. DSME
does not demonstrate that the contract required the government to help DSME conduct
an inventory of all equipment and submit a report of that inventory; nor does DSME
support with any evidence its contention that the government impeded its access to
buildings, and “simply saying it does not make it so.” ECC Int’l LLC, ASBCA
Nos. 61176, 62029, 21-1 BCA ¶ 37,824 at 183,692. For these reasons, we conclude
that DSME’s failure to inventory all equipment and submit an inventory report to the
government no later than 70 days after the contract’s phase-in period started is not
excused.
III. Removal of Sludge from Cooling Towers
Section 9.2.2 of the PWS requires that the contractor “remove sludge on . . .
inside/outside of the cooling towers every other week or more frequently.” 23 With the
removal of some buildings from the scope of work, DSME was ultimately responsible
for removing sludge, at least twice per month, from 29 cooling towers. 24 However,
DSME removed sludge from only three cooling towers, and only once from each. 25
That constitutes a default.
21
See app. br. at 24-26, 29 ¶ 106, 31 ¶ 115; app. reply br. at 25.
22
See app. br. at 24-35; app. reply br. at 24-26.
23
R4, tab 1a at 42.
24
Gov’t br. at 18 ¶ 39; app. br. at 23-24 ¶ 81.
25
Gov’t br. at 18 ¶ 39; see app. br. at 14-15 ¶¶ 37-39. DSME says that it removed
sludge “from three cooling towers in Building 6100,” in response, not to a call
for preventative maintenance pursuant to ¶ 9.2.2 of the PWS, but to “an urgent
5
By way of excuse, DSME says that it “had great difficulty in removing sludge”
from those three cooling towers, because, pointing to ¶ 9.1.1 of the PWS, “the
government did not provide the cooling tower Manuals.” 26 Paragraph 9.1.10,
Preventive Maintenance (PM), provides that:
The Preventive Maintenance consists primarily of
inspection, cleaning, lubrication, adjustment, calibration,
operation, on-call minor repair services and component
replacement for minor repair as required minimizing
malfunction, breakdown, and deterioration of equipment.
The PMs shall be performed as specified in manufacture’s
maintenance manual or recommendation. 27
However, paragraph 9.1.10 does not state that the government must provide
maintenance manuals; moreover, paragraph 9.1.5 of the PWS required DSME to
“maintain [Operation and Maintenance] Manuals, at an on-site location,” 28 and, as the
government points out, 29 paragraph 9.9 of the PWS required DSME to “update
manufacture’s manual for preventive maintenance tasks for all equipment in the
contract during the base year,” and to “submit the updated manufacture’s (sic) manual
[to the government] by 5th day (sic) of every month.” 30 Finally, ¶ 1.0 of the PWS
required DSME to provide all equipment, supplies, tools, materials, and other items
necessary to provide maintenance and repair services at the two camps. 31 Those
provisions indicate that DSME was responsible for obtaining manuals, and do not
indicate that the government was required to provide manuals to DSME.
Consequently, DSME’s obligation to perform sludge removal in cooling towers was
not dependent upon the government providing “a manufacturer’s maintenance manual
or recommendation.”
DSME also says that “the three cooling towers were not chemically treated as
required in paragraph 9.2.24 of [the] PWS within the six (6) months preceding July 1,
2023,” which DSME says resulted in sludge hardening. 32 Indeed, as DSME points
out, the government admitted in discovery that none of the cooling towers was
call for service and repair” pursuant to ¶¶ 9.1.1 and 9.1.2.3. App. br. at 15
¶¶ 38-41.
26
App. br. at 14 ¶ 37.
27
R4, tab 1a at 37 (emphasis added).
28
R4, tab 1a at 35 (alteration added).
29
Gov’t reply at 3 ¶ 5.
30
R4, tab 1a at 65.
31
R4, tab 1a at 1-2.
32
App. br. at 14 (alteration added).
6
chemically treated “as required in paragraph 9.2.24.” 33 However, we take DSME’s
statement that it removed sludge from three cooling towers as an admission that it was
able to remove sludge from cooling towers not only without a government-provided
manual, but without the cooling towers having been previously chemically treated to
address sludge hardening. We further note that DSME does not demonstrate that it
could have removed sludge three times from all 29 cooling towers at least every other
week during the month spanning July 3 through August 3, 2020, if only the
government had provided manuals and the cooling towers had been pre-treated.
Indeed, DSME does not even say how long it took to remove sludge from the
three cooling towers from which it removed sludge. Nor does DSME point to any
record evidence of the sludge hardening that it says it encountered, or say that it
inspected the 26 cooling towers from which it did not remove sludge and discovered
the same sludge hardening that it claims it discovered in the three cooling towers from
which it did remove sludge. For these reasons, we conclude that DMSE’s failure to
remove sludge from cooling towers at the rate required by the contract is not excused.
IV. Payment for Work Performed
DSME claims 2,090,097,537 KRW for work performed, pointing to
two spreadsheets that appear to reflect expenses incurred from April through
October 2023. 34 DSME also says that “[t]he government acknowledged . . . that it
owed [DSME] 79,528,329 [KRW] for the work performed from August 1 to August 8,
2023”; that is, through the date that the government issued the stop work order. 35 The
government replies that it “has already paid appellant the full firm-fixed price for each
month of phase-in (April through June 2023), as well as for all CLINs for the month of
July 2023,” 36 and that it owes DSME 97,174,240 KRW 37 “for full performance [of
certain contract line items] from August 1, 2023 to August 8, 2023,” but that, “[a]s of
May 29, 2025, [DSME] had not submitted an invoice to be paid for [that period].” 38
Again, we have not considered DSME’s surreply in arriving at this opinion. Finding
that the government’s statement is unrebutted, and that it includes an admission
against the government’s interest that it owes DSME 97,174,240 KRW amount for
work performed from August 1 to 8, 2023, we award DSME that amount. The
government provides no authority for its apparent position that DSME should not be
awarded that amount because DSME did not invoice that amount. The government
also urges that interest not be awarded upon this amount, but, as the government also
notes, quoting and citing 41 U.S.C. § 7109(a)(1), “[i]nterest on an amount found due
33
App. br. at 18; app. supp. R4, tab 109 at 7-8.
34
App. br. at 51, 54 (citing app. supp. R4, tabs 106-07).
35
App. br. at 52 ¶ 197 (alterations added); R4, tab 4.
36
Gov’t reply at 41-42.
37
$65,699.11, as of April 16, 2026.
38
Gov’t reply at 5 ¶ 9 (alterations added).
7
to a contractor on a claim shall be paid to the contractor for the period beginning with
the date the contracting officer receives the contractor’s claim”; 39 consequently,
interest will be paid. The government does not say that the 97,174,240 KRW that it
owes DSME for work performed in August 2023 is not included in DSME’s
November 16, 2023 claim to the contracting officer; indeed, that claim includes a
spreadsheet requesting 375,036,587 KRW for August 2023. 40
CONCLUSION
We have considered the parties’ other positions, including the government’s
affirmative defense that the contract is void ab initio, and find them unnecessary to
address because we are denying the appeal except as to amounts that the government
does not dispute that it owes. Accordingly, the appeal is sustained in the amount of
97,174,240 KRW, with interest under 41 U.S.C. § 7109, from November 16, 2023—
the date that the contracting officer received appellant’s certified claim—and is
otherwise denied.
Dated: April 17, 2026
TIMOTHY P. MCILMAIL
Administrative Judge
Armed Services Board
of Contract Appeals
I concur I concur
J. REID PROUTY MICHAEL N. O’CONNELL
Administrative Judge Administrative Judge
Acting Chairman Vice Chairman
Armed Services Board Armed Services Board
of Contract Appeals of Contract Appeals
39
Gov’t reply at 42.
40
R4, tab 56 at 201.
8
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 63878, Appeal of DSME
Construction Co., Ltd., rendered in conformance with the Board’s Charter.
Dated: April 20, 2026
PAULLA K. GATES-LEWIS
Recorder, Armed Services
Board of Contract Appeals