Walsh Turner Joint Venture II v. Secretary of the Army
CourtCourt of Appeals for the Federal Circuit
Date FiledNovember 23, 2026
Docket25-2024
StatusUnpublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
Case: 25-2024 Document: 36 Page: 1 Filed: 11/23/2026
NOTE: This disposition is nonprecedential.
United States Court of Appeals
for the Federal Circuit
______________________
WALSH TURNER JOINT VENTURE II,
Appellant
v.
SECRETARY OF THE ARMY,
Appellee
______________________
2025-2024
______________________
Appeal from the Armed Services Board of Contract Ap-
peals in No. 63665, Administrative Judge Heidi L. Oster-
hout, Administrative Judge J. Reid Prouty, Administrative
Judge Owen C. Wilson.
______________________
Decided: November 23, 2026
______________________
SEAN MICHAEL HOWLEY, Kraftson Caudle, McLean,
VA, argued for appellant. Also represented by LARRY
WAYNE CAUDLE, JR., BRAD C. FRIEND.
VIJAYA SURAMPUDI, Commercial Litigation Branch,
Civil Division, United States Department of Justice, Wash-
ington, DC, argued for appellee. Also represented by
STEVEN MICHAEL MAGER, PATRICIA M. MCCARTHY, BRETT
SHUMATE.
Case: 25-2024 Document: 36 Page: 2 Filed: 11/23/2026
2 WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY
______________________
Before TARANTO, LINN, and CUNNINGHAM, Circuit Judges.
TARANTO, Circuit Judge.
Walsh Turner Joint Venture II (Walsh) contracted with
the United States Army Corps of Engineers (Corps, or gov-
ernment) in August 2021 to build a new Veterans Affairs
Medical Center (VAMC) in Louisville, Kentucky, in ex-
change for about $840 million. On September 9, 2021, the
President of the United States issued an executive order
that broadly required employees of government contractors
and subcontractors to be vaccinated against COVID-19.
On November 3, after Department of Defense implementa-
tion of the executive order, the Corps sent Walsh a request
for a proposal (RFP) to address recovery of contractor costs
of the new obligations, with a cover letter using the word
“mandatory.” On November 30, a district court preliminar-
ily enjoined the executive order in Kentucky as likely un-
constitutional and statutorily unauthorized. Two days
later the government rescinded the obligations and RFP.
Shortly thereafter, Walsh argued to the Corps that the
government, by its actions based on the executive order,
had made a material change to the terms of the construc-
tion contract, warranting damages to compensate for re-
sulting increases in raw-material and labor costs. The
Corps denied relief. Walsh then sought relief from the
Armed Services Board of Contract Appeals, but the Board
dismissed Walsh’s complaint for failure to state a claim.
Appeal of Walsh Turner Joint Venture II, ASBCA
No. 63665, 2025 WL 1554019 (May 8, 2025) (Decision). Be-
cause Walsh’s complaint sufficiently alleges a constructive
change, we reverse and remand for further proceedings, in-
cluding full analysis of the government’s sovereign-acts-
doctrine defense, which the Board did not address.
Case: 25-2024 Document: 36 Page: 3 Filed: 11/23/2026
WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY 3
I
A
The government awarded Walsh a contract to construct
a new VAMC in Louisville, Kentucky, on August 17, 2021,
in exchange for $840,131,340. “The contract incorporated
by reference Federal Acquisition Regulation (FAR) 52.243-
4, CHANGES (J[une] 2007) [48 C.F.R. § 52.243-4].” Deci-
sion, at 2. 1 The FAR Changes Clause specifies that a con-
tracting officer may, “by written order designated or
indicated to be a change order, make changes in the work
within the general scope of the contract, including
changes— . . . [i]n the method or manner of performance of
the work” or directing “acceleration in the performance of
the work.” FAR 52.243-4(a) (emphasis added); see
Bell/Heery v. United States, 739 F.3d 1324, 1333 n.2 (Fed.
Cir. 2014) (quoting FAR 52.243-4(a)–(d)). The clause then
calls for similar treatment of changes (with no further def-
inition of what constitutes a change) even if there is no ex-
press “change order”:
(b) Any other written or oral order (which, as used
in this paragraph (b), includes direction, instruc-
tion, interpretation, or determination) from the
Contracting Officer that causes a change shall be
treated as a change order under this clause; pro-
vided[] that the Contractor gives the Contracting
Officer written notice stating . . . [t]hat the Con-
tractor regards the order as a change order.
...
(d) If any change under this clause causes an in-
crease or decrease in the Contractor’s cost of, or the
1 We give the native page numbers on the Board de-
cision, which match the Joint Appendix page numbers. See
J.A. 1–13.
Case: 25-2024 Document: 36 Page: 4 Filed: 11/23/2026
4 WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY
time required for, the performance of any part of
the work under this contract, whether or not
changed by any such order, the Contracting Officer
shall make an equitable adjustment and modify the
contract in writing.
FAR 52.243-4(b), (d), quoted in Decision, at 2–3. That lan-
guage provides for compensation for constructive changes.
See Sauer Inc. v. Danzig, 224 F.3d 1340, 1348 (Fed. Cir.
2000).
The contract also contained a series of exercisable op-
tions, each with an accompanying deadline, allowing the
Corps to alter the terms of performance in certain, agreed-
upon ways. One such option, “Option K,” allowed the Corps
to call for a particular sound system—an “alternate digital
public address system”—to be installed in the VAMC.
J.A. 397 (capitalization altered). But the option had to be
exercised within 60 days after the Corps issued the notice
to proceed with contract performance. Id. According to
Walsh, this was the contract option with the shortest turn-
around following the notice to proceed. J.A. 15, ¶ 4.
On September 9, 2021, the President, invoking the au-
thority granted by the Federal Property and Administra-
tive Services Act (FPASA), 40 U.S.C. § 101 et seq., and his
authority to delegate executive functions, 3 U.S.C. § 301,
issued Executive Order 14042 (E.O. 14042), titled “Ensur-
ing Adequate COVID Safety Protocols for Federal Contrac-
tors,” which was published in the Federal Register five
days later. 86 Fed. Reg. 50985 (Sept. 14, 2021). The order
instructed executive agencies to ensure that contracts “in-
clude a clause that the contractor and any subcontractors
(at any tier) shall incorporate into lower-tier subcontracts,”
the clause to implement COVID-safety guidance, as issued
by the Safer Federal Workforce Taskforce (Taskforce).
E.O. 14042 § 2. The order specified certain categories of
covered contracts, including procurement contracts for con-
Case: 25-2024 Document: 36 Page: 5 Filed: 11/23/2026
WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY 5
struction, and stated that it applied to new contracts, solic-
itations for or extensions or renewals of the same, and “ex-
ercise[s] of an option on [ ] existing contract[s]” for
procurement (all of the above also covering “contract-like
instrument[s]”). E.O. 14042 § 5.
In response, on October 1, the Department of Defense
(DOD) issued Class Deviation 2021-O0009, which specified
model contract language to be incorporated into contracts,
codifying the language as DOD Defense Federal Acquisi-
tion Regulation Supplement (DFARS) 252.223-7999.
J.A. 63; see J.A. 77–78. The parties refer to the language
as the “DFARS Clause.” The clause required that all con-
tractors “comply with all guidance” issued by the Taskforce
“as amended during [ ] performance” for “contractor or sub-
contractor workplace locations.” DFARS Clause § (c). It
required the contractor to “include the substance of this
clause . . . in subcontracts at any tier that exceed” a certain
(low) threshold “and are for services, including construc-
tion, performed in whole or in part within the United
States or its outlying areas.” Id. § (d). According to the
Corps contracting officer, the Taskforce “protocols man-
dated COVID-19 vaccination for federal contractor-covered
employees at all tiers by 8 December 2021.” J.A. 356.
On October 4, 2021, the Corps issued Walsh a notice to
proceed with the work under the August contract, specify-
ing a completion date of January 5, 2026. Decision, at 2.
On November 3, 2021, the Corps sent to Walsh a re-
quest for proposal (RFP) addressing implementation of the
DFARS Clause. J.A. 61. The cover letter to which the RFP
was attached, see Decision, at 4, states that, pursuant to
E.O. 14042, the DFARS Clause “will be incorporated into
[Corps] contracts,” J.A. 24. The letter also states that the
Corps “strongly encourages” Walsh to “accept this contract
modification at this time” and that “[t]he modification is
mandatory before [the Corps] will renew, extend the pe-
Case: 25-2024 Document: 36 Page: 6 Filed: 11/23/2026
6 WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY
riod of performance . . . , or exercise an option.” Id. (em-
phasis in original). The body of the enclosed RFP (itself in
the form of a letter from the contracting officer) states that
“the following change” to the contract’s statement of work,
i.e., adding the DFARS Clause to “[p]rovide all labor, ma-
terials, and equipment to perform the following scope of
work”—“is under consideration,” and it then immediately
says that Walsh is “hereby requested to submit a proposal
to provide all labor, material, and equipment necessary to
complete the statement of work” in light of the just-noted
change. J.A. 61. The RFP letter notes that it “does not
constitute a notice to proceed with the work involved”—
which, we note, had already issued for this contract—and
instructs Walsh to submit its proposal by November 9.
J.A. 61–62. On November 5, the Corps gave Walsh an ex-
tension of the due date to sometime in December. Decision,
at 4.
On November 30, 2021, a federal district court prelim-
inarily enjoined the government from enforcing E.O. 14042
against both state and private contractors within Ken-
tucky, Ohio, and Tennessee. Kentucky v. Biden, 571 F.
Supp. 3d 715 (E.D. Ky. 2021). The court ruled that the
three States who were plaintiffs (Kentucky, Ohio, and Ten-
nessee) were likely to succeed on their claims that the ex-
ecutive order was unconstitutional and exceeded the
President’s statutory authority. Id. at 724–30. 2
2 The Sixth Circuit soon denied the government’s
motion to stay the district court’s preliminary injunction
pending appeal. Kentucky v. Biden, 23 F.4th 585 (6th Cir.
2022). The Sixth Circuit later affirmed, while narrowing,
the preliminary injunction. Kentucky v. Biden, 57 F.4th
545 (6th Cir. 2023). The court held that the President
likely exceeded his power under the FPASA. Id. at 547.
But the court narrowed the injunction to protect only the
Case: 25-2024 Document: 36 Page: 7 Filed: 11/23/2026
WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY 7
On December 2, 2021, two days after the district court’s
order, the Office of Management and Budget released a
nonenforcement instruction for the affected States,
J.A. 78–79, and the Corps advised Walsh that it had re-
scinded the DFARS Clause and would not enforce the RFP,
J.A 37. The next day, the deadline for the Corps to exercise
Option K, the Corps exercised the option without incorpo-
rating contract modifications. Decision, at 5. Walsh’s per-
formance deadline under the contract was not extended.
B
Beginning in December 2021, and eventually in a cer-
tified claim in December 2022, Walsh asserted to the Corps
that it incurred higher costs (in particular, materials and
labor costs) because of the government actions based on
E.O. 14042, and it sought an equitable adjustment from the
Corps under the FAR Changes Clause in the contract. See
J.A. 18–20, ¶¶ 25–31; 21–22, ¶¶ 39–42. The contracting
officer denied the request on April 13, 2023. J.A. 76–82.
On July 12, 2023, within the 90 days permitted, 41 U.S.C.
§ 7104(a), Walsh filed a notice of appeal to the Board. De-
cision, at 6. Pursuant to Board Rule 6, Walsh followed the
notice with a complaint filed with the Board on August 17,
2023. J.A. 14–22 (misdated August 17, 2022); see J.A. 405.
The complaint asserts that the Corps breached the Au-
gust 2021 contract by denying an equitable adjustment.
J.A. 20–22, ¶¶ 33–42. According to Walsh, subcontractors
that had provided quotations to Walsh for structural steel
and metal fabrication (major inputs for the project) were,
after receiving the RFP from Walsh, no longer willing to
three plaintiff States as contractors, not all contractors
within the jurisdiction of those States. Id. at 557. The
President revoked E.O. 14042 on May 9, 2023. Executive
Order 14099, 88 Fed. Reg. 30891 (May 15, 2023).
Case: 25-2024 Document: 36 Page: 8 Filed: 11/23/2026
8 WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY
contract if they had to comply with the DFARS Clause re-
quirements; all suppliers of those inputs that provided quo-
tations now increased their prices significantly and
specified longer periods for erecting the structures; and
Walsh was unable, between issuance of the RFP on Novem-
ber 3, 2021, and its rescission in early December, to find a
supplier that could meet the DFARS Clause requirements.
J.A. 17–18, ¶¶ 18–21; see Decision, at 3, 5. Only on Decem-
ber 15, after the rescission, could Walsh reach an agree-
ment with a supplier of steel and metal fabrication inputs
for the project, and that agreement reflected an increase in
prices that had occurred during the one-month delay be-
tween RFP issuance and rescission. J.A. 19–20, ¶¶ 26–27,
31; see Decision, at 6.
In response, the Corps filed a motion to dismiss for fail-
ure to state a claim. It argued that the issuances of E.O.
14042 and the RFP were sovereign acts of public and gen-
eral applicability for which Walsh was not entitled to an
equitable adjustment. J.A. 92–95. It also argued that the
RFP was not a constructive change because Walsh was “not
required to perform the work contemplated by” the execu-
tive order, so “the scope of the [c]ontract was never en-
larged.” J.A. 98; see J.A. 95–98.
The Board dismissed Walsh’s appeal for failure to state
a claim under Rule 12(b)(6). Decision, at 10–12. It gave
two reasons for doing so. First, the Board determined that
Walsh “did not actually perform outside the requirements
of the contract” because the contract required Walsh “to
procure steel for this project” irrespective of any RFP. Id.
at 11 (emphasis in original). Second, it found that Walsh’s
complaint limited its challenge to “the mere issuance” and
recission of the RFP itself and, therefore, excluded a chal-
lenge to the cover letter accompanying the RFP. Id. at 12.
Stating that the RFP “explicitly direct[ed] that it [wa]s not
a notice to proceed,” the Board held that it could not be “a
constructive change to the contract.” Id.
Case: 25-2024 Document: 36 Page: 9 Filed: 11/23/2026
WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY 9
The Board entered final judgment on May 8, 2025.
Walsh appealed on August 15, 2025, within the 120 days
allowed by 41 U.S.C. § 7107(a)(1)(A). We have jurisdiction
to review the Board’s final judgments under 28 U.S.C.
§ 1295(a)(10).
II
Before us is the Board’s grant of a motion to dismiss for
failure to state a claim. “The [Board] applies the same
[Federal Rule of Civil Procedure] 12(b)(6) standard as Fed-
eral Courts.” Government Response Br. at 11; see Lockheed
Martin Integrated Systems, Inc., ASBCA Nos. 59508,
59509, 17-1 BCA ¶ 36,597 at 177,281, 2016 WL 7655944
(Dec. 20, 2016). Under that standard, the adjudicator
“must accept well-pleaded factual allegations as true and
must draw all reasonable inferences in favor of the claim-
ant,” Kellogg Brown & Root Services, Inc. v. United States,
728 F.3d 1348, 1365 (Fed. Cir. 2013), and ask whether the
complaint contains “sufficient facts, accepted as true, to
state a claim to relief that is plausible on its face,” Sharifi
v. United States, 987 F.3d 1063, 1066–67 (Fed. Cir. 2021)
(citing Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009)) (internal
quotation marks omitted). See Lockheed Martin, ¶ 36,597
at 177,281. “The decision that a party is entitled to” dis-
missal under this standard “is a conclusion of law, which is
reviewed de novo.” Government Response Br. at 11; see
Sharifi, 987 F.3d at 1066.
A
We first consider whether Walsh has plausibly pleaded
a claim under the constructive-change doctrine. See, e.g.,
Zafer Taahhut Insaat ve Ticaret A.S. v. United States, 833
F.3d 1356, 1361 (Fed. Cir. 2016); Bell/Heery, 739 F.3d at
1335; International Data Products Corp. v. United States,
492 F.3d 1317, 1325 (Fed. Cir. 2007). Walsh contends that
(a) the Board erred in viewing the complaint as challenging
only what appears in the body of the RFP letter alone, to
the exclusion of the RFP cover letter, the relevant executive
Case: 25-2024 Document: 36 Page: 10 Filed: 11/23/2026
10 WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY
order, and the imminent deadline for Corps exercise of Op-
tion K under the contract, and (b) the constructive-change
claim passes muster at the pleading stage, certainly (but
not only) when the full context is properly considered.
Walsh Opening Br. at 16–24. The government maintains
that, even if we consider the full pleaded context, we should
conclude that there was no constructive change to the Au-
gust 2021 contract. Applying the standard applicable at
the pleading stage, we agree with Walsh.
1
As an initial matter, we conclude that the complaint
filed by Walsh is not fairly read to plead that the construc-
tive change for which it was entitled to compensation was
the RFP in isolation. A complaint must be given a “fair
reading,” Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 564
(2007); BGT Holdings LLC v. United States, 984 F.3d 1003,
1009 (Fed. Cir. 2020), and must be “assessed as a whole,”
not by “taking the allegations in isolation and failing to
draw reasonable inferences in the [plaintiff’s] favor,” Na-
tional Rifle Association of America v. Vullo, 602 U.S. 175,
194–95 (2024). Walsh’s complaint seeks relief from the
consequences of the demands that the RFP embodied, in-
cluding as understood by its potential subcontractors. The
context pleaded, and incorporated into the statement of the
claim, is important to understanding those demands.
The RFP was not even presented to Walsh in isolation.
It was an attachment to the cover letter, which communi-
cated in express terms that the vaccination obligation was
mandatory. See J.A. 24. The complaint quotes the cover
letter and its restrictive language. J.A. 15–16, ¶¶ 8–11.
And the statement of the (single) cause of action, for wrong-
ful denial of equitable adjustment under the FAR Changes
Clause, incorporates the allegations of all the previous par-
agraphs of the complaint. J.A. 20, ¶ 33.
Case: 25-2024 Document: 36 Page: 11 Filed: 11/23/2026
WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY 11
More generally, in paragraphs incorporated into the
cause of action, the complaint alleges the collection of cir-
cumstances surrounding the RFP that led to the claimed
increased costs for which Walsh is seeking compensation.
Besides what is stated in the cover letter, the allegations
include the DOD Class Deviation 2021-O0009 announce-
ment of the DFARS Clause itself, the Corps’s intent that
the DFARS Clause would be incorporated into the contract,
the imminent deadline for exercising Option K, the de-
mands of E.O. 14042, and the pronouncements of the Task-
force. E.g., J.A. 15–17, ¶¶ 7, 8, 12–15. It was the imminent
imposition of the vaccination requirement, which would
reach subcontractors, that the complaint must be under-
stood as alleging to have caused its increased costs,
through delays and higher prices when, e.g., potential sup-
pliers balked at inking subcontracts. J.A. 17–18, ¶¶ 15–21;
J.A. 21, ¶¶ 36–38.
The complaint, fairly read, does not complain of the
RFP in isolation from all of this pleaded context. Indeed,
the RFP itself points toward the context. It attaches the
DFARS Clause that implements the executive order. See
J.A. 61–63. And the very fact that the Corps took the ini-
tiative of issuing the RFP and directed payment-increase
proposals to be promptly presented invoked the surround-
ing material by conveying that the vaccine obligation was
likely imminent for this contract and could well increase
project costs.
We conclude that the Board took an impermissibly
cramped view of the pleading in conducting the necessary
inquiry into whether Walsh presented well-pleaded allega-
tions of fact that, taken as true, state a plausible claim for
relief under the constructive-change doctrine. See Sharifi,
987 F.3d at 1066–67.
Case: 25-2024 Document: 36 Page: 12 Filed: 11/23/2026
12 WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY
2
When this matter was before the Board, the govern-
ment suggested a seemingly categorical basis for answer-
ing that question in the negative: that the constructive-
change doctrine does not apply whenever the underlying
contract is a firm-fixed-price contract. J.A. 392–93. In this
court, the government adverts to that position only in a
footnote, Government Response Br. at 27 n.10, and so it
has not adequately preserved the argument, see
SmithKline Beecham Corp. v. Apotex Corp., 439 F.3d 1312,
1320 (Fed. Cir. 2006) (“[A]rguments raised in footnotes are
not preserved.”). In any event, the argument lacks merit:
At least where the FAR Changes Clause is incorporated
into the contract, as here, what is firmly fixed in a firm-
fixed-price contract is the government payment for per-
forming the contract on the unchanged terms, a cap that
does not preclude a duty to pay more money where the gov-
ernment has caused a change qualifying under the con-
structive-change doctrine. See Zafer, 833 F.3d at 1361
(“Nevertheless, [even under a firm-fixed price contract] a
contracting officer may adjust the work within the general
scope of the contract under a Changes clause, and the con-
tractor may receive an equitable adjustment for changes
contemplated by that clause.” (internal quotation marks
and citations omitted)).
3
As we have already laid out, Walsh’s complaint, fairly
read, asserts at least the following: Because of the govern-
ment actions, Walsh newly had to attempt to negotiate sub-
contracts under the condition that subcontractors
vaccinate their employees, a condition that was not in the
August 2021 contract. The new condition prevented Walsh
from completing in-process negotiations and immediately
signing important subcontractor agreements, because po-
tential suppliers balked at the vaccination obligation. The
Case: 25-2024 Document: 36 Page: 13 Filed: 11/23/2026
WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY 13
result was delay in reaching agreements on steel and re-
lated fabrication inputs in particular, and steel prices had
risen by the time the vaccination condition was rescinded
and subcontracting agreements could be reached. The an-
nouncements of the condition, which were not provided for
in the August contract, resulted in higher costs to Walsh.
The FAR Changes Clause enumerates examples of
what can constitute a “change” for equitable-adjustment
purposes. We have summarized the constructive-change
doctrine as calling for an inquiry into whether the plaintiff
has shown (or, in this case, plausibly alleged) “(1) that it
performed work beyond the contract requirements, and
(2) that the additional work was ordered, expressly or im-
pliedly, by the government.” Bell/Heery, 739 F.3d at 1335.
Under the FAR Changes Clause, the Bell/Heery formula-
tion, and other precedent, we conclude Walsh has pleaded
facts that plausibly meet the requirement of a constructive
change for purposes of claiming an equitable adjustment
based on the set of government actions that ripened with
the RFP. The government presents essentially two argu-
ments for a contrary conclusion. We reject both.
a
The government’s core submission on the constructive-
change issue is that, because Walsh was obligated to pro-
cure steel for the project regardless, the challenged govern-
ment action did not require Walsh to “perform work outside
of the contract.” Government Response Br. at 17; see id. at
12–20. This is not a persuasive ground for dismissing the
constructive-change claim.
Under ordinary contract principles, the parties’ mani-
fested assent, as evidenced in the contract, dictates the per-
formance obligation. Restatement (Second) of Contracts
§ 21. Here, “construction of the [VA medical center]” would
require Walsh to engage many subcontractors. See
J.A. 395, 397. As far as the record before us shows, the
Case: 25-2024 Document: 36 Page: 14 Filed: 11/23/2026
14 WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY
August 2021 contract left Walsh free to procure subcontrac-
tors that were not under the later-imposed restriction of
the federal vaccination standard.
The challenged government action—starting with the
September executive order, then the DOD implementation
based on Taskforce choices, then made specific to the pre-
sent contract in the RFP and associated communications
with an impending deadline for an important government
exercise of an option—imposed a new restriction that lim-
ited how Walsh could perform the contract. This action
plausibly qualifies as a “change” in “the work within the
general scope of the contract,” at least “[i]n the method or
manner of performance of the work,” under FAR 52.243-
4(a), which covers express change orders. That kind of
change qualifies under FAR 52.243-4(b) as well, which
simply expands coverage from express to constructive
changes, with no narrowing of what constitutes a change.
Cf. Zafer, 833 F.3d at 1361–62 (discussing subsection (a)’s
language regarding expressly made changes, then explain-
ing subsection (b)’s coverage of constructive changes, with
no narrowing of what would amount to a “change”).
The same conclusion is warranted under a proper read-
ing of the Bell/Heery formulation and our case law. The
Bell/Heery summary refers to performing “work beyond
the contract requirements.” 739 F.3d at 1335. A govern-
ment restriction on the method or manner of performing
the work to be undertaken, where additional expenses are
incurred, requires performance of work “beyond the con-
tract requirements” because the work now must be per-
formed (at greater expense) under tighter-than-contract-
specified requirements and so the bargain has been
changed. Notably, after Bell/Heery, we decided Zafer,
which involved the “acceleration in the performance of the
work” portion of FAR 52.243-4(a), and we recognized that
“an informal order to accelerate contract performance (con-
structive acceleration) can effect a constructive change to
the contract” (where, among other things, expenses were
Case: 25-2024 Document: 36 Page: 15 Filed: 11/23/2026
WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY 15
increased), even though the product or service provided
may not have changed. 833 F.3d at 1361–62. The govern-
ment has not shown why a government change in “the
method or manner of performance of the work,” FAR
52.243-4(a)(2), by constricting the choice of subcontrac-
tors—e.g., newly ruling out a whole class of potential sub-
contractors, raising the costs for the contractor—should be
treated differently from a government constriction of the
time of performance. Bell/Heery itself did not involve and
had no occasion to address this issue, because it rejected
the claim on the ground that a state agency, not the federal
government, was responsible for the challenged change in
what the plaintiff had to do to perform. 739 F.3d at 1335.
In this case, Walsh has plausibly pleaded that the chal-
lenged government conduct, when it reached the stage of
the RFP and accompanying communications, had a signif-
icant effect on Walsh’s ability to move forward with con-
tract performance on the August 2021 terms. Specifically,
Walsh has plausibly pleaded that it was on the cusp of
making a subcontractor award for steel before the RFP is-
sued, that potential subcontractors either backtracked on
near-final agreements or ended negotiations altogether fol-
lowing the RFP’s issuance, and that no agreement could be
entered into until after the RFP’s rescission (at which
point, raw-material costs had increased considerably).
That Walsh always was going to have to buy steel does not
disqualify these allegations from supporting a construc-
tive-change claim. 3
3 We need not and do not separately address whether
Walsh has made allegations of accelerated performance
(with associated costs) that could state a claim of construc-
tive change. See Zafer, 833 F.3d at 1362–63 (reciting re-
quirements for the accelerated-performance claim there at
Case: 25-2024 Document: 36 Page: 16 Filed: 11/23/2026
16 WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY
b
In its second main argument on the constructive-
change issue, the government contends that it never re-
quired a change because the “COVID clause was never
adopted” and the Corps did not instruct Walsh to “stop
work, accelerate work, or perform work outside of the con-
tract.” Government Response Br. at 16–17. We reject this
argument as a basis for dismissal on the pleadings.
The RFP itself—a letter from the Corps’s contracting
officer—indicated that the attached DFARS Clause was
“under consideration.” J.A. 61. But it went on to instruct
Walsh to “submit a proposal to provide all labor, material,
and equipment necessary” to perform the scope of work un-
der the contract with an additional subcontractor-vaccina-
tion requirement in place. J.A. 61 (emphasis added). Such
a proposal would necessarily require Walsh to seek quotes
from subcontractors willing to complete the work and ac-
cept the vaccination requirement and to pause (or termi-
nate) its discussions with subcontractors who entered
negotiations with a different understanding of the terms:
an understanding that vaccination would not be required.
See J.A. 17–18, ¶¶ 15, 19–21. The RFP’s statement that it
does not constitute a “notice to proceed” should not save the
government’s otherwise-explicit direction. It is doubtful
that this was referring to the direction about the proposal,
rather than to the ordinary “notice to proceed” to launch
performance under a contract, and in this case, as we have
noted, the government had already issued the notice to pro-
ceed with performance. See Decision, at 2.
issue, among them that “the government denied the con-
tractor’s request for an extension or failed to act on it
within a reasonable time”).
Case: 25-2024 Document: 36 Page: 17 Filed: 11/23/2026
WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY 17
The cover letter to which the RFP was attached was
even more express that the government was issuing a di-
rective. It explained that “to ensure the health and safety
of the Federal workforce and contractor community,” the
President had signed an Executive Order, whose require-
ments “will be incorporated into Louisville District con-
tracts.” J.A. 24 (emphasis added). For that reason, the
Corps “strongly encourage[d]” acceptance “at this time” be-
cause “[t]he modification is mandatory before [the Corps]
will” renew, extend performance, or “exercise an option.”
Id. (emphasis in original). This amounts to a plausible al-
legation that work was ordered by the government.
B
In addition to defending the dismissal based on its view
of the constructive-change doctrine, the government makes
an alternative argument for affirmance of the dismissal. It
argues, as it did to the Board, that it is insulated from con-
tract liability by the sovereign acts doctrine. Government
Response Br. at 20–27. The Board did not rule on this de-
fense. Decision, at 12. We may in certain circumstances
affirm, and sometimes do affirm, a judgment on grounds
not passed on by the fact-finding tribunal whose decision is
before us. See, e.g., Glaxo Group Ltd. v. TorPharm, Inc.,
153 F.3d 1366, 1371 (Fed. Cir. 1998) (doing so where “the
ground urged is one of law, and that issue has been fully
vetted by the parties on appeal”). Here, recognizing the
substantiality of the defense and the potential significance
of the issues raised, we decline to reach it in the first in-
stance.
The United States, by virtue of its sovereignty, may not
be sued without its consent. United States v. Mitchell, 463
U.S. 206, 212 (1983). Congress waived sovereign immunity
in government-contractor disputes, most recently through
the Contract Disputes Act. Pub. L. No. 95-563, 92 Stat.
2383 (1978) (codified as amended at 41 U.S.C. §§ 7101–09).
Case: 25-2024 Document: 36 Page: 18 Filed: 11/23/2026
18 WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY
But the government retains a longstanding affirmative de-
fense to liability for sovereign acts, precluding recovery for
breaches merely incidental to generally applicable and
public acts. Conner Brothers Construction Co. v. Geren, 550
F.3d 1368, 1371–74 (Fed. Cir. 2008).
Here, the government alleges that E.O. 14042 and the
RFP (based on the DOD and Taskforce actions) were sov-
ereign acts insulating the government from liability. Gov-
ernment Response Br. at 25–27. 4 The government argues,
as may well be the case, that the sovereign acts doctrine is
a purely legal defense and that there remains little to no
necessary fact-finding. Government Response Br. at 20–
21, 26–27; see Horowitz v. United States, 267 U.S. 458, 459
(1925) (dismissed on demurrer by finding a sovereign act
before presentation of evidence). We nevertheless exercise
our discretion to leave the issue to the Board for a fuller
analysis than has yet been provided.
In Conner Brothers, 550 F.3d at 1373–74, we adopted
as governing law the analysis of the sovereign acts doctrine
set forth by the principal opinion (by Justice Souter, for a
plurality) in United States v. Winstar, 518 U.S. 839, 896
(1996). Justice Souter’s plurality opinion explains that the
“essential point” of the sovereign acts doctrine is “to put the
[g]overnment in the same position that it would have en-
joyed as a private contractor.” Winstar, 518 U.S. at 892.
Applying the doctrine, an adjudicator should ask whether,
had the government been a private party, “it would have
4 The government might be arguing one or more var-
iations on that submission. For example, it might be argu-
ing that, even if the contracting officer’s actions (in
particular, the RFP and cover letter) were not sovereign
acts, all the asserted harm derives from sovereign acts, in
particular, E.O. 14042 (and possibly acts of DOD and the
Taskforce).
Case: 25-2024 Document: 36 Page: 19 Filed: 11/23/2026
WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY 19
been entitled to assert the common-law defense of impossi-
bility of performance,” keeping in mind that such a defense
“is traditionally unavailable where the barrier to perfor-
mance arises from the act of the party seeking discharge.”
Id. at 895 (citing Restatement (Second) of Contracts § 261).
Thus, application of the sovereign acts doctrine requires
asking whether the government act challenged in a case is
properly attributable to the government as contractor or as
law giver. Id. at 895–96.
The government’s dual roles as contractor and law
giver are often “fused”—for example, where a law or regu-
lation targets particular contractors. Id. at 893–94. When
that is so, adjudicators should consider whether the alleged
act was “meant to advance a broader public interest,” id. at
894; whether it was undertaken by the government in “the
same capacity in which it entered into” the contract, id.;
whether the abrogation of contracts was a “focal point” of
the act’s enacting debate, id. at 900; whether the act was
limited to contractors, id. at 897 n.42; whether the public
contracts had obvious private analogs, id.; and the relative
significance of “the [g]overnment’s self-interest” in the “im-
pact of the [g]overnment’s action” on its contractual obliga-
tions, id. at 898. All of this remains subject to any
“additional requirements” that the common-law doctrine of
impossibility imposes before a party may avoid liability for
breach. Id. at 904.
The foregoing merely identifies aspects of the issue pre-
sented by the sovereign acts doctrine. We do not discuss
the application of the doctrine in Winstar or the variety of
cases we have decided under the doctrine. We are not set-
ting forth a required analytic structure. We do only enough
to suggest why more analysis of the application of the doc-
trine to this case is needed than what we have been fur-
nished, whether or not there is a need for what would
constitute adjudicative fact finding.
Case: 25-2024 Document: 36 Page: 20 Filed: 11/23/2026
20 WALSH TURNER JOINT VENTURE II v. SECRETARY OF THE ARMY
One additional aspect of the required analysis is worth
flagging. The executive order at issue was preliminarily
enjoined as likely unlawful by the Eastern District of Ken-
tucky, a conclusion with which the Sixth Circuit agreed (as
specified above). How, if at all, the unlawfulness rulings,
and the accompanying injunction, bear on the sovereign
acts defense warrants exploration. See, e.g., Restatement
(Second) of Contracts § 264 cmt. b (“It is not necessary that
the regulation or order be valid, but a party who seeks to
justify his non-performance [through the common-law im-
possibility defense] must have observed the duty of good
faith . . . in attempting, where appropriate, to avoid [the
regulation or order’s] application.”); U.C.C. § 2-615 cmt. 10
(explaining that the application of the impossibility de-
fense does not “depend upon the eventual judicial determi-
nation of the legality of the particular government
action”—rather, “[t]he seller’s good faith belief in the valid-
ity of the regulation is the test under this Article and the
best evidence of his good faith is the general commercial
acceptance of the regulation”); Koppers Co. v. United
States, 405 F.2d 554, 558 (Ct. Cl. 1968) (“Whether specifi-
cations are factually impossible or commercially impracti-
cable to perform is a question of fact, not of law[,] and
shou