Full Opinion

In the United States Court of Federal Claims ALAMO CITY ENGINEERING SERVICES, INC., No. 25-cv-579 Plaintiff, Filed Under Seal: July 21, 2026 v. Publication: July 29, 2026 1 THE UNITED STATES, Defendant. Steven Herrera of Bradley Arant Boult Cummings LLP, Houston, TX, argued for Plaintiff. With him on the briefs were Aron Beezley, Nathaniel J. Greeson, and Owen E. Salyers of Bradley Arant Boult Cummings LLP, Washington, D.C., and Alexander Grant Thrasher, Bradley Arant Boult Cummings LLP, Birmingham, AL. Nelson Kuan of the United States Department of Justice, Civil Division, Washington, D.C. argued for Defendant. With him on the briefs were Albert S. Iarossi, Patricia M. McCarthy, and Brett A. Shumate of the United States Department of Justice, Civil Division, Washington, D.C., and Jack D. Myers and Ashley Kelly of the Defense Logistics Agency. MEMORANDUM AND ORDER On May 24, 2020, Plaintiff Alamo City Engineering Services, Inc. (Alamo City or ACES) entered into Order Number SP4701-20-F-0078 (Task Order) with the Defense Logistics Agency (DLA), an agency of Defendant the United States, promising to configure SAP enterprise software that DLA uses to manage stock in its warehouses. ECF No. 1 (Complaint) ¶¶ 2, 5, 6. After 1 This Memorandum and Order was filed under seal in accordance with the Court’s order allowing exhibits to the Motion to Dismiss to be filed under seal. ECF No. 14 (Motion for Leave to File Under Seal); Minute Order dated Aug. 12, 2025 (granting Motion for Leave to File Under Seal). On July 28, 2026, the parties informed the Court that there were no proposed redactions. ECF No. 30 (Notice Regarding Proposed Redactions). The sealed and public versions of this Memorandum and Order are identical, except for this footnote and the publication date. performance began, ACES learned that DLA’s software was not configured according to the conditions that were allegedly promised in the specifications, requiring more work than ACES had expected. Id. ¶¶ 13–14. DLA had configured its SAP software in an Internet Demonstration and Evaluation System (IDES) environment, rather than the operational environment that ACES had expected. Id. ¶ 10. The parties bilaterally modified the Task Order repeatedly to account for the increased scope of work caused by the IDES environment. Id. ¶¶ 16, 18, 21. Even after these modifications however, ACES claimed that the IDES environment was a defective specification that constructively changed the work required under the Task Order and accordingly requested an adjustment of $3,805,934.12 above the contract price. Id. ¶ 22. Accordingly, on November 28, 2023, ACES filed a certified claim with its contracting officer (CO) concerning the alleged changes. Id. ¶ 27; see ECF No. 20-4 (Certified Claim). The Certified Claim also alleged that the CO had failed to collaborate with ACES to mitigate the challenges posed by the IDES environment. Certified Claim at 2. On April 2, 2024, the CO denied the Certified Claim. See ECF No. 20-5 at 1. Subsequently, ACES filed its Complaint in this Court under the Contract Disputes Act (CDA). ACES includes two counts in its Complaint, each based on a different legal theory: (1) defective specifications, and (2) the implied duty of good faith and fair dealing. Compl. ¶¶ 30, 39. Defendant now seeks to dismiss ACES’s Complaint for lack of jurisdiction and for failure to state a claim. See ECF No. 13 at 5 2 (Motion to Dismiss or Motion). Defendant makes four arguments: (1) Plaintiff fails to demonstrate Article III standing for the entire Complaint, (2) Plaintiff failed to present its good faith and fair dealing claim to the CO in the Certified Claim, (3) Plaintiff has 2 Citations throughout this Memorandum and Order correspond to the ECF-assigned page numbers, which do not always correspond to the pagination within the document. 2 failed to plead plausible facts showing that DLA provided defective specifications, and (4) Plaintiff has failed to plead plausible facts establishing a breach of the implied duty of good faith and fair dealing. Id. at 5–6. For the reasons stated below, the Court GRANTS IN PART and DENIES IN PART Defendant’s Motion to Dismiss (ECF No. 13). The Court DENIES Defendant’s Rule 12(b)(1) Motion to Dismiss alleging a lack of subject matter jurisdiction. The Court GRANTS Defendant’s Rule 12(b)(6) Motion to Dismiss for failure to state a claim with respect to Count One of the Complaint, concerning defective specifications for the IDES environment, and accordingly DISMISSES Count One. The Court DENIES Defendant’s Rule 12(b)(6) Motion to Dismiss for failure to state a claim with respect to Count Two of the Complaint, concerning DLA’s alleged breach of the implied covenant of good faith and fair dealing. BACKGROUND 3 On May 24, 2020, DLA awarded ACES Order Number SP-4701-20-F-0078 (Task Order), from Contract Number GS-35F-0598S. Compl. ¶ 5. The Task Order procured “SAP Support Services for the Configuration of DLA Business Segments in support of Warehouse Management System (WMS).” Id. ¶ 6. The original base period of performance ran from the date of award for one year, to May 23, 2021. Id. ¶ 7. The Task Order included two one-year options, through which 3 At this motion to dismiss stage, the Court does not make factual findings; rather, the Court accepts the well-pleaded facts in the Complaint as true for purposes of resolving a motion to dismiss for failure to state a claim under Rule 12(b)(6). Boyd v. United States, 134 F.4th 1348, 1352 (Fed. Cir. 2025) (“‘We take all factual allegations in the complaint as true and construe the facts in the light most favorable to the non-moving party.’” (quoting Jones v. United States, 846 F.3d 1343, 1351 (Fed. Cir. 2017))). As Defendant in its Motions does not controvert any factual allegations in the Complaint, the Court also accepts as true all well-pleaded facts for purposes of the resolving Defendant’s Rule 12(b)(1) motion to dismiss for lack of subject matter jurisdiction. See infra Discussion I; Estes Express Lines v. United States, 739 F.3d 689, 692 (Fed. Cir. 2014) (“In deciding a motion to dismiss for lack of subject matter jurisdiction, the court accepts as true all uncontroverted factual allegations in the complaint, and construes them in the light most favorable to the plaintiff.”). 3 DLA could extend performance through May 23, 2022, and May 23, 2023. Id. DLA issued a stop work order on June 2, 2020, shortly after performance began. Id. ¶ 8. DLA lifted the stop work order on July 20, 2020, and ACES subsequently began performance. Id. ¶ 8–9. At an unspecified time in “mid-2020,” after performance had resumed, ACES viewed “a slide from another contractor” during a meeting with DLA, which revealed that DLA had supplied the Minimal Viable Product (MVP) SAP WMS in an Internet Demonstration and Evaluation System (IDES) environment. Id. ¶ 10. An IDES environment is different from an operational environment—the environment which ACES had expected. Id. ¶ 12. According to ACES, the IDES environment posed problems for development because “[d]eploying a system in IDES may not reveal performance, integration, or security challenges that could arise in actual operations.” Id. ¶ 11. According to ACES, “[a]n IDES environment is a controlled setting for testing and evaluation, whereas an operational environment reflects real-world conditions with live data, security constraints, and mission-critical demands.” Id. Before this meeting, ACES allegedly had not been aware that DLA used an IDES environment, and ACES contends that DLA had not informed ACES of the IDES environment. Id. ¶ 12. Subsequently, ACES “notified DLA that deployment in the IDES environment was a changed condition of the work and would result in significant re-work to build its MVP SAP WMS in an operational environment for use by DLA.” Id. ¶ 13. ACES contends that it “was required to conduct significant additional work beyond what was originally contemplated under the Contract to salvage the existing SAP WMS solution from the IDES environment” because DLA used an IDES environment. Id. ¶ 14. ACES asserts that such additional work led ACES “to incur additional costs associated with both the hiring [of] additional personnel and working overtime hours.” Id. ¶ 15. ACES also claims that while the Task Order required it to purchase 30 SAP 4 classroom sessions to train DLA staff, DLA required ACES to perform “many more” classroom sessions. Id. ¶¶ 27, 35. Following the discovery of the IDES environment, on September 15, 2020, the parties executed a bilateral modification (Modification P00002) to the contract. Id. ¶ 16. This modification extended the base period of performance through July 10, 2021. Id. Under Modification P00002, the periods of performance in DLA’s Options 1 and 2 were also modified: Option 1 would extend performance until July 10, 2022, and Option 2 would extend performance until July 10, 2023, if exercised. Id. DLA exercised Option 1 on June 30, 2021. Id. ¶ 17. Several more modifications followed before the contract expired. The parties bilaterally modified the contract (Modification P00014) on August 12, 2021. Id. ¶ 18. According to ACES, this modification changed the scope of work and “recognized that the ‘IDES environment was deficient because software was outdated, non-DLA sample customer data resid[ed] within, limitations with licensing of software, and servers weren’t sized adequately.’” Id. On July 6, 2022, DLA exercised Option 2, extending the period of performance until July 10, 2023. Id. ¶ 19. DLA then unilaterally extended the period of performance to August 10, 2023. Id. ¶ 20. Subsequently, the parties bilaterally modified the contract to extend the period of performance to September 10, 2023. Id. ¶ 21. ACES submitted a Request for Equitable Adjustment (REA) to DLA on September 25, 2023, in which it sought to recover costs arising from the IDES environment. Id. ¶ 22. The REA characterized the IDES environment as an “express and constructive change[] caused by the government” that forced ACES to perform work beyond the contract requirements. Id. The REA alleged that “DLA also interfered with ACES’s means and methods of performing its work under the Contract.” Id. ¶ 24. DLA rejected the REA on November 22, 2023. Id. ¶ 26. 5 After receiving the denial of its REA, ACES submitted a certified claim to the CO on November 28, 2023. Certified Claim at 1. The Certified Claim requested payment of $3,805,934.12 “due to the existence of numerous differing site conditions, the existence of which significantly impacted and increased ACES’ costs and time of performance on the subject contract.” Id. These alleged differing site conditions included an “inaccurate description” of each of the following: “Business Process Re-engineering (BPR) lots,” “Distribution Standard Systems (DSS) services,” “Agile services,” “SAP [IDES] services,” and “platform configuration services.” Id. The Certified Claim also alleged a “failure to collaborate effectively” by DLA, including a “failure to provide sufficient resources as required under the contract.” Id. at 2. The Certified Claim alleged that DLA “directed and controlled the methods used by the contractor in its performance of the services under the contract,” including by not mentioning the IDES environment. Id. The Certified Claim also claimed that “DLA’s inaccurate description of SAP classroom sessions to be performed (i.e., 30 courses described, but many more required)” constituted a constructive change. Id. at 1. On April 2, 2024, the CO denied ACES’s Certified Claim. See ECF No. 20-5 at 1. PROCEDURAL HISTORY Plaintiff filed its Complaint on April 2, 2025, but due to a docketing error by the Clerk of Court, Defendant’s counsel, the Department of Justice, was not served with the Complaint until June 12, 2025. See ECF Nos. 1 (Complaint), 10 at 1. Subsequently, on August 12, 2025, Defendant filed the present Motion to Dismiss under seal. See Motion; ECF No. 14 at 1; Minute 6 Order dated Aug. 12, 2025. The Court conducted oral argument on February 10, 2026. See Minute Entry dated Feb. 10, 2026. The Motion is fully briefed and ripe for review. 4 STATUTORY FRAMEWORK Under Section 1491(a)(2) of the Tucker Act, this Court has jurisdiction over claims brought under the Contracts Dispute Act (CDA). 28 U.S.C. § 1491(a)(2) (“The Court of Federal Claims shall have jurisdiction to render judgment upon any claim by or against, or dispute with, a contractor arising under section 7104(b)(1) of title 41 . . . .”); see 41 U.S.C. § 7101, et seq. “The CDA exclusively governs Government contracts and Government contract disputes.” Cecile Indus., Inc. v. Cheney, 995 F.2d 1052, 1055 (Fed. Cir. 1993); see Boeing Co. v. United States, 968 F.3d 1371, 1381 (Fed. Cir. 2020) (“[A] ‘matter of contract administration . . . can only be challenged under the Contract Disputes Act.’” (quoting Coast Pro., Inc. v. United States, 828 F.3d 1349, 1355 (Fed. Cir. 2016)). Thus, “[w]hen the Contract Disputes Act applies, it provides the exclusive mechanism for dispute resolution.” Tex. Health Choice, L.C. v. Off. of Pers. Mgmt., 400 F.3d 895, 898–99 (Fed. Cir. 2005) (alteration in original) (quoting Dalton v. Sherwood Van Lines, Inc., 50 F.3d 1014, 1017 (Fed. Cir. 1995)). The CDA imposes strict jurisdictional prerequisites, which must be met for each individual claim. K-Con Bldg. Sys., Inc. v. United States, 778 F.3d 1000, 1005 (Fed. Cir. 2015) (citing Joseph Morton Co. v. United States, 757 F.2d 1273, 1281 (Fed. Cir. 1985)); see M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323, 1327–39 (Fed. Cir. 2010). To establish jurisdiction under the CDA, a plaintiff must demonstrate that it (i) previously submitted each claim to the contracting officer, and (ii) received a final decision from the contracting officer on each claim. K-Con Bldg. 4 See Defendant’s Motion to Dismiss, ECF No. 13; Plaintiff’s Response in Opposition, ECF No. 20 (Resp.); Defendant’s Reply in support of its Motion, ECF No. 21 (Reply). 7 Sys., 778 F.3d at 1005 (citing James M. Ellett Constr. Co. v. United States, 93 F.3d 1537, 1541 (Fed. Cir. 1996)); see also Tolliver Grp., Inc. v. United States, 20 F.4th 771, 775 (Fed. Cir. 2021) (“The CDA mandates that ‘[e]ach claim by a contractor against the Federal Government relating to a contract shall be submitted to the contracting officer for a decision.’” (quoting 41 U.S.C. § 7103(a)(1))). “A claim is ‘a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract.’” K-Con Bldg. Sys., 778 F.3d at 1005 (quoting Reflectone, Inc. v. Dalton, 60 F.3d 1572, 1575 (Fed. Cir. 1995) (en banc)). The claim must present a “clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of the claim” to satisfy the jurisdictional presentment requirement. Scott Timber Co. v. United States, 333 F.3d 1358, 1365 (Fed. Cir. 2003). LEGAL STANDARD I. Rule 12(b)(1) This Court must dismiss claims outside its subject matter jurisdiction. Rules 12(b)(1), 12(h)(3); St. Bernard Par. Gov’t v. United States, 916 F.3d 987, 992–993 (Fed. Cir. 2019) (“It is well settled that limitations on subject matter jurisdiction are not waivable . . . .”). When deciding a motion to dismiss for lack of subject matter jurisdiction under Rule 12(b)(1), this Court “accepts as true all uncontroverted factual allegations in the complaint, and construes them in the light most favorable to the plaintiff.” Estes Express Lines, 739 F.3d at 692; see also Banks v. United States, 741 F.3d 1268, 1277 (Fed. Cir. 2014). When “a motion to dismiss ‘challenges the truth of the jurisdictional facts,’ the Court of Federal Claims ‘may consider relevant evidence in order to resolve the factual dispute.’” Freeman 8 v. United States, 875 F.3d 623, 627 (Fed. Cir. 2017) (quoting Banks, 741 F.3d at 1277); see also Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 747 (Fed. Cir. 1988). When a Rule 12(b)(1) motion challenges jurisdictional facts—those facts pled in a complaint to establish jurisdiction—then the Court will consider those facts that either the defendant does not contest and those that the plaintiff supports with extrinsic evidence. See Shoshone Indian Tribe of Wind River Rsrv., Wyo. v. United States, 672 F.3d 1021, 1030 (Fed. Cir. 2012) (“If a Rule 12(b)(1) motion challenges a complaint’s allegations of jurisdiction, the factual allegations in the complaint are not controlling and only uncontroverted factual allegations are accepted as true. . . . [i]n resolving these disputed predicate jurisdictional facts, ‘a court is not restricted to the face of the pleadings, but may review evidence extrinsic to the pleadings.’” (quoting Cedars-Sinai Med. Ctr. v. Watkins, 11 F.3d 1573, 1584 (Fed. Cir. 1993))). Once the defendant disputes jurisdictional facts in a motion to dismiss, the burden shifts to the plaintiff to provide evidence for the jurisdictional facts. Reynolds, 846 F.2d at 748; see Estes Express Lines, 739 F.3d at 692 (“The plaintiff bears the burden of establishing subject matter jurisdiction by a preponderance of the evidence.”). On the other hand, when “a Rule 12(b)(1) motion simply challenges the court's subject matter jurisdiction based on the sufficiency of the pleading's allegations—that is, the movant presents a ‘facial’ attack on the pleading—then those allegations are taken as true and construed in a light most favorable to the complainant.” Cedars-Sinai Med. Ctr., 11 F.3d at 1583. II. Rule 12(b)(6) To withstand a motion to dismiss pursuant to 12(b)(6), “a complaint must contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)). A plaintiff also must establish “more than a sheer possibility that a defendant has acted 9 unlawfully.” Id. (citing Twombly, 550 U.S. at 556). Thus, “[a] pleading that offers ‘labels and conclusions’ or ‘a formulaic recitation of the elements of a cause of action will not do.’ Nor does a complaint suffice if it tenders ‘naked assertion[s]’ devoid of ‘further factual enhancement.’” Id. (quoting Twombly, 550 U.S. at 555, 557) (second alteration in original) (internal citations omitted). “The Court of Federal Claims may properly grant a motion to dismiss under [Rule] 12(b)(6) when a complaint does not allege facts that show the plaintiff is entitled to the legal remedy sought.” Steffen v. United States, 995 F.3d 1377, 1379 (Fed. Cir. 2021) (citing Lindsay v. United States, 295 F.3d 1252, 1257 (Fed. Cir. 2002)). At the motion to dismiss stage, this Court must “take all factual allegations in the complaint as true and construe the facts in the light most favorable to the non-moving party.” Boyd v. United States, 134 F.4th 1348, 1352 (Fed. Cir. 2025) (quoting Jones v. United States, 846 F.3d 1343, 1351 (Fed. Cir. 2017)). The Court, however, need not “accept the asserted legal conclusions.” Am. Bankers Ass’n v. United States, 932 F.3d 1375, 1380 (Fed. Cir. 2019). The Court “must consider the complaint in its entirety” as well as “documents incorporated into the complaint by reference, and matters of which a court may take judicial notice.” Tellabs, Inc. v. Makor Issues & Rts., Ltd., 551 U.S. 308, 322 (2007). The Court may rely on exhibits attached to the Complaint, as these “are not ‘matters outside the pleadings.’” Sharifi v. United States, 987 F.3d 1063, 1067 (Fed. Cir. 2021) (quoting Rule 12(d)); see also AlexSam, Inc. v. Aetna, Inc., 119 F.4th 27, 34 (Fed. Cir. 2024) (“Review of a motion to dismiss under Rule 12(b)(6) is generally limited ‘to the facts as asserted within the four corners of the complaint, the documents attached to the complaint as exhibits, and any documents incorporated in the complaint by reference.’” (quoting McCarthy v. Dun & Bradstreet Corp., 482 F.3d 184, 191 (2d Cir. 2007)). “In the event of conflict between the bare allegations of the complaint and any exhibit attached . . . , the exhibit prevails.” Allen Eng’g 10 Contractor, Inc. v. United States, 115 Fed. Cl. 457, 464 (2014), aff’d, 611 F. App’x 701 (quoting Fayetteville Invs. v. Com. Builders, 936 F.2d 1462, 1465 (4th Cir. 1991)); 5A Wright & Miller’s Federal Practice and Procedure § 1327 (3d ed. 2004 & Supp. 2016) (explaining that the Court “obviously is not bound to accept the pleader’s allegations as to the effect of the exhibit, but can independently examine the document and form its own conclusions”); see also Rocky Mountain Helium, LLC v. United States, 841 F.3d 1320, 1325–26 (Fed. Cir. 2016) (favorably quoting Wright & Miller § 1327). DISCUSSION This Discussion proceeds in four sections, corresponding to the four arguments raised by the Motion. First, Defendant argues that Plaintiff lacks Article III standing because Plaintiff’s injuries are not traceable to the alleged breach of contract. Specifically, Defendant contends that later contract modifications broke the “chain of causation” between the original contract (upon which Plaintiff brings its claims) and the injuries it asserts here. However, the presence of later modifications to the contract does not waive any claims that might have accrued to Plaintiff. Plaintiff has standing here because it pleads injuries caused by DLA’s actions that were not addressed by later contract modifications. Second, Defendant asserts that Plaintiff failed to meet the CDA’s jurisdictional presentment requirement for Count Two of the Complaint. Specifically, Defendant argues that Plaintiff never presented a good faith and fair dealing claim to the CO because the Certified Claim did not include the words “good faith and fair dealing.” To the contrary, Plaintiff need not use specific legal terms to meet the presentment requirement; rather, it needs only to present a certified claim to the CO that relies upon the same operative facts as the claim asserted in this Court. 11 Plaintiff satisfied the presentment requirement here because the Certified Claim relied upon the same operative facts as the Complaint. Third, Defendant asserts that Plaintiff failed to state a claim based on defective specifications. Defendant argues that Plaintiff’s Complaint failed to identify any design specifications in the Task Order, and that a defective specification claim requires a design specification. The Court agrees. Plaintiff only identifies performance specifications in the Task Order, rather than design specifications. Plaintiff has thus failed to state a defective specification claim. Fourth and finally, Defendant argues that Plaintiff failed to state a superior knowledge claim based on the implied duty of good faith and fair dealing. Defendant contends that a superior knowledge claim requires DLA to have more knowledge than Plaintiff, and that here DLA was unlikely to have more knowledge than Plaintiff. However, Plaintiff pleads that DLA had superior knowledge and, at this stage, the Court must take as true all plausible facts that are pled. As such, the Court holds that Plaintiff has sufficiently pleaded a claim for breach of the implied duty of good faith and fair dealing, based on DLA’s superior knowledge. I. Article III Standing Defendant first challenges Plaintiff’s ability to meet the traceability requirement of Article III standing. See Mot. at 12. The Court of Federal Claims “applies the same standing requirements enforced by other federal courts created under Article III.” Starr Int’l Co., Inc. v. United States, 856 F.3d 953, 964 (Fed. Cir. 2017) (quoting Anderson v. United States, 344 F.3d 1343, 1350 n.1 (Fed. Cir. 2003)). Article III standing has three requirements: “[t]he plaintiff must have (1) suffered an injury in fact, (2) that is fairly traceable to the challenged conduct of the defendant, and (3) that is likely to be redressed by a favorable judicial decision.” Spokeo, Inc. v. Robins, 578 12 U.S. 330, 338 (2016) (citing Lujan v. Defs. of Wildlife, 504 U.S. 555, 560–61 (1992)); see Associated Energy Grp., LLC v. United States, 131 F.4th 1312, 1318 (Fed. Cir. 2025) (same). “Article III standing . . . is a threshold jurisdictional issue.” Associated Energy Grp., 131 F.4th at1317. At issue in this case is Plaintiff’s ability to prove the second requirement, traceability. Mot. at 13. The traceability questions asks whether there is “a causal connection between the injury and the conduct complained of.” Dep’t of Educ. v. Brown, 600 U.S. 551, 561 (2023) (quoting Lujan, 504 U.S. at 560); see also Lujan, 504 U.S. at 560 (cleaned up) (“[T]he injury has to be fairly traceable to the challenged action of the defendant, and not the result of the independent action of some third party not before the court.”). Here, Defendant moves to dismiss the Complaint pursuant to Rule 12(b)(1) for lack of jurisdiction because Plaintiff “has not alleged sufficient facts showing that ACES’ additional ‘costs’ were fairly traceable to the purported ‘deficient specifications’ provided by DLA.” Mot. at 13. In particular, Defendant argues that the repeated bilateral modifications and DLA’s exercise of options broke the “alleged chain of causation” from DLA’s alleged defective specification. Id. at 12. Defendant contends that the modifications and options caused the increased work that Plaintiff blames on defective specification. Id.; see Reply at 8 (“Allegation of injury caused by a defendant’s action that was different from the conduct complained of should nevertheless be dismissed.”). Notably, Defendant does not cite any cases in its briefing in which a contractor with a valid government contract lacked standing to bring a breach of contract claim. See Mot.; Reply. In response, Plaintiff makes two arguments in support of traceability. First, Plaintiff argues that the Complaint pleads traceability because the Complaint “points to the actions of one entity— and one entity only: Defense Logistics Agency.” Resp. at 15. Plaintiff cites several cases for the proposition that “the Court of Federal Claims has consistently found traceability when contractors 13 plead the Government solely and directly caused its damages.” Id. (emphasis in original); see Walsh Constr. Co. v. United States, 140 Fed. Cl. 385, 404 (2018); RDA Constr. Corp. v. United States, 132 Fed. Cl. 732, 766 (2017), aff’d, 739 F. App’x 644 (Fed. Cir. 2018); NCLN20, Inc. v. United States, 99 Fed. Cl. 734, 750 (2011), aff’d, 495 F. App’x 94 (Fed. Cir. 2012). Plaintiff argues it has met the standard for traceability because the Complaint alleges conduct exclusively caused by DLA led to Plaintiff’s injuries. Id. at 15–16. Second, Plaintiff rebuts Defendant’s arguments that the bilateral modifications waived any claim to defective specifications for the original contract and that the alleged injury of increased workload stemmed from the modifications, not the defective specifications. Resp. at 18. Plaintiff asserts Defendant’s contentions are each questions of fact, which are inappropriate to be resolved at this stage of litigation. Id. (“That is a factual dispute—plain and simple.”). It is clear that Plaintiff has standing to bring its suit. Defendant’s argument confuses the merits question of causation for purposes of liability with causation needed to establish traceability. This action instead resembles Centech, in which the chain of causation was not too “attenuated from the Government’s purported actions” to defeat traceability. See Centech Grp., Inc. v. United States, 167 Fed. Cl. 1, 8 (2023). There, the defendant challenged traceability because several intervening events occurred between the defendant’s actions and the damages that led to the suit: the defendant authorized a subcontractor to purchase materials, then refused to accept the materials, so the subcontractor had to cancel the order, for which the contractor refused to reimburse the subcontractor, and the supplier sued the subcontractor. Id. at 6–7. The defendant’s argument failed in Centech because plaintiff had adequately pleaded that the defendant was the but-for cause of the injury, which met the traceability requirement for standing purposes. Id. at 7. Here, similarly, Plaintiff alleges that if not for the DLA’s alleged provision of defective 14 specifications, Plaintiff would not have incurred the injury of increased work: “Upon ACES’s discovery that it had been working in an IDES environment since the beginning of the Contract, ACES notified DLA that deployment in the IDES environment was a changed condition of the work and would result in [a] significant re-work.” Compl. ¶ 13. Although there were several bilateral modifications, Plaintiff alleges further increased costs that the bilateral modifications did not address. Id. ¶ 22. Indeed, traceability is more straightforward here than in Centech because, here, no third parties contributed to the alleged injuries. See Centech, 167 Fed. Cl. at 7. Here, Plaintiff claims that DLA caused injuries, and that no other actors participated in the chain of causation, so the alleged injury was “not the result of the independent action of some third party not before the court.” See Lujan, 504 U.S. at 560 (cleaned up) (quoting Simon v. Eastern Ky. Welfare Rts. Org., 426 U.S. 26, 41–42 (1976)). As such, Plaintiff has properly established traceability for standing purposes in this case. See id. Defendant’s arguments that modifications to the Task Order break any causal chain between the alleged harm and injury belong at a later stage of the case. See Mot. at 12. Defendant argues that the “alleged chain of causation was broken by the repeated modifications to the task order.” Id. However, Plaintiff alleges that the defective specifications caused increased costs that the bilateral modifications did not address. Compl. ¶ 22 (“On September 25, 2023, ACES submitted a request for equitable adjustment seeking $3,805,934.12 in additional compensation for ‘express and constructive changes caused by the government’ that ‘significantly increased ACES’ costs and time of performance under the [C]ontract.’”). “For purposes of ruling on a motion to dismiss for want of standing, both the trial and reviewing courts must accept as true all material allegations of the complaint, and must construe the complaint in favor of the complaining party.” James v. J2 Cloud Servs., LLC, 887 F.3d 1368, 1372 (Fed. Cir. 2018). Defendant has 15 failed to introduce contrary evidence or point to any contract modification provisions that waived or settled ACES’ legal argument. See Mot.; Reply. Thus, accepting the facts as pled, the Complaint alleges an injury (increased costs) traceable to the harm (defective specifications not addressed by the modifications), sufficient to meet the traceability requirement. See Brown, 600 U.S. at 561. Defendant’s argument that the increased costs stemmed only from the Task Order modifications, rather than any defective specifications, is more appropriate for adjudication at summary judgment. Defendant also argues in its Reply that it has “challenged ACES’ allegations of jurisdictional facts,” so that ACES now bears a burden to present evidence supporting the facts. See Reply at 6–7. However, Defendant does not, in fact, challenge any of the facts that support jurisdiction. Throughout the Motion and the Reply, Defendant cites a single paragraph that it challenges from the Complaint, but that paragraph offers a conclusion of law at the end of the Complaint’s Count One and does not plead any jurisdictional facts. See Reply at 6 (challenging Compl. ¶ 36); see also Compl. ¶ 36 (“These various specification deficiencies caused ACES to perform work and incur costs beyond what was originally contemplated under the Contract and for which ACES is entitled to payment.”). Defendant claims that another paragraph in the Complaint contradicts Plaintiff’s argument that the allegedly defective specifications increased the scope of work because the paragraph acknowledges that modifications to the Task Order increased the scope of work. See Mot. at 12 (arguing that Compl. ¶ 18 contradicts traceability) (“The complaint admits that ACES agreed to Modification P00014 in ‘modifying the work to be performed’ to address the alleged development environment issue.”). However, as discussed above, the fact that the parties modified the Task Order to increase the scope of work does not foreclose the possibility, as the Complaint pleads, that defective specifications also increased the 16 scope of work. Defendant has therefore failed to identify any contradictions in the Complaint that defeat jurisdiction. As Defendant has not challenged any jurisdictional facts, the Court must accept the facts in the Complaint as true. See Trusted Integration Inc. v. United States, 659 F.3d 1159, 1163 (Fed. Cir. 2011). Based on these relevant undisputed facts as alleged in the Complaint, Plaintiff has established standing. II. Presentment Defendant argues that this Court lacks jurisdiction because ACES failed to meet the presentment requirement for its claim in Count Two of the Complaint, based on the implied duty of good faith and fair dealing. Mot. at 13. The CDA requires that each claim in this Court must have been “previously presented to and denied by the contracting officer.” Scott Timber, 333 F.3d at 1365 (quoting Cerberonics, Inc. v. United States, 13 Cl. Ct. 415, 417 (1987)). To establish jurisdiction under the CDA, a plaintiff must both (i) submit each claim to the contracting officer and (ii) receive a final decision from the contracting officer on each claim. K-Con Bldg. Sys., 778 F.3d at 1005; see also Raytheon Co. v. United States, 747 F.3d 1341, 1354 (Fed. Cir. 2014) (citing 41 U.S.C. § 7103(a)(3)) (“It is a bedrock principle of government contract law that contract claims, whether asserted by the contractor or the Government, must be the subject of a contracting officer’s final decision.”). Presentment is a jurisdictional requirement for CDA claims in the Court of Federal Claims. See Tolliver Grp., 20 F.4th at 776; see also Avant Assessment, LLC v. United States, 171 Fed. Cl. 212, 216 (2024), aff’d, No. 2024-2054, 2025 WL 3511163 (Fed. Cir. Dec. 8, 2025) (finding that the presentment requirement remains jurisdictional after ECC Int’l Constrs., LLC v. Sec’y of the Army, 79 F.4th 1364 (Fed. Cir. 2023)). “A claim need not ‘be submitted in any particular form or use any particular wording . . . .’” K-Con Bldg. Sys., 778 F.3d at 1005 (quoting Contract Cleaning Maint., Inc. v. United States, 811 17 F.2d 586,592 (Fed. Cir. 1987)). Rather, the contractor must “submit in writing to the contracting officer a clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of the claim.” Scott Timber, 333 F.3d at 1365 (quoting Contract Cleaning Maint., 811 F.2d at 592); see also Tolliver Grp., 20 F.4th at 776 (“The focus is on whether the contracting officer was given ‘an ample pre-suit opportunity to rule on a request, knowing at least the relief sought and what substantive issues are raised by the request.’” (quoting K-Con Bldg. Sys., 778 F.3d at 1006)). To determine if a claim has been presented, the key question is whether the claim presented in this Court “is the ‘same claim’ as the one presented to the contracting officer.” Tolliver Grp., 20 F.4th at 776 (quoting Raytheon, 747 F.3d at 1354). To determine if the claims are the same, courts assess whether the claims “arise from the same operative facts, claim essentially the same relief, and merely assert differing legal theories for that recovery.” Scott Timber, 333 F.3d at 1365. Defendant contends that Plaintiff did not satisfy the presentment requirement for its implied duty of good faith and fair dealing claim because ACES’s “certified claim never expressly asserts that DLA breached any implied duty of good faith and fair dealing—none of those terms appear in its certified claim.” Mot. at 14. Defendant further asserts that the Complaint does not rely upon the same operative facts as the Certified Claim because the Complaint accuses DLA of “failing to cooperate,” whereas the Certified Claim alleged a “failure to collaborate effectively.” Id. at 15. Similarly, Defendant argues that the Complaint accuses DLA of “interfering” with ACES’s performance, whereas the Certified Claim alleges that DLA “directed and controlled the methods used by the contractor.” Id. Further, Defendant argues that the Certified Claim’s “operative facts” “fell short of demonstrating the specific targeting necessary to give rise to a breach of an implied duty of good faith and fair dealing.” Id. at 14. This argument rests upon its 18 assertion that a breach of the implied duty of good faith and fair dealing requires that a government official “specifically targeted” the contractor. Id. (citing Precision Pi