Visionary Construction, Inc. dba Visionary Services
CourtArmed Services Board of Contract Appeals
Date FiledAugust 20, 2026
Docket64426
JudgeOsterhout
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Visionary Construction, Inc. dba Visionary ) ASBCA No. 64426
Services )
)
Under Contract No. N40085-25-C-2500 )
APPEARANCE FOR THE APPELLANT: Ms. Tasha Reid
Atlanta, GA
APPEARANCES FOR THE GOVERNMENT: Tracey R. Rockenbach, Esq.
Acting Navy Chief Trial Attorney
Howard A. Smith, Esq.
Joseph T. Hargis, Esq.
Trial Attorneys
OPINION ON THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT BY
ADMINISTRATIVE JUDGE OSTERHOUT
This appeal involves a contract for Visionary Construction, Inc. (Visionary or
appellant) to perform parking garage repairs for Building 7401 at Great Lakes Naval
Base in Illinois. Visionary alleges that the United States Navy (the Navy or the
government) wrongfully terminated the contract for default and seeks to have the
termination converted into a termination for convenience. The Navy moves for
summary judgment, asserting that the default termination was proper because Visionary
failed to timely secure contractually compliant performance and payment bonds. We
grant the government’s motion.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
1. On March 27, 2025, the Navy awarded Contract No. N40085-25-C-2500 to
Visionary for the “furnishing [of] all labor, transportation, supervision, material,
equipment, and performing [of] all operations in connection with performing parking
garage repairs at Building 7401” at Great Lakes Naval Base in Illinois (R4, tab 20
at 752-53).
2. The contract incorporated by reference Federal Acquisition Regulation (FAR)
52.228-15, PERFORMANCE AND PAYMENT BONDS – CONSTRUCTION
(Deviation 2020-O0016) (JUN 2020) (R4, tab 20 at 762). This clause provides that
“[t]he Contractor shall furnish all executed bonds, including any necessary
reinsurance agreements, to the Contracting Officer [CO], within the time period
specified in the Bid Guarantee provision of the solicitation, or otherwise specified by
the Contracting Officer, but in any event, before starting work.” FAR 52.228-15(c)
(Deviation 2020-O0016).
3. The solicitation stated that “[i]n accordance with FAR 52.228-15,
Performance and Payment bonds equal to 100% of the awarded dollar value are
required 10 days after date of award” (R4, tab 3 at 287).
4. The contract also incorporated by reference FAR 52.228-1, BID
GUARANTEE (SEP 1996) (R4, tab 20 at 762). FAR 52.228-1 provides in relevant
part:
(d) If the successful bidder, upon acceptance of its bid by the
Government within the period specified for acceptance, fails
to execute all contractual documents or furnish executed
bond(s) within 10 days after receipt of the forms by the
bidder, the Contracting Officer may terminate the contract
for default.
(e) In the event the contract is terminated for default, the
bidder is liable for any cost of acquiring the work that
exceeds the amount of its bid, and the bid guarantee is
available to offset the difference.
(Emphasis added).
5. Upon notification of award on March 27, 2025, the Navy directed Visionary to
submit the required performance and payment bonds within 15 calendar days of the
award (R4, tab 20 at 750-51).
6. On April 11, 2025, 15 days later, Visionary submitted Standard Form (SF) 25
– Performance Bond and SF 25A – Payment Bond to the Navy, which indicated that
First Standard Asurety, LLLP (FSA) would act as the surety for both the payment
and performance bonds (R4, tab 21 at 838, 840-47).
7. The signature block for both bonds was executed by “David Harris, Managing
Partner of FSA, LLLP” in the space identified as “Individual Surety(ies)” (R4, tab 21
at 841, 844). Each signature block also included a stamp labeled “First Standard
Asurety LLLP” (id. at 841, 844).
8. By letter dated April 15, 2025, the Navy advised Visionary that its SF 25 and
SF 25A submissions were “NON-COMPLIANT” because FSA was not listed in the
Treasury Department Circular 570 as an approved corporate surety as required by
2
FAR 52.228-15(d) (R4, tab 22 at 852). The Navy further warned that “[t]he contract
may be terminated for default in accordance with FAR clause 52.228-1, BID
GUARANTEE” if compliant bonding was not submitted (id.).
9. That same day, Visionary replied via email requesting the Navy to “[p]lease
see attached POA for an individual surety and advise if there are any additional
documents needed” (R4, tab 23 at 853). Included as an attachment was a document
entitled “Special Meeting of the Members of: First Standard Asurety, L.L.L.P.,”
which authorized:
David Harris, as Manager Partner of First Standard Asurety,
LLLP, alone, or with other officers, to execute any and all
instruments, affidavits, certificates, agreements, guaranty
agreements, surety bonds, bid bonds, and any and all other
instruments, documents, and agreements on behalf of First
Standard Asurety, LLLP, with full Power of Attorney as he
shall deem necessary or desirable, to effect or facilitate the
issue of bonds, not to exceed Twenty-five Million United
States Dollars ($25,000,000).
(Id. at 854) (emphasis in original)
10. The Navy informed Visionary via email dated April 21, 2025, that it had
determined that FSA did not meet FAR 2.101’s definition of “individual surety”
because FSA was a business entity and not an individual person (R4, tab 27 at 978-
79). Specifically, the Navy stated “it appears that Mr. David Harris is executing the
bonds in his capacity as managing partner of First Standard Asurety, LLLP, not in
his personal capacity” (id. at 979).
11. Visionary replied that same day that it would submit new payment and
performance bonds by the end of the week (R4, tab 27 at 978).
12. On May 9, 2025, 43 calendar days after contract award, the Navy issued a
letter to Visionary expressing its concern with Visionary’s “lack of progress” in
securing acceptable performance and payment bonds (R4, tab 31 at 1000-02). The
letter directed Visionary to “submit, in writing, when Visionary Services intends to
submit compliant performance & payment bonds and certificate of insurance and the
procedures or steps you intend to take to ensure the completion of this contract in a
timely manner” no later than May 16, 2025 (id. at 1002).
13. Visionary responded on May 13, 2025, with an attachment containing
“additional information reviewed by legal counsel” (R4, tab 32 at 1003). The
attachment provided a legal analysis from counsel for FSA on its belief that FSA
3
qualified as an individual surety under FAR 2.101’s definition (id. at 1005-06). The
attachment asserted that:
In sum, because an LLLP is not within the FAR definition of
a corporate surety, a natural person (such as Mr. Harris) is
behind the LLLP and remains fully and personally liable,
and the pledged assets meet every substantive requirement of
FAR 28.203-1, FSA should be admitted as an individual
surety for Visionary Construction, Inc.
(Id. at 1006)
14. The Navy responded via letter dated May 20, 2025, reiterating its
determination that FSA was “not an acceptable surety as it neither qualifies as a
‘corporate surety’ or an ‘individual surety’ under the Federal Acquisition
Regulation” (R4, tab 33 at 1009). The Navy further advised that if Visionary wished
to use Mr. Harris as an individual surety for the performance and payment bonds, he
must act exclusively in his individual capacity (id.).
15. Visionary acknowledged the Navy’s determination that FSA did not qualify
as an acceptable surety via letter dated May 23, 2025, and presented a “Bond
Compliance Plan” advising that Visionary was “working with an approved surety
agent and anticipate[d] submission of [Small Business Administration]-backed bonds
no later than June 13, 2025” (R4, tab 34 at 1018).
16. Via email dated June 13, 2025, Visionary provided a summary of a Microsoft
Teams meeting concerning the outstanding bond requirements to the Navy. During
the meeting, Visionary proposed a teaming agreement with Martin Construction
(Martin) to address the bonding issues. (R4, tab 36 at 1020)
17. On July 9, 2025, Visionary’s counsel provided the Navy with a copy of the
proposed teaming agreement with Martin (R4, tab 36 at 1022-34). Paragraph 3.1.2
of the agreement stipulated that “Payments from the Customer shall be made directly
to Martin” (id. at 1026).
18. The Navy advised Visionary’s counsel via email dated July 10, 2025, that the
proposed teaming agreement violated the Assignment of Claims Act (31 U.S.C. §
3727) and FAR 32.802 because it required the Navy to pay Martin directly instead of
Visionary and Martin was not a bank, trust company, or other financing institution
(R4, tab 37 at 1036).
4
19. Visionary informed the Navy via email dated August 1, 2025, that it was “in
the final stages of securing the bond” through ACSTAR Insurance Company
(ACSTAR) (R4, tab 38 at 1039).
20. By email dated August 15, 2025, ACSTAR inquired whether the Navy
would consent to assignment of monies due under the contract as a precondition of
executing the bond (R4, tab 39 at 1042-43).
21. On August 18, 2025, the Navy responded that it did not believe that
ACSTAR met the statutory definition of “other financial institutions” based upon
Government Accountability Office (GAO) guidance and its own interpretation of the
Assignment of Claims Act and thus would not consent to an assignment of monies to
ACSTAR (R4, tab 39 at 1041-42). ACSTAR replied that same day that it “will not
be able to write this bond” (id. at 1041).
22. The Navy issued a cure notice to Visionary on August 20, 2025, 146
calendar days after contract award, directing Visionary to submit compliant
performance and payment bonds no later than September 2, 2025. The notice also
warned that the Navy could terminate the contract for default if this deadline was not
met. (R4, tab 40 at 1053-55)
23. On September 3, 2025, Visionary replied: “Apologies for the delay in
responding, due to the holiday, our new surety encountered some roadblocks. Per
the attached, they respectfully asked for an additional day to finalize the paperwork”
(R4, tab 42 at 1072). Visionary’s reply included an email attachment from Ms.
Amanda Quigley of CCI Surety dated September 3, 2025, informing Visionary that
Ms. Quigley was “still working on the underwriting for [Visionary’s performance
and payment] bond. I do need some more time, if you are able to get an extension on
your deadline, that would be great” (id.; R4, tab 43 at 1076).
24. Visionary informed the Navy via email dated September 8, 2025, that it was
“not in a position to meet [the Navy’s] final submission deadline for acceptable
bonds” and requested that the Navy “exercise its discretion to terminate this contract
for the convenience of the Government” (R4, tab 43 at 1077-78) (emphasis in
original).
25. The Navy terminated the contract for default on September 24, 2025 (R4,
tab 45 at 1082-83, tab 46 at 1084-85).
26. Following the default termination, the Navy awarded the contract to Diverse
Solutions Group, Inc. (Diverse Solutions) (R4, tab 47 at 1086).
5
27. Visionary appealed the default termination to the Board. The Board
docketed Visionary’s appeal as ASBCA No. 64426 on December 30, 2025.
DECISION
The Parties’ Contentions
The Navy moves for summary judgment on the grounds that Visionary’s failure
to obtain compliant performance and payment bonds required by the contract justified
the termination for default as a matter of law (gov’t mot. at 3-5; gov’t reply at 1).
Visionary asserts that (1) the Navy’s failure to comply with the FAR renders the
default termination procedurally deficient (app. opp’n at 5); (2) the Navy’s actions were
responsible for the final bond failure with ACSTAR (id. at 5-6); (3) the CO’s decision to
terminate for default rather than convenience was arbitrary and capricious (id. at 6-7);
and (4) conversion of the default termination into a termination for convenience would
be appropriate based on the record (id. at 7). Visionary asserts that “multiple genuine
disputes of material fact” impact the appeal, including: 1) whether the government
provided Visionary an opportunity to cure the bond deficiency before deciding to
terminate for default; 2) whether the government shifted its own position and rulings to
cause the bond impasse; and 3) whether the CO appropriately applied FAR 49.402-3(f)
(id. at 1). Visionary also requested that the Board deny the government’s request for a
stay of discovery (id. at 8)
In its reply, the government disputes Visionary’s characterization of its genuine
issues of material fact, mostly stating that Visionary’s arguments are characterizations of
its position, not factual issues (gov’t reply).
Standard of Review
When deciding a motion for summary judgment, the Board looks to Rule 56 of
the Federal Rules of Civil Procedure (FED. R. CIV. P.) for guidance. Board Rule 7(c)(2).
Summary judgment is appropriate when there are no genuine issues of material fact and
the movant is entitled to judgment as a matter of law. FED. R. CIV. P. 56(a); Celotex
Corp. v. Catrett, 477 U.S. 317, 322 (1986); Mingus Constructors, Inc. v. United States,
812 F.2d 1387, 1390 (Fed. Cir. 1987). A fact is material if it may affect the outcome of
the decision. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248-49 (1986). The
movant bears the burden of establishing the absence of any genuine issue of material
fact. Celotex, 477 U.S. at 322. Such facts must be viewed in the light most favorable to
the non-moving party. Liberty Lobby, 477 U.S. at 255; C. Sanchez and Son, Inc. v.
United States, 6 F.3d 1539, 1541 (Fed. Cir. 1993). However, the non-movant must set
forth specific facts demonstrating the existence of a genuine issue of material fact; mere
conclusory statements and bare assertions are inadequate. Mingus, 812 F.2d at 1390-91;
6
see also Liberty Lobby, 477 U.S. at 252 (“The mere existence of a scintilla of evidence
in support of the [non-movant]’s position will be insufficient . . . .”). The Board’s
responsibility at this stage is not “‘to weigh the evidence and determine the truth of the
matter,’ but rather to ascertain whether material facts are disputed and whether there
exists any genuine issue for trial.” Holmes & Narver Constructors, Inc., ASBCA Nos.
52429, 52551, 02-1 BCA ¶ 31,849 at 157,393 (quoting Liberty Lobby, 477 U.S. at 249).
The Termination of the Contract for Default Was Justified as a Matter of Law
It is well settled that a contractor’s failure to obtain bonding justifies a default
termination as a matter of law. Odyssey Int’l, Inc., ASBCA No. 62085 et al., 20-1 BCA
¶ 37,623 at 182,654; Marshall’s Elec., Inc., ASBCA No. 59749, 16-1 BCA ¶ 36,300
at 177,017; Ruffin’s A-1 Contracting, Inc., ASBCA No. 38343, 90-3 BCA ¶ 23,243
at 116,626; FAR 52.228-1(d). Visionary and the Navy do not dispute that the contract
required Visionary to secure payment and performance bonds within 10 days of award
and the government allowed 15 days (findings 2-5). It is further undisputed that despite
numerous extensions of time, Visionary failed to secure compliant bonds (findings 8, 10,
12-14, 18, 21-24). Thus, Visionary can only succeed in overturning the default
termination by demonstrating that the CO’s exercise of discretionary judgment “was so
unreasonable, arbitrary, or capricious as to be invalid.” Ruffin’s, 90-3 BCA ¶ 23,243
at 116,626; see also Pac. Sunset Builders, Inc., ASBCA No. 39312, 93-3 BCA ¶ 25,923
at 128,945.
Visionary asserts that there is a genuine issue of material fact as to whether the
Navy provided it with the opportunity to cure correctable bond deficiencies before
resorting to a default termination (app. opp’n at 5). We find that there is no such issue.
While Visionary cites its “good faith efforts” to obtain compliant bonding as evidence
that the default termination was improper (app. opp’n at 7-8), a review of the Navy’s
actions and rejections of Visionary’s proposed bond submittals demonstrates a
reasonable effort to allow Visionary additional opportunities and time to secure adequate
bonding despite Visionary’s repeated failures to do so.
The Navy denied Visionary’s first attempt to submit the bonds through FSA
because FSA was not listed as an approved corporate surety in the Treasury Department
Circular 570 as required by FAR 52.228-15(d) and because FSA did not meet
FAR 2.101’s definition of an “individual surety” (findings 6-8, 10, 14). The Navy
further advised that Mr. Harris could qualify as an individual surety if he acted
exclusively in his individual capacity (finding 14), yet there is no evidence in the record
that Visionary ever pursued this avenue. On May 9, 2025, 43 days after contract award,
the Navy issued its letter of concern regarding Visionary’s lack of progress but
nevertheless continued to allow Visionary to submit proposals (finding 12). The Navy
rejected Visionary’s second attempt involving the proposed teaming agreement with
7
Martin because the agreement would have violated the Assignment of Claims Act by
requiring the Navy to pay Martin directly instead of Visionary (findings 16 18).
Visionary contends that there is a genuine issue of material fact as to whether the
Navy changing positions on the legality of securing the bonding through ACSTAR was
a primary and controlling cause of its failure to obtain adequate bonding (app. opp’n
at 2-3). We disagree. Nothing in the record supports Visionary’s contention that the
Navy changed positions. The Navy denied Visionary’s ACSTAR proposal, which
would have required the Navy to assign monies due under the contract to ACSTAR as a
precondition, because it determined that ACSTAR was not a “financial institution”
within the meaning of FAR 32.802 and thus ineligible for such an assignment under the
Assignment of Claims Act (findings 19-21).
Visionary also contends that the CO failed to appropriately weigh “all required
FAR 49.402-3(f) factors” prior to deciding to terminate for default (app. opp’n at 1).
We disagree. Visionary’s disagreement with the outcome does not mean the
government failed to properly terminate the contract and does not create a genuine issue
of material fact. The government provided Visionary with ample opportunities to cure
the bonding problem. The Navy issued the cure notice to Visionary on August 20, 2025,
146 days after contract award despite the fact that the bonding was required to be
secured within 10 days of award (findings 3, 22), and it was not until after Visionary
informed the Navy that it was unable “to meet [the Navy’s] final submission deadline
for acceptable bonds” that the Navy finally terminated the contract for default on
September 24, 2025 (181 days after award) (findings 24-25). Furthermore, while
Visionary avers that there is a genuine dispute of material fact as to whether a
termination for convenience to the government would have been more appropriate in
this situation than a termination for default (app. opp’n at 6-7), the Navy was still in
need of the services to be provided under the contract, as evidenced by the Navy
awarding the contract to Diverse Solutions after the default termination (finding 26).
Nothing in the record indicates any actions taken by the Navy or the CO to be “so
unreasonable, arbitrary, or capricious as to be invalid,” (Ruffin’s, 90-3 BCA ¶ 23,243 at
116,626), nor does Visionary specifically allege any such action. In fact, the record
shows that the Navy exhibited a remarkable amount of patience.
Once a default has been established, the onus is on the contractor to prove that its
default is excused. HK&S Constr. Holding Corp., ASBCA No. 60164, 19-1 BCA
¶ 37,268 at 181,532; ADT Constr. Grp., ASBCA No. 55358, 13-1 BCA ¶ 35,307
at 173,315. When the contractor claims that the government was responsible for its
failure to perform, the burden is on the contractor to demonstrate that the government’s
action was the primary or controlling cause of the default. Odyssey Int’l, ASBCA No.
62085 et al., 21-1 BCA ¶ 37,861 at 183,849; ADT, 13-1 BCA ¶ 35,307 at 173,315.
Visionary alleges that its default was caused by reasonable reliance on a position the
Navy later reversed regarding the ACSTAR bond submission, asserting that “[t]he
8
Government cannot simultaneously tell a contractor that an assignment based [on]
bonding structure is legally viable, then reverse that position five weeks later without
that reversal being examined as a contributing cause of the contractor’s inability to
perform” (app. opp’n at 2-3). Specifically, Visionary asserts that the Navy advised that
certain assignments would be permissible if they met the Assignment of Claims Act’s
requirements when the Navy rejected the Martin teaming agreement proposal, then
diverted from this position by refusing to agree to assign monies due under the contract
to ACSTAR as a precondition of executing the bond (id.). This was not a reversal.
Rather, the Navy simply advised that it did not believe that it could legally assign the
payments directly to ACSTAR based upon both GAO guidance and its own
interpretation of the Assignment of Claims Act, and ACSTAR decided that it would not
be able to write the bonds based upon this determination (finding 21). Because
Visionary raises no dispute of material fact as to whether the Navy acted in accordance
with the proper governing authorities in determining that ACSTAR did not qualify as a
permissible surety, it has failed to establish that its default was not justified. Celotex,
477 U.S. at 322; Mingus, 812 F.2d at 1390.
Visionary further asserts that the Navy’s failure to comply with FAR 28.203(c)
renders the default termination procedurally deficient (app. opp’n at 5). Visionary
claims that FAR 28.203(c) requires a CO reviewing individual surety submissions to
notify the contractor of deficiencies and provide an opportunity to correct them (id.).
The Board is unable to identify any section of the FAR as 28.203(c). 1 Appellant appears
to be referencing FAR 28.203-1(c), which provides:
Using the information from the SF 28 submitted by the
offeror or contractor, the contracting officer shall notify the
Treasury’s collateral operations support team by email at
BMT@fiscal.treasury.gov or by phone at 888–568–7343, of
the individual surety, the assets to be pledged, and the
amount necessary to cover the individual surety bond, i.e.,
the required amount to be collateralized. Treasury will
advise the contracting officer whether the assets are eligible
to be pledged, consistent with 28.203–1(a), and of the
valuation of the assets offered to be pledged, consistent with
the valuation standards in 28.203–1(b)(2). If after 3 business
days the contracting officer has not received a response from
Treasury, the contracting officer may seek assistance from
the Director, Bank Policy and Oversight, at 202-504-3502.
The contracting officer shall determine whether the
individual surety bond is acceptable as to the amount
1
FAR 28.203 is entitled “Individual Sureties” and is divided into sections 28.203-1,
28.203-2, 28.203-3, 28.203-4, and 28.203-5.
9
necessary to cover the individual surety bond based on the
asset eligibility and valuation assessment from Treasury.
The contracting officer shall notify both the offeror or
contractor and the individual surety of this determination.
(Emphasis added). Notably absent from this section, or any other section of
FAR 28.203 for that matter, is a requirement that the CO notify the contractor of
deficiencies or provide a chance to resolve them. Moreover, even if such a requirement
existed, the Navy issued a cure notice that afforded Visionary the opportunity to submit
acceptable performance and payment bonds no later than September 2, 2025, and
advised that the contract could be terminated for default if this deadline was not met
(finding 22).
Finally, Visionary asserts that the Board should deny the government’s request to
stay discovery because the Rule 4 file “may not contain all documents relevant to the
Government’s legal determinations . . . .” (app. opp’n at 8). The Board stayed discovery
by order dated April 2, 2026. However, because appellant is proceeding pro se, we
interpret appellant’s request as a motion pursuant to Federal Rule 56(d) alleging that it is
unable to oppose the government’s motion because facts are unavailable to the
nonmovant. Pursuant to Rule 56(d), the nonmoving party must support its request with
an affidavit or declaration specifying the reasons why it was unable to present the facts
essential to defend against the government’s motion. Odyssey Int’l, Inc., ASBCA
Nos. 62062, 62279, 21-1 BCA ¶ 37,902 at 184,074. Even ignoring that Visionary has
not complied with the requirement that it submit an affidavit or declaration, it has not
explained how discovery would allow it to rebut the summary judgment motion. At
most, Visionary asserts that the Rule 4 file “may not contain all documents relevant to
the Government’s legal determinations” (app. opp’n at 8) (emphasis added). Alleging
that something might turn-up in discovery is insufficient to prevent entry of summary
judgment. Odyssey, 21-1 BCA ¶ 37,069 at 184,074.
10
CONCLUSION
For the foregoing reasons, the Navy is entitled to judgment as a matter of law and
its motion for summary judgment is granted. Visionary’s appeal is denied.
Dated: August 20, 2026
HEIDI L. OSTERHOUT
Administrative Judge
Armed Services Board
of Contract Appeals
I concur I concur
J. REID PROUTY DAVID D’ALESSANDRIS
Administrative Judge Administrative Judge
Acting Chairman Acting Vice Chairman
Armed Services Board Armed Services Board
of Contract Appeals of Contract Appeals
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 64426, Appeal of Visionary
Construction, Inc. dba Visionary Services, rendered in conformance with the Board’s
Charter.
Dated: August 20, 2026
PAULLA K. GATES-LEWIS
Recorder, Armed Services
Board of Contract Appeals