Seabee Construction, Inc. v. United States
CourtUnited States Court of Federal Claims
Date FiledJuly 2, 2026
Docket26-506
JudgeEric G. Bruggink
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
In the United States Court of Federal Claims
No. 26-506
(Filed: June 24, 2026)
(Reissued July 2, 2026) 1
**************************
SEABEE CONSTRUCTION, INC.,
Plaintiff,
v.
THE UNITED STATES,
Defendant,
and
ALPINE CONSTRUCTION MANAGEMENT, LLC,
Defendant-Intervenor.
**************************
Jonathan A. DeMella, Seattle, WA, with whom was Matthew C. Gurr,
for plaintiff, Seabee Construction, Inc.
Dirk D. Haire, Washington, D.C., with whom were Michael J. Brewer
and Isabella S. Capanna, for defendant-intervenor, Alpine Construction
Management, LLC.
Patrick S. Angulo, Trial Attorney, United States Department of
Justice, Commercial Litigation Branch, Civil Division, Washington, D.C.,
with whom were Brett A. Shumate, Assistant Attorney General, Patricia M.
McCarthy, Director, and Douglas K. Mickle, Acting Director, for defendant.
1
This opinion was originally issued under seal to afford the parties an
opportunity to propose redactions of protected information. The parties have
conferred and reached an agreement on proposed redactions, which we have
adopted. Redactions are indicated by the insertion of brackets in place of
original material.
OPINION
Pending in this post-award bid protest are Seabee Construction, Inc.’s
(“Seabee”) motion for judgment on the administrative record and the
government’s and Alpine Construction Management, LLC’s (“ACM”) cross-
motions for judgment on the administrative record. This matter is fully
briefed, and we heard oral argument on June 12, 2026. For the reasons set
out below, we grant the government’s and Alpine’s motions and deny
Seabee’s motion.
BACKGROUND 2
I. Relevant Facts
A. The Solicitation and Invitation for Bids
On July 3, 2025, 3 the government, acting through the United States
Department of Veterans Affairs, National Cemetery Administration (“NCA”
or the “agency”), issued solicitation No. 36C78625B0038 for the “cemetery
expansion and improvements construction project at the Snake River Canyon
Nat’l Cemetery” in Buhl, Idaho. Administrative Record (“AR”) Tab 8, 100.
The NCA sought to award a single firm, fixed price contract in accordance
with FAR Part 14, Sealed Bidding. Id. The solicitation was issued as an
invitation for bids (“IFB”) procurement and therefore incorporated by
reference FAR 52.214-19, Contract Award–Sealed Bidding–Construction.
Id. at 100, 114. That FAR provision provides that “[t]he Government will
evaluate bids in response to this solicitation without discussions and will
award a contract to the responsible bidder whose bid, conforming to the
solicitation, will be most advantageous to the Government, considering only
price and the price-related factors specified elsewhere in the solicitation.”
FAR 52.214-19. The IFB called for a one-year period of performance and
anticipated commencement of the project within 20 days after contract
award. AR Tab 8, 100.
Section 2.1 of the IFB contained the bid instructions. Id. at 109. The
instructions informed potential bidders of what was required to be contained
within their bid packages, including, among other things, a bid guarantee, a
2
These facts are drawn from the Administrative Record.
3
While the solicitation was originally issued on July 3, 2025, it was later
updated and reissued on August 20, 2025.
2
completed contract administration data sheet, and a completed price/cost
schedule. Id. A bid that failed to include any of the required documents would
be deemed “non-responsive.” Id. The IFB provided a price/cost schedule that
required bidders to provide the bid’s overall price as well as a unit price
breakout for on-site rock removal. Id. at 105.
The IFB informed potential bidders that the project would need to be
completed in accordance with the statement of work, specifications,
drawings, and other attachments. Id. at 100; see AR Tab 8a, 184 (scope of
work); AR Tab 8b, 188 (bid document specifications); AR Tab 8c, 1235
(revised bid document specifications); AR Tab 8d, 2266 (bid drawings). The
specifications outlined the mandatory experience and certification standards
that the contractor and its subcontractors were required to meet. The initial
specifications were included with the original IFB, see AR Tab 8b, 188, and
a subsequent amendment revised the specifications in ways immaterial to this
case, see AR Tab 8c, 1235.
Relevant for our purposes, the specifications set forth standards for
the concrete burial crypt installer and the columbarium installer. Section 03
48 21, paragraph 1.6 of the specifications addresses the qualifications for the
burial crypt installer. See AR Tab 8c, 1427. Subsection C of paragraph 1.6
states:
Installation Qualifications: Provide written documentation that
verifies:
1. The installer has been regularly engaged, for at least three
years, in installation of pre-cast concrete similar to this
project.
Id. Section 03 48 24, paragraph 1.5 of the specifications addresses the
qualifications for the columbarium unit installer. See id. at 1450. That
paragraph states:
A. Precast concrete columbarium unit installer shall have been
regularly engaged for at least three years in installation of
precast concrete similar to this project. Installers that have
previously completed at least three successful NCA
columbarium projects within the past 10 years are deemed to
be acceptable. Installer to submit successful projects for NCA
review. Installer to submit resumes with names of those
experienced installers performing the installation.
3
B. Installer shall have had a minimum of 3 years of experience
in installation of niche cover attachment hardware.
Id. Importantly, the specifications for the columbarium installer provides that
the qualifications are due “[p]rior to the commencement of work.” Id. at
1448.
On July 20, 2025, the NCA issued Amendment No. 0001. AR Tab 9,
2355. The purpose of the amendment was to “answer the request for
information (RFI) submitted from interested bidders.” Id. Relevant here, one
bidder asked: “If the awarded contractor is unable to provide an installer that
meets the required qualifications: What are the contractual consequences
(e.g., rejection, termination for default, re-bid)?” Id. at 2361. The NCA
responded:
No. The requirements for installer qualifications are firm and
must be met at the time of contract award and performance.
There is no established waiver process under FAR Part 14.
Bidders are expected to ensure compliance with all solicitation
requirements prior to submission and during contract
performance. Any proposed personnel must meet all
mandatory qualification criteria as specified.
Id. The same bidder also asked whether the agency “offer[ed] any case-by-
case evaluation process or temporary waiver mechanism for otherwise
qualified personnel?” Id. The NCA provided the same response. Id.
B. The Award Process
1. Bid Proposals and Bid Opening
In total, the NCA received nine bids in response to the IFB. See AR
Tab 22, 2654–56. Both Seabee and ACM submitted their respective bids on
September 8, 2025, which was the date of the bid opening. 4 ACM’s bid was
the lowest with an overall bid price of $5,748,586.60. AR Tab 14, 2415.
Seabee submitted the second-lowest bid with an overall bid price of
$6,294,496.98. AR Tab 19, 2584. Both bids satisfied all of the IFB’s express
4
The IFB initially required bids to be submitted by August 25, 2025. AR Tab
8, 100. Later, however, the NCA extended the deadline to September 8, 2025.
AR Tab 12, 2374.
4
requirements; and, importantly, neither bid disclosed proposed installers or
installer qualifications. See id. at 2413, AR Tab 19, 2575.
2. Communications Within the Agency and With ACM
NCA identified ACM as the lowest bidder. See AR Tab 24, 2689.
Because the IFB called for sealed bidding under FAR Part 14, the contracting
officer could not award the contract to ACM without first determining that
ACM was responsible and that ACM’s prices were reasonable. FAR 14.408-
2. The “responsibility” criteria are set forth in FAR 9.104-1. FAR 9.105-1
allows the contracting officer to obtain information to aid in making the
responsibility determination and requires the officer to do so “promptly after
bid opening.”
Auvorie Benson, the contracting officer originally responsible for this
solicitation, requested by letter additional information from ACM on
September 9, 2025—the day after bid opening. AR Tab 23a, 2660. Mr.
Benson informed ACM that ACM’s bid was 23% lower than the Independent
Government Cost Estimate (IGCE). Id. Thus, due to this “variance,” the
agency sought to “confirm and clarify certain aspects of [ACM’s] bid to
ensure” that ACM understood the project requirements and was “capable of
successfully executing the contract.” Id. Referencing FAR Parts 9 and 14,
Mr. Benson explicitly stated that the request was solely intended to “ensure
that [ACM] comprehend[ed] the scope of work and possess[ed] the necessary
qualifications to meet the project’s demands.” Id.
Mr. Benson’s request tracked the categories of FAR 9.104-1 by
requesting information regarding ACM’s financial resources, performance
record, technical capabilities, cost breakdown, and ability to meet the
contract’s minimum requirements. Pertaining to the request for information
relating to ACM’s technical capabilities, the letter stated:
Technical Capabilities: Submit documentation outlining your
technical capabilities, including relevant experience and any
certifications held by your key personnel. Specifically, please
furnish evidence of having a certified crypt installer, as
referenced in specification document 03 48 21 - 3 (Precast
Concrete Burial Crypts) for 1.6.C. Additionally, provide proof
of a concrete columbarium unit installer with a minimum of 3
years of experience as referenced in specification document 03
48 24 - 4 (Precast Concrete Columbarium Units) paragraphs
5
1.5.A & B. This information is necessary to determine
capability as per FAR Part 9.104-2.
Id. at 2660–61.
On September 10, 2025, after sending the letter requesting additional
information but before ACM responded to that request, Mr. Benson emailed
Dimasalang Junio, the NCA Deputy Director of Design and Construction,
and Juan Kays, the NCA Project Manager, to inform them that he was “a bit
hesitant to award” the contract to ACM. AR Tab 29, 2924. Mr. Benson
explained that he could not “find anything that shows [ACM’s] true
capabilities” and that ACM’s past federal contracts were “nowhere near the
complexity of Snake River.” Id. After explaining that he had sent a letter to
ACM requesting additional information (as we explained above), Mr.
Benson stated:
Depending on their reply, I highly recommend that we still
send it to SBA to get a certificate of competency to allow them
to review and see if they can provide us some surety of
awarding to them. It may even make them truly review their
bid and ensure they can stand by their cost. I know we want to
award this prior to Sept 30, but I think we need to be sure
before we move forward.
Id. In response to this email, Mr. Kays stated: “[Mr. Benson, ACM] is
required to hire columbarium and crypt installers with experience. Can you
check to see that they’ll honor that?” Id.
On September 12, 2025, in response to Mr. Benson’s letter requesting
additional information, ACM provided a document titled “Confirmation and
Clarification of Bid Submission.” AR Tab 46, 4372. The confirmation and
clarification included, among other things, ACM’s past performance, 5 its
proposed columbarium unit manufacturer, and its planned burial crypt and
columbarium unit installers. Id. at 4374–77. ACM identified
[ ] as its planned crypt installer and provided
5
While ACM provided a variety of past performance examples, Seabee
argues that “ACM’s submission demonstrated an overall absence of
horizontal civil construction experience similar to the project scope of work.”
Pl.’s Mot. J. Admin. R. 13, ECF No. 20.
6
the relevant pre-cast experience of [ ] and [ ]’s key personnel. 6
Id. at 4376–77. Additionally, ACM identified
[ ] as its columbarium unit
manufacturer and installer. Id. at 4377. 7
Later that day, after reviewing ACM’s bid confirmation and
clarification, Mr. Benson responded to Mr. Kays’ prior email and stated:
“[T]hey are standing by their bid. However, I still don’t think they provided
enough to give me confidence in them.” AR Tab 29, 2923. He went on to
state: “I am asking for more information[,] and I think we should allow SBA
to do a Certificate of Competency (COC). I know this delays award[,] but we
need to make sure we do our due diligence as much as possible since we did
this as a IFB.” Id. Mr. Kays’s response, which brought Jessica Holdren, the
principal planner for FourFront Design, Inc. (“FourFront”), 8 into the
discussion, identified two issues to discuss: ACM’s budget and its capability.
Id. at 2922. On September 15, 2025, Ms. Holdren responded to Mr. Kays’
email and agreed with the concerns Mr. Benson raised. After reviewing
ACM’s bid confirmation and clarification, Ms. Holdren stated that “[t]heir
relevant pre-cast experience does not seem relevant enough to me.” Id. She
further stated that “[t]heir crypt installer and columbarium unit references
need more information – we need to see they’ve installed 3 NCA projects in
the past 10 years. I am not aware of [ ] doing any installation
on previous projects.” Id. Later that day, Mr. Benson responded to Ms.
Holdren’s email and indicated that he had “already reached out to the SBA
to provide assistance and do a Certificate of Competency.” Id. at 2921.
Back again on September 12, 2025, Mr. Benson responded to ACM’s
bid confirmation and clarification by informing ACM that “several concerns
need[ed] to be addressed to determine [its] capability to meet the project’s
specifications.” AR Tab 25, 2696. Specifically, Mr. Benson requested the
6
Seabee argues that “[ ]’s purportedly applicable experience largely
consisted of scopes of work inapplicable to NCA projects” and, therefore,
ACM “failed to timely identify qualified burial crypt installers at the time it
submitted its bid.” Pl.’s Mot. J. Admin. R. 13, ECF No. 20.
7
Seabee argues that because [ ] “is not an installer, ACM
effectively failed to timely include and identify any evidence of a qualified
columbarium installer as required by the Solicitation.” Pl.’s Mot. J. Admin.
R. 13, ECF No. 20.
8
FourFront served as the designer of record for the project.
7
following information:
• Clarification and documentation proving
[ ]’s experience as an installer.
• Detailed relevant experience of [ ] as the
crypt installer.
• Verification of your role as the prime contractor on past
projects and examples of similar scope projects.
• Proof of certifications for the irrigation specification and
any other relevant specifications requiring certifications.
• A full list of all subcontractors you plan to use for this
project, along with their qualifications and relevant project
experience. To ensure transparency and maintain the
highest standards for this project, we intend to reach out to
the subcontractors provided in your submission to confirm
their suitability for the contract requirements. . . . Please
confirm if we have your permission to contact these
subcontractors directly to carry out this verification. Your
timely response will facilitate the continuation of our
review process.
Id. at 2697. Mr. Benson requested that ACM respond by September 16, 2025,
and informed ACM that “[f]ailure to provide the necessary information may
result in us referring this matter to the Small Business Administration (SBA)
for a Certificate of Competency (COC) review to further assess your
qualifications and cost.” Id.
On September 16, 2025, ACM responded to Mr. Benson’s new
request and first informed him that ACM had made an error in its bid
confirmation and clarification by mistakenly identifying [ ] as
both its columbarium manufacturer and installer. Id. at 2693. ACM clarified
that while [ ] would serve as the columbarium manufacturer,
the columbarium installer would be [ ].
ACM also provided a list of previous columbarium projects that [ ]
had completed for the federal government. Tab 25c, AR 2706.
Addressing Mr. Benson’s second request, ACM attached a “detailed
list of relevant precast concrete installation experience of [ ]” and
8
explained that [ ]’s “experience meets the minimum requirements of
specification 03 48 21-3 1.6C because [ ] has been regularly engaged,
for over three years, in the installation of pre-cast concrete similar to the
project.” AR Tab 25, 2693–94. To supplement [ ]’s experience in crypt
installation, ACM informed Mr. Benson that it would be bringing in
[ ]—project manager at [ ]—
to be a consultant. Id. at 2694. ACM attached a list of [ ]’s
relevant experience where he “estimated, managed and installed burial vaults
on,” which included over twenty projects and 122,011 burial crypts over the
last twenty-five years. AR Tab 25d, 2709.
As for Mr. Benson’s third request, ACM confirmed that it served as
the prime contractor on all the projects that it had listed in its bid confirmation
and clarification. AR Tab 25, 2694. ACM then highlighted for Mr. Benson
three of ACM’s past projects that were “similar in scope and price to the
cemetery expansion.” Id. ACM posited that these three projects were “similar
in scope because they include[d] but [we]re not limited to; demolition of
existing hardscapes and softscapes, site infrastructure, utilities, site
improvements, and landscaping.” Id.
In response to Mr. Benson’s fourth request, ACM stated: “We have
verified that the subcontractor [ ] has the
certifications, but on such short notice haven’t been able to send us their
information.” ACM also included that subcontractor’s contact information
and encouraged the government to contact it if necessary. Id.
Lastly, as to Mr. Benson’s fifth request, ACM included a list of all its
subcontractors and vendors as requested, and ACM also assured Mr. Benson
that the subcontractors and vendors “verified their qualifications[] and
relevant experience to complete [the] work in accordance with the bid
documents (specifications and drawings) at the time of their quotes.” Id. at
2695. However, ACM took issue with the short notice it was given to collect
the required information:
The Government has not provided adequate time (less than 1.5
business days) to compile and submit all of their qualifications,
certifications, and relevant project experience. This type of
submittal process is a burden normally accomplished through
a Proposal process or during the Pre-construction phase of the
submittal process after award of the contract.
9
Id. Although it was unable to gather the required information in time, ACM
gave the government permission to “contact these subcontractors directly to
personally verify these subcontractors’ information.” Id. 9
On September 17, 2025, Mr. Benson responded to ACM’s September
16th email and asked, “If you don’t mind, please provide a cost breakdown
of your proposal to help us understand your cost better.” AR Tab 26, 2736–
37. On September 18, 2025, Mr. Benson again emailed ACM and requested,
in addition to the cost breakdown, “further information and clarification”
regarding ACM’s installation consultant from [ ],
[ ]. 10 Id. at 2735. Specifically, Mr. Benson requested that ACM
provide the contract numbers for the two most recent projects that were listed
as [ ]’s relevant experience and further describe “his direct role
with the project and his experience.” Id.
ACM responded on September 19, 2025, and sent to Mr. Benson
seven documents that provided “additional information regarding
[ ]’s experiences and performance.” Id. 2733–34; see AR Tab
26a, 2749; AR Tab 26b, 2755; AR Tab 26c, 2759; AR Tab 26d, 2760; AR
Tab 26e, 2818; AR Tab 26f, 2820; AR Tab 26g, 2825. ACM then followed
up that email with another that attached a document providing “the additional
information that [ ] was able to produce as requested.” AR
Tab 26, 2733.
Later that same day, ACM sent Mr. Benson a draft of the requested
cost breakdown and requested a meeting on the afternoon of September 22,
2025, “to make sure ACM is providing . . . the desired information.” AR Tab
9
ACM went on to state:
ACM is asserting that we have the ability to manage this
contract as Prime Contractor and that being deemed
nonresponsible would be inconsistent with the FAR . . . . This
was advertised as an IFB, and we are now having to provide
what seems to be evaluation information without having
evaluation criteria to be considered by all parties prior to the
bid.
AR Tab 25, 2695.
10
Mr. Benson also thanked ACM for meeting with the agency.
10
27, 2850. During that requested meeting, 11 Mr. Benson and Mr. Kays
emphasized the project’s requirements with a particular emphasis on the
“columbarium and [pre-placed crypts] installation.” AR Tab 35, 3059. ACM
assured the agency that it was “bringing experienced people to the site and if
those people for some reason [were not] available, [ACM was] ready to
contract with backup people with experience to ensure successful project.”
Id.
On September 22, 2025, Mr. Benson forwarded to Mr. Kays and Ms.
Holdren all the information that ACM had provided through the prior email
exchanges. Id.; see also AR Tab 29, 2920; AR Tab 30, 2928. Later that day,
Ms. Holdren (from FourFront) responded to Mr. Benson’s email. AR Tab 30,
2928. She noted that “[t]he crypt experience does seem better qualified with
these documents, provided that [ ] will be the actual installer
on-site throughout construction.” Id. While pointing out certain concerns
with ACM’s cost breakdown compared with the estimate, she went on to note
that they were “somewhat aligned with [ACM’s] total of $5,748,586” and
that she otherwise could not “find any obvious discrepancies.” Id.
3. The Replacement of the Contracting Officer and the
Subsequent Contract Award
Around this time, the NCA replaced Mr. Benson with Michael
Giaquinto as the contracting officer. 12 On September 22, 2025, Mr. Kays
brought Mr. Giaquinto up to speed on the status of the procurement and
forwarded to him all the information ACM had thus far provided through the
prior email exchanges. See AR Tab 29, 2920. The next day, ACM emailed
Mr. Giaquinto and requested a meeting to discuss whether the information it
had provided was adequate and whether the agency needed anything else
from ACM. AR Tab 32, 2940. Over the next few days, Mr. Giaquinto and
ACM exchanged multiple emails regarding the breakdown of the cost of
burial crypt delivery and material and burial crypt installation. Id. at 2939–
11
The Administrative Record is not clear as to exactly when the meeting
occurred.
12
Seabee speculates that the NCA replaced Mr. Benson with Mr. Giaquinto
to ensure that the award was made before the end of the fiscal year, while the
government contends that the change was made due to issues regarding Mr.
Benson’s workload. The reason for the change is not clear from the
Administrative Record. As we explain below, we have no reason to question
the replacement.
11
40.
On Saturday, September 27, 2025, Mr. Kays emailed Mr. Giaquinto
to recap a prior discussion between the two that presumably took place on
Friday, September 26, 2025. AR Tab 35, 3059. Mr. Kays reiterated that he
recommended awarding the contract to ACM. Id. While acknowledging that
the agency had some prior concerns about ACM, Mr. Kays stressed that
ACM “addressed a lot of” those concerns and that ACM assured the agency
that it was “bringing experienced people to the site” and “[was] ready to
contract with backup people with experience” if necessary. Id.
On September 26, 2025, presumably after the discussion referenced
in Mr. Kays’ September 27, 2025, email, Mr. Giaquinto issued his
determination that ACM was responsible. AR Tab 33, 2956. In a separate
memorandum issued that same day, Mr. Giaquinto noted that ACM
“confirmed all work was covered within their bid and competent
subcontractors would be hired and managed and provided bid bonding to
ensure proper security for the government.” Tab 34, 3058. Thus, after noting
that ACM’s bid was “within a competitive range” based on the price analysis,
Mr. Giaquinto stated: “I hereby determine [ACM’s] bid price to be fair and
reasonable, and an award should be made to them as this represents the best
value to the Government.” Id. The NCA accordingly awarded the contract to
ACM on September 30, 2026. Tab 36, AR 3067.
II. Procedural History
Seabee filed its complaint on April 1, 2026. It alleges: (1) that ACM’s
bid failed to comply with the solicitation’s requirements, (2) that the
agency’s responsibility determination was arbitrary and capricious, and (3)
that the agency engaged in improper discussions with ACM after bid opening
but before contract award.
On April 8, 2026, we granted ACM’s motion to intervene. On April
20, 2026, Seabee filed its motion for judgment on the administrative record,
and the government and ACM filed their cross-motions on May 15, 2026.
The motions are fully briefed, and we heard oral argument on June 12, 2026.
At the conclusion of oral argument, we briefly explained why Seabee’s
motion must be denied and why the government’s and ACM’s motions must
be granted. After oral argument, we entered an order to that effect but delayed
entry of judgment pending the issuance of this opinion more fully laying out
the court’s reasoning.
12
STANDARD OF REVIEW
We review bid protests under the standards set forth in the
Administrative Procedure Act (“APA”). 28 U.S.C. § 1491(b)(4). Under the
APA, we will not disturb an agency’s decision unless it was “arbitrary,
capricious, an abuse of discretion, or otherwise not in accordance with law.”
5 U.S.C. § 706(2)(A). Thus, we will not set aside an agency’s procurement
action unless either: “(1) the procurement official’s decision lacked a rational
basis; or (2) the procurement procedure involved a violation of regulation or
procedure.” Glenn Def. Marine Asia, PTE Ltd. v. United States, 720 F.3d
901, 907 (Fed. Cir. 2013) (quoting Savantage Fin. Servs., Inc. v. United
States, 595 F.3d 1282, 1285–86 (Fed. Cir. 2010)).
Where a protester argues that an agency’s decision lacks a rational
basis, the Federal Circuit has made clear that “contracting officers are
‘entitled to exercise discretion upon a broad range of issues confronting
them’ in the procurement process.” Impresa Construzioni Geom. Domenico
Garufi v. United States, 238 F.3d 1324, 1332 (Fed. Cir. 2001) (quoting
Latecoere Int’l, Inc. v. United States Dep’t of Navy, 19 F.3d 1342, 1356 (11th
Cir. 1994)). As such, “the ‘disappointed bidder bears a “heavy burden” of
showing that the award decision “had no rational basis.”’” Id. at 1333
(quoting Saratoga Dev. Corp. v. United States, 21 F.3d 445, 456 (D.C. Cir.
1994)); see also Glenn Def. Marine Asia, 720 F.3d at 907 (“The protestor
bears the burden of proving that a significant error marred the procurement
in question.”). An agency’s action lacks a rational basis and is thus arbitrary,
capricious, or an abuse of discretion if “the agency ‘entirely failed to consider
an important aspect of the problem, offered an explanation for its decision
that runs counter to the evidence before the agency, or [the action] is so
implausible that it could not be ascribed to a difference in view or the product
of agency expertise.’” Ala. Aircraft Indus., Inc.–Birmingham v. United
States, 586 F.3d 1372, 1375 (Fed. Cir. 2009) (quoting Motor Vehicle Mfrs.
Ass’n of the United States, Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S.
29, 43 (1983)). Where a protestor argues that the procedure involved a
violation of regulation or procedure, “the disappointed bidder must show ‘a
clear and prejudicial violation of applicable statutes or regulations.’”
Impresa, 238 F.3d at 1333 (quoting Kentron Hawaii, Ltd. v. Warner, 480
F.2d 1166, 1169 (D.C. Cir. 1973)).
Accordingly, “[i]n applying the APA standard of review, this Court
affords considerable deference to an agency’s procurement decisions.”
Ekagra Partners, LLC v. United States, 163 Fed. Cl. 189 (2022) (quoting IAP
13
Worldwide Servs., Inc. v. United States, 159 Fed. Cl. 265, 286 (2022)). And
“in the post-award context, the protester must show that there was a
substantial chance it would have received the contract award but for” the
alleged error. Statistica, Inc. v. Christopher, 102 F.3d 1577, 1582 (Fed. Cir.
1996).
Lastly, under Rule 52.1 of the Rules of the United States Court of
Federal Claims, we conduct “the equivalent of an expedited trial on a ‘paper
record, allowing fact-finding by the trial court.” Elec. On-Ramp v. United
States, 104 Fed. Cl. 151, 158 (2012) (quoting Bannum, Inc. v. United States,
404 F.3d 1346, 1356 (Fed. Cir. 2005)). We resolve questions of fact “by
reference to the administrative record.” Id. (citing Bannum, Inc., 404 F.3d at
1356).
DISCUSSION
Seabee’s motion puts forth three distinct (although related)
arguments. First, Seabee argues that the solicitation, as modified by
Amendment 0001, “contained mandatory experience and certification
standards . . . related to a bidder’s identified precast burial crypt and precast
columbarium unit installers” that had to be satisfied at the time of bid
submission. Pl.’s Mot. J. Admin. R. 19, ECF No. 20. In Seabee’s view,
because ACM’s first response to Mr. Benson’s initial request for information
“failed to identify compliant installers with sufficient experience in the
respective scopes of work,” ACM’s bid was nonresponsive. Id. at 20. In fact,
Seabee goes further and argues that ACM improperly failed “to identify
subcontractor-installers at the time of bid submission.” Id. at 20–21
(emphasis added). Therefore, because ACM’s bid was nonresponsive, ACM
was ineligible for the contract award, and the agency’s decision to award the
contract to ACM was arbitrary and capricious.
Second, and building off the first, Seabee argues that the agency
engaged in impermissible discussions with ACM that allowed ACM to revise
its allegedly nonresponsive bid. 13 In other words, by allowing ACM an
opportunity to revise and supplement its response to Mr. Benson’s initial
request for information, the agency improperly allowed ACM to materially
alter its bid and thus engaged in impermissible discussions. Third, Seabee
argues that the agency’s responsibility determination lacked a rational basis
13
As we discuss below, Seabee seemingly merges the concepts of
responsibility and responsiveness in making its argument on this point.
14
for multiple reasons, including that there is no indication in the
administrative record that “the outstanding concerns regarding ACM’s lack
of understanding of the project, lack of technical capability, and related
failure to timely satisfy Solicitation requirements” had been resolved at the
time of contract award. Id. at 26.
As to Seabee’s first argument, the government and ACM respond that
ACM’s bid was responsive because it included all the information required
by the bid instructions of the IFB. Amendment 0001, they argue, did not
transform the installer requirements into a matter of responsiveness but
instead simply confirmed that those requirements were firm and had to be
met by the awarded contractor. And to the extent that Amendment 0001 can
be read as requiring bidders to identify its installers and provide their
experience and qualifications at the time of bid submission, Seabee has at
best identified a patent ambiguity and has thus waived the argument under
Blue & Gold Fleet, L.P. v. United States, 492 F.3d 1308 (Fed. Cir. 2007).
Furthermore, even if Seabee did not waive the argument under Blue & Gold,
Seabee cannot establish prejudice because its bid also did not identify its
installers or provide their experience and qualifications.
As to Seabee’s second argument, the government and ACM argue that
there were no impermissible discussions here because the communications
between the agency and ACM constituted permissible clarifications relating
to the responsibility inquiry. Indeed, the government and ACM argue that it
is impossible for there to have been discussions here because ACM plainly
did not alter or revise the terms of its bid.
As to Seabee’s third argument, the government and ACM respond that
Mr. Giaquinto’s responsibility determination was rational because the
administrative record contains a plethora of supportive information and
further reveals that Mr. Giaquinto reviewed that extensive information.
Seabee acknowledged at oral argument that the crux of its case relies
on its interpretation of Amendment 0001. See Oral Arg. Tr. 12–14, June 12,
2026. If Amendment 0001 did not impose a requirement that bidders have
their proposed installers in place at the time of bid submission (and thus bid
opening), then the entirety of Seabee’s first argument and most of its second
must fail. See id. at 12–14, 21–22. Thus, we begin our analysis with
Amendment 0001.
15
I. The Meaning of Amendment 0001
To properly understand Amendment 0001, we must start with the big
picture. This was a FAR Part 14, Sealed Bidding solicitation that was issued
as an IFB. It incorporated by reference FAR 52.214-19. Recall that FAR
52.214-19 provides that “[t]he Government will evaluate bids in response to
this solicitation without discussions and will award a contract to the
responsible bidder whose bid, conforming to the solicitation, will be most
advantageous to the Government, considering only price and the price-
related factors specified elsewhere in the solicitation.” FAR 52.214-19. Thus,
the government was obligated to award the contract to the lowest priced,
responsive bid so long as that bidder was responsible.
Seabee relies almost entirely on its theory that Amendment 0001
transformed the solicitation’s installer requirements into a matter of
responsiveness. By regulation, a bid is responsive so long as it “compl[ies]
in all material respects with the invitation for bids.” J.E. McAmis, Inc. v.
United States, 164 Fed. Cl. 650, 659 (2023) (alteration in original) (quoting
FAR 14.301). Critically, “[t]he responsiveness determination is conducted at
bid opening ‘based upon the contents of the bid.’” Id. (quoting VMS Hotel
Partners v. United States, 30 Fed. Cl. 512, 514 (1994)). Section 2.1 of the
IFB contained the bid instructions. The instructions required bidders to
include within their bid packages, among other things, a bid guarantee, a
completed contract administration data sheet, and a completed price/cost
schedule. Importantly, there is no dispute that, at the time of bid opening, the
contents of ACM’s bid complied with the IFB’s explicit bid instructions.
Therefore, the only way ACM’s bid can be deemed nonresponsive is if
Amendment 0001 made the identification of installers and provision of their
qualifications and experience a matter of responsiveness.
It did not. The relevant part of Amendment 0001 was issued in
response to a question submitted by a potential bidder: “If the awarded
contractor is unable to provide an installer that meets the required
qualifications: What are the contractual consequences (e.g., rejection,
termination for default, re-bid)?” AR Tab 9, 2361 (emphasis added). Thus,
the agency’s response was elicited by an inquiry that was itself concerned
with the consequences an awarded contractor would face if it failed to
provide an adequate installer. In that context, the agency’s response to the
question makes sense:
16
No. The requirements for installer qualifications are firm and
must be met at the time of contract award and performance.
There is no established waiver process under FAR Part 14.
Bidders are expected to ensure compliance with all solicitation
requirements prior to submission and during contract
performance. Any proposed personnel must meet all
mandatory qualification criteria as specified.
Id. Furthermore, the agency issued the same response to another question:
“Does the VA offer any case-by-case evaluation process or temporary waiver
mechanism for otherwise qualified personnel?” Id.
In other words, a potential bidder asked the agency what would
happen if the awarded contractor could not satisfy the installer requirements
and whether there could be a waiver of such requirements. In response, the
agency clarified that because this was a FAR Part 14 procurement, the
installer requirements were firm and had to be satisfied by the awarded
contractor. As such, the agency implored potential bidders to ensure that they
would comply with all solicitation requirements—including the installer
requirements—before submitting their bids. Again, this makes sense because
the solicitation, being a FAR Part 14 procurement, left no room for an
awarded contractor to seek to skirt certain inconvenient solicitation
requirements, i.e., it would have been futile for a potential bidder to submit
a bid with the intention of later seeking some form of waiver of or exception
to the installer requirements. Thus, Amendment 0001 did not make the
installer requirements a matter of responsiveness—whether due with bid
submission or upon request of the contracting officer after bid opening. In
fact, the amendment can at most be conceivably interpreted as requiring the
contractor to satisfy the installer requirements at the time of contract award,
but no sooner.
II. ACM’s Bid Was Responsive
There is no dispute that ACM’s bid conformed to the requirements of
the bid instructions. Additionally, the burial crypt a