Arctic Swan Construction Inc.
CourtArmed Services Board of Contract Appeals
Date FiledJune 16, 2026
Docket63510, 64085
JudgeWoodrow
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeals of - )
)
Arctic Swan Construction Inc. ) ASBCA Nos. 63510, 64085
)
Under Contract No. FA5004-22-C-0002 )
APPEARANCE FOR THE APPELLANT: Mr. Edmund Charles Palmer
President
APPEARANCES FOR THE GOVERNMENT: Caryl A. Potter, III, Esq.
Air Force Deputy Chief Trial Attorney
Geoffrey R. Townsend, Esq.
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE WOODROW
ON THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT
Pending before the Board is the government’s Motion for Summary Judgment
regarding the appellant’s claim for additional compensation under a fixed-price
contract to transport and set-up furniture and appliances in housing on and around
Eielson Air Force Base in Alaska. The main dispute is whether the contract’s
Performance Work Statement (PWS) and accompanying bid schedules required
appellant, Arctic Swan Construction, Inc. (Arctic Swan or appellant), to install,
connect, and disconnect washers and dryers as a part of the base contract price, or if
such requirements were out-of-scope work warranting an equitable adjustment.
Arctic Swan opposes the motion, arguing that there are genuine issues of
material fact and that the contract contains a latent ambiguity regarding the scope of
work and price structure.
Based upon a review of the record, solicitation, the contract, the cross-briefing,
and the applicable law, we conclude that there are no genuine disputes of material fact.
The dispute presents a pure question of contract interpretation, which is a matter of
law. The plain language of the contract supports the government’s interpretation and
any perceived ambiguity would be patent, precluding the appellant’s recovery.
Therefore, we grant the government’s Motion for Summary Judgment with regard to
ASBCA No. 64085 and deny the appeal. We also dismiss ASBCA No. 63510 for lack
of jurisdiction.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
The Solicitation and Contract
1. On July 15, 2021, the government issued Solicitation No. FA500421B0004
for drayage and furnishing management services (R4, tab 1 at 1-44). This solicitation
culminated in the award of Contract No. FA500422C0002 to the appellant (R4, tab 20
at 1-34).
Performance Work Statement (PWS) Requirements
2. The PWS incorporated into the contract contained explicit, mandatory
directives regarding the handling, delivery, and installation of appliances, specifically
including washers and dryers (R4, tab 21).
• PWS ¶ 1 stated: “The contractor shall assemble/disassemble & setup all
government-owned furnishings . . . as well as setup and connect all
appliances” (R4, tab 21 at 3);
• PWS ¶ 1.1.9 stated: “The contractor shall deliver, assemble/disassemble
and setup all furnishings, washers/dryers & appliances” (id. at 5);
• PWS ¶ 1.1.10 specifically directed: “The contractor shall deliver
washers and dryers per the [request order]. The contractor shall be
responsible for supplying a certified installer to insure both water and
electrical connections are correctly installed and the unit is setup
correctly” (id.).
The Bid Schedules
3. The Solicitation included two distinct Bid Schedules: Attachment 2 for
Housing and Attachment 3 for Unaccompanied Housing (Dorm). Both schedules
utilized a tabular format requiring the contractor to input pricing for various Contract
Line Item Numbers (CLINs). (R4, tabs 3-4) The tables included columns for “Item
Description,” “Qty” (Quantity), “Unit,” “Unit Price,” and “Total Price.” Within these
schedules, “Washer” and “Dryer” were listed as distinct line items, quantified by the
unit “EA” (Each). Crucially, neither Bid Schedule contained a separate line item,
CLIN, or designated sub-contract line item for “installation labor,” “certified
installer,” “connection,” or “disconnection” services. Bidders were required to
provide a single, fully burdened “Unit Price” for each washer or dryer handled. (R4,
tabs 3 at 1, 4 at 1)
2
Lack of Pre-Bid Inquiry
4. There is no evidence in the record, nor does the appellant allege that it
submitted any Requests for Information (RFIs) or sought clarification from the
Contracting Officer regarding how to price the “certified installer” requirement within
the provided Bid Schedule structure prior to the submission of its bid (see gov’t reply
at 1; app. opp’n at 1-2).
Administrative Claims and Contracting Officer Final Decisions (COFDs)
5. During contract performance, a dispute arose regarding whether washer and
dryer installation was included in the base contract price, prompting the appellant
to seek additional compensation (R4, tabs 30, 44). Arctic Swan submitted a document
dated August 8, 2022, captioned as a “Request for Equitable Adjustment” (R4, tab 30
at 1). The document did not request a contracting officer’s final decision and did not
contain a claim amount (id. at 1-2). Because no claim amount was stated, it is unclear
whether certification was required. However, the document contained a certification
stating “I certify that the request is made in good faith, and that the supporting data
will be provided are accurate and complete to the best of my knowledge and belief”
(id. at 1). On September 15, 2022, the contracting officer (CO) issued a Final
Decision referencing a claim amount of $685,200 and denying it (R4, tab 31). The
origin of the claim amount does not appear to be in the record. Arctic Swan’s appeal
from that final decision was docketed as ASBCA No. 63510.
6. On November 7, 2024, following the government’s submission of a Motion
to Dismiss the Appeal for Lack of Jurisdiction, Arctic Swan submitted what it
characterized as a “full certified claim” in the amount of $334,213. This document
also asked for a CO’s decision and included certification language consistent with that
required by the Contract Disputes Act (R4, tab 44). On December 9, 2024, the CO
issued a Final Decision denying Arctic Swan’s November 7, 2024 claim in its entirety
(R4, tab 45). Arctic Swan’s appeal from the second final decision was docketed as
ASBCA No. 64085. Both final decisions denied the appellant’s requests for equitable
adjustment and additional compensation, affirming the government’s position that the
PWS required the installation and connection of washers and dryers at the unit prices
established in the contract (R4, tabs 31 at 1-2, 45 at 2-3).
DECISION
I. Procedural History and Dismissal of ASBCA No. 63510
Before addressing the merits of the summary judgment motion, we must clarify
the procedural background of the two appeal numbers in this case: ASBCA
3
Nos. 63510 and 64085. Both appeal numbers relate to the exact same underlying
dispute, but they were filed at different times.
When Arctic Swan filed its first appeal, ASBCA No. 63510, it had not yet
submitted a “claim” to the CO that fully complied with the legal requirements. Under
the law that governs these contracts (the Contract Disputes Act), submitting a certified
claim is a strict requirement before this Board has the legal authority (“jurisdiction”)
to hear an appeal. M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323,
1327-28 (Fed. Cir. 2010). Because the initial claim was jurisdictionally deficient, the
Board did not have jurisdiction over ASBCA No. 63510. Recognizing this defect, the
government filed a Motion to Dismiss ASBCA No. 63510.
To fix this missing step, Arctic Swan did exactly what it was supposed to do:
it submitted a fresh, properly certified claim to the Contracting Officer. After the CO
issued a final decision denying that new claim, Arctic Swan appealed again. That
second, legally valid appeal became ASBCA No. 64085. Alternatively, Arctic Swan
could have attempted to remedy the deficiencies in its August 2022 submission and
convert the request for equitable adjustment into a claim. As we interpret Arctic
Swan’s submission of the November 2024 claim as replacing the August 2022
submission, the August 2022 submission should have been dismissed.
On September 26, 2025, we issued an order denying the government’s Motion
to Dismiss ASBCA No. 63510, stating that the motion was “moot” because Arctic
Swan had cured the problem with its second appeal. That ruling was an error. The
proper legal procedure was to grant the government’s motion and formally dismiss the
first appeal for lack of jurisdiction. Ball, Ball & Brosamer, Inc. v. United States, 878
F.2d 1426, 1428 (Fed. Cir. 1989); Cobeal Consulting Group, ASBCA No. 63815, 25-1
BCA ¶ 38,742 at 188,340. This decision corrects that mistake. Accordingly, the
government’s Motion to Dismiss ASBCA No. 63510 is granted, and ASBCA
No. 63510 is dismissed for lack of jurisdiction.
We want to make it absolutely clear that dismissing ASBCA No. 63510 is
strictly a procedural “housekeeping” matter. It does not punish Arctic Swan or
prejudice its rights in any way. Because Arctic Swan successfully corrected the
paperwork issue by filing ASBCA No. 64085, all of Arctic Swan’s substantive
arguments and claims remain fully protected. The remainder of this decision entirely
resolves those claims under the valid appeal, ASBCA No. 64085.
II. The Standard of Review for a Motion for Summary Judgment
Summary judgment is appropriate when the record shows there are no genuine
issues of material fact and the moving party is entitled to judgment as a matter of law.
Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). The party requesting summary
4
judgment (here, the government) has the initial burden to prove that no such factual
disputes exist, and the Board must resolve any significant doubt in favor of the party
opposing the motion. Mingus Constructors v. United States, 812 F.2d 1387, 1390
(Fed. Cir. 1987) (citing United States v. Diebold, Inc., 369 U.S. 654, 655 (1962)).
However, to successfully defeat the motion, the opposing party cannot simply claim
that the facts conflict; rather, they must point out specific facts showing there is a
genuine issue that requires a trial. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248
(1986) (quoting First Nat’l Bank of Ariz. v. Cities Serv. Co., 391 U.S. 253, 288
(1968)). Finally, contract interpretation is a question of law, making it an issue that is
properly resolved through summary judgment. Varilease Tech. Grp., Inc. v. United
States, 289 F.3d 795, 798 (Fed. Cir. 2002) (citing Textron Def. Sys. v. Widnall, 143
F.3d 1465, 1468 (Fed. Cir. 1998)); see also Walsh Grp. Ventures, ASBCA No. 61222,
20-1 BCA ¶ 37,615 at 182,584.
III. The Meaning of Contract Terms is a Question of Law, Not Fact
We find that summary judgment is appropriate here because the material facts
are undisputed, and the appeal turns entirely upon contract interpretation. Arctic Swan
attempts to defeat summary judgment by raising several arguments, none of which
establish a genuine dispute of material fact. We address each of Arctic Swan’s
arguments below.
A. The Contract, Read as a Whole, Mandates Installation
Arctic Swan first argues that summary judgment is precluded because there is a
factual dispute over whether the PWS terms such as “setup,” “connect,” and “install”
define a uniform scope of work, or materially different levels of effort, and whether
the requirement for a “certified installer” created a distinct scope of work requiring
increased labor (app. opp’n at 2).
This argument fails because the actual text of the contract is undisputed. The
disagreement lies solely in the interpretation of those undisputed words. Under
established Federal Circuit precedent, the interpretation of contract terms, including
whether specific words convey different levels of effort, is a question of law, not fact.
Varilease, 289 F.3d at 798. The government correctly notes that the Board is tasked
with determining the legal effect of these terms based on the four corners of the
document (gov’t mot. at 7). Therefore, Arctic Swan’s differing interpretation of these
terms does not create a triable issue of fact.
Arctic Swan argues that the government-furnished bid schedule templates
define the economic scope of the work. Specifically, Arctic Swan contends that,
because the bid schedules only listed “Washer” and “Dryer,” the pricing was strictly
5
limited to the transportation and basic handling of the items, not their installation (app.
opp’n at 2-3).
A bedrock principle of contract interpretation requires that the contract must be
read as a whole, giving reasonable meaning to all its parts so that no provision is
rendered useless or superfluous. Lockheed Martin Aeronautics Co., ASBCA
No. 62209, 22-1 BCA ¶ 38,178 at 185,419 (citing NVT Techs., Inc. v. United States,
370 F.3d 1153, 1159 (Fed. Cir. 2004)). The bid schedules cannot be read in a vacuum.
Section 1.1.10 of the PWS unambiguously requires the contractor to supply a
“certified installer” to ensure water and electrical connections are installed correctly
for washers and dryers (R4, tab 21 at 5). The only reasonable interpretation of the
contract, when read as an integrated whole, is that the unit price submitted by Arctic
Swan for a washer or dryer encompassed all requirements tied to that item in the
PWS—including delivery, connection, and certified installation (gov’t reply at 2).
Finding otherwise would render the explicit directives of PWS ¶¶ 1, 1.1.9, and 1.1.10
meaningless.
B. There Is No Ambiguity, and Any Ambiguity Would Be Patent
Arctic Swan contends that the interaction between the PWS, which demands
certified installation labor, and the bid schedule, which groups appliances under
general unit pricing without separate line items for installation, creates a “latent
ambiguity,” entitling Arctic Swan to have the ambiguity construed against the
government (app. opp’n at 3-4).
Arctic Swan’s argument fails at the threshold because the contract is not
ambiguous. Contract language is ambiguous only when it is susceptible to more than
one reasonable interpretation; it is not enough that the parties advance competing
readings. NVT Techs., 370 F.3d at 1159; Lebolo-Watts Constructors 01 JV, LLC,
ASBCA No. 59740 et al., 21-1 BCA ¶ 37,789 at 183,432. Both proffered
interpretations must fall within a “zone of reasonableness,” and a party that advances
an unreasonable interpretation may not invoke the rule of contra proferentem to
construe the contract against the drafter. HPI/GSA-3C, LLC v. Perry, 364 F.3d 1327,
1334 (Fed. Cir. 2004).
As explained above, Arctic Swan’s reading—that its unit prices covered only
transportation and basic handling and excluded the connection and installation work
required by PWS ¶¶ 1, 1.1.9, and 1.1.10—is not reasonable, because it can be reached
only by disregarding three provisions that assigned that work to the contractor and by
rendering them superfluous. Because only the government’s interpretation is
reasonable, the contract is not ambiguous, and the rule of contra proferentem, on
which Arctic Swan’s latent-ambiguity theory depends, never comes into play.
6
Even if the interaction between the PWS and the bid schedule created an
ambiguity, that ambiguity would be patent rather than latent. A patent ambiguity is an
obvious omission, inconsistency, or discrepancy of significance. A contractor can
discover a patent ambiguity through reasonable and customary care. A latent
ambiguity, by contrast, is a hidden defect that is not apparent on the face of the
contract and cannot be discovered through ordinary care. Per Aarsleff A/S v. United
States, 829 F.3d 1303, 1312-13 (Fed. Cir. 2016); Lebolo-Watts, 21-1 BCA ¶ 37,789
at 183,433.
Arctic Swan now points to what it characterizes as a discrepancy in the contract
documents. The PWS expressly required the contractor to supply a “certified
installer” and to assume liability for water and electrical connections (R4, tab 21 at 5).
However, the bid schedule provided only a single unit-price line for each washer and
dryer. To the extent a bidder was unsure whether to include the cost of the certified
installer in the unit cost, this conflict would have been obvious on the face of the
solicitation. A reasonable contractor reviewing those documents before bidding would
have recognized the alleged uncertainty about how to price the required certified-
installation labor. Such a facial discrepancy is a clear example of a patent ambiguity.
See Triax Pac., Inc. v. West, 130 F.3d 1469, 1474-75 (Fed. Cir. 1997) (applying the
patent-ambiguity doctrine where a reasonable contractor reviewing the specifications
before bidding would have recognized the facial inconsistency).
Under the doctrine of patent ambiguity, a contractor has an affirmative duty
to inquire about such inconsistencies prior to bidding. Kallidus Techs., ASBCA
Nos. 61377, 61976, 26-1 BCA ¶ 38,971 at 189,728 (citing Blue & Gold Fleet, L.P. v.
United States, 492 F.3d 1308, 1313 (Fed. Cir. 2007); NVT Techs., 370 F.3d at 1162)).
It is undisputed that Arctic Swan did not seek clarification on this pricing structure
before contract award. Arctic Swan’s failure to fulfill its duty to inquire precludes it
from relying on its unilateral interpretation after the fact.
The Board may resolve questions regarding whether a contract is ambiguous,
and whether such an ambiguity is patent or latent, as matters of law on summary
judgment. Certified Constr. Co. of Ky., LLC, ASBCA No. 58782, 15-1 BCA ¶ 36,068
at 176,130-31 (citing Varilease, 289 F.3d at 798). Although Arctic Swan points to its
course of performance and internal pricing intent to support its position, extrinsic
evidence cannot manufacture an ambiguity where the contract’s plain text allows for
only one reasonable meaning. Therefore, Arctic Swan’s latent ambiguity argument
fails to raise a genuine dispute of material fact and does not preclude summary
judgment.
7
C. Varying Claim Amounts Do Not Alter Contract Interpretation
Finally, Arctic Swan argues that differing dollar amounts referenced in the two
CO’s Final Decisions ($685,200 versus $334,213) reflect material inconsistencies
requiring fact-finding (app. opp’n at 4-5).
This argument conflates the administrative processing of a claim with the legal
interpretation of the contract’s scope. As the government points out, the varying
financial amounts claimed or evaluated during the dispute process have no bearing on
the legal question of whether the PWS required the installation of washers and dryers
in the first instance (gov’t reply at 2). Consequently, these monetary discrepancies
do not constitute a dispute of material fact that would bar summary judgment.
CONCLUSION
There are no genuine disputes of material fact in this appeal. The plain and
unambiguous language of the contract required Arctic Swan to connect, install, and
disconnect washers and dryers, utilizing a certified installer. To the extent the pricing
structure in the Bid Schedule created confusion regarding how to bill for this explicitly
required labor, it constituted a patent ambiguity. Arctic Swan’s failure to inquire
about this ambiguity prior to bidding bars its claim for an equitable adjustment. We
grant summary judgment in favor of the government and deny the appeal in ASBCA
No. 64085. We dismiss ASBCA No. 63510 for lack of jurisdiction.
Dated: June 16, 2026
KENNETH D. WOODROW
Administrative Judge
Armed Services Board
of Contract Appeals
I concur I concur
J. REID PROUTY DAVID D’ALESSANDRIS
Administrative Judge Administrative Judge
Acting Chairman Acting Vice Chairman
Armed Services Board Armed Services Board
of Contract Appeals of Contract Appeals
8
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA Nos. 63510, 64085, Appeals of
Arctic Swan Construction Inc., rendered in conformance with the Board’s Charter.
Dated: June 16, 2026
PAULLA K. GATES-LEWIS
Recorder, Armed Services
Board of Contract Appeals