Full Opinion
ARMED SERVICES BOARD OF CONTRACT APPEAL
Appeal of - )
)
VESEQU LLC ) ASBCA No. 64468
)
Under Contract No. SP8000-25-C-0005 )
APPEARANCE FOR THE APPELLANT: Mr. Jason Shadburn
VESEQU, LLC
Los Angeles, CA
APPEARANCES FOR THE GOVERNMENT: Steven M. Sosko, Esq.
DLA Chief Trial Attorney
Rachel M. Noble, Esq.
Trial Attorney
DLA Land and Maritime
Columbus, OH
OPINION BY ADMINISTRATIVE JUDGE SWEET
On April 10, 2026, the Defense Logistics Agency (DLA or government) filed
a motion to dismiss—or in the alternative to strike—two of the causes of action in the
complaint (Complaint) of pro se appellant VESEQU LLC (VESEQU) for lack of
jurisdiction (Motion). Because the causes of action assert new claims, we grant the
Motion. 1
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
1. On June 17, 2025, DLA awarded Contract No. SP8000-25-C-0005 (Contract)
for VESEQU to acquire and make available to DLA Strategic Materials certain
web-based subscriptions, publications, and periodicals, including, inter alia,
Bloomberg Professional Service B-Unit Device, Platts Metal Daily (Nonferrous
Market Data and Market Insight), Benchmark Minerals Intelligence-Industrial
Minerals, and the Project Blue Reports (collectively, Cancelled Subscriptions) (R4,
tab 6 at 1-2, 4-5, 8-9; tab 6A).
1
On May 8, 2026, VESEQU filed a motion for leave to file a sur-reply. We grant that
motion because the government raises a new argument regarding different
remedies in its reply brief (compare gov’t mot. at 5-7 with gov’t reply at 4-6).
2. On October 27, 2025, the contracting officer (CO) issued a stop work order
pursuant to Federal Acquisition Regulation (FAR) 52.242-15, which directed
VESEQU to stop work on the Cancelled Subscriptions (R4, tab 18A at 1-2).
3. On November 4, 2025, VESEQU submitted a request for an equitable adjustment
(REA) (R4, tab 19 at 1-4). Under the “Request for Relief” section, the REA asserted
that:
VESEQU LLC respectfully requests an equitable
adjustment in the amount of $70,930.80 to recover direct
and indirect costs reasonably incurred as a direct result of
the Government’s Stop Work Order under Contract
SP8000-25-C-0005 (P00003).
This request includes no profit or unallowable cost
elements and is supported by contemporaneous
documentation.
(Id. at 4)
4. On November 17, 2025, DLA partially terminated the Contract for convenience
pursuant to FAR 52.212-4(l), terminating the Cancelled Subscriptions (R4, tabs
23A-23C).
5. On December 18, 2025, VESEQU converted its REA into a claim to the CO
(Claim) (R4, tab 24 at 1-2). The Claim asserted that VESEQU “hereby converts its
REA into a claim under the Contract Disputes Act and formally requests a Contracting
Officer’s Final Decision on its claim in the amount of $70,930.80 arising from the
Stop Work Order issued under Contract SP8000-25-C-0005 (Modification P00003)”
(id. at 2). The Claim alleged that:
VESEQU fully recognizes the Government’s discretion to
pursue its acquisition strategy. The concern is not the
existence of resolicitation activity, but the sequencing and
prioritization. [DLA] has demonstrated the ability to staff
and advance replacement procurement actions for these
subscriptions, while VESEQU’s incurred, documented
pre-Stop Work costs for the same scope of work remain
unresolved.
From both a practical and fairness standpoint this creates a
disconnect. If resources exist to resolicit and advance
replacement actions, it is reasonable to expect parallel
2
capacity to resolve the associated Stop Work claim tied to
the original award.
(Id. at 2) The Claim contained no allegation that the subscriptions required DLA to
execute subscription agreements, or that DLA prohibited the execution of such
agreements (id. at 1-34). Nor did the Claim contain any factual allegations related to
the execution of subscription agreements (id.). VESEQU attached the REA to the
Claim, including the portion of the REA indicating that “[t]his request includes no
profit” (id. at 30).
6. On February 20, 2026, the CO issued a final decision (COFD) denying the Claim
(R4, tab 29A at 1, 5).
7. That same day, VESEQU appealed the COFD to the Board. In its Complaint,
VESEQU alleges four Counts: (I) termination settlement under FAR 52.212-4(l);
(II) government-caused impasse/constructive change; (III) equitable adjustment under
FAR 52.242-15(d) (stop work order); and (IV) bad faith termination-government
re-solicitation of identical requirements (compl. ¶¶ 7-34). In particular, Count II
alleges that there was a defective specification, constructive change, and commercial
impossibility because, by their nature, the subscriptions required DLA to execute
subscription agreements, but DLA prohibited the execution of such agreements (id.
¶¶ 20-22). Count IV alleges that the termination for convenience was motivated by a
bad faith intent to re-acquire the Cancelled Subscriptions outside of the Contract at a
lower price because DLA immediately reacquired the Cancelled Subscriptions after
the termination for convenience (id. at ¶¶ 31-33). Count IV also alleges that “[i]f the
Board finds bad faith, VESEQU is entitled to breach of contract damages, including
lost profits on the terminated contract work that would have been performed absent the
wrongful termination, in addition to all costs and damages recoverable under Counts I
through III” (id. at ¶ 34). In the damages section, the Complaint states that VESEQU
is seeking termination settlement costs under Counts I through III, reasonable profit on
the work performed, settlement and claim preparation costs, lost profits on the
terminated contract under Count IV, and CDA interest (id. at ¶ 35). The Complaint
contains no allegations that there is new information on damages that was not
reasonably available to VESEQU when it submitted its Claim that supports the
addition of a claim for lost profit damages (id. at ¶¶ 34-35).
DECISION
The government’s Motion is granted because, since Counts II and IV raise new
claims, we do not possess jurisdiction over those claims. In order to give “the
contracting officer an ample pre-suit opportunity to rule on a request, knowing at least
the relief sought and what substantive issues are raised by the request,” K-Con Bldg.
Sys., Inc. v. United States, 778 F.3d 1000, 1006 (Fed. Cir. 2015), the submission of a
3
claim is a jurisdictional prerequisite for an appeal to the Board under the Contract
Disputes Act, 41 U.S.C. § 7101 et seq. Reflectone, Inc. v. Dalton, 60 F.3d 1572, 1575
(Fed. Cir. 1995). Thus, we do not possess jurisdiction over new claims that a
contractor did not present to the CO. Lockheed Martin Aircraft Ctr., ASBCA No.
55164, 07-1 BCA ¶ 33,472 at 165,934. We treat causes of action as involving new
claims “if they either request different remedies (whether monetary or nonmonetary)
or assert grounds that are materially different from each other factually or legally.”
ECC Int’l LLC, ASBCA No. 60167, 2022 WL 509701 (Jan. 25, 2022) (quoting K-Con
Bldg. Sys., 778 F.3d at 1005) (emphasis in original). Under the different asserted
grounds component, a claim presented to the Board is a new claim if it is not based
upon facts that are common, or related, to the facts that the contractor raised in its
claim to the CO. Lockheed Martin, 07-1 BCA ¶ 33,472 at 165,934. In order to raise a
bad faith termination claim, a claim need only allege, in effect, unfair and deceptive
treatment; it need not use the words “bad faith.” Lockheed Martin, 07-1 BCA ¶
33,472 at 165,934. Under the different remedies component, “claims seeking different
types of remedy, such as expectation damages versus consequential damages, may be
determined to be separate claims.” ECC Int’l, 2022 WL 509701 (citing K-Con Bldg.
Sys., 778 F.3d at 1006). 2 However, the standard is not so rigid as to preclude all
litigation adjustments in amounts “based upon matters developed in litigation.” K-Con
Bldg. Sys., 778 F.3d at 1006 (quoting Tecom, Inc. v. United States, 732 F.2d 935, 937-
38 (Fed. Cir. 1984)). Here, as discussed in greater detail below, both Counts II and IV
assert new claims.
I Count II Asserts a New Claim
Count II asserts grounds that are materially different from those asserted in the
Claim because Count II is not based upon facts that are common, or related, to the
facts that VESEQU raised in its Claim. The factual basis of Count II is that the
subscriptions required DLA to execute subscription agreements, and that DLA
prohibited the execution of such agreements (SOF ¶ 7). However, the Claim contained
no allegation that the subscriptions required DLA to execute subscription agreements,
or that DLA prohibited the execution of such agreements (SOF ¶ 5). Indeed, the
Claim contained no factual allegations related to the execution of subscription
2
Expectation damages are damages that provide the non-breaching party with the
benefits he expected from a contract, and may include anticipated lost profits on
that contract. Glendale Fed. Bank, FSB v. United States, 239 F.3d 1374, 1380
(Fed. Cir. 2001). However, anticipatory lost profit damages are not available
for a termination for convenience absent a showing of bad faith or an abuse of
discretion. Nexagen Networks, Inc., ASBCA No. 60641, 19-1 BCA ¶ 37,258
at 181,328. Consequential damages are losses that do not flow directly or
immediately from an injurious act, but that result indirectly from the act, such
as lost profits on other contracts. Id.
4
agreements at all (id.). Because the Claim did not raise the substantive issue of
whether DLA prohibited the execution of required subscription agreements, Count II
raises a new claim over which we do not possess jurisdiction. See Lockheed Martin,
07-1 BCA ¶ 33,472 at 165,934. As a result, VESEQU denied the CO an adequate
pre-suit opportunity to rule on VESEQU’s request knowing that the substantive issue
raised by VESEQU was that DLA prohibited the execution of required subscription
agreements. See K-Con Bldg. Sys., 778 F.3d at 1006.
II. Count IV Asserts a New Claim
While Count IV does not assert grounds that are materially different from those
asserted in the Claim, it nevertheless asserts a new claim because it seeks a different
type of remedy than the Claim sought. First, Count IV does not assert grounds that are
materially different from those asserted in the Claim because Count IV is based upon
facts that are common, or related, to the facts that VESEQU raised in its Claim. The
factual basis of Count IV is that it was unfair for DLA to reacquire the terminated
subscriptions immediately after the termination for convenience (SOF ¶ 7). Similarly,
the Claim asserted that the sequencing and prioritization of the resolicitation was unfair
(SOF ¶ 5). The Claim did not use the magic words “bad faith” (SOF ¶ 5), but that fact
does not establish that Count IV asserts grounds that are materially different from those
asserted in the Claim. See Lockheed Martin, 07-1 BCA ¶ 33,472 at 165,934. Rather,
Count IV is based upon facts that are common, or related, to the facts that VESEQU
raised in its Claim because its factual basis of an unfair reacquisition of the terminated
subscriptions relates to the facts regarding an unfair reacquisition of the terminated
subscriptions that VESEQU raised in its Claim. Id.; (SOF ¶ 7). Thus, Count IV does
not assert grounds that are materially different from those asserted in the Claim.
However, Count IV seeks a different type of remedy than the Claim sought.
Count IV expressly indicates that it is seeking “lost profits on the terminated contract
work that would have been performed absent the wrongful termination” (SOF ¶ 7
(emphasis added)). However, the Claim did not seek lost profits. On the contrary, the
Claim expressly stated that “[t]his request includes no profit” (SOF ¶ 5 (emphasis
added)). VESEQU has made no showing that Count IV’s addition of the lost profit
damages is due to new information on damages that was not reasonably available to it
when it submitted its Claim (SOF ¶ 7; app. sur-reply). Therefore, Count IV seeks a
different type of remedy than the Claim, such that Count IV is a new claim over which
we do not possess jurisdiction. See GAP Instrument Corp., ASBCA No. 55041,
07-1 BCA ¶ 33,567 at 166,280 (citing Tecom, 732 F.2d at 938). As a result, VESEQU
denied the CO an adequate pre-suit opportunity to rule on the claim raised in Count IV
knowing the relief sought was lost profits. See K-Con Bldg. Sys., 778 F.3d at 1006.
VESEQU argues that it indicated it was not seeking lost profits in its REA;
not in its Claim (app. sur-reply at 2). However, we have recognized that a contractor
5
incorporates an REA into its claim when it attaches and references that REA as part of
its claim. The Pub. Warehousing Co., ASBCA No. 56022, 11-2 BCA ¶ 34,788
at 171,225. Here, the Claim both referenced and attached the REA and failed to state
that VESEQU was adding a claim for lost profit (SOF ¶ 5). Thus, the Claim
incorporated the REA, such that the REA’s indication that VESEQU was not seeking
lost profit is part of the Claim. See Pub. Warehousing, 11-2 BCA ¶ 34,788 at 171,225.
VESEQU also argues that the statement that VESEQU was not seeking lost profit
appeared in a section describing the methodology for calculating actual allowable costs
incurred; not in sections electing or waiving equitable remedies (app. sur-reply at 2). In
actuality, the statement that VESEQU was not seeking lost profit appeared in a section
entitled “Request for Relief,” and thus, it defines the scope of the remedies sought (SOF
¶ 3). As discussed above, because those remedies were different than the remedies
sought by Count IV, Count IV asserts a new claim (SOF ¶¶ 5, 7).
Finally, VESEQU argues that we should defer ruling on the Motion pending
DLA’s responses to VESEQU’s discovery requests (app. sur-reply at 3). However, the
cited discovery requests only seek information on whether DLA terminated the contract
in bad faith; they do not seek new information on damages that was not reasonably
available to VESEQU when it submitted its Claim (id.). As discussed in greater detail
above, the jurisdictional defect in Count IV is not that Count IV asserts a bad faith claim
that materially differs from the allegations in the Claim; it is that Count IV seeks a
different type of remedy for that alleged bad faith termination than the Claim sought by
seeking lost profits (SOF ¶¶ 5, 7). Thus, the information that VESEQU seeks through
the cited discovery requests will not resolve the jurisdictional defect.
6
CONCLUSION
For the reasons discussed above, the government’s motion to dismiss, or in the
alternative to strike, is granted. We strike Counts II and IV of the Complaint without
prejudice.
Dated: May 21, 2026
JAMES R. SWEET
Administrative Judge
Armed Services Board
of Contract Appeals
I concur
MICHAEL N. O’CONNELL
Administrative Judge
Vice Chairman
Armed Services Board
of Contract Appeals
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 64468, Appeal of VESEQU
LLC, rendered in conformance with the Board’s Charter.
Dated: May 21, 2026
PAULLA K. GATES-LEWIS
Recorder, Armed Services
Board of Contract Appeals
7