VESEQU LLC
CourtArmed Services Board of Contract Appeals
Date FiledAugust 21, 2026
Docket64468
JudgeSweet
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
VESEQU LLC ) ASBCA No. 64468
)
Under Contract No. SP8000-25-C-0005 )
APPEARANCE FOR THE APPELLANT: Mr. Jason Shadburn
Principal Program Director
APPEARANCES FOR THE GOVERNMENT: Steven M. Sosko, Esq.
DLA Chief Trial Attorney
Rachel M. Noble, Esq.
Trial Attorney
DLA Land and Maritime
Columbus, OH
OPINION BY ADMINISTRATIVE JUDGE SWEET
This appeal involves a contract between the Defense Logistics Agency Strategic
Materials (DLA or government) and pro se appellant VESEQU LLC (VESEQU) for
VESEQU to acquire and make available to DLA 30 web-based subscriptions,
publications, and periodicals. DLA partially terminated the contract for convenience,
and the parties were unable to resolve the amount due to VESEQU as a result of that
termination. Therefore, VESEQU appealed the contracting officer’s final decision
(COFD) determining the settlement amount. VESEQU has elected to proceed under
the Board’s Accelerated Procedure, see Board Rule 12.3, and the parties have elected
to proceed under Board Rule 11. As discussed in greater detail below, VESEQU has
failed to meet its burden of proving that it is entitled to a greater termination settlement
amount than the amended termination settlement amount offered by the contracting
officer (CO) because VESEQU has failed to demonstrate using its standard record
keeping system an amount of loss greater than the amended settlement amount with
sufficient certainty so that that determination will be more than mere speculation.
Therefore, the appeal is denied.
FINDINGS OF FACT
1. On April 3, 2025, DLA issued Solicitation No. SP8000-25-Q-0005
(Solicitation) as a request for quote to obtain a variety of commercially available,
web-based subscriptions, publications, and periodicals (R4, tab 1 at 1, 3). 1 Attachment
0F
B listed 30 required subscription services, including: (1) Bloomberg Professional
Service B-Unit Device Online (Bloomberg); (2) S&P Platts (Nonferrous Market Data
and Market Insight)’s Online & Email-Basic Service + 1 Enhanced Add-On (S&P);
(3) Benchmark Minerals Intelligence’s Industrial Minerals (Benchmark); and
(4) Project Blue Additional Reports (Up to 10) Digital (Project Blue; collectively
Cancelled Subscriptions) (R4, tab 1B).
2. Amendment No. 0001 to the Solicitation answered questions from
prospective offerors, and amended the solicitation (R4, tab 2 at 2). In particular, in
question 24, one prospective offeror asked which specific subscription DLA wanted
from Benchmark because there was no subscription entitled Industrial Minerals (id.
at 5). DLA responded that it was interested in Rare Earth Forecast Reports from
Benchmark (id.). In question 40, a prospective offeror asked if there were any known
pain points or challenges encountered under past contracts with prior vendors that
offerors should consider addressing (id. at 8). Amendment No. 0001 responded that it
“will not sign a Master Subscription Agreement” (id.). Amendment No. 0003
reiterated in highlighting that “[t]he government will not sign Master Service
Agreements directly with the subcontractors in order to obtain access to the requested
items in Attachment B” (R4, tab 5 at 9).
3. VESEQU’s proposal stated that VESEQU would perform five other
government contracts for at least part of the period between June 17, 2025 and
October 27, 2025 (R4, tab 6 at 4-5).
4. Based upon the Solicitation, DLA awarded VESEQU Contract No. SP8000-
25-C-005 (Contract) on June 17, 2025 (R4, tab 8 at 1-2, tab 8A). The Contract
included a termination for the government’s convenience clause pursuant to Federal
Acquisition Regulation (FAR) 52.212-4(l), which stated that:
The Government reserves the right to terminate this
contract, or any part hereof, for its sole convenience. In
the event of such termination, the Contractor shall
immediately stop all work hereunder and shall immediately
cause any and all of its suppliers and subcontractors to
cease work. Subject to the terms of this contract, the
Contractor shall be paid a percentage of the contract price
reflecting the percentage of the work performed prior to
the notice of termination, plus reasonable charges the
Contractor can demonstrate to the satisfaction of the
Government using its standard record keeping system,
1
All references to “R4” are to the government’s supplemental Rule 4 file.
2
have resulted from the termination. The Contractor shall
not be required to comply with the cost accounting
standards or contract cost principles for this purpose. This
paragraph does not give the Government any right to audit
the Contractor’s records. The Contractor shall not be paid
for any work performed or costs incurred which reasonably
could have been avoided.
(R4, tab 8 at 20)
5. After award, S&P and Bloomberg insisted that the government sign a master
service agreement (MSA). From June 2025 to September 2025, VESEQU
unsuccessfully attempted to negotiate mutually agreeable license terms between DLA
on the one hand, and S&P and Bloomberg on the other hand. (R4, tabs 10-12, 14,
17A, 21-22, 26)
6. During that period, a dispute also arose between VESEQU and DLA
regarding what Benchmark subscription the Contract required, with VESEQU
indicating that it would cost extra to provide the Benchmark Rare Earths Forecast
Reports (R4, tabs 13, 18, 21, 25).
7. Also during the September 2025 to October 2025 period, a dispute arose
between VESEQU and DLA regarding whether VESEQU had to provide the Project
Blue subscription on a per subscription or per material basis (R4, tabs 23, 27; gov’t br.,
stmt. of fact ¶ 48).
8. On October 27, 2025, the CO issued a Stop Work Order (SWO) pursuant to
FAR 52.242-15, which directed VESEQU to stop work on the Cancelled Subscriptions
(R4, tab 29 at 1).
9. Two days later, on October 29, 2025, VESEQU submitted a document
entitled Five-Day Written Status and Cost Summary (Cost Summary), which
acknowledged receipt of the SWO and confirmed that “[u]pon receipt of the Stop
Work Order, VESEQU halted all related setup activity and instructed vendors to
suspend all billable actions. Costs tied to the suspended subscriptions have been
contained and no further charges are being incurred.” (R4, tab 31 at 5-6) There is no
evidence that the Cost Summary was part of a regular, organized method for tracking
relevant costs (id.). Nor did the Cost Summary provide any contemporaneous records
tracking and allocating its costs (id.). Instead, the Cost Summary contained a post hoc
estimate that, up to the SWO on October 27, 2025, VESEQU spent 760 hours on the
Canceled Subscriptions—consisting of 200 hours each on the Bloomberg, the S&P,
and the Benchmark subscriptions, and 160 hours on the Project Blue subscription (id.
at 6).
3
10. On November 4, 2025, VESEQU submitted a Request for Equitable
Adjustment (REA) (R4, tab 31 at 1-5). There is no evidence that the REA was part of
a regular, organized method for tracking relevant costs (id.). Nor did the REA provide
any contemporaneous records tracking and allocating VESEQU’s costs (id.). In
particular, the REA stated that “[a]ll hours were recorded through VESEQU’s internal
time-tracking system and are directly attributable to the contract line items placed
under stop work” (id. at 3). VESEQU did not provide evidence from that internal
time-tracking system (id.). Instead, the REA reiterated the Cost Summary’s assertion
that VESEQU spent 760 hours on the Canceled Subscriptions, applied an $85 hourly
rate, and added $6,330.80 in indirect (G&A) costs, for a “Total Estimated Cost to
Date” of $70,930.80 (id. at 3).
11. On November 12, 2025, the CO requested additional evidence to
substantiate how VESEQU calculated its expenses, and information on how VESEQU
calculated its $85 per hour labor rate (R4, tab 34 at 2-3).
12. Later that day, VESEQU responded with a document entitled
Substantiating Documentation (Substantiating Documentation) (R4, tabs 34-34A).
There is no evidence that the Substantiating Documentation was part of a regular,
organized method for tracking relevant costs (id.). Nor did the Substantiating
Documentation provide any contemporaneous records tracking and allocating
VESEQU’s costs (id.). Instead, the Substantiating Documentation estimated that
VESEQU spent 760 hours on the Canceled Subscriptions—200 hours each on the
Bloomberg, the S&P, and the Benchmark subscriptions, and 160 hours on the Project
Blue subscription—between June 17, 2025 and October 27, 2025, and provided a
narrative of the work VESEQU purportedly performed (R4, tab 34A at 4-10, 12). The
Substantiating Documentation also stated that the 760 hours excluded “post-
suspension or administrative follow-up activities” and “costs related to proposal
preparation, litigation, or claim development” (id. at 13). Finally, the Substantiating
Documentation explained how VESEQU calculated its labor rate, including that it was
a “fully burdened amount encompassing . . . [o]verhead and general and administrative
(G&A) costs related to personnel, systems, and compliance management” (id. at 11).
13. On November 17, 2025, DLA partially terminated the contract for
convenience pursuant to FAR 52.212-4(l), terminating the Canceled Subscriptions
(R4, tabs 35-35B).
14. On December 18, 2025, VESEQU converted its REA into a Claim (R4,
tab 36 at 1-2).
15. On February 20, 2026, the CO issued a COFD (R4, tab 41A at 1). The
COFD granted VESEQU $2,550 for 30 hours of work on the Benchmark subscription
at an hourly rate of $85 (id. at 4). In support of that conclusion, the COFD noted that
4
the government resolved the Benchmark issue in 10 hours (id.). The COFD did not
award any G&A expenses because the Substantiating Documentation stated that the
$85 per hour rate was fully burdened and encompassed G&A (id. at 5). Moreover, the
COFD did not award any costs for the Bloomberg, the S&P, or the Project Blue
subscriptions because VESEQU allegedly failed to provide sufficient evidence
demonstrating that it incurred the claimed costs, or that those costs were properly
attributable to the Contract and its partial termination (id.).
16. That same day, VESEQU appealed the denial of its Claim. 2 1F
17. During discovery, DLA propounded Interrogatories and Requests for the
Production of Documents upon VESEQU. Interrogatory No. 1 asked VESEQU to
identify every person—including their names, positions, salaries, dates worked, daily
hours worked, and type of work—who worked on the Contract from award to the
partial termination; to provide a description of the work performed; and to provide the
relied-upon documents (R4, tab 44 at 24).
18. VESEQU’s response to Interrogatory No. 1, which it called a 760-Hour
Crosswalk Table (Crosswalk), 3 was a narrative supporting VESEQU’s post hoc
2F
estimates (R4, tab 44 at 26-27). There is no evidence that the Crosswalk was part of a
regular, organized method for tracking relevant costs (id.). The Crosswalk’s response
to the name, position, and salary of each person who worked on the Contract portion
of Interrogatory No. 1 stated that only its Principal Program Director, Jason Shadbum,
worked on the Contract, and his salary—including taxes—was $85 per hour (id. at 25).
The Crosswalk’s response to the dates worked and daily hours portion of Interrogatory
No. 1 stated that:
Mr. Shadbum worked on the contract from June 18, 2025
(the first business day following the June 17, 2025 award
2
In its complaint, VESEQU added $23,052.51 to the Claim’s $70,930.80, for a total of
$93,983.31 (compl. ¶ 35(A)). However, in its Rule 11 Brief, VESEQU stated
that the $23,052.51 “is a separate amount VESEQU reserves and does not press
as part of the certified claim.” (App. br. at 1) Similarly, VESEQU stated in its
Rule 11 Brief that the additional $23,052.51 “form[s] no part of the $70,930.80
certified amount now before the Board” (id. at 7). Therefore, we do not address
the $23,052.51 added by the complaint.
3
VESEQU repeatedly referred to “The 760-Hour Crosswalk Table produced with
VESEQU’s Interrogatory 1 answer” (R4, tab 44 at 7, 9, 11, 13, 15). There is no
evidence in the record that VESEQU produced a document separate from its
Interrogatory No. 1 Response entitled 760-Hour Crosswalk Table (R4, tab 44).
Therefore, we conclude that the 760-Hour Crosswalk Table refers to
VESEQU’s Interrogatory No. 1 Response.
5
date) through November 17, 2025 (effective date of
Modification No. P00004), partial termination for
convenience). Total direct labor hours: 760 hours over the
153-calendar-day performance period. Work was
performed on a variable daily schedule consistent with the
demands of an active subscription procurement and
management contract involving 28+ commercial
publishers, multiple Government stakeholders, ongoing
license negotiations, and regulatory compliance activities.
The 760-hour total is allocated across five activity phases
as described in the Crosswalk submitted concurrently with
this response:
Phase 1—Contract Initiation & Onboarding (June 18-July
8): 78 hours
Phase 2—Subscription Activation & Publisher
Coordination (July 1-July 31): 186 hours
Phase 3—MSA Impasse Resolution & Licensing
Negotiation (Aug 1-Sep 30): 275 hours
Phase 4—Final Resolution Efforts & Stop-Work
Compliance (Oct 1-Oct 29): 145 hours
Phase 5—REA Preparation & T4C Processing (Oct 29-
Nov 17): 76 hours
Mr. Shadbum devoted substantially all of his professional
working time to performance of hours by primary cost-
driver subscription: Bloomberg Professional Service
(200 hours), S&P Global Platts Metal Daily (200 hours),
Benchmark Minerals Intelligence (200 hours), and Project
Blue Reports (160 hours). The allocation reflects the
subscriptions that generated the heaviest program
management burden during the performance period. The
underlying activities in Phase 1 and 2—including publisher
outreach to all 28+ CLIN subscription providers, contract-
wide activation coordination, WAWF setup, COR user-list
management, weekly dashboard production, and Cure
Notice response preparation—were performed across the
full scope of the contract and are not attributable to any
single subscription.
6
(Id. at 25-26 (emphasis omitted)) The Crosswalk’s response to the description of work
performed portion of Interrogatory No. 1 provided a narrative of the work that
Mr. Shadbum allegedly performed (id. at 26-27). In particular, in addressing the MSA
Impasse Resolution and Licensing Negotiation (Phase 3), the Crosswalk included in its
narrative, “Fastmarkets—user expansion pricing negotiation; invoice reconciliation”
(id. at 27). Similarly, in addressing the Final Resolution and Stop-Work Compliance
(Phase 4), the Crosswalk included, “Fastmarkets refund coordination; Darton
Commodities delivery confirmation” (id. at 27). Fastmarkets was the publisher of
five of the non-Canceled Subscriptions, and Darton Commodities, Ltd. was the
publisher of one of the non-Canceled Subscriptions (R4, tab 1B). In addressing REA
Preparation and Termination for Convenience Processing (Phase 5), the Crosswalk
included in its narrative “Substantiating Documentation preparation and submission”
(R4, tab 44 at 27). The Crosswalk’s response to the documents relied upon portion of
Interrogatory No. 1 did not provide or identify any contemporaneous records tracking
and allocating its costs (id. at 27).
19. DLA’s Requests for the Production of Documents asked VESEQU to
produce documents substantiating its alleged costs during discovery. VESEQU
responded by pointing to: (1) “The Bucket C Time Ledger (Rule 4(b) Supplement,
Tab A-11),” which purportedly “contains contemporaneous time entries for all post-
certification claim preparation work, including Bloomberg-specific coordination;”
(2) the Substantiating Documentation; (3) the Crosswalk; and (4) various emails. (R4,
tab 44 at 6-13) VESEQU never submitted to the Board a supplemental R4 file,
tab A- 11, or a Bucket C Time Ledger, despite VESEQU’s representation that the
“Bucket C time ledger . . . will be produced in accordance with the Board’s schedule . .
. .” (June 12, 2026 email from VESEQU to DLA at 2 (docket #78)), and the
government indicating in its Rule 11 briefing that VESEQU had failed to provide that
document (gov’t br. at 17).
20. Attached to its discovery requests, VESEQU also produced a document
entitled Cost-To-Price Relationship Summary (R4, tab 44 at 65). In that Cost-To-Price
Relationship Summary, under § IV (Termination Cost Claim-Component Breakdown),
VESEQU included a table (Breakdown) where row A was illegible due to overwriting,
except an indication of “$85/hr per int” (id. at 66).
21. In connection with the government’s Rule 11 brief, the CO submitted a
declaration, which attached a June 17, 2026 memorandum of record (Memorandum of
Record). The Memorandum of Record analyzed and estimated VESEQU’s labor
effort for the S&P, the Bloomberg, and the Project Blue subscriptions based upon the
emails that VESEQU produced or referenced in discovery (R4, tab 46). We derive the
following table from the Memorandum of Record’s findings:
7
TABLE 1: Memorandum of Record Findings Summary
Subscription # of Emails Hours Per Amount MSA Total
(Discovery Email Review
Responses) Hours
Bloomberg 65 .25 13.75 2 15.75
S&P 76 .25 19 3 22
Project Blue About 8 .25 2 2
Total 39.75
(Id. at 5-7) We read the declaration and Memorandum of Record as an amendment to
the settlement determination in the COFD. As a result, the total number of hours
VESEQU worked on the Canceled Subscriptions, according to the CO, was 69.75
(30 hours on the Benchmark subscription from the COFD (R4, tab 41A at 4) plus
39.75 hours on the Bloomberg, the S&P, and the Project Blue subscriptions from the
Memorandum of Record (R4, tab 46 at 5-7)). Using the $85 hourly rate from the
COFD, that means that the CO’s amended settlement determination was $5,928.75.
22. VESEQU attached as Exhibit B-1 to its Rule 11 Brief, a document entitled
Performance-Period Vendor Engagement Timeline (Timeline) (app. br., ex. B-1).
There is no evidence that the Timeline was part of a regular, organized method for
tracking relevant costs (id.). Nor did the Timeline provide any contemporaneous
records tracking and allocating its costs (id.). Instead, the Timeline again reiterated the
post hoc estimate that VESEQU spent 760 hours on the Canceled Subscriptions—
200 hours each on the Bloomberg, the S&P, and the Benchmark subscriptions, and
160 hours on the Project Blue subscription —between June 17, 2025 and
October 27, 2025, and provided a narrative in support of that estimate (id.).
DECISION
VESEQU has failed to demonstrate using its standard record keeping system an
amount of loss greater than the amended settlement amount with sufficient certainty so
that that determination will be more than mere speculation. The overall purpose of a
termination for convenience settlement is to fairly compensate the contractor, and to
make it whole for the costs it incurred in connection with the terminated work. SWR,
Inc., ASBCA No. 56708, 15-1 BCA ¶ 35,832 at 175,223. The contractor is not
supposed to suffer as a result of a termination for convenience of the government, nor
to underwrite the government’s decision to terminate. Id. Under FAR 52.212-4(l)—
which was included in the Contract (finding 4)—when the government terminates a
contract for commercial products or services for its convenience, the contractor shall
be paid:
8
[A] percentage of the contract price reflecting the
percentage of the work performed prior to the notice of
termination, plus reasonable charges the Contractor can
demonstrate to the satisfaction of the Government using its
standard record keeping system, have resulted from the
termination.
48 C.F.R. § 52.212-4(l).
We segregate FAR 52.212-4(l) into two prongs allowing for the recovery of
monetary amounts: (1) a percentage of the contract price reflecting the percentage of
work performed (First Prong); and (2) the reasonable charges that have resulted from
the contract termination (Second Prong). Dellew Corp., ASBCA No. 58538, 15-1
BCA ¶ 35,975 at 175,783. Under the First Prong, a contractor is entitled to the “price
of work performed under the contract prior to notice of termination . . . .” Id. There
can be no recovery under the First Prong if the government terminates the contract for
convenience before work was performed under the contract. Al Muamroon Trading,
ASBCA No. 63648, 25-1 BCA ¶ 38,857 at 189,070.
Under the Second Prong, a contractor is entitled to “settlement expenses . . .
[and] costs resulting from the termination.” Dellew Corp., 15-1 BCA ¶ 35,975
at 175,783. The costs resulting from the termination include “reasonable expenses
incurred [prior to the termination for convenience] in preparation for the terminated
portion of the contract.” Id. The phrase “its standard record keeping system” under
the Second Prong means “a regular, organized method for tracking relevant costs . . . .”
ACLR, LLC v. United States, 23-1190, 2024 WL 4315111, at *7 (Fed. Cir. Sept. 27,
2024). The use of the term:
does not impose any broad prescription as to precisely how
every government contractor must maintain its books and
records. But this does not mean . . . that [a contractor can]
fail to contemporaneously track and allocate its costs and
then, only for purposes of litigation, dump essentially
every record it can find on the court, and expect the court
to sift through it and find it to be a “standard record
keeping system.”
Id. Nor may a contractor rely solely upon “post hoc estimates.” Id.
It is a contractor’s burden to prove by a preponderance of the evidence that it is
entitled to a greater termination settlement amount than that determined by the CO.
SWR, 15-1 BCA ¶ 35,832 at 175,225. A contractor must prove “the amount of loss
with sufficient certainty so that that determination of the amount of . . . damages will
9
be more than mere speculation.” Id. (quoting Lisbon Contractors, Inc. v. United
States, 828 F.2d 759, 767 (Fed. Cir. 1987)); see also Globe Trailer Mfg., Inc., ASBCA
No. 60979, 26-1 BCA ¶ 38,972 at 189,744 (holding that spreadsheets with vague
entries regarding labor costs that purportedly resulted from a termination for
convenience were insufficient to meet a contractor’s burden of proof).
Here, VESEQU relies upon the Cost Summary, the Substantiating
Documentation, the Timeline (collectively, Narratives), and unspecified emails. (App.
br. at 3-4, ex. B-1; app. reply at 4). As discussed in greater detail below, those
documents fail to demonstrate using VESEQU’s standard record keeping system an
amount of loss greater than the amended settlement amount with sufficient certainty so
that that determination will be more than mere speculation. 4 3F
I. The Narratives Fail To Demonstrate Using VESEQU’s Standard Record
Keeping System an Amount of Loss Greater Than the Amended Settlement
Amount With Sufficient Certainty so That That Determination Will Be More
Than Mere Speculation
The Narratives fail to demonstrate using VESEQU’s standard record keeping
system an amount of loss greater than the amended settlement amount with sufficient
certainty so that that determination will be more than mere speculation. The
Narratives were not part of VESEQU’s standard record keeping system because they
were not part of a regular, organized method for tracking relevant costs. (Findings 9,
12, 22); ACLR, 2024 WL 4315111, at *7. In particular, the Narratives did not
contemporaneously track and allocate VESEQU’s costs (id.). Rather, the Narratives
were post hoc estimates and narratives (id.). 5
4F
4
VESEQU does not expressly identify under which prong it is claiming that DLA’s
settlement determination is inadequate. However, it clearly is not relying upon
the First Prong because it makes no arguments regarding the percentage of the
work performed. Rather, because it relies upon costs allegedly incurred in
preparation for the terminated portion of the Contract, it is clear that it is relying
upon the Second Prong. (App. br. at 4-6)
5
The Crosswalk—upon which VESEQU relied in its discovery responses—also was
not part of VESEQU’s standard record keeping system because it was a post
hoc estimate and narrative instead of a document that contemporaneously
tracked and allocated VESEQU’s costs as part of a regular, organized method
for tracking relevant costs (finding 18). Further, we cannot determine whether
the Bucket C Time Ledger—upon which VESEQU also relied in its discovery
responses—contemporaneously tracked and allocated VESEQU’s costs as part
of a regular, organized method for tracking relevant costs because VESEQU
never submitted to the Board a supplemental R4 file, tab A-11, or a Bucket C
Time Ledger (finding 19). That is despite VESEQU’s representation that the
10
Moreover, those post hoc estimates and narratives are not credible for three
reasons. First, the Narratives are not credible because they indicated that VESEQU
spent 760 hours preparing for the Canceled Subscriptions between award on
June 17, 2025 and the SWO on October 27, 2025, (findings 9, 12, 22), which would
mean that Mr. Shadbum—whom VESEQU asserts was the only person who worked
on the Contract (finding 18)—worked more than full-time just on the Canceled
Subscriptions for over four months. 6 That is particularly unbelievable in light of the
5F
dozens of non-Canceled Subscriptions on which VESEQU had to work under the
Contract during that period—to say nothing of the five other government contracts
VESEQU also was working on during that period. (Finding 3)
Second, the Narratives are not credible because they are inconsistent with the
Crosswalk—upon which VESEQU relied in its discovery responses—regarding when
VESEQU worked the claimed 760 hours on the Canceled Subscriptions, and what
tasks those 760 hours included. While the Narratives asserted that VESEQU worked
the claimed 760 hours between June 17, 2025 and October 27, 2025 (findings 9, 12,
22), the Crosswalk asserted that VESEQU worked those same claimed 760 hours
between June 18, 2025 and November 17, 2025. (Finding 18) Those numbers are
inconsistent because the Crosswalk asserted that VESEQU worked 76 of those
claimed 760 hours after it received the SWO on October 29, 2025, while the
Substantiating Documentation indicated that VESEQU worked all of the claimed
760 hours prior to October 27, 2025 (findings 12, 18). As a result, while the
Crosswalk included proposal preparation and termination processing in the claimed
760 hours, the Substantiating Documentation indicated that it excluded “post-
suspension or administrative follow-up activities” and “costs related to proposal
preparation, litigation, or claim development” from those same claimed 760 hours
(findings 12, 18). Indeed, the Crosswalk’s assertion that VESEQU worked 76 hours of
the claimed 760 hours on proposal preparation and termination processing after
October 29, 2025 is impossible to square with the fact that VESEQU already was
“Bucket C time ledger . . . will be produced in accordance with the Board’s
schedule, subject to VESEQU’s positions in the appeal,” and the government
indicating in its Rule 11 briefing that VESEQU had failed to provide that
document. (Id.) In any event the Bucket C Time Ledger only purportedly
tracked post-certification claim preparation work (id.).
6
We take judicial notice of the fact that there were 90 business days (i.e.,
calendar days, excluding weekends and Federal Holidays) between June 17,
2025 and October 27 2025. See www.timeanddate.com/date/workdays.html.
Dividing the claimed 760 hours preparing for the Canceled Subscriptions
between June 17, 2025 and October 27, 2025, by those 90 business days
produces an average of 8.44 hours of work per business day on the Canceled
Subscriptions, which exceeds the full-time schedule of 8 hours of work per
business day.
11
claiming in the Cost Summary on October 29, 2025 that it had worked 760 hours on
the Canceled Subscriptions (findings 9, 18). Thus, the numbers simply do not add up.
Third, the Narratives are not credible because they are inconsistent with the
Crosswalk regarding the subscriptions to which VESEQU allocated the claimed
760 hours. The Narratives allocated the claimed 760 hours of work on the Canceled
Subscriptions as follows: 200 hours to the Bloomberg subscription; 200 hours to the
S&P subscription; 200 hours to the Benchmark subscription; and 160 hours to the
Project Blue subscription. (Findings 9, 12, 22) However, in the Crosswalk, VESEQU
allocated 264 hours of the claimed 760 hours to Contract Initiation and Onboarding
(Phase 1) and Subscription Activation and Publisher Coordination (Phase 2), both of
which the Crosswalk stated “were performed across the full scope of the contract and
are not attributable to any single subscription” (finding 18). Even as to MSA Impasse
Resolution & Licensing Negotiation (Phase 3) and Final Resolution and Stop-Work
Compliance (Phase 4), the Crosswalk included time during those phases for user
expansion pricing negotiation, invoice reconciliation, refund coordination, and
delivery confirmation for non-Canceled Subscriptions. (Id.) Because the Narratives
indicated that all of the claimed 760 hours was for work on the Canceled Subscriptions
(findings 9, 12, 22), while the Crosswalk indicated that a substantial portion of the
claimed 760 hours was for work not attributable to any single subscription or for work
on the non-Canceled Subscriptions (finding 18), the Narratives are inconsistent with
the Crosswalk. That is particularly problematic because the costs of work that are not
allocable to the Canceled Subscriptions is not recoverable. See Hugo Auchter GmbH,
ASBCA No. 39642, 91-1 BCA ¶ 23,645 at 118,442.
In sum, due to the lack of contemporaneous evidence tracking and allocating
VESEQU’s costs as part of a regular, organized method for tracking related costs, and
the lack of credibility in their post hoc estimates and narratives, the Narratives fail to
demonstrate using VESEQU’s standard record keeping system an amount of loss
greater than the amended settlement amount with sufficient certainty so that that
determination will be more than mere speculation.
II. The Emails Fail To Demonstrate Using VESEQU’s Standard Record
Keeping System an Amount of Loss Greater Than the Amended Settlement
Amount With Sufficient Certainty so That That Determination Will Be
More Than Mere Speculation
The emails also fail to demonstrate using VESEQU’s standard record keeping
system an amount of loss greater than the amended settlement amount with sufficient
certainty so that that determination will be more than mere speculation. VESEQU
fails to specify the emails upon which it relies. (App. br. at 3-4, ex. B-1; app. reply
at 4) Moreover, such dumps of essentially every record a contractor can find on the
Board expecting the Board to sift through them do not constitute a standard record
12
keeping system. See ACLR, 2024 WL 4315111, at *7. Nor could we determine from
the emails the reasonable charges that have resulted from the termination because
VESEQU does not even estimate—let alone present contemporaneous evidence—of
the amount of time that it spent on those emails (app. br. at 3-4, ex. B-1; app. reply
at 4).
In any event, the CO has estimated the reasonable charges for the emails that
VESEQU produced or referenced in discovery as part of its amended settlement
determination, which we calculate to be $5,928.75 (finding 21). Neither party has
shown that that determination was unreasonable. On the one hand, the government
argues that we should use an hourly rate of $45.50 per hour instead of $85 per hour
because, if highlighted and copied, the illegible portion of the Breakdown purportedly
indicates that the hourly rate was $45.50 per hour. (Gov’t br. at 19) However, the
Board was unable to observe the purported $45.50 indication by highlighting and
copying the illegible portion of the Breakdown. Even if we could, the fact that
VESEQU overwrote that indication with $85 (finding 20) suggests that any $45.50 per
hour rate was not VESEQU’s actual hourly rate. Thus, the Board follows the COFD’s
original determination that the hourly rate was $85 per hour. The government also
argues that we should reduce the number of hours spent on the Benchmark
subscription from the 30 hours that the COFD determined was reasonable to 10 hours
because the COFD stated that the government resolved the Benchmark subscription
issues within 10 hours (gov’t reply at 9). However, the fact that the government spent
10 hours on the Benchmark subscription does not negate the fact that VESEQU spent
30 hours on that subscription because there is no reason that the parties had to spend
the same amount of time on the Benchmark subscription as each other. Certainly, the
COFD found that VESEQU spent 30 hours on the Benchmark subscription, despite
noting that the government only spent 10 hours on that subscription. (Finding 15)
Therefore, the government has failed to show that VESEQU is entitled to less than the
amended settlement amount. On the other hand, as discussed above, VESEQU has
failed to demonstrate using VESEQU’s standard record keeping system an amount of
loss greater than the amended settlement amount of $5,928.75 with sufficient certainty
so that that determination will be more than mere speculation.
III. VESEQU’s Arguments
VESEQU’s arguments in support of its claim are meritless. VESEQU argues
that, under FAR 52.212-4(l), it need not comply with cost accounting standards or
contract cost principles, and the government does not have the right to audit its records
(app. br. at 3-4). That is true (finding 4) However, under FAR 52.212-4(l), VESEQU
must demonstrate using its standard record keeping system an amount of loss greater
than the amended settlement amount with sufficient certainty so that that
determination will be more than mere speculation. (Id.); SWR, 15-1 BCA ¶ 35,832
at 175,225. As discussed above, VESEQU has failed to meet that burden.
13
VESEQU also argues that the COFD is entitled to no weight under our de novo
review, and the government offers no evidence that VESEQU did not work 760 hours
on the Canceled Subscriptions (app. br. at 4, 6-7; app. reply at 1, 3-4). However, it is
not the government’s burden to prove the number of hours that VESEQU did not
work. Rather, it is VESEQU’s burden to prove using its standard record keeping
system an amount of loss greater than the amended settlement amount with sufficient
certainty so that that determination will be more than mere speculation. 48 C.F.R.
§ 52.212-4(l); SWR, 15-1 BCA ¶ 35,832 at 175,225. Again, as discussed above,
VESEQU has failed to meet that burden.
VESEQU finally argues that the Narratives contemporaneously tracked and
allocated costs because at least some of the Narratives generated the 760 hour
breakdown before the termination or litigation (app. reply at 4). Books and records
contemporaneously track and allocate costs when they track and allocate those costs
“at the same time” as a contractor incurs those costs. See WEBSTER’S THIRD NEW
INT’L DICTIONARY (UNABRIDGED) 491 (8th ed. 1986). Here, the Cost Summary—the
earliest Narrative—acknowledged that it did not contemporaneously track and allocate
costs by expressly stating that VESEQU was not incurring costs at the time of the Cost
Summary (finding 9). Indeed, a few days after the Cost Summary, VESEQU admitted
in the REA that, instead of contemporaneously tracking and allocating costs, the
760 hour breakdown narrative relied upon an internal time-tracking system, stating
that “[a]ll hours were recorded through VESEQU’s internal time-tracking system and
are directly attributable to the contract line items placed under stop work ”
(finding 10). Yet, VESEQU has failed to provide evidence from that internal time-
tracking system (id.). Thus, VESEQU has failed to provide evidence of the
contemporaneous tracking and allocation of its costs.
CONCLUSION
VESEQU has failed to demonstrate using its standard record keeping system an
amount of loss greater than the amended settlement amount of $5,928.75 with
sufficient certainty so that that determination will be more than mere speculation.
Therefore, we deny the appeal.
Dated: August 21, 2026
JAMES R. SWEET
Administrative Judge
Armed Services Board
of Contract Appeals
(Signatures continued)
14
I concur
MICHAEL N. O’CONNELL
Administrative Judge
Vice Chairman
Armed Services Board
of Contract Appeals
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 64468, Appeal of
VESEQU LL