First Street Contractors, LLC
CourtArmed Services Board of Contract Appeals
Date FiledJune 10, 2026
Docket64028
JudgeSweet
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
First Street Contractors, LLC ) ASBCA No. 64028
)
Under Contract No. W912P6-20-C-0021 )
APPEARANCES FOR THE APPELLANT: Jonathan R. Neri, Esq.
Lauren R. Brier, Esq.
Josephine R. Farinelli, Esq.
PilieroMazza PLLC
Washington, DC
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Ian T. McDaniel
Engineer Trial Attorney
U.S. Army Engineer District, Chicago
OPINION BY ADMINISTRATIVE JUDGE SWEET
On March 20, 2026, the government filed a motion for reconsideration of our
denial of its motion for summary judgment in First Street Contractors, LLC, ASBCA
No. 64028, 26-1 BCA ¶ 39,004 (First Street I). * In its motion for reconsideration, the
government argues that First Street I erred by: (1) relying upon an annotated Drawing
Sheet M-6 in the government’s summary judgment motion reply brief (Annotated
Drawing); and (2) purportedly asserting in footnote 4 that the government agreed in its
summary judgment motion that there was a material variation between the expected
and the encountered conditions (gov’t mot. for recon. at 3-4). In its motion for
reconsideration reply brief, the government also argues that First Street I erred by
failing to analyze whether there was a patent ambiguity (gov’t mot. for recon. reply
at 6). As discussed in greater detail below, the government waived the first and last
arguments. In any event, none of the government’s arguments satisfy its burden for
establishing entitlement to reconsideration.
I. Motion for Reconsideration Standard
A motion for reconsideration is only appropriate if it is based upon newly
discovered evidence, mistakes in the findings of fact, or errors of law. Green Valley
Co., ASBCA No. 61275, 18-1 BCA ¶ 37,044 at 180,330 (citing Alliance Roofing &
Sheet Metal, Inc., ASBCA No. 59663, 15-1 BCA ¶ 36,063). “Motions for
*
We presume familiarity with First Street I.
reconsideration do not afford litigants the opportunity to take a ‘second bite at the
apple’ or to advance arguments that properly should have been presented in an earlier
proceeding.” Dixon v. Shinseki, 741 F.3d 1367, 1378 (Fed. Cir. 2014) (citations and
quotations omitted). As a result, in our discretion, we may find that an argument not
raised earlier in a proceeding has been waived. Becton Dickinson & Co. v. C.R. Bard,
Inc., 922 F.2d 792, 800 (Fed. Cir. 1990).
II. The Government Waived its Arguments that First Street I’s Reliance Upon
the Annotated Drawing Was an Error, Which, in any Event, Are Meritless
The government raises two arguments in support of its assertion that First
Street I’s reliance upon the Annotated Drawing was erroneous, both of which have
been waived and, in any event, are meritless. The government first argues that
Drawing Sheet M-6 did not depict the concrete floor openings at all, and that the
Annotated Drawing merely showed where the existing concrete floor openings should
be located (gov’t mot. for recon. at 3; gov’t mot. for recon. reply at 2-4). As an initial
matter, that is a new argument that the government waived by failing to raise during its
summary judgment briefing (gov’t summ. j. reply); see Dixon, 741 F.3d at 1378;
Becton Dickinson, 922 F.2d at 800. Indeed, that new argument is inconsistent with the
arguments that the government raised in its summary judgment briefing. In particular,
the government’s new argument that the Drawing Sheet M-6 did not show concrete
floor openings is inconsistent with the government’s assertion in its summary
judgment motion that “Drawing Sheet M-6 . . . provides a section view of the
[wastewater treatment plant] pump room, depicting the positions of the [Smith &
Loveless, Inc.] Grit Pumps and the concrete floor openings” (gov’t summ. j. mot.
at 11, ¶ 14). Likewise, the government’s summary judgment motion reply brief did
not state that the Annotated Drawing highlighting indicated where the existing
concrete openings “should be located” (gov’t mot. for recon. at 3); it stated that the
highlighting indicated “where the existing concrete openings are located (highlighted)
in Drawing Sheet M-6” (gov’t summ. j. reply at 2 (emphasis added)).
In any event, the government’s new argument that Drawing Sheet M-6 did not
depict concrete floor openings at all merely would contribute to the factual dispute as
to whether First Street’s interpretation of Drawing Sheet M-6 as showing existing
concrete floor openings that were larger than the Grit Pumps was reasonable; it would
not resolve that dispute. Thus, that new argument would not establish that First Street
I erred when it held that there are genuine issues of material fact as to whether First
Street reasonably interpreted and relied upon Drawing Sheet M-6. 26-1 BCA ¶ 39,004
at 189,937-38.
Second, in its reply brief on its motion for reconsideration, the government also
argues that the Board mistook the Annotated Drawing for part of the Contract, and that
the Annotated Drawing did not modify Drawing Sheet M-6 (gov’t mot. recon. reply
2
at 2, 4-5). As an initial matter, the government waived that argument by failing to
raise it in its motion for reconsideration opening brief (gov’t mot. recon.). Novosteel
SA v. United States, 284 F.3d 1261, 1274 (Fed. Cir. 2002); Buck Town Contractors,
Co., ASBCA No. 60939, 18-1 BCA ¶ 36,951 at 180,059. In any event, the argument
is meritless. Nowhere in the Concrete Floor Openings Claim Statement of Facts did
First Street I find that the Annotated Drawing was part of, or modified, Drawing Sheet
M-6. 26-1 BCA ¶ 39,004, at 189,933-35. Rather, in the Concrete Floor Openings
Claim Discussion, First Street I relied upon the Annotated Drawing as a party
admission regarding what Drawing Sheet M-6 showed. Id. at 189,937. That is an
acceptable use of an attorney’s statement. See Paice LLC v. Toyota Motor Corp.,
504 F.3d 1293, 1312 (Fed. Cir. 2007). Thus, the government has failed to show that
First Street I’s reliance upon the Annotated Drawing was erroneous based upon newly
discovered evidence, involved a mistake in the findings of fact, or involved an error of
law.
III. The Government’s Argument That First Street I Erred by Purportedly
Asserting That the Government Agreed That There Was A Material
Variation Between the Expected and the Encountered Conditions Is
Meritless
Also meritless is the government’s challenge to First Street I’s alleged assertion
in footnote 4 that the government agreed in its summary judgment motion that there
was a material variation between the expected condition of concrete floor openings
that were larger than the Grit Pumps and the encountered conditions of concrete floor
openings that were smaller than the Grit Pumps (gov’t mot. for recon. at 4). In
particular, the government argues that it did not agree in its summary judgment motion
that the expected condition included concrete floor openings that were larger than the
Grit Pumps because its summary judgment motion asserted that Drawing Sheet M-6—
which First Street argued showed the expected conditions—depicted the effort’s post-
installation results instead of the pre-installation expectation of existing conditions
(id.). However, First Street I acknowledged the government’s argument that Drawing
Sheet M-6 depicted the effort’s post-installation results instead of the pre-installation
expectation of existing conditions, holding that there was a genuine issue of material
fact as to that issue. 26-1 BCA ¶ 39,004 at 189,937 (“On the one hand, as the Corps
argues (gov’t [summ. j.] reply at 3-4), it is reasonable to infer from the fact that
Drawing Sheet M-6 is entitled ‘NEW WORK’ that it merely depicted the Corps’
expectations of the project’s post-installation results . . . .”).
First Street I’s footnote 4 also acknowledged the parties’ dispute regarding
whether the expected conditions included concrete floor openings that were larger than
the Grit Pumps by referring to the “alleged indication that the existing concrete floor
openings were larger than the Grit Pumps.” Id. at 189,943 n.4 (emphasis added). The
motion for reconsideration simply ignores footnote 4’s use of the word “alleged” to
3
qualify the phrase “indication that the existing concrete floor openings were larger
than the Grit Pumps” (gov’t mot. for recon. at 4). Footnote 4 merely noted the lack of
a dispute as to whether that alleged existing condition materially differed from the
conditions encountered of existing concrete floor openings that were smaller than the
Grit Pumps. First Street, 26-1 BCA ¶ 39,004 at 189,937 n.4. Because the government
has failed to show that its summary judgment motion argued that the alleged indication
that the existing concrete floor openings were larger than the Grit Pumps did not
materially differ from the condition encountered of concrete floor openings that were
smaller than the Grit Pumps (id.), the government has failed to show that footnote 4
erred in its characterization of the argument in the government’s summary judgment
motion.
IV. The Government Waived Its Patent Ambiguity Argument, Which, in any
Event, Is Meritless
The government waived its patent ambiguity argument, which, in any event, is
meritless. In its motion for reconsideration reply brief, the government argues that the
Board erred as a matter of law in failing to decide whether any ambiguity was patent
because, under Korte Constr. Co., ASBCA No. 63148, 23-1 BCA ¶ 38,454 at 186,909
(quoting Newsom v. United States, 676 F.2d 647, 650 (Ct. Cl. 1982)), the:
existence of a patent ambiguity in itself raises the duty of
inquiry, regardless of the reasonableness vel non of the
contractor’s interpretation. . . . The court may not consider
the reasonableness of the contractor’s interpretation, if at
all, until it has determined that a patent ambiguity did not
exist.
(Gov’t reply mot. recon. at 6) As an initial matter, the government waived that
argument by failing to raise it in its motion for reconsideration opening brief (gov’t
mot. recon.); Novosteel, 284 F.3d at 1274; Buck Town Contractors, 18-1 BCA ¶
36,951 at 180,059.
In any event, the argument is meritless because the government’s reliance upon
Newsom and Korte ignores the fact that the reasonableness of a contractor’s
interpretation of contract language is a factor we consider in both determining whether
there is an ambiguity in the first place, and whether that ambiguity is patent—which
we only analyze if we determine that there was an ambiguity. First, as we correctly
held in First Street I, the Board considers the reasonableness of a contractor’s
interpretation in deciding whether a contract is ambiguous. 26-1 BCA ¶ 39,004
at 189,936. Indeed, Korte acknowledged that we must analyze whether a contractor’s
interpretation of a contract is reasonable in deciding if it is ambiguous. 23- 1 BCA ¶
38,454 at 186,908. Second, as Newsom held, the patent ambiguity analysis contains
4
two steps—namely whether an ambiguity is patent and, if not, whether the contractor’s
interpretation was reasonable. 676 F.2d at 650.
Newsom merely held that a tribunal will not conduct the second step of the
patent ambiguity analysis of determining the reasonableness of the contractor’s
interpretation until after it has determined that the ambiguity was not patent under the
first step. 676 F.2d at 650. Newsom did not analyze whether the contract was
ambiguous in the first place, and, as a result, did not hold that we may not conduct the
reasonableness inquiry that we perform as part of that ambiguity determination before
we determine whether any ambiguity is patent. Id. Indeed, such a reading of Newsom
would contradict the well-established precedent that we must determine whether a
contract is ambiguous before we analyze whether any ambiguity is patent, see
Grumman Data Sys., Corp. v. Dalton, 88 F.3d 990, 997 (1996); Interwest Const. v.
Brown, 29 F.3d 611, 614-15 (1994), and that that analysis of whether a contract is
ambiguous includes a consideration of the reasonableness of a contractor’s
interpretation. CDM Constructors, Inc., ASBCA No. 60454 et al., 18-1 BCA ¶ 37,190,
at 181,012 (quoting E.L. Hamm & Assocs., Inc. v. England, 379 F.3d 1334, 1341 (Fed.
Cir. 2004); NVT Techs., Inc. v. United States, 370 F.3d 1153, 1159 (Fed. Cir. 2004);
Hol-Gar Mfg. Corp. v. United States, 351 F.2d 972, 975 (Ct. Cl. 1965)). In fact, it
would be a logical impossibility to determine that an ambiguity was patent before we
first decided that there was an ambiguity. Because there is a genuine issue of material
fact as to whether the Contract is ambiguous based upon a genuine dispute regarding if
First Street’s interpretation of the Contract is reasonable, First Street I properly
declined to reach the subsequent question of whether any ambiguity was patent in
deciding the cross-motions for summary judgment. 26-1 BCA ¶ 39,004 at 189,936-37.
CONCLUSION
For the reasons discussed above, we deny the government’s motion for
reconsideration.
Dated: June 10, 2026
JAMES R. SWEET
Administrative Judge
Armed Services Board
of Contract Appeals
(Signatures continued)
5
I concur I concur
J. REID PROUTY MICHAEL N. O’CONNELL
Administrative Judge Administrative Judge
Acting Chairman Vice Chairman
Armed Services Board Armed Services Board
of Contract Appeals of Contract Appeals
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 64028, Appeal of First Street
Contractors, LLC, rendered in conformance with the Board’s Charter.
Dated: June 10, 2026
PAULLA K. GATES-LEWIS
Recorder, Armed Services
Board of Contract Appeals
6