Bessemer and Lake Erie Railroad Co. v. PA PUC
CourtCommonwealth Court of Pennsylvania
Date FiledSeptember 8, 2026
Docket965 C.D. 2025
JudgeFizzano Cannon
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
IN THE COMMONWEALTH COURT OF PENNSYLVANIA
Bessemer and Lake Erie :
Railroad Company, :
Petitioner :
:
v. :
:
Pennsylvania Public Utility :
Commission, : No. 965 C.D. 2025
Respondent : Argued: June 17, 2026
BEFORE: HONORABLE RENÉE COHN JUBELIRER, President Judge
HONORABLE PATRICIA A. McCULLOUGH, Judge
HONORABLE ANNE E. COVEY, Judge
HONORABLE MICHAEL H. WOJCIK, Judge
HONORABLE CHRISTINE FIZZANO CANNON, Judge
HONORABLE STACY WALLACE, Judge
HONORABLE MATTHEW S. WOLF, Judge
OPINION
BY JUDGE FIZZANO CANNON FILED: September 8, 2026
Petitioner, Bessemer and Lake Erie Railroad Company (Railroad),
seeks review of the July 10, 2025 Opinion and Order (Order) of the Pennsylvania
Public Utility Commission (PUC) allocating costs of remediation and future
maintenance responsibilities for the Blackburn Tunnel, a railroad crossing.1 The
PUC’s Order adopted the findings of an Administrative Law Judge (ALJ) and denied
the Railroad’s exceptions, thereby assigning all costs, including future maintenance,
to the Railroad. After careful review, we affirm the PUC’s Order.
1
Originally there were two railroad crossings in question, Brady’s Bend and Blackburn
Tunnel. However, by way of Joint Stipulation submitted to the PUC on November 12, 2021, all
issues related to Brady’s Bend were resolved. Because only Blackburn Tunnel remains at issue,
Brady’s Bend will be discussed herein only where relevant.
I. Background
The Blackburn Tunnel is a railroad tunnel crossed by Pennsylvania
State Route 268 (SR0268) in Fairview Township, Butler County. Reproduced
Record (R.R.) at 4a, 24a & 114a. In 1967, the Railroad acquired the Western
Allegheny Branch railroad line from the Western Allegheny Railroad Company. Id.
at 298a & 358a-85a. This railroad line included the Blackburn Tunnel. Id. at 115a.
The Railroad discontinued operation of rail service on the Western Allegheny
Branch around 1998. Id. at 294a, 306a-09a & 311a-13a.
In 2000, the Railroad filed a notice with the federal Surface
Transportation Board (STB)2 to abandon rail service along approximately 20 miles
of rail line in Butler and Armstrong Counties. R.R. at 294a, 306a-09a & 311a-13a.
The STB authorized the abandonment of rail service on January 17, 2001. Id. at
311a-13a.
On May 31, 2001, the Railroad filed an application with the PUC
seeking authorization to abolish 29 crossings, including the Blackburn Tunnel. See
R.R. at 115a. The PUC granted the Railroad’s application to abolish 27 out of the
29 requested crossings on April 30, 2002, via Secretarial letter. Id. at 315a-20a. The
PUC specifically stated, however, that neither the Blackburn Tunnel nor the Brady’s
Bend crossing could be abolished at that time because the Railroad and the
Pennsylvania Department of Transportation (PennDOT) were negotiating final
dispositions regarding those crossings. Id. at 318a; see also id. at 115a. In March
2009, the PUC issued a letter disposition regarding the Brady’s Bend Crossing. Id.
2
The STB is a federal agency charged with the economic regulation of various modes of
surface transportation, primarily freight rail. The STB has jurisdiction over railroad rate, practice,
and service issues and rail restructuring transactions, including mergers, line sales, line
construction, and line abandonments. See https://www.stb.gov/about-stb/ (last visited September
4, 2026).
2
at 671a-72a. However, the record reflects no further negotiation concerning the
Blackburn Tunnel. Thus, the record does not reflect that any resolution was ever
reached with PennDOT concerning the Blackburn Tunnel, nor that the PUC ever
approved the Railroad’s application to abolish that crossing. See id. at 215a.
On October 24, 2002, the Railroad conveyed its interest in a 394-acre
property containing the Blackburn Tunnel to the Western Allegheny Landowners
Association (WALA) via quitclaim deed. R.R. at 95a-96a & 334a-37a. The record
does not indicate that the Railroad ever sought or received a certificate of public
convenience from the PUC approving that sale. Accord id. at 814a (observing that
the Railroad “conveyed the property that included the Blackburn Tunnel to WALA
on October 24, 2002, without receiving [PUC] authorization to abolish the
Blackburn Tunnel after the April 2002 Secretarial Letter and before it conveyed the
property”) & 986a (observing that the Railroad “was aware of its duty to obtain
approval of the abolition of the Blackburn Tunnel crossing in 2001, and instead of
giving the required notice and obtaining the necessary approval, it sold the property,
thereby depriving the Commission and PennDOT of the ability to fully address the
safety of the tunnel”). The deed did not reserve to the Railroad any easement rights
over the property. See id. at 95a-96a & 334a-37a. The property was thereafter
subdivided and conveyed to four different individuals in 2003. See id. at 100a-11a.
Thereafter, the Blackburn Tunnel was not maintained, and it deteriorated to the point
that by July of 2021, it lacked “the structural integrity to prevent future collapsing
or any subsidence in the roadway above.” Id. at 68a.
On February 1, 2012, the PUC issued a purportedly final Secretarial
letter, captioning the matter as follows:
Application of [the Railroad] for approval of the abolition
of twenty-eight crossings where applicant’s former
3
Hilliard’s Branch and Western Allegheny Branch are
intersected by public highways and streets in the
Township of Marion, Clay, Concord and Fairview in
Butler County and in the Township of Brady’s Bend in
Armstrong County and application for the abolition of
one Tunnel located in the Township of Fairview in
Butler County.
R.R. at 673a (emphasis added). Notwithstanding that the PUC had never granted
approval for the requested abolition of the Blackburn Tunnel crossing, the
Secretarial letter stated that the work in the referenced matter had been completed
and the case was closed. Id. It further directed that any interested parties dissatisfied
with the resolution of the matter could file a petition with the PUC within 20 days.
Id. There is no evidence of record that any petition was filed in response.
In October 2019, due to concern for public safety, the PUC initiated an
investigation into the Blackburn Tunnel prior to a final disposition of the crossing.
R.R. at 5a & 1038a. This investigation involved an engineering study to be
completed and paid for by the Railroad. Id. at 5a. The engineering study revealed
that over time, the Blackburn Tunnel presented safety and structural concerns;
specifically, the study concluded that the Blackburn Tunnel “does not have the
structural integrity to prevent future collapsing or any subsidence in the roadway
above.” Id. at 576a & 634a; see also id. at 629a. In December 2022, the PUC
determined that the Railroad was responsible for Blackburn Tunnel’s deteriorated
condition because the Railroad had failed to provide proper maintenance over time.
Id. at 810a-16a; see also id. at 795a-99a.
Meanwhile, in January 2022, the Railroad filed a motion for summary
judgment with the PUC concerning the disposition of the Blackburn Tunnel matter,
positing that it was not a concerned party before the PUC because the federal STB
had granted the cessation of rail service related to the Blackburn Tunnel crossing in
4
2001 and because the Railroad no longer owned the property in which the Blackburn
Tunnel lay. See R.R. at 277a-80a. The motion for summary judgment was addressed
during an evidentiary hearing before an ALJ. See id. at 156a, 168a & 280a. The
ALJ entered a recommended decision opining that the Railroad’s motion for
summary judgment should be dismissed because the Railroad was a concerned party
with respect to allocating costs for remediation of the Blackburn Tunnel. Id. at 705a-
44a.
The Railroad filed exceptions to the ALJ’s recommended decision,
continuing to assert that it was not a concerned party due to its lack of ownership of
the property and the STB’s prior abolition of the Blackburn Tunnel. R.R. at 746a-
59a. In December 2022, the PUC entered its Final Opinion and Order concluding
that the Railroad was a concerned party with respect to the Blackburn Tunnel and
would remain a party in subsequent proceedings where costs would be allocated for
remediation. Id. at 780a-817a. The PUC reasoned that the Railroad remained a
concerned party because it had failed to follow the proper procedure to receive PUC
approval to abolish the Blackburn Tunnel, and thus, the tunnel remained active and
neglected. Id. at 814a. Accordingly, the PUC denied the Railroad’s motion for
summary judgment and adopted the ALJ’s recommended decision. Id. at 816a.
In July 2024, the Railroad, PennDOT, and the Bureau of Investigation
and Enforcement attended a prehearing conference before a different ALJ to
determine how to address cost allocations for remediation at the Blackburn Tunnel.
At that conference, the ALJ suggested that he would render a recommended decision
addressing cost allocations based upon stipulated facts from the record evidence
presented in the 2022 proceeding. R.R. at 861a-62a. The parties agreed and
submitted their joint stipulation of facts in September 2024. Id. at 878a-916a.
5
On January 30, 2025, the ALJ entered his recommended decision
opining that the Railroad should be responsible for the engineering reports, tunnel
fill project costs, traffic control reimbursement, and final closure costs. R.R. at 958a-
96a. This reasoning was based on the Railroad’s historical ownership of Blackburn
Tunnel, the operational benefits, decades of maintenance neglect while enjoying cost
savings, failure to follow proper regulatory procedures for tunnel abandonment, and
the principle that entities responsible for infrastructure deterioration should bear
remediation costs. Id. at 987a-90a.
The Railroad filed exceptions to the ALJ’s recommended decision.
R.R. at 998a-1010a. On July 10, 2025, the PUC entered its Final Order adopting the
ALJ’s recommended decision and denying all of the Railroad’s exceptions. Id. at
1069a-70a. Thus, the PUC approved the assignment of costs to the Railroad from
the recommended decision in the amount of $2,817,685.15, in addition to future
costs and maintenance of the Blackburn Tunnel. Id. at 1070a.
On August 4, 2025, the Railroad filed a petition with this Court seeking
review of the PUC’s July 10, 2025 Order. PennDOT intervened in the matter in
support of the proposition that substantial evidence exists to show that the Railroad
is a concerned party responsible for Blackburn Tunnel’s maintenance costs.
II. Issues
In its petition for review, the Railroad argues that the PUC’s Order
constituted an error of law3 under the Public Utility Code (Code), 66 Pa.C.S. §§ 101-
3
Our scope and standard of review of PUC decision are as follows:
On a petition to review a decision of [the] PUC, our standard of
review is limited to determining whether substantial evidence
6
3316. Specifically, the Railroad argues that the plain language of the Code does not
support the conclusion that the Railroad is a “concerned party” to which the PUC
has statutory authority to allocate costs for the present and future repair, removal,
reconstruction, and maintenance of the Blackburn Tunnel, because the Railroad
holds no property interest in, or right of access to, the Blackburn Tunnel.
III. Discussion
A. The Railroad Is a “Concerned Party”
Under Section 2704 of the Code,
[t]he cost of construction, relocation, alteration,
protection, or abolition of such crossing, and of facilities
at or adjacent to such crossing which are used in any kind
of public utility service, shall be borne and paid as
provided in this section, by the public utilities . . .
concerned, or by the Commonwealth, in such proper
proportions as the commission may, after due notice and
hearing, determine, unless such proportions are mutually
agreed upon and paid by the interested parties.
66 Pa.C.S. § 2704(a) (emphasis added). The Railroad asserts that it is not a
concerned party because it no longer owns the property where the Blackburn Tunnel
is located due to the private quitclaim deed executed in 2002. The Railroad further
relies on this Court’s decision in City of Chester v. Pennsylvania Public Utility
supports the necessary findings of fact, whether [the] PUC erred as
a matter of law, and whether constitutional rights were violated. . . .
We may not substitute our judgment for that of [the] PUC []when
substantial evidence supports the PUC’s decision on a matter within
[its] expertise. . . . On issues of law, []our standard of review is de
novo and our scope of review is plenary. . . .
Johnson v. Pa. Pub. Util. Comm’n, 338 A.3d 203, 207 (Pa. Cmwlth. 2025) (quoting Retail Energy
Supply Ass’n v. Pa. Pub. Util. Comm’n, 185 A.3d 1206, 1220 (Pa. Cmwlth. 2018) (internal
citations and quotation marks omitted)).
7
Commission, 798 A.2d 288 (Pa. Cmwlth. 2002), in which we posited that “it is the
ownership interest at the crossing, not mere usage that gives [the PUC] the authority
to allocate costs . . . . [O]wnership of the rail line involved []places liability on the
railroad for costs associated with a crossing, including repairs, removal,
reconstruction or maintenance.” Id. at 294.
We disagree with the Railroad’s reasoning. As discussed below, we
conclude that Norfolk Southern Railway Co. v. Pennsylvania Public Utility
Commission, 77 A.3d 619 (Pa. 2013) (Norfolk Southern III), not City of Chester,
controls the determination of who is a concerned party.
Section 1501 of the Code provides:
Every public utility shall furnish and maintain adequate,
efficient, safe, and reasonable service and facilities, and
shall make all such repairs, changes, alterations,
substitutions, extensions, and improvements in or to such
service and facilities as shall be necessary or proper for
the accommodation, convenience, and safety of its
patrons, employees, and the public.
66 Pa.C.S. § 1501 (emphasis added). Nothing in the statutory language authorizes
a public utility to abdicate its repair and maintenance obligations unilaterally or to
foist those obligations upon a third party by the expedient of transferring the utility’s
interest in its property to the third party without PUC authorization.
To the contrary, Section 2702(c) of the Code gives the PUC exclusive
jurisdiction to determine whether and how a rail-highway crossing should be
physically abolished. 66 Pa.C.S. § 2702(c) (referring to the PUC’s exclusive
jurisdiction over relocation, alteration, suspension, and abolition of crossings,
whether upon its own motion or upon complaint). Section 2702(a) of the Code
provides:
8
No public utility, engaged in the transportation of
passengers or property, shall, without prior order of the
[PUC], construct its facilities across the facilities of any
other such public utility or across any highway at grade or
above or below grade, or at the same or different levels;
and no highway, without like order, shall be so constructed
across the facilities of any such public utility, and, without
like order, no such crossing heretofore or hereafter
constructed shall be altered, relocated, suspended or
abolished.
Id. § 2702(a) (emphasis added). Notably, Section 2702(f) requires the PUC to “order
[a] crossing to be immediately altered, improved, or suspended” upon a finding of
an “immediate danger to the safety and welfare of the public.” Id. § 2702(f). If
immediate danger is found, a hearing shall be held, and costs shall be allocated to
the concerned parties. Id.; see also Norfolk Southern III, 77 A.3d at 628-29 (holding
that the PUC is vested with the discretion to determine the “‘proper proportions’ of
costs to be allocated to concerned parties”). It has long been established that the
PUC takes all relevant factors into consideration when apportioning costs in rail-
highway crossing cases, with the fundamental requirement being that the PUC’s
order be “just and reasonable.” Dep’t of Transp. v. Pa. Pub. Util. Comm’n, 469 A.2d
1149, 1152 (Pa. Cmwlth. 1983).
Here, the Railroad’s reliance on City of Chester is misplaced. That case
was decided in 2002, prior to our Supreme Court’s decision in Norfolk Southern III,
in which the Supreme Court expressly held that “a transportation utility need not
own facilities at a rail-highway crossing to be a concerned party for purposes of
the PUC’s cost-allocation jurisdiction and authority . . . .” 77 A.3d at 633
(emphasis added). In Norfolk Southern III, the Pennsylvania Supreme Court
considered the limits of the PUC’s authority to allocate costs associated with rail-
highway crossing projects. There, the Colebrook Road Bridge in Lancaster County
9
carried a local road above train tracks owned and used by Amtrak.4 Norfolk Southern
III, 77 A.3d at 621. Norfolk Southern operated freight trains on the same tracks
pursuant to an express written easement and operating agreement with Amtrak. Id.
at 621. Norfolk Southern did not own any property at the crossing in question. Id.
When the bridge deteriorated, the PUC directed Lancaster Township to remove it at
the Township’s initial expense, subject to a later final allocation of costs among
concerned parties per Section 2704(a) of the Code, 66 Pa.C.S. § 2704(a). Id.
Norfolk Southern challenged its joinder as a concerned party, arguing that any
allocation of costs to it would be unjust and unreasonable because “the company
owned no property or facilities at the crossing site and paid Amtrak for the privilege
of operating on [the] railroad’s line.” Id. Our Supreme Court disagreed with Norfolk
Southern and held, as set forth above, that “a transportation utility need not own
facilities at a rail-highway crossing to be a concerned party for purposes of the
PUC’s cost-allocation jurisdiction and authority, at least where the utility conducts
regular operations at the crossing and may enforce an easement-based right of way.”
Id. at 633.
Norfolk Southern III addressed only the concerned party status of a
utility whose rights in property arose through a lease and easement rather than
outright ownership. It did not speak to the specific situation here, where the Railroad
sought to evade its statutory repair and maintenance obligations by means of an
unauthorized conveyance through a quitclaim deed. Nonetheless, the analysis and
holding of Norfolk Southern III indicate clearly that concerned party status does not
4
The National Railroad Passenger Corporation (Amtrak) was created pursuant to the Rail
Passenger Service Act, as amended, 45 U.S.C. §§ 501-658. Amtrak “is a corporation created by
Congress to compete for the transportation business of the intercity traveller, to the end that the
travelling public will have a choice of travel modes.” 49 C.F.R. § 700.2.
10
depend solely on ownership of the property at issue. Thus, although City of Chester
indicates that ownership will confer maintenance responsibilities, Norfolk Southern
III clarifies that there may also be non-ownership interests in a railroad crossing that
confer concerned party status regarding maintenance expenses. Any suggestion to
the contrary in City of Chester was overridden by the analysis and holding of Norfolk
Southern III.
Additionally, Section 1102(a)(3) of the Code requires a utility to obtain
a certificate of public convenience from the PUC authorizing a transfer of utility
property before any such conveyance may occur. 66 Pa.C.S. § 1102(a)(3); see also
Pub. Serv. Water Co. v. Pa. Pub. Util. Comm’n, 645 A.2d 423, 427 (Pa. Cmwlth.
1994) (quoting Section 1102(a)(3)). Here, the Railroad conveyed its interest in the
394-acre property containing Blackburn Tunnel to WALA via quitclaim deed in
2002, after the PUC had already denied the Railroad’s request to abolish the
crossing. The Railroad did not seek or receive the requisite PUC approval for the
conveyance. Nonetheless, because the Railroad had purported to convey its interest
in the property through the quitclaim deed, the Railroad did not maintain the
Blackburn Tunnel thereafter. Indeed, given that the PUC had denied the Railroad’s
request to abolish the Blackburn Tunnel just one year earlier, the quitclaim deed
appears to have been intended to circumvent the PUC abolition procedure.
As our Supreme Court has observed, “‘[t]he distinguishing
characteristic of a quitclaim deed is that it is a conveyance of the interest or title of
the grantor in and to the property described, rather than of the property itself.’”
Greek Cath. Congregation of Borough of Olyphant v. Plummer, 12 A.2d 435, 437
(Pa. 1940) (quoting 16 Am. Jur. Deeds § 219). Thus, “the law is that ‘a quitclaim
deed is one which purports to convey, and is understood to convey, nothing more
11
than the interest or estate of which the grantor is seised or possessed, if any, at the
time.’” Id. (quoting 18 C.J. Deeds § 32). Our Supreme Court recently elaborated:
A quitclaim deed does not warrant or profess that the
grantor’s title is valid. . . . Therefore, if there is any doubt
as to the validity of the grantor’s ownership, the grantee
bears the risk. In sum, a quitclaim deed “excludes any
implication that [the grantor] has good title, or any title at
all. Such a deed in no way obligates the grantor. If he has
no interest, none will be conveyed.” . . . It is as though the
grantor “quits” making any “claim” to the property, and
gives the grantee the right to assert that claim.
Grant v. Grant, 341 A.3d 685, 689 (Pa. 2025).
Thus, there is nothing about the nature or function of a quitclaim deed
that would make it effective to transfer a grantor’s statutory obligations owed to a
third party, as opposed to merely conveying, without any warranty, the grantor’s
potential rights. Accordingly, here, the Railroad possessed no authority to convey
to a third party the repair and maintenance responsibilities imposed on the Railroad
under the Code. A quitclaim deed, therefore, was ineffective to transfer such
responsibilities.
Section 1102(a)(3) of the Code provides, in pertinent part, that
[u]pon the application of any public utility and the
approval of such application by the commission,
evidenced by its certificate of public convenience first had
and obtained, . . . it shall be lawful . . . to transfer to, any
person or corporation, including a municipal corporation,
by any method or device whatsoever, . . . any tangible or
intangible property used or useful in the public service.
66 Pa.C.S. § 1102(a)(3). Thus, although the Code requires PUC approval through a
certificate of public convenience before a public utility conveys its property, the
Code does not provide that any conveyance without such approval is automatically
void. Section 2102(a) similarly provides that a contract or arrangement for sale of a
12
public utility’s property is not “valid or effective unless and until such contract or
arrangement has received the written approval of the [PUC].” 66 Pa.C.S. § 2102(a).
The language of this provision also does not suggest that a sale not preapproved by
the PUC is void ab initio. Rather, Section 2102(b) provides, in pertinent part, that
“[i]f at the end of 30 days after the filing of a contract or arrangement, no order of
rejection has been entered, such contract or arrangement, whether written or
unwritten, shall be deemed, in fact and law, to have been approved.” 66 Pa.C.S.
§ 2102(b).
Here, the PUC was aware of the quitclaim deed from the Railroad to
WALA as soon as the Railroad began asserting that the quitclaim deed eliminated
the Railroad’s concerned party status. The PUC took no action to disapprove the
conveyance or void the quitclaim deed within 30 days or at any other time thereafter.
Thus, the transfer effected by the quitclaim deed was deemed approved. See 66
Pa.C.S. § 2102(b). However, nothing in the Code required the PUC to void the
quitclaim deed or the conveyance it purported to accomplish in order to retain
discretionary authority to determine and allocate costs for repair and maintenance of
the Blackburn Tunnel. In that regard, we observe that a public transportation utility’s
repair and maintenance responsibilities imposed by the Code do not constitute
“tangible or intangible property” so as to be subject to possible conveyance under
Section 1102(a)(3) of the Code.
Because, as explained above, the Railroad possessed no authority to
convey to a third party the repair and maintenance responsibilities imposed on the
Railroad under the Code, the quitclaim deed was ineffective to transfer those
responsibilities. Therefore, the PUC retained its discretion to determine and allocate
repair and maintenance costs notwithstanding the execution of the quitclaim deed.
13
As we observed above, it appears the Railroad executed the quitclaim
deed here in an attempt to avoid future repair and maintenance costs after the PUC
originally denied the Blackburn Tunnel abolition request. However, that attempt
was legally ineffective. The Railroad remains a concerned party for purposes of the
PUC’s allocation of remediation costs associated with the Blackburn Tunnel.
B. The Doctrine of Laches and the Statute of Limitations
The Railroad also contends that, even if it is properly deemed a
concerned party, either the doctrine of laches or the applicable statute of limitations
bars the PUC from seeking to set aside the 2002 conveyance of the property by the
Railroad. We disagree. As discussed in the previous section, the PUC is not seeking
to set aside the quitclaim deed; it is merely exercising its statutory authority to
allocate remediation costs.
Moreover, the Railroad failed to preserve these issues, as neither was
raised in the exceptions to the ALJ’s recommended decision. See R.R. at 998a-
1010a. Rule 1551(a) of the Pennsylvania Rules of Appellate procedure provides that
“[r]eview of quasijudicial orders shall be conducted by the court on the record made
before the government unit” and states, as a general rule, that “[o]nly questions
raised before the government unit shall be heard or considered . . . .” Pa.R.A.P.
1551(a); McKnight v. Pub. Util. Comm’n, 313 A.3d 337, 341 (Pa. Cmwlth. 2024)
(concluding that the petitioner waived review by this Court of issues not raised in
exceptions before the PUC) (quoting HIKO Energy, LLC v. Pa. Pub. Util. Comm’n,
209 A.3d 246, 261 (Pa. 2019) (observing that “[g]enerally, a party waives appellate
review of a claim when it fails to raise the issue before an administrative tribunal
14
rendering a final decision”)). Therefore, issues concerning laches5 and the statute of
limitations6 are not subject to review by this Court.
5
In any event, if we were to consider the laches issue, we would reject the Railroad’s
argument. “Laches is an equitable doctrine that bars relief when a complaining party is guilty of
want of due diligence in failing to promptly institute an action to the prejudice of another.” Peden
v. Gambone Bros. Dev. Co., 798 A.2d 305, 312 (Pa. Cmwlth. 2002). The party asserting laches as
a defense must present evidence demonstrating prejudice from the lapse of time. Cmwlth. ex rel.
Baldwin v. Richard, 751 A.2d 647 (Pa. 2000).
However, this Court has repeatedly held that laches, an equitable doctrine, cannot be
invoked as a shield against liability by a party who does not come to court with “clean hands.”
Hurwitz v. City of Phila. (In re Pres. of FDR Park Richard Garella), 344 A.3d 461, 471 (Pa.
Cmwlth. 2025); Superior Lawn Care & State Workers’ Ins. Fund v. Workers’ Comp. Appeal Bd.
(Hoffer), 878 A.2d 936, 941 n.7 (Pa. Cmwlth. 2005); Mrkich v. Workers’ Comp. Appeal Bd.
(Allegheny Cnty. Child. & Youth Servs.), 801 A.2d 668, 673 (Pa. Cmwlth. 2002); Giddings v. State
Bd. of Psychology, 669 A.2d 431, 434 (Pa. Cmwlth. 1995). This Court has elucidated the doctrine
of clean hands as follows:
The doctrine of clean hands is grounded in the historical notion of a
court of equity as a vehicle for affirmatively enforcing the
requirements of conscience and good faith, and thus any willful act
concerning the cause of action which rightfully can be said to
transgress equitable standards of conduct is sufficient cause for
closing the doors of a court of equity to one tainted with
inequitableness. Precision Instrument [Mfg.] Co. v. Auto[.] Maint[.]
Mach[.] Co.[,] 324 U.S. 806 . . . (1945); In re: Est[.] of Pedrick, . . .
482 A.2d 215 ([Pa. ]1984). The clean hands doctrine . . . applies
where the wrongdoing directly affects the relationship subsisting
between the parties and is directly connected to the matter in
controversy. Est[.] of Pedrick.
Giddings, 669 A.2d at 434-35.
Here, the Railroad purported to convey to a third party the property containing the
Blackburn Tunnel, despite the PUC’s refusal to authorize abolition of the tunnel and without
seeking the requisite PUC approval of the conveyance. That wrongful conduct was directly
connected to the controversy presented here. See Giddings, 669 A.2d at 435. Accordingly, the
Railroad lacks clean hands and cannot invoke the doctrine of laches. See Hurwitz, 344 A.3d at
471 (explaining that the city could not invoke the doctrine of laches because it lacked clean hands
15
IV. Conclusion
Based on the foregoing discussion, the PUC Order is affirmed.
__________________________________
CHRISTINE FIZZANO CANNON, Judge
where it failed to seek requisite legal approval before engaging in the conduct that subjected it to
liability).
6
Similarly, even if the Railroad had properly preserved its statute of limitations argument,
we would reject it. Section 3314(a) of the Code sets forth the applicable statute of limitations,
which provides:
No action for the recovery of any penalties or forfeitures incurred
under the provisions of this part, and no prosecutions on account of
any matter or thing mentioned in this part, shall be maintained unless
brought within three years from the date at which the liability
therefor arose, except as otherwise provided in this part.
66 Pa.C.S. § 3314(a). The portion of Section 3314(a) that applies to “action[s] for the recovery of
any penalties or forfeitures,” id., is not implicated here because remediation and abolition are
discretionary regulatory functions, not punitive measures or forfeitures. See City of Phila. v. Pa.
Pub. Util. Comm’n, 676 A.2d 1298, 1301 (Pa. Cmwlth. 1996) (explaining that the imposition of
costs is a discretionary function of the PUC as a matter of regulating public safety).
Regarding any “prosecution” involved in this matter, the Code does not define that term,
and research has not revealed any judicial decisions addressing its applicability to PUC
proceedings. However, to the extent that proceedings alleging failure to maintain railroad
crossings may properly be called “prosecutions” under Section 3314(a), we observe that failures
to maintain railroad crossings are ongoing violations of the Code to which no statute of limitations
has previously been applied. See, e.g., Norfolk S. Ry. Co. v. Pa. Pub. Util. Comm’n, 875 A.2d
1243 (Pa. Cmwlth. 2005) (Norfolk Southern I) (a proceeding for failure to maintain a crossing
under a 1930 order of the PUC’s predecessor, based on the crossing’s deteriorated condition, with
no suggestion that the three-year limitations period barred the PUC’s action); Norfolk S. Ry. Co.
v. Pa. Pub. Util. Comm’n, 971 A.2d 545 (Pa. Cmwlth. 2009) (Norfolk Southern II) (a proceeding
for failure to maintain a retaining wall at a crossing under a 1938 PUC order, with no assertion of
the three-year statute of limitations).
Here, as in Norfolk Southern I and II, the issue is the Railroad’s failure to perform its
maintenance responsibilities. Those responsibilities were ongoing. Thus, there is no statute of
limitations issue.
16
IN THE COMMONWEALTH COURT OF PENNSYLVANIA
Bessemer and Lake Erie :
Railroad Company, :
Petitioner :
:
v. :
:
Pennsylvania Public Utility :
Commission, : No. 965 C.D. 2025
Respondent :
ORDER
AND NOW, this 8th day of September, 2026, the July 10, 2025 Order of the
Public Utility Commission is AFFIRMED.
__________________________________
CHRISTINE FIZZANO CANNON, Judge