Al Ghanim Combined Group W.L.L.
CourtArmed Services Board of Contract Appeals
Date FiledMay 18, 2026
Docket62321, 62984
JudgeHerzfeld
StatusPublished
📰 News Coverage: Read the LAWS.com news report on this case
Full Opinion
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeals of - )
)
Al Ghanim Combined Group W.L.L. ) ASBCA Nos. 62321, 62984
)
Under Contract No. W912ER-14-D-0005 )
APPEARANCE FOR THE APPELLANT: Sam Zalman Gdanski, Esq.
Gdanski Law PC
Teaneck, NJ
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Cara M. Mroczek, Esq.
Ken T Kajihiro, Esq.
Aimee L. Rippeon, Esq.
Engineer Trial Attorneys
U.S. Army Engineer District, Middle East
OPINION BY ADMINISTRATIVE JUDGE HERZFELD
Al Ghanim Combined Group W.L.L. (Al Ghanim) seeks its delay costs from
the United States Army Corps of Engineers (Army Corps) for awaiting the arrival of
security escorts before it could travel to do construction work at two buildings
at Camp Ali Al Salem, Kuwait, in 2018. The parties submitted the appeals on the
record under ASBCA Rule 11. For the reasons discussed below, we sustain
Al Ghanim’s appeal in the amount of $34,320.11, plus applicable Contract Disputes
Act (CDA) interest.
FINDINGS OF FACT
I. The Contract and the Security Escort Process
On November 7, 2013, the Army Corps awarded Al Ghanim an indefinite
delivery/indefinite quantity job order contract (Contract) to perform “sustainment,
restoration, and modernization . . . projects at installations in Kuwait” (62321 R4, tab 3
at 3; 62984 R4, tab 5 at 3). On September 29, 2017, the Army Corps awarded two task
orders to Al Ghanim to perform minor construction and repair work at Camp Ali Al
Salem’s Joint Logistics Operations Center Facility A office (JLOC-A) and Joint
Logistics Operations Center Facility B office (JLOC-B) (62321 R4, tab 12 at 2 (JLOC-
A); 62984 R4, tab 7 at 3 (JLOC-B)). The task orders included a contract completion
date of July 16, 2018 (62321 R4, tab 12 at 3; 62984 R4, tab 7 at 4).
To perform the task orders necessarily required Al Ghanim to work on-site
at Camp Ali Al Salem in Kuwait. The base’s Air Force wing served “as the primary
airlift hub and gateway for delivering combat power to joint and coalition forces in the
U.S. Central Command Area of Responsibility” (supp. R4, tab 28 at 1; tab 29 at 1).
The air base is located approximately 39 miles from the Iraqi border (supp. R4, tab 29
at 1; tab 27).
Before the parties entered the contract, the Air Force’s Commander of the Ninth
Air Force had issued an order requiring military escorts while on base: “All [local
national/other country national] personnel under [United States Air Force] control and
performing contracted services require escort unless the wing commander deems
otherwise” (supp. R4, tab 24 at 3 (Air Force Central Instruction 32-1002); tab 36 –
Lantz decl. ¶ 4). 1 This order – Air Force Central Instruction 32-1002 – applied to “all
Air Force military, civilian, and contracted personnel” of the Ninth Air Force “while
deployed to the” United States Central Command area of responsibility, which
included Camp Ali Al Salem (supp. R4, tab 24 at 3 (Air Force Central Instruction 32-
1002); tab 36 – Lantz decl. ¶ 4). The instruction’s “Commander’s Intent” section
explained that “escorts are needed for [local national], [other country national] and
contract employees in areas containing essential personnel, equipment, or information
that must be protected from sabotage or disclosure to enemy forces” (supp. R4, tab 24
at 3 (Air Force Central Instruction 32-1002)). However, later in the instruction under
the “Personnel Requiring Escort” section, it clarified that it only applied to contracting
personnel: “All [local national/other country national] personnel under USAF control
and performing contracted services require escort unless the wing commander deems
otherwise” (id.). The order also warned service members that “[f]ailure to comply is a
potential violation” of the Uniform Code of Military Justice (id.).
Consistent with the order, the Contract warned that “[a]ll work under this
contract is to be accomplished on secure sites,” which meant “[c]ontractor personnel
and work crews shall be required to be in the presence of Government Escorts at all
times they are on the installations” (62321 R4, tab 3 at 53-54; 62984 R4, tab 5 at 53-
54). The Contract further explained, “Security requirements and restrictions are for
the specific purpose of protecting the security and force protection interests of the
government. Protecting these interests will at all times take precedence over the
accomplishment of the work under this contract.” (62321 R4, tab 3 at 54; 62984 R4,
1
The Army Corps provided a 2021 version of Air Force Instruction 32-1002, but
explained by declaration that this version is “substantively similar” to the
version in effect in 2018 at the time the Al Ghanim escorts at issue took place
(supp. R4, tab 36 – Lantz decl. ¶ 4). Al Ghanim has not disputed these facts.
2
tab 5 at 54) The Contract also warned, “The capacity of the government to provide
Escorts is limited, and subject to unavoidable shortages” (62321 R4, tab 3 at 54; 62984
R4, tab 5 at 54). “Work and work schedule shall be required to be adjusted in
accordance with the Government’s ability to provide Escorts” (62321 R4, tab 3 at 54;
62984 R4, tab 5 at 54).
The Contract set up a process for Al Ghanim to obtain escorts (62321 R4, tab 3
at 54; 62984 R4, tab 5 at 54). The Contract required Al Ghanim to “provide the
Contracting Officer with a twice per week report (in writing) with projections of
manpower to be working on a daily basis . . . . to obtain accurate estimates weekly in
order that the number of Government Escorts can be planned and provided to meet
Contractor work requirements” (62321 R4, tab 3 at 54; 62984 R4, tab 5 at 54). “No
later than 1200 hours each day, Contractor shall provide the Contracting Officer with
an accurate report as to numbers of personnel, crews and crew sizes to be working on
the following work day, and shall confirm that the required escorts will be available”
(62321 R4, tab 3 at 54; 62984 R4, tab 5 at 54).
The Contract indicated that site locations requiring escorts “[m]ost commonly .
. . pertain to U.S. Air Force and they shall provide escorts” (62321 R4, tab 3 at 56;
62984 R4, tab 5 at 56). As anticipated by the Contract, the Air Force conducted the
escorts at Camp Ali Al Salem and required Al Ghanim to submit escort request forms
(app. R11 br., ex. F; supp. R4, tab 30; tab 33 at 50 (Al Ghanim representative
acknowledging Air Force provided escorts)). The escort forms stated: “An escort
request does not guarantee availability” (app. R11 br., ex. F at 147; supp. R4, tab 30).
As part of the bidding process on the Contract, contractors (including
Al Ghanim) had to submit a price based on a coefficient, which meant “a numerical
factor that represents costs not considered to be included in ‘Unit Price Book’ unit
prices” that were provided as an attachment to the Contract (62321 R4, tab 3 at 37, 39;
62984 R4, tab 5 at 37, 39). “Coefficients shall consist of items such as: general and
administrative and other overhead costs, insurance costs, bonding and alternative
payment protection costs, protective clothing, equipment rental, sales tax and
compliance with tax laws and also contractor’s profit, as applicable” (62321 R4, tab 3
at 39; 62984 R4, tab 5 at 39). The Contract also stated, “In formulating his proposal
for the coefficients, Contractor will consider and account for the cost implications
inherent in accomplishment of work on secure installations” (62321 R4, tab 3 at 54;
62984 R4, tab 5 at 54). The Contract specifically stated that it should include all costs
of “complying with security measures including obtaining host nation gate passes,
DBIDS [Defense Biometric Identification System] Registration . . . Local Employed
Personnel (LEP) interviews, processing times through vehicle search area both in and
out of base, and complying with escort policies” as part of the coefficients (62321 R4,
tab 3 at 40; 62984 R4, tab 5 at 40). Al Ghanim’s coefficients factored in all these
security requirements including delays of up to 30 minutes to account for the
3
contractor’s completion of all required on-base processing at the facility and when
government escorts would be available to shepherd the contractor around the base to
conduct work (app. R11 br., Lakshmi aff. ¶¶ 9, 15; 62321 R4, tab 3 at 9-11; 62984 R4,
tab 5 at 9-11).
II. Delays During Performance
Consistent with the Contract, Al Ghanim submitted escort request forms in
advance of days the contractor planned to work (app. R11 br., ex. F). Al Ghanim
usually identified the time it would arrive at the Visitor Control Center and the time
30 minutes later when the Air Force would need to provide the security escort (id.). 2
Air Force enlisted personnel with the force protection unit regularly coordinated with
and approved Al Ghanim’s escort requests, usually stating that the force protection
unit could “accommodate” the escort request (id.; supp. R4, tab 38 – Nichols decl. ¶ 6
(officer noting that he was sometimes copied on escort requests, but he was not part of
the force protection unit). Al Ghanim copied the Army Corps when it submitted its
security escort requests and the Corps’ project manager “actively monitored” the force
protection process in an attempt to avoid or mitigate delays (supp. R4, tab 35 –
Heffern decl. ¶¶ 13-15).
Each day, Al Ghanim personnel and equipment had to present their base access
badges and to pass through the vehicle and contractor security checkpoint at the
Visitor Control Center before joining the security escorts (supp. R4, tab 40 – Yassin
decl. ¶¶ 5-8; tab 35 – Heffern decl. ¶¶ 6-10). The Army Corps’ contracting officer’s
representative agrees with Al Ghanim that this process normally took about 30 minutes
(supp. R4, tab 40 – Yassin decl. ¶ 11). Thus, we find this 30-minute estimate to be
reasonable.
During performance, Al Ghanim notified the contracting officer that it was
encountering weather and government-caused delays for both the JLOC-A and JLOC-
B task orders (supp. R4, tab 7 at 20, 22; 62321 R4, tabs 46, 47, 52; 62984 R4, tabs 40,
51). As to government-caused delays, Al Ghanim explained: “Nearly every time[,]
the escort arrives late at the [Visitor Control Center] to pick up our crew, consequently
our crew reaches late to the site” (62321 R4, tab 49 at 1; 62984 R4, tab 47 at 1). The
government had approved Al Ghanim’s escort requests for a particular time but
frequently did not come at the specified time to escort Al Ghanim’s personnel to the
site (supp. R4, tab 33 – Krishna tr. at 58; app R11 br., ex. F). On its daily quality
2
The record is missing escort request forms for March 10-31, 2018, April 1-2, 4-15,
23-30, 2018, May 1-3, 5-8, 12-15, 2018, for the JLOC-A crew; and March 12-
31, 2018, April 1-2, 5-15, 23-30, 2018, and May 1-3, 5-8, 12-15, 2018, for the
JLOC-B crew (supp. R4, tab 39 – Witherington decl. ¶ 25(f)(v); tabs 39e, 39f
(orange highlighted); app. R11 br., ex. F).
4
control reports, Al Ghanim noted when Al Ghanim’s personnel arrived at the Visitor
Control Center, when the security escort arrived at the Visitor Control Center (for most
days), and when Al Ghanim arrived at the work site that day (app. R11 br., exs. A.4,
A.5). On some days, however, Al Ghanim’s personnel arrived at the Visitor Control
Center later than the agreed-to time (supp. R4 tab 39 – Witherington decl. ¶ 12(k)(v);
tabs 39e & 39f (gray highlighted days); app. R11 br., ex. F; ex. A.4 at 668, 776-78, ex.
A.5 at 135, 460, 568-669).
III. Al Ghanim’s Requests for Equitable Adjustment and Claims Seeking Costs for
Security Escort Delays
On November 18, 2018, Al Ghanim submitted two documents styled as
requests for equitable adjustment seeking time extensions and costs for security escort
and weather delays from January through October 2018 (62321 R4, tab 57; 62984 R4,
tab 3). For JLOC-A, Al Ghanim requested a 41-day time extension and costs of
$206,621.96 (62321 R4, tab 57 at 1). For JLOC-B, Al Ghanim also requested a 41-
day time extension and costs of $206,328.89 (62984 R4, tab 3 at 1). For each day on
which Al Ghanim alleged a delay, Al Ghanim broke its delay costs into four items: (1)
technical staff and manpower costs; (2) equipment costs; (3) indirect extended
overhead costs; and (4) other indirect expenses (62321 R4, tab 57 at 9-368; 62984 R4,
tab 3 at 10-364). Al Ghanim certified each request as required by the Requests for
Equitable Adjustment clause, Defense Federal Acquisition Regulation Supplement
(DFARS) 252.243-7002 (DEC 2012) (62321 R4, tab 57 at 2; 62984 R4, tab 3 at 2;
62321 R4, tab 3 at 23 (Contract incorporating DFARS clause); 62984 R4, tab 5 at 23
(same)).
For the first several months of 2019, representatives from Al Ghanim and the
Army Corps met and attempted to negotiate a resolution to Al Ghanim’s requests for
equitable adjustment (supp. R4, tabs 16, 17; tab 40 – Yassin decl. ¶¶ 13-18). By April
2019, the parties had reached a stalemate. The Army Corps would not award any cost
adjustment for any delays, but recognized escort delays of 12 days (and delays of 22
days due to badging appointments and seven days due to severe weather) (supp. R4,
tab 16 at 2-3; tab 17 at 2-3; tab 40 – Yassin decl. ¶¶ 18, 20-21).
On May 20, 2019 (after the unsuccessful negotiations and while waiting for a
decision on its requests for equitable adjustment), Al Ghanim submitted a combined
document styled as a request for equitable adjustment, reiterating its requests for a 41-
day time extension and $412,950.85 for delays encountered at the Visitor Control
Center while accessing the base between January and October 2018 (62984 R4, tab 56
at 1; 62321 R4, tab 58 at 1). Of the total costs, Al Ghanim again reiterated that it
sought $206,621.96 related to work on JLOC-A and $206,328.89 related to work on
JLOC-B (62984 R4, tab 56 at 1-2, 16-21, 389-94; 62321 R4, tab 58 at 1-2, 16-21, 389-
94). Al Ghanim attached a document labeled as a “draft” titled “Letter Request for
5
Contracting Officer Final Decision (‘COFD’) under the Contract Disputes Act
(‘CDA’)” which Al Ghanim “submitted so that the Government can immediately
review the matter for a mutual and amicable finalization, and . . . . [i]f resolution
cannot be achieved bilaterally, then consider this a ‘Claim’ under the Contract
Disputes Act” (62984 R4, tab 56 at 2; 62321 R4, tab 58 at 2). Al Ghanim included no
certification with this submission, neither as a claim under the CDA nor as a request
for equitable adjustment (62984 R4, tab 56 at 2; 62321 R4, tab 58 at 2). Although
seeking delay costs, Al Ghanim cited the Contract’s Changes clause, which states: “If
any change under this clause causes an increase or decrease in the Contractor’s cost of,
or the time required for, the performance of any part of the work under this contract,
whether or not changed by any such order, the Contracting Officer shall make an
equitable adjustment and modify the contract in writing.” Federal Acquisition
Regulation (FAR) 52.243-4(d) (JUN 2007) (incorporated by reference in Contract,
62321 R4, tab 3 at 22; 62984 R4, tab 5 at 22; 62984 R4, tab 56 at 2; 62321 R4, tab 59
at 2). The Contract also includes a Suspension of Work clause that states:
If the performance of all or any part of the work is, for an
unreasonable period of time, suspended, delayed, or
interrupted (1) by an act of the Contracting Officer in the
administration of this contract, or (2) by the Contracting
Officer’s failure to act within the time specified in this
contract (or within a reasonable time if not specified), an
adjustment shall be made for any increase in the cost of
performance of this contract (excluding profit) necessarily
caused by the unreasonable suspension, delay, or
interruption, and the contract modified in writing
accordingly.
FAR 52.242-14(b) (APR 1984) (incorporated by reference in Contract, 62321 R4,
tab 3 at 22; 62984 R4, tab 5 at 22).
On June 16, 2019, the Army Corps responded to Al Ghanim’s November 2018
requests for equitable adjustment for “entry-related delays to site access due to security
forces being late in providing necessary escorts and delays due to severe weather
conditions” from January through October 2018 (62321 R4, tab 59 at 1; 62984 R4,
tab 57 at 1). The contracting officer recognized that Al Ghanim had shown six days of
severe weather delays and 36 days related to security escort delays (62321 R4, tab 59
at 2; 62984 R4, tab 57 at 2). The agency explained: “The Government’s daily Quality
Control records support [Al Ghanim’s] assertions of escort delays on the days
identified” (62321 R4, tab 59 at 2; 62984 R4, tab 57 at 2). The contracting officer
granted Al Ghanim an “additional two days of time extension for escort delays”
because the “overall impact” was likely greater than just the specific days directly
impacted (62321 R4, tab 59 at 3; 62984 R4, tab 57 at 3).
6
While granting time extensions, the contracting officer refused to award any
costs to Al Ghanim for the delays (62321 R4, tab 59 at 4; 62984 R4, tab 57 at 4). “The
Government has made no change to the contract regarding its weather or escort
requirements, and therefore no change has occurred” (62321 R4, tab 59 at 4; 62984
R4, tab 57 at 4). The contracting officer believed that “both weather and escort delays
are to be considered as excusable, non-compensable delays” under the Contract (62321
R4, tab 59 at 4; 62984 R4, tab 57 at 4). The contracting officer relied on the excusable
delays provision of the Contract’s Default clause, which states a contractor “shall not
be terminated” where the “delay in completing the work arises from unforeseeable
causes beyond the control and without the fault or negligence of the Contractor” such
as “acts of the Government in either its sovereign or contractual capacity” and
“unusually severe weather.” FAR 52.249-10(b)(1)(ii) & (x) (APR 1984) (incorporated
by reference in the Contract, 62321 R4, tab 3 at 23; 62984 R4, tab 5 at 23). The
contracting officer explained, “Default-related events do not entitle [Al Ghanim] to
extended site overhead costs; only the time it was impacted by the events” (62321 R4,
tab 59 at 4; 62984 R4, tab 57 at 4). Thus, the contracting officer denied Al Ghanim’s
request for costs but agreed “to a time extension of 44 days due to excusable, non-
compensable delay” (62321 R4, tab 59 at 4; 62984 R4, tab 57 at 4). While the
contracting officer titled the final section of the letter as the “Final Decision,”
throughout the letter (including in that section) the government was responding to Al
Ghanim’s requests for equitable adjustment (62321 R4, tab 59 at 1, 4; 62984 R4, tab
59 at 1, 4). The contracting officer’s responses to the requests for equitable adjustment
did not include any notice of appeal rights as required by the CDA and FAR
33.211(a)(4)(v).
After issuing the decisions on the requests for equitable adjustment, the Army
Corps unilaterally modified each task order to grant Al Ghanim “a time extension of
44 non compensable days” for weather and security escort delays (62321 R4, tab 16 at
1, 4; 62984 R4, tab 12 at 1; supp. R4, tab 20 at 1; supp. R4, tab 21 at 1). The
modification extended the contract completion date to November 7, 2018 (supp. R4,
tab 20 at 1; tab 21 at 1).
On August 22, 2019, the parties exchanged correspondence indicating an
understanding that the requests for equitable adjustment were still open to discussion
(supp. R4, tab 22). The contracting officer’s representative stated, “We understand
there are open REA for the JLOC projects . . . , but we need to confirm when are you
submitting your final invoices” (supp. R4, tab 22 at 2). Al Ghanim responded to the
contracting officer’s representative and the contracting officer: “[F]or JLOC’s REA,
we will be submitting a reply to the KO’s letter next week. Upon receiving KO’s
reply to our letters, we will notify you with our decision on the submission of the final
payments” (id.). On September 10, 2019, the contracting officer’s representative
requested an update, indicating that the contracting officer had not yet received Al
Ghanim’s letter with the “JLOC closeout invoice” (id.). Later that day the contracting
7
officer stated that “REA Response Letters for JLOC A & B” were “final” and “[t]his
REA is considered closed and we need it close it” [sic] (supp. R4, tab 22 at 1).
The next day, on September 11, 2019, Al Ghanim requested that the contracting
officer issue a final decision under the CDA regarding its JLOC-A claim for delay
costs of $206,621.96 (62321 R4, tab 2 at 1; supp. R4, tab 23 at 2 (email attaching the
letter)). On December 30, 2019, Al Ghanim requested a final decision under the CDA
regarding its JLOC-B claim for delay costs of $206,328.89 (62984 R4, tab 4 at 1, 3).
Responding to the contracting officer’s June 16, 2019 determination, Al Ghanim
argued that there was no sovereign act that justified awarding only a time extension
but not costs due to the delay (62321 R4, tab 2 at 1; 62984 R4, tab 4 at 3). Al Ghanim
also noted its belief that the contracting officer’s response to the request for equitable
adjustment “was apparently not issued as a ‘final decision’” and “[t]hus we do not
believe any jurisdictional requirements had attached for Appeal purposes to the
ASBCA and/or the United States Corps [sic] of Federal Claims” (62321 R4, tab 2 at 1;
62984 R4, tab 4 at 3). Consistent with this understanding, Al Ghanim certified its
claim per the CDA as delineated by the Contract’s Disputes clause (62321 R4, tab 2
at 2; 62321 R4, tab 3 at 22 (Contract incorporating by reference, FAR 52.233-1 Alt. 1,
DISPUTES (DEC 1991)); 62984 R4, tab 4 at 4; 62984 R4, tab 5 at 22).
On October 9, 2019, Al Ghanim sent an email to the Army Corps Area
Engineer (copying the contracting officer) that it still was “waiting” for a response
from the Army Corps regarding its September 11, 2019 certified claim (supp. R4,
tab 23 at 1). In response on the same day (now more than 90 days after the June 2019
request for equitable adjustment decisions), the Army Corps Area Engineer (copying
the contracting officer) asserted that the June 2019 decision “WAS the final decision”
and “[t]here is no other letter coming your way to respond” to the certified claim (id.).
On December 20, 2019, Al Ghanim noticed an appeal to this Board based on a
deemed denial of its claim regarding costs relating to the JLOC-A task order, which
we docketed as ASBCA No. 62321. On July 16, 2021, Al Ghanim noticed an appeal
to this Board based on a deemed denial of its claim regarding costs relating to the
JLOC-B task order, which we docketed as ASBCA No. 62984. We subsequently
granted Al Ghanim’s request to consolidate the appeals. In its complaints, Al Ghanim
stated that the “underlying dispute arises out of delay claims” and the “government
failure to properly sustain its own employees where the government is responsible for
the delay is a ‘constructive change’” (62321 compl. at 1-2; 62984 compl. ¶¶ 1, 7).
IV. The Costs Sought by Al Ghanim on Appeal
Al Ghanim has reduced the amount it seeks for the delay costs because (1) it
determined that several days were the result of weather conditions (for which it seeks
no compensation) rather than delays in arrival of the Air Force security escorts, and (2)
8
it now seeks only its direct costs and no longer seeks any overhead costs (app. R11 br.,
ex. A.1; Lakshmi aff. ¶ 15). Al Ghanim seeks $131,174.88 in delay costs related to its
work at JLOC-A (app. R11 br., ex. A.2 at 6). Al Ghanim seeks $124,056.07 in delay
costs related to its work at JLOC-B (app. R11 br., ex. A.3 at 101).
To support its appeal, Al Ghanim relies on its daily quality control reports, in
which it noted contemporaneously when Al Ghanim’s personnel arrived at the Visitor
Control Center, when the security escort arrived at the Visitor Control Center (for most
days), and when Al Ghanim arrived at the work site that day (app. R11 br., exs. A.4,
A.5). For each of the days of delay, Al Ghanim subtracts 30 minutes as priced into its
daily costs for processing through the Visitor Control Center (app. R11 br., exs. A.2,
A.3). Based on these daily records and subtracting 30 minutes of time each day, Al
Ghanim claims delays of between 10 minutes and four hours on 73 days for JLOC-A
and 71 days for JLOC-B (app. R11 br., exs. A.1-A.3). For each day, Al Ghanim
calculated its total manpower daily rate by using the number and type of employees (as
reflected in the contractor’s daily quality control reports and the government’s quality
assurance reports), hours worked, and an average hourly rate from the labor rates for
each day using the timecards of each employee that worked for Al Ghanim (app. R11
br., ex. A.2 at 7-76; ex. A.3 at 130-73; exs. C & D; exs. A.4-A.5; 62321 R4, tab 69;
62984 R4, tab 68). For each day, Al Ghanim calculated its equipment rate based on
the equipment it used that day (as reflected on the contractor’s quality control reports
and the government’s quality assurance reports) using the “actual values” for the
hourly rates of the equipment identified by name and serial number (app. R11 br.,
ex. A.2 at 77-97; A.3 at 107-24; Lakshmi aff. ¶ 17; app. R11 br., exs. A.4-A.5; 62321
R4, tab 69; 62984 R4, tab 68). Al Ghanim stated that it owned all the equipment used
(app. R11 br., ex. A.1 at 2).
The Army Corps presented evidence analyzing Al Ghanim’s alleged delays
(supp. R4, tab 39). The agency’s cost analyst questioned the reliability and sufficiency
of Al Ghanim’s documentation to support its labor rates because Al Ghanim “did not
provide certified payroll information” in addition to the daily timecards (supp. R4,
tab 39 – Witherington decl. ¶ 27(f)). Nevertheless, the cost analyst concluded that “the
number and type of direct laborers claimed in the New Documentation was mostly
supported by the Working Cards, but there were a small number of discrepancies
where [Al Ghanim] either slightly overreported or underreported the number of
laborers” (supp. R4, tab 39 – Witherington decl. ¶ 27(g)).
The agency’s cost analyst also questioned the equipment rates because
Al Ghanim allegedly failed to include information regarding the “equipment’s year
purchased, make, model, tire type, and engine type” that would allow confirmation of
“industry standard active and standby rates” (supp. R4, tab 39 – Witherington decl.
¶ 27(d)(iii)). The analyst asserted that the equipment should be billed at a standby or
idle rate “because it is not actively being operated and used,” during the delay, which
9
would result in a “lower hourly rate based on use and equipment depreciation,” but it
“appear[ed]” that Al Ghanim used its “active rate for all equipment” (supp. R4, tab 39
– Witherington decl. ¶¶ 27(d)(i) & (ii)).
Despite questioning the labor and equipment documentation, the cost analyst
nevertheless used Al Ghanim’s cost information in assessing the delay costs (supp. R4,
tab 39 – Witherington decl. ¶¶ 25(a)-(b)). The cost analyst reviewed Al Ghanim’s cost
and supporting documentation and re-calculated Al Ghanim’s delay costs (id.). First,
the cost analyst determined that Al Ghanim “provided no justification . . . as to why
[Al Ghanim] included additional time past the escorts’ arrival” at the Visitor Control
Center, so any travel time from the Visitor Control Center to the site was eliminated
from his calculation of recoverable delay costs (id. ¶ 27(a); tabs 39g-39h). Second, the
cost analyst removed any days where Al Ghanim provided no supporting
documentation (such as quality control reports or approved security escort request
forms) to prove when the security escorts arrived or were supposed to arrive at the site
(supp. R4, tab 39 – Witherington decl. ¶¶ 25(f)(i)-(ii) & (v); tabs 39e & 39f (red and
orange highlights)). Third, the cost analyst removed any days where adverse weather
caused work stoppages or Al Ghanim encountered wet site conditions (supp. R4, tab
39 – Witherington decl. ¶¶ 25(f)(iii) & (iv); tabs 39e & 39f (blue and yellow
highlights)).
For the remaining days, the cost analyst calculated the delays from the time
when Al Ghanim arrived at the Visitor Control Center (whether on-time or late)
through when the security escorts arrived at the Visitor Control Center (subtracting out
30 minutes for Al Ghanim’s processing through security at the center) (supp. R4,
tab 39 – Witherington decl. ¶ 29, tabs 39e-39h). The cost analyst then multiplied the
delay time for each day with Al Ghanim’s equipment and personnel costs for the day
(supp. R4, tab 39 – Witherington decl. ¶ 29; tabs 39g & 39h). The cost analyst
concluded that Al Ghanim should recover for 31.14 hours of delay and $17,940 for
JLOC-A, and 26.7 hours of delay and $14,936 for JLOC-B (supp. R4, tab 39 –
Witherington decl. ¶ 29; tabs 39g & 39h). In total, the cost analyst concluded that Al
Ghanim would be entitled to $32,876 in compensable delays for both JLOC-A and
JLOC-B (supp. R4, tab 39 – Witherington decl. ¶ 29; tabs 39g & 39h).
The government initially moved for summary judgment on its sovereign acts
defense and the parties briefed the matter. The parties then requested that the entire
appeal be submitted on the record under ASBCA Rule 11, including agreeing to treat
the summary judgment briefing of the sovereign acts defense under the same standard
of review as Rule 11 instead of the summary judgment standard of review.
10
DECISION
I. Standard of Review
Board Rule 11 allows the parties to waive a hearing and submit an appeal on
the record. Board Rule 11(a); Consorzio Stabile GMG S.c.ar.l., ASBCA No. 62753,
23-1 BCA ¶ 38,347 at 186,213. Under Board Rule 11, we conduct a “trial on the
record;” we may weigh evidence, including resolving any disputed facts in making our
findings of fact and rendering our decision. D-STAR Eng’g Corp., ASBCA
Nos. 62075, 62780, 25-1 BCA ¶ 38,816 at 188,819, 188,826. We conduct a de novo
review without deference to the contracting officer’s final decisions. Dep’t of Transp.
v. Eagle Peak Rock & Paving, Inc., 69 F.4th 1367, 1374-76 (Fed. Cir. 2023);
41 U.S.C. § 7103(e); ASBCA Rule 10(c), (d).
Al Ghanim, as the proponent of the claims, bears the burden of proof.
FlightSafety Int’l, Inc., ASBCA No. 62659, 23-1 BCA ¶ 38,245 at 185,709, aff'd, 130
F.4th 926 (Fed. Cir. 2025). The Army Corps bears the burden of proving its
affirmative defense invoking the sovereign acts doctrine. Conner Bros. Constr. Co. v.
Geren, 550 F.3d 1368, 1371 (Fed. Cir. 2008) (“The doctrine is an affirmative defense
that is an inherent part of every government contract.”); Frazier Invs., Inc., ASBCA
No. 63001, 23-1 BCA ¶ 38,313 at 186,042 (“As the proponent of any affirmative
defense, the [government] bears the burden of proof.”).
II. Jurisdiction – Al Ghanim Timely Appealed
Neither party has challenged our jurisdiction to consider Al Ghanim’s appeals
but based on our review of the record we are obligated to raise the issue of timeliness
sua sponte to assure that the Board has jurisdiction. White Balad Co., ASBCA
No. 62934, 22-1 BCA ¶ 38,056 at 184,786. We must assess whether the Army Corps’
June 2019 determinations regarding Al Ghanim’s requests for equitable adjustment
triggered the running of the 90-day statute of limitations for bringing appeals to the
Board, which is jurisdictional and may not be waived. 41 U.S.C. § 7104(a) (“A
contractor, within 90 days from the date of receipt of a contracting officer’s decision
under section 7103 of this title, may appeal the decision to an agency board as
provided in section 7105 of this title.”); Kellogg Brown & Root Servs., Inc., ASBCA
No. 62681 et al., 22-1 BCA ¶ 37,974 at 184,426 (“The 90-day limitation is
jurisdictional and, thus, may not be waived.”). We conclude that Al Ghanim’s appeals
were timely because the agency did not treat the determinations as final and
prejudicially failed to include the required appeal rights in its June 2019
determinations.
Al Ghanim labeled its November 2018 submissions as requests for equitable
adjustments (62321 R4, tab 57; 62984 R4, tab 3). However, the Federal Circuit has
11
instructed that labels are not dispositive as to whether a submission is a request for
equitable adjustment or a claim. Zafer Constr. Co. v. United States, 40 F.4th 1365,
1367-68 (Fed. Cir. 2022); Hejran Hejrat Co. v. United States Army Corps of Eng’rs,
930 F.3d 1354, 1357 (Fed. Cir. 2019). We look to three objective criteria to assess
whether a submission is a claim rather than a request for equitable adjustment: (1) the
submission must meet the definition of a “claim” as defined by the Disputes clause in
a contract (and FAR); (2) the submission includes a CDA certification (or some type
of sworn statement that can be perfected into a CDA certification); and (3) the
contractor must request a final decision from the contracting officer. Mindseeker, Inc.,
ASBCA No. 63197, 24-1 BCA ¶ 38,666 at 187,960 (citing Zafer Constr., 40 F.4th
at 1367-68).
First, Al Ghanim’s November 2018 submissions met the definition of a
monetary “claim” under the CDA – “a written demand or written assertion by one of
the contracting parties seeking, as a matter of right, the payment of money in a sum
certain . . . arising under or relating to this contract.” FAR 52.233-1(c) (incorporated
by reference in the Contract, 62321 R4, tab 3 at 22; 62984 R4, tab 5 at 22); Zafer
Constr., 40 F.4th at 1367 (recognizing that the FAR definition of a claim governs the
use of the term under the CDA).
Second, the November 2018 submissions included a certification per the
Contract’s Requests for Equitable Adjustment clause (not under the CDA) (62321 R4,
tab 57 at 2; 62984 R4, tab 3 at 2). DFARS 252.243-7002 (incorporated by reference in
Contract, 62321 R4, tab 3 at 23; 62984 R4, tab 5 at 23 (same)). That is some evidence
that Al Ghanim meant the submissions to be requests for equitable adjustment, but it is
not dispositive to whether the document constituted a certified claim because any
defective certification can be perfected into a CDA certification by statute. BAE Sys.
Ordnance Sys., Inc., ASBCA No. 62416, 21-1 BCA ¶ 37,800 at 183,578 (noting “that
the use of the REA certification [does] not prevent a submission from being a valid
claim since the REA certification, notwithstanding its limitations, could be considered
a defective, but curable CDA certification”); 41 U.S.C. § 7103(b)(3) (“A defect in the
certification of a claim does not deprive a court or an agency board of jurisdiction over
the claim.”).
Third, Al Ghanim requested a final decision from the contracting officer.
During the parties’ negotiations they treated the submission as a request for equitable
adjustment (supp. R4, tabs 16, 17; tab 40 – Yassin decl. ¶¶ 13-18). However, after
negotiations broke down, Al Ghanim’s May 2019 submission included a “draft”
document titled “Letter Request for Contracting Officer Final Decision (‘COFD’)
under the Contract Disputes Act (‘CDA’)” and requesting “that the Government can
immediately review the matter for a mutual and amicable finalization, and . . . . [i]f
resolution cannot be achieved bilaterally, then consider this a ‘Claim’ under the
Contract Disputes Act” (62984 R4, tab 56 at 2; 62321 R4, tab 58 at 2). Thus, Al
12
Ghanim’s May 2019 submission (although lacking any certification) met the third
requirement for a claim: making a request for a final decision from the contracting
officer and we hold that, at that point, the requests for equitable adjustment were
definitively a CDA claim.
Given the circumstances above, the contracting officer’s June 2019
determinations could be considered final decisions under the CDA, triggering the 90-
day statute of limitations for filing an appeal before the Board. Here, nevertheless, Al
Ghanim reasonably believed that there was no final decision on a claim for it to
appeal, and in such circumstances, the appeal clock does not run. See Guardian
Angels Medical Service Dogs, Inc. v. United States, 809 F.3d 1244, 1250-51 (Fed. Cir.
2016). As discussed above, the June 16, 2019 responses from the contracting officer
constituted final decisions on the requests for equitable adjustments that we have
found to meet the definition of “claims.” But they were followed immediately by
discussion between the Army Corps and Al Ghanim revisiting the issues in the
requests for equitable adjustment and treating them as “open” (supp. R4, tab 22 at 2).
Such discussions after the issuance of a final decision “serve to vacate the earlier
decision along with the accompanying appeal period,” because they demonstrate that
the decision is non-final. Guardian Angels, 809 F.3d at 1250 (quoting Royal Int’l
Builders Co., ASBCA No. 42637, 92-1 BCA ¶ 24,684 at 123,135 (emphasis omitted));
BR Grp., ASBCA No. 63507, 24-1 BCA ¶ 38,699 at 188,158 (finding an appeal timely
where agency indicated reconsideration of the final decision “was at least a
possibility”). Thus, the government’s participation in additional talks make the June
16, 2019 decisions non-final (and the indicia of non-finality is strengthened by the
contracting officer’s failure to include the statutorily-required notice of appeal rights in
the June 16 decisions, as discussed below).
Moreover, the contracting officer’s email on September 10, 2019 – stating that
the June decisions were “final,” and that “this REA is considered closed and we need
to close it” – did not reset the final decision date back to June 16, 2019 (supp. R4,
tab 22 at 1). The Army Corps’ “after-the-fact” characterizations do not change the
effects of its prior actions, which kept the requests for equitable adjustment open.
Guardian Angels, 809 F.3d at 1250.
Nor did the September 10, 2019 email reset the appellate clock. Even if we
considered the September 10, 2019 email to nominally meet the criteria for a new final
decision on a “claim,” the Army Corps’ failure to include the statutorily-required
appeal rights prevented the appeal clock from running, because of actual prejudice to
Al Ghanim. In particular, the CDA requires that the contracting officer “issue a
decision in writing,” provide it by mail or otherwise to the contractor, 41 U.S.C. §
7103(d), and “state the reasons for the decision reached and shall inform the contractor
of the contractor’s rights as provided in this chapter.”