Full Opinion

NOTICE: NOT FOR OFFICIAL PUBLICATION. UNDER ARIZONA RULE OF THE SUPREME COURT 111(c), THIS DECISION IS NOT PRECEDENTIAL AND MAY BE CITED ONLY AS AUTHORIZED BY RULE. IN THE ARIZONA COURT OF APPEALS DIVISION ONE BERT MARTINEZ, Plaintiff/Appellant, v. FIRST UNITED METHODIST CHURCH OF GLENDALE, Defendant/Appellee. No. 1 CA-CV 26-0250 FILED 11-27-2026 Appeal from the Superior Court in Maricopa County No. CV2025-023240 The Honorable Gregory Como, Judge AFFIRMED COUNSEL Bert Martinez, Gilbert Plaintiff/Appellant Pro Se Clarke Law Firm PLC, Scottsdale By Marilee Miller Clarke, Brayden Harn Counsel for Defendant/Appellee MARTINEZ v. FIRST UNITED Decision of the Court MEMORANDUM DECISION Chief Judge Randall M. Howe delivered the decision of the Court, in which Presiding Judge Andrew M. Jacobs and Judge Daniel J. Kiley joined. H O W E, Judge: ¶1 Bert Martinez appeals the superior court’s grant of summary judgment for First United Methodist Church. We affirm. FACTS AND PROCEDURAL BACKGROUND ¶2 We view the facts in the light most favorable to the non- moving party. Mirchandani v. BMO Harris Bank, N.A., 235 Ariz. 68, 69 ¶ 2 (App. 2014). In 2016, First United leased a solar panel system from “Clean Energy Systems” for a twelve-year term. In 2025, Martinez sued First United for breach of contract and unjust enrichment, claiming that it failed to make payments on that solar lease. In doing so, he noted that “Celan [sic] Energy was the original lessor,” who then transferred the lease to “Solar Covered Parking Systems,” who then assigned the lease to him. But he claimed that “[s]ection 44-1763 does not require the lessor or assignee to hold a contractor’s license to collect lease payments.” First United denied most of his allegations and counterclaimed, confirming that it entered a solar lease with “Clean Energy Systems,” who then assigned the lease agreement to “Solar Covered Parking Systems,” who then assigned the lease to Martinez, all without First United’s knowledge. It also alleged that the assignments were improper, that Solar Covered Parking Systems and Martinez were “unlicensed and unqualified,” and that Solar Covered Parking Systems and Martinez failed to “perform [the] ongoing maintenance and service obligations.” ¶3 Both parties moved for summary judgment. First United argued that Martinez failed to notify it of the assignment of the solar lease and that he admitted his company “has never held a contractor’s license” that the law required. The court held a hearing on the motions. It found Martinez’s claims “barred by A.R.S. § 32-1153,” which prevents claims for compensation for “any act for which a license is required,” “without alleging and proving that the contracting party whose contract gives rise to the claim was a duly licensed contractor when the contract sued upon was 2 MARTINEZ v. FIRST UNITED Decision of the Court entered into and when the alleged cause of action arose.” Though the court noted that, regardless of Martinez’s licensure status, he could maintain an action if “the original Lessors were licensed when the cause of action accrued,” it found that “no evidence was presented by either party regarding whether the original Lessors remained licensed in June 2024, when the cause of action accrued due to [First United]’s failure to make the monthly lease payments.” Thus, it denied Martinez’s motion for summary judgment and granted First United’s. ¶4 Martinez moved for reconsideration “based on [a] change of circumstances” alleging that Solar Covered Parking Systems was “now” a licensed contractor. The court denied his motion, explaining that (1) Solar Covered Parking Systems was not the original lessor, and so Martinez had to prove Clean Energy Systems was licensed at the time the cause of action arose, and (2) even if Solar Covered Parking Systems were the original lessor, Martinez would have to show they were licensed at the time the cause of action arose, not “now” as his motion alleged. ¶5 The court awarded attorney’s fees and costs to First United and issued a judgment under Arizona Rule of Civil Procedure 54(c). Martinez appealed and we have jurisdiction. A.R.S. § 12-2101(A)(1). DISCUSSION ¶6 Martinez argues that the court erred in granting summary judgment and should not have applied A.R.S. § 32-1153 but rather “A.R.S. §§ 44-1761 through 44-1763, which regulate distributed energy generation system leases and recurring payment obligations.” “We review the entry of summary judgment de novo, viewing the facts in the light most favorable to the nonmoving party.” Dinsmoor v. City of Phoenix, 251 Ariz. 370, 373 ¶ 13 (2021). A court shall grant summary judgment when “there is no genuine dispute as to any material fact and the moving party is entitled to judgment as a matter of law.” Ariz. R. Civ. P. 56(a). ¶7 Martinez argues that his claim is for “payment enforcement, not construction activity” and that A.R.S. § 32-1153 applies only “where a party performs construction labor, supplies materials, or engages in regulated contracting activity.” Not so. Section 32-1153 applies anytime a “contractor” seeks to “commence or maintain any action in any court of the state for collection of compensation for the performance of any act for which a license is required. A “contractor” is any party who “for compensation, undertakes to or offers to undertake . . . [c]onstruct[ion], alter[ation], repair[s]” of any building or other structure or “[p]rovide[s] mechanical or 3 MARTINEZ v. FIRST UNITED Decision of the Court structural service” for any “structure or improvements.” A.R.S. § 32- 1101(3)(a)(i), (iii). The lease contained ongoing repair and maintenance obligations for the lessor, whom Martinez alleged assigned its entire interest to him. Although he claims his dispute did not concern “repair work,” the lease confirms otherwise. And A.R.S. § 44-1763—which Martinez argues should govern his matter—also assumes the lessor to be a “contractor.” See A.R.S. § 44-1763 (F) (“Before entering into a contract for the purchase or lease of a residential solar energy system, the licensed contractor shall . . . .”(emphasis added)). Thus, he was a contractor for the purposes of A.R.S. § 32-1153. ¶8 Martinez argues A.R.S. §§ 44-1761–1763, not A.R.S. § 32-1153 should apply. He argued to the superior court that “[s]ection 44-1763 does not require the lessor or assignee to hold a contractor’s license to collect lease payments.” But a contract can be subject to more than one statute, and, even assuming the truth of his claim that Title 44 does not require him to hold a contractor’s license to “collect lease payments,” he still may not “commence or maintain” a legal action “for collection of compensation” without meeting the requirements of A.R.S. § 32-1153. As a threshold matter, Martinez must still show that the “contracting party,” Clean Energy Systems, was licensed at the time his cause of action allegedly accrued. A.R.S. § 32-1153. He claimed that he did not need a license, but he was not the “contracting party.” He then claimed that Solar Covered Parking Systems became licensed, but it was also not the “contracting party.” Nor did he claim that Solar Covered Parking Systems was licensed “when the alleged cause of action arose.” A.R.S. § 32-1153. To succeed, Martinez had to present evidence that Clean Energy Systems was a licensed contractor at the time his cause of action allegedly accrued. A.R.S. § 32-1153. He presented no evidence of that. Therefore, the court did not err in awarding First United summary judgment. See Ariz. R. Civ. P. 56(a). ¶9 Finally, Martinez argues that the superior court erred in awarding attorney’s fees because it “resolved the dispute under statutory grounds rather than through adjudication of contract liability.” Section 12- 341.01 provides that “[i]n any contested action arising out of a contract, express or implied, the court may award the successful party reasonable attorney fees.” Martinez’s claim was for “breach of contract.” Thus, his claim arose out of a contract. The court did not err in awarding attorney’s fees under A.R.S. § 12-341.01. On appeal, First United “requests its reasonable attorneys’ fees and taxable costs incurred on appeal under A.R.S. §§ 12-341, 12-341.01, 12-342, and ARCAP 21.” We decline to award attorney’s fees, but award First United its costs on appeal upon compliance with Arizona Rule of Civil Appellate Procedure 21. See A.R.S. § 12-341. 4 MARTINEZ v. FIRST UNITED Decision of the Court CONCLUSION ¶10 For these reasons, we affirm. MATTHEW J. MARTIN • Clerk of the Court FILED: JR 5