Hopper Resources, Inc. v. Webster
HOPPER RESOURCES, INC., Construction Division, Appellant, v. Wendell WEBSTER, Appellee
Attorneys
Robert R. Faulkner, Evansville, IN, Attorney for Appellant.
Full Opinion (html_with_citations)
*420 OPINION
STATEMENT OF THE CASE
Hopper Resources, Inc., Construction Division (âHopperâ), appeals the trial courtâs order denying judgment to Hopper on its claim asserted against Wendell Webster in a complaint seeking the foreclosure of a mechanicâs lien and additional damages.
We affirm.
ISSUE
Whether the trial court erred in denying judgment to Hopper.
FACTS
John Shamo is a geologist and president of Hopper Resources, Inc., which undertakes construction projects through its Construction Division. Shamo learned that Wendell Webster wanted to have an addition built on his home. After meeting with Webster, Shamo presented Webster with a proposal dated September 27, 2003, from âHopper Construction, Inc., A Division of Hopper Resources, Inc.,â as âContractor,â to âfurnish all equipment, material and labor necessaryâ to add a finished bathroom, pour a concrete patio adjoining the finished bathroom and the back of Websterâs house, and extend the house roof over both. (Ex. 7). The total cost for the proposed work was $15,900.00. The proposal was signed by Shamo, as President; and reflects that on October 8, 2003, Webster signed his âacceptance of proposalâ and âauthorizedâ Hopper âto do the work as specified.â Id. Webster gave Sha-mo $8,000.00 as a down payment.
Hopper directed John Claspell, Tony Dorris, and James Clark to perform the contracted project at Websterâs home. âHalf way [sic] through the project, Mr. Webster requested that the room [added for the bathroom] be divided and an exterior bathroom accessâ be installed, such that the addition would also contain a half-bath that could be reached from the newly poured adjoining patio. (Tr. 29). An âaddendumâ from Hopper, dated November 3, 2003, proposed to âfurnish all equipment, materials and labor necessary toâ add a wall, and install and finish the requested half-bath for an additional cost of $2,100.00. (Ex. 11). Webster signed his acceptance on November 5, 2003.
Sometime thereafter, Shamo learned that there had been no building permit obtained for the work being done at Websterâs home. On November 25, 2003, Sha-mo went to the Building Commission office and obtained an Improvement Location Permit for the addition of a bathroom and a porch to Websterâs residence. Shamo completed a âHomeowner Affidavitâ stating that âWendel [sic] Websterâ thereby swore that âeither [he] or a member of [his] immediate familyâ would âperform the ... workâ of adding the room and porch at his residence, âfor which Building Permit # 106771Eâ was being issued, and that he would not be âsubcontracting out any of the workâ thereon. (Ex. A). Sha-mo signed Websterâs name on the affidavit. The Commission then issued to âapplicant Wendel [sic] Websterâ building permit # 106771E authorizing the âbathroom & porch additionâ at Websterâs residence. (Ex. 10). The permit in Websterâs name for the work at the residence was thereafter posted on the site.
The Hopper workers proceeded to complete most of the work specified in the contracts. According to John Claspell, on March 10, 2004 (Shamo believed it was at a later date in March but could not identify an exact date), he and other Hopper workers went to the Webster home to install a vapor barrier and pea gravel under the *421 addition as ordered by âCode Enforcementâ to âbring everything into [C]ode (Tr. 32, 25). Claspell testified that the workers were told that Webster wanted them off the property and not to return.
On April 19, 2004, Shamo sent Webster an invoice from Hopper demanding $7,500.00 in payment for the work completed. On May 13, 2004, Shamo signed and recorded a notice asserting Hopperâs entitlement to a lien of $7,500.00 for Hopperâs âlabor or ... materials or machinery for improvements toâ Websterâs property, and that Hopper âperformed labor on the 23rd day of March, 2004.â (Ex. 15).
On October 19, 2004, Hopper filed a complaint on mechanicâs lien, asserting that Webster had refused to pay $7,500.00 for home improvements and seeking judgment of foreclosure of the mechanicâs lien in the amount of $7,500.00, plus pre-judgment interest, attorney fees, and costs. On December 9, 2004, Webster filed an answer that also asserted the affirmative defense of âfraud.â (App.14). On August 31, 2005, Webster filed a counter-claim, asserting Hopperâs breach of contract â by performing âunworkmanlikeâ and âinferi- orâ work that âneed[ed] to be razedâ and rebuilt. (App.16). On September 8, 2005, Hopper filed a motion to strike both Websterâs counterclaim and affirmative defense. Hopper asserted that the counterclaim was untimely, and was filed without leave of the court; and that the affirmative defense failed to comply with Indiana Trial Rule 9(B)âs requirement that the circumstances constituting fraud be specifically pled. On January 13, 2006, the trial court ruled that Webster would be allowed to file a more specific pleading of his affirmative defense. On January 24, 2006, Webster filed a more specific affirmative defense, asserting that Hopper had âheld [itjself out to be a licensed and bonded contractor,â that Hopper obtained a building permit by âpullfing] a homeownerâs permitâ and âforg[ing] [Webster]âs name on the homeownerâs affidavit,â and that Hopper was ânot a licensed and bonded contractor and his [sic] forging of [Webster]âs name on an affidavit constituted fraud.â (App.24).
At the outset of trial on February 8, 2007, the motion to strike Websterâs counterclaim was discussed. The trial court ruled that the late filed counterclaim was denied and stated, â[T]here is no Counterclaim.â (Tr. 58). Hopper then presented its case, with Claspell and Shamo as the only witnesses. Webster did not call witnesses but did introduce as an exhibit the Homeowner Affidavit (during its cross examination of Shamo). On May 9, 2007, the trial court issued its judgment order, which includes sua sponte findings and conclusions. Therein, the trial court found inter alia that âa lawful permit was a necessary condition precedent toâ Hopperâs performance of work âand any recovery for the value thereofâ; that because Hopper âhad no legal permit to perform the workâ on Websterâs residence, Webster âwas justified in refusing to allowâ Hopperâs workers âto return to the job site and perform any further illegal operationsâ; and that Hopper could ânot benefit from its/his own wrongdoing.â (App.37). The trial court concluded that Hopper was not âentitled to recover any further compensatory damagesâ and entered âfinal judgment against [Hopper] on [Hopper]âs claim.â Id.
DECISION
We note at the outset, that Webster has not filed a brief in response to Hopperâs appeal. When the appellee does not file a brief, the âappellant may prevail by establishing a prima facie case of error.â Trinity Homes, LLC v. Fang, 848 N.E.2d 1065, 1068 (Ind.2006). Prima facie *422 error in this context is defined as, âat first sight, on first appearance, or on the face of it.â Id.
The standard for the appellate review of claims tried to the bench provides that the reviewing court shall not set aside the judgment unless clearly erroneous, and due regard shall be given to the opportunity of the trial court to judge the credibility of the witnesses. Bennett v. Broderick 858 N.E.2d 1044, 1047 (Ind.Ct.App.2006), trans. denied. In determining whether a judgment is clearly erroneous, we will not reweigh the evidence or determine the credibility of witnesses but will consider only the evidence that supports the judgment and the reasonable inferences to be drawn from that evidence. Id. at 1048. Here, Hopper bore the burden of proof on its complaint at trial and did not prevail; therefore, it appeals from a negative judgment. Id. When a party appeals from a negative judgment, it must demonstrate that the evidence points unerringly to a conclusion different from that reached by the trial court. Id. Further, when the trial court enters findings of fact and conclusions of law under Indiana Trial Rule 52(A), the reviewing court may only reverse if the findings or conclusions are clearly erroneous. Butterfield v. Constantine, 864 N.E.2d 414, 417 (Ind.Ct.App.2007). The trial courtâs judgment is clearly erroneous only if its findings of fact do not support its conclusions or its conclusions do not support its judgment. Id. However, when, as here, the trial court enters findings sua sponte, the specific findings control only the issues they cover, while a general judgment standard applies to any issue not found by the court. Id.
We begin with the observation that Hopperâs action â which was styled âComplaint to Foreclose Mechanicâs Lien,â (App.9)â sought relief in equity. See Brighton v. White, 128 Ind. 320, 27 N.E. 620, 621 (Ind.1891) (âwhere a lien upon real estate is to be foreclosed the equity power of the court is called into exerciseâ). Hence, we begin by citing some âmaxims of equity.â 121.L.E. Equity (2001).
First, âone who comes into equity must come with clean handsâ; a principle that denies ârelief to one whose conduct concerning the matter in controversy has been fraudulent, illegal, or unconscionableâ as to another such that the other party is harmed. Id. at § 24; see also Traylor v. By-Pass 46 Steak House, Inc., 259 Ind. 224, 285 N.E.2d 820, 822 (1972) (citing Ferguson v. Boyd, 169 Ind. 537, 81 N.E. 71 (1907)). In application, this principle âmeans that one who seeks relief in a court of equity must be free of wrongdoing in the matter before the court.â Community Care Centers, Inc. v. Sullivan, 701 N.E.2d 1234, 1242 (Ind.Ct.App.1998), trans. denied.
Another maxim provides that âwhomever seeks equity must do equityâ; a principle whereby ârelief which involves perpetration of an injustice will be denied.â 12 I.L.E. Equity § 25. Thus, âhe who would invoke the aid of a court of equity âmust show that he has done equity to him of whom he complains.â â Shaw v. Meyer-Kiser Bank, 199 Ind. 687, 156 N.E. 552, 554 (1927) (citations omitted).
Yet another maxim provides that âequity follows the law,â 12 I.L.E. Equity § 22. In application, this means that âan equitable right cannot be founded on a violation of law.â Noble v. Davison, 177 Ind. 19, 96 N.E. 325, 330 (1911).
The trial court found Hopper âobtained the requisite building permit by applying for and obtaining a homeownerâs permitâ; that the application therefor was a âHomeownerâs Affidavitâ on which Shamo signed Websterâs name as homeowner; and this affidavit led to the Building Commission *423 erâs issuance of âthe requisite permit for performing the work in question.â (App.36, 37). The trial court concluded that a âlawful permit was a condition precedentâ to Hopperâs âperformance of work and any recovery for the value thereofâ; that Hopper could ânot benefit from its/his own wrongdoingâ; and that Hopper âhad no valid permit to perform the work in question.â (App.36, 37).
Hopper did not introduce into evidence, and in its arguments to the trial court it did not reference, the requirements of the Evansville Zoning Ordinance concerning building permits. However, the contents of the exhibits introduced support the inference that a building permit is a prerequisite for work such as the addition to Websterâs house, and that only a homeowner may obtain a permit based on a Homeownerâs Affidavit. 1 The Affidavit states that the homeowner or an immediate family member will perform the work on the residence in which the homeowner resides. The Affidavit also includes a requirement that the homeowner disclose the âsubcontracting out of any work outlined in the permit issued to [the homeowner],â and further states in bold print that âall subcontractors must be licensed in Vanderburgh County.â (Ex. A). Moreover, Shamo admitted that he was the person who went to the Building Commission office and signed Websterâs name on the Homeowner Affidavit.
Thus, the evidence supports the trial courtâs findings that a building permit was necessary to perform the work, that the permit obtained was one issued based on a Homeowner Affidavit signed by Shamoâ not Webster, the homeowner. Accordingly, the trial courtâs conclusion that Hopper had no valid permit to perform the work on Websterâs residence is supported by the findings. Moreover, given that Hopperâs complaint sought relief based on the trial courtâs equity jurisdiction, and the trial courtâs express conclusion that Hopper could not profit from its own wrongdoing, the trial courtâs judgment denying relief to Hopper is not clearly erroneous.
Hopper presents a series of challenges to the trial court judgment, but all seek to persuade us to reverse the trial courtâs judgment and remand for judgment in favor of Hopper on its claim to foreclose mechanicâs lien or breach of contract. However, we find those arguments unavailing.
Hopper argues that the trial court committed reversible error âin failing to apply an adverse inference against Webster based upon his failure to testify and failure to call any witnesses.â Hopperâs Br. at 9. However, Hopper presents no authority for the proposition that such shifts the burden of proof. As the plaintiff, Hopper bore the burden of proof: to establish its claim by a preponderance of the evidence. The trial court concluded that it had failed to satisfy its burden, and we agree.
Hopper next argues that the evidence does not support the trial courtâs âconclusion that the work was being performed illegality [sic],â and that even if that were so, recovery may be had. Id. We have already found that the evidence supports the trial courtâs findings and conclusion that the addition to Websterâs house required a building permit, and that the permit Shamo obtained for Hopper was not a valid permit, ie., the work was being performed illegally. Hopper cites Phend v. Midwest Engineering and Equip. Co., 93 Ind.App. 165, 177 N.E. 879 (1931), and *424 Drost v. Professional Bldg. Serv. Corp., 153 Ind.App. 273, 286 N.E.2d 846 (1972), for the proposition that there may be recovery on a contract performed in a manner not allowed by law. However, such authority does not establish error by the trial court here, where the matter is within equity jurisdiction and the facts establish the failure of Hopperâs actions to meet the standards of equity.
Hopper cites Greenhaven Corp. v. Hutchcraft & Assocs., Inc., 463 N.E.2d 283 (Ind.Ct.App.1984), for the proposition that recovery may be had on a contract containing specifics not in compliance with local building codes. However, in Green-haven, the parties had agreed as to the nonconforming code matter. There was no evidence that Webster agreed that the construction need not meet Code requirements.
Throughout its brief, Hopper argues that Shamoâs signature of Websterâs name was with Websterâs acquiescence and at Websterâs request. However, the credibility of witnesses is a matter for the trial court. See Bennett, 858 N.E.2d at 1048. Further, the validity of the Homeowner Affidavit rests on its execution in compliance with its own terms, ie., that it is executed by âthe [ojwnerâ of the residence to be improved. (Ex. A). Finally, we have found that if parties bear âequal faultâ in an âillegal contract,â such as Sha-mo and Webster agreeing that Shamo would sign an affidavit which not only stated on its face that it was being signed by Webster but also that Webster would perform work that had been contracted to be performed by Hopper, âjustice would require that we left the parties where we found them, even where [the one party] had fully performed.â Monsignor Bernard P. Sheridan Counsel No. 6138 Knights of Columbus v. Bargersville State Bank, 620 N.E.2d 732, 735 n. 2 (Ind.Ct.App.1993). This result is exactly that obtained by the trial courtâs judgment here. .
Hopper also argues that the trial court erred in finding that Hopper could not recover under the contract âbased upon the principle of illegalityâ because Webster failed to expressly plead âillegalityâ as an affirmative defense. Hopperâs Br. at 16. We again return to the fact that by the nature of its complaint, Hopper sought equitable relief and that it bore the burden of proving its entitlement to relief. Therefore, this argument fails.
In a similar vein, Hopper argues that Webster âfailed to meet his burden of proof on his affirmative defense of fraudâ by not establishing all of the elements of fraud. Id. at 17. Inter alia, he asserts the lack of any âintent to deceiveâ on the part of Shamo, citing Shamoâs testimony that the staff of the Building Commission office were aware âthat he was not Wendell Webster but John Shamoâ and âdirectedâ him âto execute the homeownerâs affidavit on behalf of Mr. Websterâ and to sign Websterâs name. Id. at 19. Again, we note that whether this testimony was credible was a matter for the trial court. Bennett, 858 N.E.2d at 1048. Moreover, Shamoâs signing of Websterâs name on an affidavit â swearing that he was Webster, the owner of the residence to be improved, and that he personally or a member of his immediate family would perform the work and not subcontract it out â would support the reasonable inference that this conduct was a fraud upon the Building Commission.
Next, Hopper argues that the evidence fails to support the trial courtâs finding that Hopperâs âwork was performed in a defective manner and caused the Building Inspector to require additional corrective work.â Hopperâs Br. at 22. As recounted in FACTS, Hopperâs workers were at Websterâs residence in mid-March to in *425 stall a vapor barrier and pea gravel under the addition as ordered by âCode Enforcementâ to âbring everything into [C]ode.â (Tr. 32.25). This evidence supports the reasonable inference that construction work which fails to meet the construction code is defective work.
Hopper argues that he âis entitled to recover on the mechanicâs lienâ because it âsubstantially conforme[ed] with statutory requirements.â Hopperâs Br. at 24. Hopper cites Premier Investments v. Suites of America, 644 N.E.2d 124, 130 (Ind.1994), for the proposition that âthe purpose of mechanicâs lien laws is to prevent the inequity of a property owner enjoying the benefits of the labor and materials furnished by others without recompense.â That said, the quotation itself alludes to the matter being one of equity. We have already determined that the trial courtâs judgment comports with application of the law of equity.
Next, Hopper argues that it âwas entitled to recover on breach of contract,â citing âunrefuted evidenceâ that it âwas owed and ha[d] incurred damagesâ in the amount of $7,500.00 âas a result of Webster breaching the partiesâ contract by running Hopper off the job and refusing to pay.â Hopperâs Br. at 29, 30. The evidence was that Webster refused to allow further work by Webster after the inspector found that the work failed to comply with Code. The Homeowner Affidavit expressly provides that âif the Inspector should find the work in the violation of the Code, then [the homeowner] shall employ a master installer of the required trade or craft to change, alter, or repair the work that is in violation.â (Ex. A). Hopper offered no evidence to establish that it held such credentials. The only evidence as to licensing was Shamoâs testimony that on other projects, Hopper had âworked under somebody elseâs license ... many times.â (Tr. 53). Absent a showing that Hopper held credentials to perform the corrective work required by the Homeowner Affidavit, the circumstances here did not require that Webster allow Hopper workers to perform further work. Therefore, Hopperâs breach of contract claims must fail.
Affirmed.
. The Affidavit refers to provisions of âArticle 15.3140 of the Vanderburgh County Building Code or Article 15.150.134 of the Municipal Code of Evansvilleâ regarding the consequences âif the inspector should find work in violation of the Code.â (Ex. A).