Crawford v. Weather Shield Mfg., Inc.
Full Opinion (html_with_citations)
Opinion
Standard comprehensive liability insurance policies provide that the insurer must both indemnify and defend the insured against claims within the scope of the policy coverage. The insurerâs duty to defend is broader than its duty to indemnify. The latter duty runs only to claims that are actually covered by the policy, while the duty to defend extends to claims that are merely potentially covered. (E.g., Buss v. Superior Court (1997) 16 Cal.4th 35, 45-46 [65 Cal.Rptr.2d 366, 939 P.2d 766] (Buss); Montrose Chemical Corp. v. Superior Court (1993) 6 Cal.4th 287, 295 [24 Cal.Rptr.2d 467, 861 P.2d 1153].) âThe [insurerâs] defense duty is a continuing one, arising on tender of defense and lasting until the underlying lawsuit is concluded [citation], or until it has been shown that there is no potential for coverage . . . .â (Montrose, supra, at p. 295.)
Here, however, we address issues concerning the contractual duty to defend in a noninsurance context. We consider whether, by their particular terms, the provisions of a pre-2006 residential construction subcontract obliged the subcontractor to defend its indemniteeâthe developer-builder of the projectâin lawsuits brought against both parties, insofar as plaintiffsâ complaints alleged construction defects arising from the subcontractorâs negligence, even though (1) a jury ultimately found that the subcontractor was not negligent, and (2) the parties have accepted an interpretation of the subcontract that gave the builder no right of indemnity unless the subcontractor was negligent. We conclude that the answer is yes. We will therefore affirm the judgment of the Court of Appeal.
FACTS AND PROCEDURAL BACKGROUND
The basic facts are not in dispute. J.M. Peters Co. (JMP) was the developer, builder, and general contractor of a large Huntington Beach residential project. Weather Shield Mfg., Inc. (Weather Shield), contracted with JMP to manufacture and supply wood-framed windows for the project. In the contract, Weather Shield promised (1) âto indemnify and save [JMP] harmless against all claims for damages . . . loss,. . . and/or theft. .. growing
In September and October 1999, 220 owners of 122 finished homes in the project sued JMP, Weather Shield, and other participants in the projectâs construction. The defendants included Darrow the Framing Corporation (Darrow), the projectâs principal subcontractor, whose responsibilities included framing the structures and installing the windows. The complaints alleged numerous construction defects, including electrical, plumbing, roofing, chimney, framing, and other structural problems. As relevant here, they also asserted that, because of improper design, manufacture, and installation, windows in the homes, including those supplied by Weather Shield, leaked and fogged, causing extensive damage. Theories of negligence, strict liability, breach of warranty, and breach of contract were set forth.
In April 2000, JMP cross-complained against Weather Shield, Darrow, and all the other project subcontractors sued by the homeowners. The cross-complaints asserted, among other things, that under the pertinent subcontract provisionsâall of which had been drafted by JMP and were identical on the pointâthe subcontractors owed JMP duties of indemnity and defense against the homeownersâ complaints. The cross-complaints sought declaratory relief with respect to JMPâs alleged indemnity and defense rights.
JMP, and all the subcontractors except Weather Shield and Darrow, settled before trial. The âsliding scaleâ settlement agreement provided the homeowners a minimum payment of $2.55 million, and guaranteed an additional sum of $1.45 million against any recovery from the nonsettling subcontractors. The settling defendants also agreed to assist the homeowners in prosecuting their claims against the nonsettling parties. JMP and the settling subcontractors mutually released all claims, demands, and liabilities among themselves. All complaints and cross-complaints were dismissed except as to Weather Shield and Darrow.
The window leak and framing issues went to trial against Weather Shield and Darrow on the remaining theories of negligence and breach of warranty. In October 2002, the jury returned general verdicts against Darrow and in favor of Weather Shield. The jury awarded the homeowners approximately $1 million in damages against Darrow. Following the jury verdict, Darrow settled all the complaints against it.
Thereafter, in March 2003, IMFâs cross-complaint against Weather Shield was separately tried to the court. IMP sought both (1) express indemnity for amounts paid to the homeowners in settlement, and (2) under the duty-to-defend provisions of Weather Shieldâs subcontract, attorney fees and expenses incurred by IMP in defending itself against the homeownersâ suit.
The trial court ruled that the subcontractâs terms obliged Weather Shield to indemnify IMP for amounts paid to the homeowners only if Weather Shield was found negligent. Thus, the court determined, the juryâs verdict that Weather Shield was not negligent absolved Weather Shield of indemnity liability in this case. On the other hand, the court concluded, the subcontract did give Weather Shield responsibility for IMFâs legal defense against the homeownersâ claims, insofar as those claims concerned the windows supplied by Weather Shield, regardless of whether Weather Shield was ultimately found negligent.
IMP presented evidence that it had incurred $375,069 in attorney fees to defend the homeownersâ claims, and that 70 percent of the homeowner settlement amount was attributable to the window problems. IMP therefore urged that, under their subcontracts, Weather Shield and Darrow were together liable for 70 percent of IMFâs defense fees, or $262,548. The court apportioned this amount equally between Darrow and Weather Shield, and therefore awarded IMP $131,274 in damages against Weather Shield. The court also found Weather Shield contractually liable to IMP, as the prevailing party on IMFâs cross-complaint, for $46,734 in attorney fees incurred by IMP to prosecute the cross-action.
Following entry of judgment in this case in March 2003, the homeowners moved for a judgment notwithstanding the verdict (judgment NOV) (Code Civ. Proc., §§ 629, 659) and a new trial {id., §§ 657, 659) against Weather Shield. Among other things, the homeowners asserted that, under Jimenez, they were entitled to try their previously dismissed strict liability causes of action. In May 2003, the court denied the motion for a judgment NOV, but granted a new trial against Weather Shield on the issue of strict liability.
Weather Shield appealed (1) the new trial order, and (2) the declaratory relief judgment insofar as it required Weather Shield to reimburse IMFâs expense of defending the homeownersâ action and prosecuting IMFâs cross-complaint. Two of the groups of homeowner plaintiffs filed protective cross-appeals from the judgment against them, and in Weather Shieldâs favor, on the construction-defect claims. IMP did not appeal the order absolving Weather Shield from contractual indemnity liability for amounts paid by IMP to the homeowners.
In a divided decision, the Court of Appeal affirmed the orders and judgments challenged by Weather Shield, and dismissed the cross-appeals as moot. On the issue of Weather Shieldâs liability for IMFâs defense, regardless of its own negligence, the majority reasoned, in essence, that Weather Shieldâs promise âto defendâ IMP against suits founded upon claims arising out of the execution of Weather Shieldâs work necessarily contemplated an immediate duty to provide a service, which duty arose at the time such a suit was brought and a defense was therefore needed. Thus, the majority concluded, the duty could not depend upon the outcome of issues to be litigated in the very action Weather Shield was obliged to defend.
The concurring and dissenting opinion argued that the contract language did not compel the majorityâs interpretation of the duty to defend. Moreover, the concurring and dissenting opinion urged, policy concerns weigh against allowing a builder or developer with superior bargaining power to impose contractual defense obligations on a nonnegligent subcontractor.
DISCUSSION
Parties to a contract, including a construction contract, may define therein their duties toward one another in the event of a third party claim against one or both arising out of their relationship. Terms of this kind may require one party to indemnify the other, under specified circumstances, for moneys paid or expenses incurred by the latter as a result of such claims. (See Civ. Code, § 2772 [âIndemnity is a contract by which one engages to save another from a legal consequence of the conduct of one of the parties, or of some other person.â].)
As befits the contractual nature of such arrangements, but subject to public policy and established rales of contract interpretation, the parties have great freedom to allocate such responsibilities as they see fit. (E. L. White, Inc. v. City of Huntington Beach (1978) 21 Cal.3d 497, 507 [146 Cal.Rptr. 614, 579 P.2d 505] (E. L. White, Inc.); Heppler v. J.M. Peters Co. (1999) 73 Cal.App.4th 1265, 1276-1277 [87 Cal.Rptr.2d 497] (Heppler).) âWhen the parties knowingly bargain for the protection at issue, the protection should be afforded.â (Rossmoor Sanitation, Inc. v. Pylon, Inc. (1975) 13 Cal.3d 622, 633 [119 Cal.Rptr. 449, 532 P.2d 97] (Rossmoor); see Heppler, supra, at p. 1277.) Hence, they may agree that the promisorâs indemnity and/or defense obligations will apply only if the promisor was negligent, or, conversely, even if the promisor was not negligent. (Heppler, supra, at p. 1277; Continental Heller Corp. v. Amtech Mechanical Services, Inc. (1997) 53 Cal.App.4th 500, 505 [61 Cal.Rptr.2d 668] (Continental Heller); Peter Culley & Associates v.
In general, such an agreement is construed under the same rules as govern the interpretation of other contracts. Effect is to be given to the partiesâ mutual intent (§ 1636), as ascertained from the contractâs language if it is clear and explicit (§ 1638). Unless the parties have indicated a special meaning, the contractâs words are to be understood in their ordinary and popular sense. (§ 1644; Continental Heller, supra, 53 Cal.App.4th 500, 504; accord, Centex Golden Construction Co. v. Dale Tile Co. (2000) 78 Cal.App.4th 992, 996-997 [93 Cal.Rptr.2d 259] (Centex Golden).)
Though indemnity agreements resemble liability insurance policies, rules for interpreting the two classes of contracts do differ significantly. Ambiguities in a policy of insurance are construed against the insurer, who generally drafted the policy, and who has received premiums to provide the agreed protection. (See, e.g., Buss, supra, 16 Cal.4th 35, 47-48; La Jolla Beach & Tennis Club, Inc. v. Industrial Indemnity Co. (1994) 9 Cal.4th 27, 37-38 [36 Cal.Rptr.2d 100, 884 P.2d 1048].) In noninsurance contexts, however, it is the indemnitee who may often have the superior bargaining power, and who may use this power unfairly to shift to another a disproportionate share of the financial consequences of its own legal fault. (E.g., Goldman v. Ecco-Phoenix Elec. Corp. (1964) 62 Cal.2d 40, 49 [41 Cal.Rptr. 73, 396 P.2d 377] (Goldman); see Regan Roofing Co. v. Superior Court (1994) 24 Cal.App.4th 425, 436 [29 Cal.Rptr.2d 413] (Regan Roofing).)
This public policy concern influences to some degree the manner in which noninsurance indemnity agreements are construed. For example, it has been said that if one seeks, in a noninsurance agreement, to be indemnified for his or her own active negligence, or regardless of the indemnitorâs faultâ protections beyond those afforded by the doctrines of implied or equitable indemnityâlanguage on the point must be particularly clear and explicit, and will be construed strictly against the indemnitee. (E.g., E. L. White, Inc., supra, 21 Cal.3d 497, 507; Rossmoor, supra, 13 Cal.3d 622, 628; Goldman, supra, 62 Cal.2d 40, 44; Centex Golden, supra, 78 Cal.App.4th 992, 998; Heppler, supra, 73 Cal.App.4th 1265, 1278.)
For similar public policy reasons, statutory law imposes some absolute limits on the enforceability of noninsurance indemnity agreements in the construction industry. At the time Weather Shield contracted with JMP, a party to a construction contract could not validly agree to indemnify the promisee for the latterâs sole negligence or willful misconduct. (§ 2782, subd. (a); see also § 1668.)
In this regard, the statute first provides that a promise of indemnity against claims, demands, or liability âembraces the costs of defense against such claims, demands, or liabilityâ insofar as such costs are incurred reasonably and in good faith. (§ 2778, subd. 3, italics added.) Second, the section specifies that the indemnitor âis bound, on request of the [indemnitee], to defend actions or proceedings brought against the [indemnitee] in respect to the matters embraced by the indemnity,â though the indemnitee may choose to conduct the defense. (Id., subd. 4, italics added.) Third, the statute declares that if the indemnitor declines the indemniteeâs tender of defense, âa recovery against the [indemnitee] suffered by him in good faith, is conclusive in his favor against the [indemnitor].â (Id., subd. 5.) On the other hand, section 2778 provides, if the indemnitor got no reasonable notice of the action or was not allowed to control the indemniteeâs defense, recovery by the third party against the indemnitee is only presumptive evidence against the indemnitor. (Id., subd. 6.)
With these principles in mind, we examine the pertinent terms of Weather Shieldâs subcontract with IMP. We agree with the Court of Appeal majority that, even if strictly construed in Weather Shieldâs favor, these provisions expressly, and unambiguously, obligated Weather Shield to defend, from the outset, any suit against JMP insofar as that suit was âfounded uponâ claims alleging damage or loss arising from Weather Shieldâs negligent role in the Huntington Beach residential project. Weather Shield thus had a contractual obligation to defend such a suit even if it was later determined, as a result of this very litigation, that Weather Shield was not negligent.
We focus on the particular language of the subcontract. Its relevant terms imposed two distinct obligations on Weather Shield. First, Weather Shield agreed âto indemnify and save [JMP] harmless against all claims for damages to persons or to property and claims for loss, damage and/or theft . . . growing out of the execution of [Weather Shieldâs] work.â Second, Weather Shield made a separate and specific promise âat [its] own expense to defend any suit or action brought against [JMP] founded upon the claim of such damage . . . loss, ... or theft.â (Italics added.)
A contractual promise to âdefendâ another against specified claims clearly connotes an obligation of active responsibility, from the outset, for the
A duty to defend another, stated in that way, is thus different from a duty expressed simply as an obligation to pay another, after the fact, for defense costs the other has incurred in defending itself. Section 2778, the statute governing the construction of all indemnity agreements, makes the distinction clear. On the one hand, as noted above, the section specifies that a basic contractual indemnity against particular claims, demands, or liabilities âembraces the costs of defenseâ against such claims, demands, or liabilities. (Id., subd. 3.) On the other hand, the statute separately specifies the indemnitorâs duty actually âto defend,â upon the indemniteeâs request, proceedings against the latter âin respect to the matters embraced by the indemnity,â though âthe person indemnified has the right to conduct such defenses ... if he chooses to do so.â (Id., subd. 4.) Finally, section 2778 sets forth how the indemnitorâs obligations will be affected if the indemnitor fails to accept an indemniteeâs tender of defense or, alternatively, if the indemnitor is denied an opportunity to assume and control the defense. (Id., subds. 5, 6.)
Thus, in Safeway Stores, Inc. v. Massachusetts Bonding & Ins. Co. (1962) 202 Cal.App.2d 99 [20 Cal.Rptr. 820] (Safeway Stores), one King undertook, by written agreement, to act as general contractor in the construction of a new Safeway store. The agreement included Kingâs obligation to indemnify Safeway against any claims, demands, or suits for damage, loss, or injury â âresulting] from or occur[ring] in connection with the performance of [the] contract.â â (Id., at p. 105.) Construction workers employed by King sued Safeway for injuries they sustained when recently installed roof trusses collapsed. The workers alleged that Safeway had negligently permitted the installation of trusses it knew to be defective. King offered Safeway a defense, which Safeway initially accepted. However, it thereafter became apparent that the attorney furnished by King was serving Kingâs conflicting interests; in discussions between the parties, King indicated he would deny indemnity liability if Safeway was found negligent. Safeway thereupon retained its own attorney to defend the workersâ action, and later sought reimbursement of its defense costs from King.
The Court of Appeal agreed with Safeway. The court noted that âunder the contract of indemnity, no contrary intention appearing, King was bound to defend the actions. (Civ. Code, § 2778, subd. 4.)â (Safeway Stores, supra, 202 Cal.App.2d 99, 114, italics added.) However, the court reasoned, in light of the obvious conflict between Safewayâs litigation interests and Kingâs position on the indemnity issue, Safeway had reasonably inferred that, despite Kingâs technical proffer, King did not intend to honor his contractual obligation to provide Safeway with a complete defense. Under these circumstances, the court concluded, Safeway did not act as a volunteer in assuming its own defense, and was entitled to reimbursement for Kingâs breach of the duty to defend.
Similarly, in Buchalter v. Levin (1967) 252 Cal.App.2d 367 [60 Cal.Rptr. 369], the court acknowledged that subdivision 4 of section 2778 âestablishes an indemnitorâs obligation to defend the indemnitee upon request, even though the indemnity agreement does not expressly so provide . . . .â (Buchalter, supra, at p. 374, italics added.) However, the court concluded, the subdivisionâs provision that the indemnitee may âconduct his own defense âif he chooses to do soâ â (ibid.) does not mean the indemnitee ordinarily may
In Gribaldo, Jacobs, Jones & Associates v. Agrippina Versicherunges A. G. (1970) 3 Cal.3d 434 [91 Cal.Rptr. 6, 476 P.2d 406] (Gribaldo), a majority of this court carefully distinguished between the âcosts of defenseâ described in subdivision 3 of section 2778, on the one hand, and the duty âto defendâ the indemnitee, as set forth in subdivision 4 of the statute, on the other. There, an errors and omissions indemnity policy provided for a deductible of $2,500, said nothing about a duty to defend, gave the underwriters the right to assume the insuredsâ defense, specified that the insureds need not contest any legal claim unless counsel mutually chosen by the parties advised otherwise, and prohibited either party from settling a claim against the insureds without the otherâs consent. The policy further stated that if the insureds refused a settlement offer against the underwritersâ recommendation, and elected to contest the claim further, the underwritersâ liability would not exceed the amount for which the claim could have been settled, plus costs and expenses incurred by the insureds with the underwritersâ consent.
After the insureds settled a third party claim, they sought declaratory relief against the underwriters on the issue of liability for defense costs. The insureds contended that under subdivision 4 of section 2778, the policy included, and the underwriters had breached, an âactual duty to defendâ (Gribaldo, supra, 3 Cal.3d 434, 441) any claim, of a type covered by the policy, in which the initial demand exceeded the $2,500 deductible. Hence, the insureds insisted, the underwriters were now obliged to pay the insuredsâ costs of defending such claims in full, regardless of the amounts for which the claims were actually resolved.
The trial court disagreed. It reasoned that, under the particular terms of the policy, the underwriters were not obliged to defend the insureds. Hence, the court concluded, any liability of the underwriters for the insuredsâ defense costs arose solely under subdivision 3 of section 2778, as part of any indemnity the underwriters otherwise owed the insureds. That obligation, the court held, applied only to costs incurred by the insureds to defend claims âembraced within the provisions of the policy, that is, those claims in excess of $2,500 actually paid by [the insureds].â (Gribaldo, supra, 3 Cal.3d 434, 441.)
Accordingly, the majority reasoned, the underwriters had breached no duty under subdivision 4 of section 2778 to defend any and all claims in which the demand exceeded the $2,500 deductible. Instead, the majority concluded, the trial court had acted correctly in calculating the underwritersâ defense-cost liability under subdivision 3 of the statute. Under the latter provision, the majority held, the underwritersâ defense-cost liability was limited to the insuredsâ expense of defending claims as to which the underwriters otherwise owed indemnityâi.e., those claims actually paid by the insureds in amounts exceeding the $2,500 deductible. (Gribaldo, supra, 3 Cal.3d 434, 447-450.)
Recently, City of Watsonville v. Corrigan (2007) 149 Cal.App.4th 1542 [58 Cal.Rptr.3d 458] observed once again that subdivision 4 of section 2778 âdescribes the indemnitorâs duty to defend . . . actions or proceedings brought against the indemnitee if the latter requests the defense.â (City of Watsonville, supra, at p. 1549, original italics.) However, the Court of Appeal held that by failing to request a defense, or to notify the indemnitor of the third party action, and by unilaterally deciding to conduct its own defense, the indemnitee does not necessarily forfeit its contractual right to reimbursement of its defense costs under the indemnity provisions of subdivision 3 of the statute.
Thus, as these decisions indicate, subdivision 4 of section 2778, by specifying an indemnitorâs duty âto defendâ the indemnitee upon the latterâs request, places in every indemnity contract, unless the agreement provides otherwise, a duty to assume the indemniteeâs defense, if tendered, against all claims âembraced by the indemnity.â The indemnitorâs failure to assume the duty to defend the indemnitee upon request (§ 2778, subd. 4) may give rise to damages in the form of reimbursement of defense costs the indemnitee was
Implicit in this understanding of the duty to defend an indemnitee against all claims âembraced by the indemnity,â as specified in subdivision 4 of section 2778, is that the duty arises immediately upon a proper tender of defense by the indemnitee, and thus before the litigation to be defended has determined whether indemnity is actually owed. This duty, as described in the statute, therefore cannot depend on the outcome of that litigation. It follows that, under subdivision 4 of section 2778, claims âembraced by the indemnity,â as to which the duty to defend is owed, include those which, at the time of tender, allege facts that would give rise to a duty of indemnity.
Here, the subcontract at issue not only failed to limit or exclude Weather Shieldâs duty âto defendâ IMP, as otherwise provided by subdivision 4 of section 2778, it confirmed this duty. In language similar to that of the statute, the subcontract explicitly obligated Weather Shield both to indemnify IMP against certain claims, and âat [its] own expense to defendâ IMP against âany suit or action . . . founded uponâ such claims. (Italics added.) The duty âto defendâ expressly set forth in Weather Shieldâs subcontract thus clearly contemplated a duty that arose when such a claim was made,
Moreover, the subcontract at issue included a further express indication that the express duty âto defendâ actions against IMP was not strictly limited to those claims on which, in the end, Weather Shield actually owed indemnity. The indemnity and defense clauses of the subcontract contained linguistic differences that conform to the logical distinctions between the two duties. On the one hand, the subcontract obligated Weather Shield to âindemnify . . . [IMP] . . . againstâ all claims for injury, damage, loss, or theft arising from performance of the subcontract, while, on the other, it required Weather
One can only indemnify against âclaims for damagesâ that have been resolved against the indemnitee, i.e., those as to which the indemnitee has actually sustained liability or paid damages. Indemnification, after all, is the act of saving another from the legal consequence of an act. (§ 2772.) Hence, a clause requiring Weather Shield to indemnify IMP âagainstâ defined claims clearly indicated that the indemnity obligation would apply only if IMP ultimately incurred such a legal consequence as a result of covered claims.
By contrast, as noted above, the subcontract required Weather Shield âto defendâ IMP against âany suit or action . . . founded upon the claim of such damage . . . .â (Italics added.) Under this language, the duty to defend arose, as it logically must, as soon as a âsuit or actionâ was brought against IMP that was âfounded uponâ a covered claim, i.e., that asserted a claim within the coverage of both clauses. Necessarily, a duty expressed in this manner did not require a final determination of the issues, including the issue of Weather Shieldâs negligence, before Weather Shield was required to mount and finance a defense on JMPâs behalf.
The Court of Appeal majority so concluded. Dissenting on this point, Justice OâLeary conceded at the outset that âthe word âdefend,â as defined in the abstract, would ordinarily mean providing legal services for a pending claim.â Nonetheless, she stressed, noninsurance indemnity contracts, unlike liability insurance policies, are construed to limit the obligations imposed, and the duties undertaken must be stated with particular clarity and specificity. Examined in that light, she asserted, Weather Shieldâs subcontract did not make absolutely clear that Weather Shieldâs duty to defend, unlike its duty to indemnify, arose regardless of its negligence.
To conclude that, absent greater specificity, the indemnity and defense obligations stated in the subcontract both required a finding of Weather Shieldâs negligence, Justice OâLeary reasoned as follows: The indemnity and defense obligations in Weather Shieldâs subcontract were âdescribed in a single sentenceâ with two clauses. The first clause, stating the indemnity obligation, covered â âclaims for damages . . . growing out of the execution of [Weather Shieldâs] work . . . .â Everyone (the litigants, trial court, and majority) seems to agree [that] matters embraced by this indemnity clause [were] narrowly limited to damages caused by [Weather Shieldâs] own
But Justice OâLearyâs analysis overlooks the clear differences in the two clauses that we have described above. In particular, Weather Shieldâs express contractual duty to defend suits âfounded uponâ the kinds of claims specified in the agreement necessarily extended to suits that alleged such claims, not just suits in which they were proven. Assuming, as we must, that Weather Shieldâs subcontract obligated it to indemnify JMP against claims arising from Weather Shieldâs negligent performance of the subcontract, it follows that Weather Shieldâs contractual duty to defend JMP encompassed suits or actions that alleged such negligence on Weather Shieldâs part. Weather Shield could not avoid this duty on the ground that the very litigation to be defended might later result in a finding Weather Shield was, in fact, not negligent.
Parties to an indemnity contract can easily disclaim any responsibility of the indemnitor for the indemniteeâs defense, or the costs thereof. Short of that, they can specify that the indemnitorâs sole defense obligation will be to reimburse the indemnitee for costs incurred by the latter in defending a particular claim. However, the instant subcontract did neither. On the contrary, it specified that Weather Shield would be required, âat [its] own expense,â to âdefendâ JMP against suits âfounded uponâ claims arising from Weather Shieldâs performance of its subcontract. This language indicated a more immediate obligation, one that would necessarily arise before the litigation to be defended could determine whether Weather Shield owed indemnity to JMP.
In arguing otherwise, Weather Shield relies heavily on Heppler, supra, 73 Cal.App.4th 1265. There, in connection with another of JMPâs large residential construction projects, Mueller-Lewis Concrete (Mueller) signed a JMP-drafted subcontract containing indemnity and defense clauses identical to those at issue here. Homeowners sued JMP, Mueller, and others for construction defects. Mueller declined JMPâs tender of defense. In a global settlement, JMP assigned its contractual rights against Mueller to the plaintiff homeowners. As JMPâs assignees, they sought to recover against Mueller under both the indemnity and defense provisions. The defect, indemnity, and defense issues went to trial against Mueller. The trial court ruled that the plaintiffs must prove negligence and causation against Mueller in order to trigger Muellerâs contractual indemnity obligations. The jury returned a general verdict for Mueller.
However, the plaintiffs in Heppler did not contend that, even if the indemnity clause in Muellerâs subcontract was triggered only by Muellerâs actual negligence, the duty-to-defend clause applied more broadly. Accordingly, the Heppler court never separately addressed the defense clause of the subcontract, or considered how the particular language of that clause might distinguish it from the indemnity clause. In affirming the general verdict for Mueller, the court simply assumed that the indemnity and defense provisions of the subcontract were congruent.
Here, by contrast, we directly confront the relationship, and the distinctions, between the two clauses. Upon examination, as explained above, their language differs in a way suggesting that, even if the indemnity obligation is triggered only by an ultimate finding of the indemnitorâs fault, the defense obligation applies before, and thus regardless of, any finding to be made in the course of the litigation for which a defense is owed. Hence, whatever Hepplerâs merits on the issues actually considered in that case, we do not find the decision helpful or persuasive on the narrow question before us.
Similarly, Goldman, supra, 62 Cal.2d 40, cited by Weather Shield, is of little use in construing the particular defense clause at issue in this case. Our opinion noted a duty-to-defend clause, phrased in language different from that we address here, that might bind the subcontractor in that case. (See id., at
Nor, under close examination, is Mel Clayton Ford, supra, 104 Cal.App.4th 46, helpful to Weather Shieldâs cause. Weather Shield suggests Mel Clayton Ford stands for the proposition that a duty-to-defend clause in a noninsurance agreement does not extend to mere allegations that would trigger an indemnity obligation only if proven. We do not so interpret the decision. In our view, Weather Shield takes out of context the passage on which it relies.
In Mel Clayton Ford, an agreement between a vehicle manufacturer and its retail dealer specified that the manufacturer would defend and indemnify the dealer against any third party suits, complaints, or claims â âconcerning . . . injury or . . . damage arising out of an occurrence caused solely byâ â a manufacturing or design defect in a vehicle supplied to the dealer by the manufacturer. (Mel Clayton Ford, supra, 104 Cal.App.4th 46, 49, italics added.) Thus, the manufacturer excluded from its defense obligation any suit or claim that alleged dealer negligence, or any theory other than manufacturing or design defect, as a sole or contributing cause of the injury or damage.
: In 1989, the plaintiff purchased from the dealer a truck supplied by the manufacturer. Thereafter, the dealer performed maintenance on the vehicle. In 1997, while the plaintiff was driving the truck, it burst into flames, seriously injuring him. He sued both the manufacturer and the dealer, alleging not only a defectively designed and manufactured product, but also claims based on failure to warn, breach of warranty, and â âtheories of [the dealerâs] direct or active negligence in the maintenance of the vehicle.â â (Mel Clayton Ford, supra, 104 Cal.App.4th 46, 50.)
The Court of Appeal held that the manufacturer had no duty to undertake the dealerâs defense under such circumstances. This was because â[t]he indemnity provision required [the manufacturer] to defend the Dealer only where the occurrence was caused solely by a production defect, and not
Thus, in Mel Clayton Ford, it was not an allegations-versus-proof distinction that negated the duty to defend. Rather, given the word âsolelyâ in the indemnity/defense clause there at issue, the crucial fact was that the suit for which a defense was sought included allegations other than those to which the manufacturer had limited its defense dutyâdesign or production defects attributable to the manufacturer itself.
Here, Weather Shieldâs contractual duty was not similarly limited. Weather Shield promised to defend IMP against any suit âfounded uponâ a âclaim of . . . damageâ âgrowing out of the execution of [Weather Shieldâs] work.â The contract did not specify, or even hint, that no defense duty would exist unless the suit was solely concerned with Weather Shieldâs performance under its own subcontract and included no other claims or allegations. Nor does Weather Shield so claim. Hence, nothing decided in Mel Clayton Ford establishes that until Weather Shieldâs faulty performance of its work was proven, it had no duty to defend IMP.
Finally, we are not persuaded by Regan Roofing, supra, 24 Cal.App.4th 425, insofar as that decision suggests that a contractual duty to defend specified classes of claims, expressed in such terms, necessarily depends on the promisorâs ultimate liability for indemnity on those claims.
In Regan Roofing, after a housing developer, Pacific Scene, was sued for construction defects, it cross-complained against numerous project subcontractors to establish its contractual indemnity and defense rights. Each of these agreements required the subcontractor to indemnify Pacific Scene against all mechanicâs liens related to the subcontractorâs work, as well as â âany other liability, cost or expense of any nature or kind arising out of or in any way connected with Subcontractorâs performance . . . , save and except only such liability, cost or expense caused by [Pacific Sceneâs] sole negligence or sole willful misconduct.â â (Regan Roofing, supra, 24 Cal.App.4th at p. 430, italics omitted.) â âPursuant to . . . the foregoing,â â the subcontracts declared, â âSubcontractor shall indemnify and hold harmless [Pacific Scene] from any costs and expenses for attorneyâs fees . . . resulting to [Pacific Scene] from such claims or liens.â â (Ibid., italics omitted.) Finally, each agreement separately provided that â â[i]n the event any suit on any claim is
Pacific Scene sought pretrial summary adjudication of a number of issues, including rulings on the subcontractorsâ duties to indemnify and defend. The trial court determined that the indemnity provision of the subcontracts included coverage for Pacific Sceneâs own negligence. However, the court found that the question whether the subcontractors actually owed indemnity was premature, because, among other things, Pacific Scene had not yet incurred liability or paid claims subject to indemnity. On the other hand, the court concluded, under the language of the agreements and section 2778, each subcontractor did have an immediate duty to defend claims â âbrought against [Pacific Scene] in respect to matters embraced by the indemnity clause.â â (Regan Roofing, supra, 24 Cal.App.4th 425, 432.)
The Court of Appeal reversed on the latter point. The appellate court indicated that âsummary adjudication of the duty to defend and its relationship to the duty to indemnify (i.e., the scope of âthe matters embraced by the indemnityâ) is premature. No determination has yet been made as to whether the subcontractors were negligent in the performance of their work, giving rise to a duty to indemnify and a related duty to defend. Pacific Scene has not clearly established that under this indemnity clause, the duty to defend against claims of liability is entirely free-standing of the duty to indemnify for liability arising out of a subcontractorâs negligence. [Citation.]â (Regan Roofing, supra, 24 Cal.App.4th 425, 436, italics added.)
In reaching this conclusion, however, the Court of Appeal erred. The court seems to have assumed that, under subdivision 4 of section 2778, and unless the agreement at issue clearly provides otherwise, an indemnitorâs duty to defend the indemnitee upon request in matters âembraced by the indemnityâ is not, in the courtâs words, âfree-standing,â but extends only to claims as to which indemnity is actually owed. (Regan Roofing, supra, 24 Cal.App.4th 425, 436.) And the court found no such explicit contrary intent in the subcontracts there under consideration.
However, as we have explained, the duty to defend upon the indemniteeâs request, as set forth in subdivision 4 of section 2778, is distinct from, and broader than, the duty expressed in subdivision 3 of the statute to reimburse an indemniteeâs defense costs as part of any indemnity otherwise owed. Moreover, the subcontracts at issue in Regan Roofing, like the one before us here, did explicitly indicate a separate and distinct duty to defend the indemnitee, at the indemnitorâs own cost and expense, against suits raising claims covered by the indemnity. That dutyâlike Weather Shieldâs in this
Regan Roofing was therefore mistaken insofar as it concluded that, under the agreements there at issue, the subcontractorsâ defense duties arose only if the subcontractors became liable for indemnity. We will disapprove the Regan Roofing decision to that extent.
Weather Shield and its amici curiae raise numerous, and substantial, policy concerns about an indemnity agreement that requires a subcontractor to defend a residential developer or builder in a construction defect suit before, and regardless of whether, the subcontractor itself is found to be at fault. Arguments asserted include the following: Large builders and developers use their superior bargaining power, and self-drafted contract terms, unfairly to shift the financial consequences of their own legal liability to faultless subcontractors, who are not compensated for the risk and agree only because
As Weather Shield and its amici curiae point out, statutes effective January 1, 2006, and January 1, 2008, respectively, were adopted to address just such concerns. These new laws, which apply to residential construction contracts entered after their effective dates, void any term in such a contract that obliges a subcontractor to indemnify certain other project participants, âincluding the cost to defend,â against construction defect claims âto the extentâ the claims âarise out of, pertain to, or relate toâ the negligence of those other entities. (§ 2782, subds. (c), (d), as added by Stats. 2005, ch. 394, § 1; see § 2782, subd. (e), as added by Stats. 2007, ch. 32, § l.)
In effect, Weather Shield and its amici curiae ask us to conclude as a matter of law that, in a pre-2006 residential construction contract, a term which expressly obliges a subcontractor âto defendâ a builder, developer, or general contractor against claims âfounded uponâ the subcontractorâs negligent work, but says nothing further about the scope of the duty, means only that the subcontractor must reimburse the promisee, after the fact, for the promiseeâs legal expenses as part of any indemnity ultimately owed by the subcontractor to the promisee. They suggest that to produce a contrary result, the subcontract should say, in so many words, that the duty to defend arises immediately when a claim is asserted against the promisee, is not limited to later reimbursement of the promiseeâs legal expenses, and applies regardless, and independent, of any duty of indemnity for which the subcontractor may later become liable.
We are sensitive to the policy issues raised by Weather Shield and its amici curiae. Nonetheless, for reasons stated at length above, we decline the holding they propose. Even applying the rule of strict construction they espouse, the instant contract already sets forth, in unambiguous terms, an immediate and independent duty to defend. As we have indicated, an express promise âto defendâ another against claims âfounded uponâ the promisorâs acts or omissions inherently incorporates the characteristics they insist must be set forth in additional explicit terms. And if the parties intended only to give the indemnitee a right to after-the-fact reimbursement of its legal expenses as a component of any indemnity otherwise owed by the indemnitor, they would need no language to say so. That right is already included in every indemnity contract, unless otherwise specifically provided, under subdivision 3 of section 2778.
We therefore conclude that the duty âto defendâ IMP against claims âfounded uponâ damage or loss caused by Weather Shieldâs negligent performance of its work, as set forth in Weather Shieldâs subcontract, imposed such duties on Weather Shield as soon as a suit was filed against IMP that asserted such claims, and regardless of whether it was ultimately determined that Weather Shield was actually negligent. Accordingly, we affirm the judgment of the Court of Appeal.
The judgment of the Court of Appeal is affirmed. The decision in Regan Roofing Co. v. Superior Court, supra, 24 Cal.App.4th 425, is disapproved to the extent it conflicts with the conclusions set forth in this opinion.
George, C. J., Kennard, J., Werdegar, J., Chin, J., Moreno, J., and Corrigan, J., concurred.
The cases were consolidated for pretrial and trial purposes.
JMPâs cross-complaints alleged that the cross-defendant subcontractors had a âpresentâ duty to provide, and JMP had a âpresentâ right to receive, a contractual defense. Each cross-complaint also recited that â[b]y way of this Cross-Complaint, [JMP] hereby tenders the defense of this action to the Cross-Defendants, and each of them, pursuant to the applicable subcontracts. [JMP] is informed and believed and based thereon alleges that the Cross-Defendants, and each of them have and/or will reject, ignore, or fail to properly accept the tender of defense.â The record is silent as to whether JMP had previously tendered defense of the homeownersâ actions to the cross-defendant subcontractors, or any of them. Weather Shield does not urge on appeal that it was absolved of any duty to defend by reason of JMPâs failure to timely tender the defense of the homeownersâ actions.
We were informed by the parties that, following the trial court judgment, IMP assigned all its rights thereunder to the homeowners. The homeowners then defended JMPâs defense-cost award in the Court of Appeal. In this court as well, the homeowners have briefed the defense-cost issue as assignees of JMPâs rights under the defense-cost award.
Subsequent to our grant of review, an issue arose whether, despite our limitation of issues, the pendency of review precluded further proceedings in the trial court under the new trial order, the propriety of which order we did not intend to address. Concluding that there was no reason to delay the homeownersâ strict-liability trial while we considered the defense-cost issue, we therefore dismissed review with respect only to the order granting a new trial on that issue, as affirmed by the Court of Appeal. We directed the Court of Appeal to issue a partial remittitur in accordance with the partial dismissal order.
All further unlabeled statutory references are to the Civil Code.
Pursuant to subdivision 5 of section 2778, if a contractual indemnitor declines the indemniteeâs tender of defense of a third party claim against the latter, the third partyâs later judgment against the indemnitee may be conclusive evidence, against the indemnitor, of the indemniteeâs liability to the third party, and the amount thereof, while the indemniteeâs good faith settlement of the third party claim may be presumptive evidence against the indemnitor on that issue. (See, e.g., Isaacson v. California Ins. Guarantee Assn. (1988) 44 Cal.3d 775, 791 [244 Cal.Rptr. 655, 750 P.2d 297]; Peter Culley & Associates, supra, 10 Cal.App.4th 1484, 1495-1497.) In other words, a contractual indemnitorâs failure to assume the indemniteeâs defense and, with it, control of the underlying litigation may restrict the indemnitorâs later ability to separately litigate issues pertaining to its own indemnity liability. In this case, as indicated above, no issue is presented of the effect of JMPâs settlement with the homeowners on Weather Shieldâs indemnity liability. We confront the separate question whether the express terms of Weather Shieldâs subcontract required Weather Shield, at its own expense, to assume JMPâs defense, and, having failed to do so, to reimburse JMP after the fact for the latterâs actual defense costs, regardless of Weather Shieldâs liability to indemnify JMP for amounts paid to the homeowners in settlement.
We do not suggest that the indemnitorâs duty to defend would continue even if, during the progress of the third party proceeding against the indemnitee, all claims potentially subject to the contractual indemnity obligation were eliminated, or if the promisor otherwise conclusively established that the claims were not among those âembraced by the indemnity" (§ 2778, subd. 4). Such issues are not before us, and we express no views thereon.
Unlike subdivision 4 of section 2778, Weather Shieldâs subcontract did not expressly condition the duty âto defendâ upon the indemniteeâs request for a defense. In any event, as noted above (fn. 2, ante), Weather Shield does not contend it was absolved of a duty to defend on account of any failure by IMP to make such a request.
This aspect of the ruling in Heppler, supra, 73 Cal.App.4th 1265, may be what has dissuaded the homeowners in this case, acting in JMPâs stead, from challenging on appeal the trial courtâs ruling that the identical indemnity clause in Weather Shieldâs subcontract required Weather Shieldâs negligence as a condition of its indemnity liability.
This assumption is confirmed by Baldwin Builders v. Coast Plastering Corp. (2005) 125 Cal.App.4th 1339 [24 Cal.Rptr.3d 9], where the same Court of Appeal panel broadly stated the holding of Heppler as being that âan indemnitor/subcontractor generally will not be liable or have a duty to defend its general contractor pursuant to the terms of an indemnity agreement unless it was negligent in performing its work under the subcontract.â (Baldwin Builders, supra, at p. 1347, italics added.) But this passage in Baldwin Builders is dictum; the case had nothing to do with an indemnitorâs duty, regardless of fault, to defend its indemnitee. The sole question was whether, having proved in the underlying construction defect litigation that it was not negligent, and thus owed no indemnity under the terms of its subcontract, the subcontractor/indemnitor could recover, under the contractual attorney-fee reciprocity statute (§ 1717, subd. (a)), its attorney fees incurred in so establishing. The Court of Appeal concluded that the answer was yes, reasoning that these were fees expended by the subcontractor/indemnitor to enforce the indemnity agreement itself, i.e., to prove that it owed no contractual indemnity.
To the extent there is any ambiguity in Mel Clayton Fordâs holding on this point, it cannot be resolved by further examination of the Court of Appealâs opinion in that case. Except for the summary passage quoted above, the Court of Appealâs discussion of this interpretive issue appeared in the unpublished portion of its partially published opinion.
We realize that Regan Roofingâs finding of prematurity was also substantially influenced by the practical difficulties of sorting out multiple, and potentially conflicting, duties to assume the active defense of litigation then in progress. (See Regan Roofing, supra, 24 Cal.App.4th 425, 437.) Weather Shield and its amici curiae raise similar concerns. But the case before us does not present such problems. JMP cross-complained against Weather Shield and other subcontractors on indemnity and duty-to-defend issues, but the trial on these issues was postponed until after most of the subcontractors had settled with JMP, and after the underlying construction defect litigation against the remaining parties, including Weather Shield, was concluded. Thus, while the trial court correctly held that Weather Shieldâs contractual duty to defend arose when a suit alleging covered claims was brought against JMP, and that the duty thus did not depend on whether the conditions for indemnity were later established, the court was able to assess after the fact Weather Shieldâs proportionate liability for breach of its duty to defend.
The instant parties apparently saw no impropriety in this procedure, and neither do we. At least with respect to pre-2006 residential construction subcontracts, and subject to any future contrary or inconsistent legislation, the following procedures seem appropriate: When a party sues one or more other persons, seeking to establish a contractual right to a defense against litigation not yet concluded, these issues may, if the parties agree, be deferred until the underlying litigation is complete. If any party moves for summary judgment or adjudication (Code Civ. Proc., § 437c) with respect to the duty to defend against litigation still in progress, the court may proceed as it deems expedient. For example, the court may resolve legal issues then ripe for adjudication, such as whether any of the contracts at issue include a duty to defend, and, if so, whether the underlying suit or proceeding as to which a defense is sought falls within the scope of any of the partiesâ contractual duty to defend. If the court finds that an ongoing duty to defend is owed by one or more parties, but the affected parties, acting in good faith, then cannot agree on how such a defense should be provided or financed, the court may, in its discretion, permit the underlying litigation to proceed with counsel chosen and paid by the party to whom the duty is owed, subject to a later determination of how damages for breach of the duty to defend should be apportioned among the breaching parties.
By noting this argument, we do not dismiss the possibility that in many instances, subcontractors may prefer to assume, and control, the defense of suits against builders, developers, or other contractors, especially when the claims raised may expose the subcontractors themselves to direct or indirect liability.
As noted above, section 2782, subdivision (a) has long provided that a party to a construction contract cannot agree to indemnify another project participant for the latterâs sole negligence or willful misconduct. Subdivision (c) of section 2782, as adopted in 2005 and slightly amended in 2007, additionally provides in pertinent part: âFor all construction contracts, and amendments thereto, entered into after January 1, 2006, for residential construction . . . , all provisions, clauses, covenants, and agreements contained in, collateral to, or affecting any construction contract, and amendments thereto, that purport to indemnify, including the cost to defend, the builder ... by a subcontractor against liability for claims of construction defects are unenforceable to the extent the claims arise out of, pertain to, or relate to the negligence of the builder or the builderâs other agents, other servants, or other independent contractors who are directly responsible to the builder, or for defects in design furnished by those persons .... This section shall not be waived or modified by contractual agreement, act, or omission of the parties. Contractual provisions, clauses, covenants, or agreements not expressly prohibited herein are reserved to the agreement of the parties.â
Subdivision (d) of section 2782, also adopted in 2005 and effective January 1, 2006, provides in pertinent part: âSubdivision (c) does not prohibit a subcontractor and builder from
Subdivision (e) of section 2782, as added in 2007 and effective for residential construction contracts entered after January 1, 2008, uses parallel language to expand the categories of project participants as to whom a subcontractor cannot be made contractually responsible for construction defect indemnity, including defense costs, âto the extentâ such claims âarise out of, pertain to, or relate toâ the negligence of those entities or their agents, their servants, or the independent contractors directly responsible to them. Under subdivision (e), the categories of project participants who may not obtain such contractual indemnity from a subcontractor now include not only the builder, but also âthe general contractor or contractor that is not affiliated with the builder.â
Amicus curiae Jeld-Wen, Inc., suggests â[t]here is good reason to believeâ that section 2778âs reference to âcontracts] of indemnityâ was never intended to apply to anything but
Questioned on this subject at oral argument, Weather Shieldâs counsel did not deny that Weather Shield is a sizeable multistate purveyor of manufactured windows.