Bell Bci Co. v. United States
Full Opinion (html_with_citations)
Opinion for the court filed by Circuit Judge PROST. Dissenting opinion filed by Circuit Judge NEWMAN.
Bell BCI Company (âBellâ) and the National Institutes of Health (âNIHâ) entered into Contract No. 263-98-C-0102 on March 26, 1998. The fixed-price contract originally required Bell to construct a new five-story laboratory building by June 29, 2000. After several significant changes to the contract, Bell substantially completed a six-story laboratory building on February 8, 2002. After the government denied Bellâs claim for equitable adjustment, Bell sued the government for breach of contract and requested that the United States Court of Federal Claims review several of the contracting officerâs (âCOâsâ) decisions. The court ultimately found for Bell in all regards. Bell BCI Co. v. United States, 81 Fed.Cl. 617 (2008). The government now appeals the decision in its entirety. For the reasons set forth below, we affirm-in-part, vacate-in-part, and remand.
BACKGROUND
In 1998, the government decided to construct a new building on the NIH campus in Bethesda, Maryland. The government awarded the contract to Bell, even though Bell was not the lowest bidder. The contract included language from the Federal Acquisition Regulations (âFARâ), 48 C.F.R. § 52.243^4(d), which expressly allows for equitable adjustment:
If any change under this clause causes an increase or decrease in the Contractorâs cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any such order, the Contracting OfScer shall make an equitable*1339 adjustment and modify the contract in writing.
Bell was to complete the five-story building by June 29, 2000. It began construction on April 1, 1998, and proceeded on schedule until December 1998. At that time, the government realized it had a budget surplus and decided to add another floor (a ânewâ fourth floor) to the building. To govern the contractual changes, the parties entered into Modification 93 (âMod 93â) on October 2, 2000. Mod 93 included a price increase to pay for the new floor, and gave a revised project completion date. Bell agreed to meet fourteen âsubstantial completionâ milestones during the construction period, and the parties agreed upon liquidated damages of $266 per day of delay. Paragraph 4 of Mod 93 says that the modification will
increase the contract amount by $2,296,963 ... as full and equitable adjustment for the remaining direct and indirect costs of the Floor 4 Fit-out (EWO 240-R1) and full and equitable adjustment for all delays resulting from any and all Government changes transmitted to the Contractor on or before August 31, 2000.
Paragraph 8 of Mod 93 reads:
The modification agreed to herein is a fair and equitable adjustment for the Contractorâs direct and indirect costs. This modification provides full compensation for the changed work, including both Contract cost and Contract time. The Contractor hereby releases the Government from any and all liability under the Contract for further equitable adjustment attributable to the Modification.
The language in paragraph 8 was repeated in a number of subsequent modifications.
After the parties adopted Mod 93, Mr. Temme (who worked for NIHâs construction quality manager) and Mr. Kutlak (the COâs technical representative) informed NIH personnel that NIH should refrain from making additional changes to the project. Bell BCI, 81 Fed.Cl. at 623. Nonetheless, the government issued 113 additional modifications, which incorporated 216 Extra Work Orders (âEWOsâ). An additional fifty-eight issued EWOs were never incorporated into any modification. Bell ultimately missed thirteen of the fourteen milestone dates set forth in Mod 93. Shortly after Bell completed construction, it submitted a Request for Equitable Adjustment to the CO. The CO denied the claim, and instead asserted claims against Bell for liquidated damages, credits due the government, the cost of retests, and estimated costs for âoutstanding major deficiencies.â Id. at 624.
At that point, Bell filed suit in the Court of Federal Claims. Both parties filed cross-motions for summary judgment, which the court denied. Bell BCI Co. v. United States, 72 Fed.Cl. 164, 170 (2006). The court granted the governmentâs motion to dismiss Bellâs promissory estoppel claim. Id. at 167-68. After trial, the court found in favor of Bell. Bell BCI, 81 Fed.Cl. at 617. In total, the court awarded Bell $6,200,672, which breaks down as follows: (1) $2,058,456 in labor inefficiency costs attributable to the cumulative impact of the changes; (2) $1,602,053 for the delays of remaining on the project after April 30, 2001; (3) $366,051 as a 10% profit on the delay and labor inefficiency costs; (4) $563,125 as the unpaid balance of the contract price; and (5) $1,610,987 for unresolved changes covered by the fifty-eight EWOs not incorporated into any modification. Id. at 619. The court also rejected NIHâs claim to liquidated damages, id. at 640, and sustained subcontractor Stromberg Metalâs cumulative impact claim, id. at 641. We have jurisdiction over this appeal pursuant to 28 U.S.C. § 1295(a)(3).
The trial courtâs findings of fact are reviewed under the âclearly erroneousâ standard, while its legal holdings are reviewed de novo. Seaboard Lumber Co. v. United States, 308 F.3d 1283, 1292 (Fed. Cir.2002). Credibility and intent determinations are questions of fact. Comm. Contractors, Inc. v. United States, 154 F.3d 1357, 1369 (Fed.Cir.1998); Dureiko v. United States, 209 F.3d 1345, 1356 (Fed. Cir.2000). Contract interpretation is a question of law. Lucent Techs., Inc. v. Gateway, Inc., 543 F.3d 710, 717 (Fed.Cir.2008).
Different standards of review are applicable to different aspects of a damages award. â[T]he clear error standard governs a trial courtâs findings about the general type of damages to be awarded (e.g., lost profits), their appropriateness (e.g., foreseeability), and rates used to calculate them (e.g., discount rate, reasonable royalty). The abuse of discretion standard applies to decisions about methodology for calculating rates and amounts.â Home Sav. of Am. v. United States, 399 F.3d 1341, 1347 (Fed.Cir.2005). The evidentiary basis for a courtâs ruling on damages need only be âsufficient to enable a court or jury to make a fair and reasonable approximation,â and as long as a party can clearly establish a reasonable probability of damage, âuncertainty as to the amount will not preclude recovery.â Seaboard Lumber, 308 F.3d at 1302 (quoting Specialty Assembling & Packing Co. v. United States, 174 Ct.Cl. 153, 355 F.2d 554, 572 (1966) and Ace-Fed. Reporters, Inc. v. Barram, 226 F.3d 1329, 1333 (Fed.Cir.2000) (quotation marks omitted)).
A. Cumulative Impact
The first issue on appeal is whether the release language in paragraph 8 of Mod 93, repeated in later modifications, covers Bellâs cumulative impact claims. Paragraph 8 says that the modification âprovides full compensation for the changed workâ and that Bell âhereby releases the Government from any and all liability under this Contract for further equitable adjustment attributable to the Modification.â
In finding for Bell, the Court of Federal Claims drew a distinction between a âdelayâ claim and a âdisruptionâ or âcumulative impactâ claim. The court stated that â[although the two claim types often arise together in the same project, a âdelayâ claim captures the time and cost of not being able to work, while a âdisruptionâ claim captures the cost of working less efficiently than planned.â Bell BCI, 72 Fed.Cl. at 168. The court repeatedly stated that the release did not address cumulative impact or disruption claims, but failed to articulate why this was the case. See, e.g., Bell BCI, 81 Fed.Cl. at 619, 623, 629-30, 639. The court then looked to the contractâs âChangesâ clause, excerpted above as FAR 52.243-4, and determined that â[u]nless provided otherwise, the bilateral modifications will compensate the contractor for performing the changed work, but not for the impact of multiple change orders on the unchanged work.â Id. at 637. Because in the courtâs view Mod 93 did not âprovide otherwise,â the court concluded that Bell did not release its cumulative impact claims.
We do not question the courtâs finding that, in light of the numerous changes to the contract, Bell suffered a cumulative impact. But the issue is not whether Bell suffered a cumulative impactâit is whether Bell released the government from liability for that impact.
The government argues that Bellâs cumulative impact claims, if they exist, are barred by accord and satisfaction. Accord and satisfaction occur âwhen some performance different from that
The government argues that the more than $2,000,000 described in paragraph 4 of Mod 93 was âfull compensation for the changed workââin other words, that amount was paid as consideration for Bellâs release. The government also claims that because the release language is not ambiguous, parol evidence cannot be considered. To the extent extrinsic evidence is permitted, however, the government points to evidence indicating Bell âknew of the possibility of a cumulative impact claim and also knew how to reserve it,â but âBell simply failed to do so.â
Because a release is contractual in nature, it is interpreted in the same manner as any other contract term or provision. See Metric Constructors, Inc. v. United States, 314 F.3d 578, 579 (Fed.Cir.2002) (âThis case, like many contract disputes, turns on the interpretation of [the release].... â); Restatement (Second) of Contracts § 284 cmt. c (1981) (âThe rules of interpretation that apply to contracts generally apply also to writings that purport to be releases.â). To resolve the debate, then, we must first determine whether the release language in Mod 93 is unambiguous. Only in the event of an ambiguity may we examine extrinsic or parol evidence. McAbee Constr., Inc. v. United States, 97 F.3d 1431, 1434 (Fed.Cir.1996). We look to the plain language of the release, as âif the âprovisions are clear and unambiguous, they must be given their plain and ordinary meaning.â â Id. at 1435 (quoting Alaska Lumber & Pulp Co. v. Madigan, 2 F.3d 389, 392 (Fed.Cir.1993)); see Barron Bancshares, Inc. v. United States, 366 F.3d 1360, 1375-76 (Fed.Cir.2004).
We hold that the language in paragraph 8 of Mod 93 is unambiguous, and the court clearly erred in holding that Bell did not release its cumulative impact claims attributable to that modification. The language plainly states that Bell released the government from any and all liability for equitable adjustments attributable to Mod 93. At best, there may be ambiguity as to which claims are âattributable toâ a given modification, but we cannot glean any ambiguity about which types of claims are released-Mod 93 clearly, unambiguously releases the government from âany and allâ liability. As the Supreme Court stated in United States v. William Cramp & Sons Ship & Engine Building Co., â[i]f parties intend to leave some things open and unsettled, their intent so
In the absence of an ambiguity, we decline to examine the partiesâ extrinsic evidence. We therefore remand to the Court of Federal Claims so it can determine which of Bellâs cumulative impact claims, if any, are âattributable toâ modifications other than those modifications that contain the release language discussed above.
B. Delay and 10% Profits
For the same reason, we take issue with the Court of Federal Claimsâs decision to award $1,602,053 for the delays of remaining on the project after April 30, 2001. The court arrived at its April 30, 2001 date because Bell originally was to complete construction by June 29, 2000, and Bell received extensions from NIH accounting for 304 days (making the new contract completion date April 30, 2001). Bell did not finish construction until February 8, 2002, however, and the 284 days between April 30, 2001 and February 8, 2002 are at issue in Bellâs âdelayâ claim.
Again, we defer to the trial courtâs finding that âevidence of excusable delay from changed workâ was âso overwhelming that a reasonable person could not reach a contrary result.â Bell BCI, 81 Fed.Cl. at 640. We also defer to the courtâs determination that the governmentâs expert, who concluded that NIH caused just thirty-two days of delay on the project, was âsimply ... not credible.â Id. But this does not end our inquiry, since as before the question is whether the release language present in Mod 93 and later modifications excuses the government from liability for Bellâs delay claims. We hold that it does. As explained above, the language of the release is unambiguousâBell released the government from âany and allâ liability, which plainly includes the governmentâs liability for delays. On remand, the Court of Federal Claims must determine which delays, if any, are attributable to modifications that do not include the release language identified in paragraph 8 of Mod 93.
As a result, we must also vacate the trial courtâs award of 10% profits on the delay and cumulative impact claims. Once the court determines which specific delays or cumulative impacts are not âattributable toâ modifications containing the release language, the court is free to award appropriate profits on those amounts.
C. Other Arguments
The government raises challenges to other aspects of the trial courtâs decision, including the courtâs methodology for calculating delays and damages, the courtâs award to Bell for the balance of the contract price and the fifty-eight EWOs not incorporated into any modification, the courtâs award to subcontractor Stromberg Metal, and the courtâs decision to deny the government any liquidated damages. As to these arguments, we affirm the decisions of the Court of Federal Claims. We discern no clear error in the courtâs judgment as to the type of damages to be awarded, their appropriateness, or the rates used to calculate them. Nor did the court abuse its discretion in adopting Bellâs expertâs methodology in determining the amount of delay or the damages due to
CONCLUSION
For the reasons set forth above, we affirm-in-part, vacate-in-part, and remand to the Court of Federal Claims for proceedings consistent with this opinion.
AFFIRMED-IN-PART, VACATED-IN-PART, AND REMANDED
COSTS
Each party shall bear its own costs.
. We leave it to the Court of Federal Claims on remand to determine whether the government provided adequate consideration for other modifications containing the release language discussed herein.